This is a request for proposal for environmental services at the Former Nike Battery PR-58 and Disaster Training Village Area, a Formerly Used Defense Site in North Kingstown, Rhode Island. The U.S. Army Corps of Engineers, New England District is seeking proposals for in-situ thermal remediation of chlorinated volatile organic compounds within the site's contamination source area and downgradient groundwater plume. Offerors will be required to provide equipment and materials to complete a seed task order to design and execute pre-remediation investigation and bench-scale testing to support a phase one ISTR effort. The solicitation is set aside for small businesses with a NAICS code size standard of 750 employees. The single award task order contract has a capacity of $25 million over five years. Proposals are due by visiting the System for Award Management website. Questions may be directed to the listed contract specialist.

View the file

Other files

File Type Posted
W912WJ22R0011 Amendment 0007.pdf PDF
W912WJ22R0011 Amendment 0006.pdf PDF
W912WJ22R0011 Amendment 0005.pdf PDF
Revised Attachment G- SECTION 02 61 18.pdf PDF
Revised Binding Rates 6.6.2022.xlsx XLSX spreadsheet
W912WJ22R0011 Amendment 0004.pdf PDF
W912WJ22R0011 Amendment 0003.pdf PDF
QDC Stormwater Drainage.pdf PDF
SES-05.pdf PDF
EA-119D.pdf PDF
SES-07.pdf PDF
EA-121S.pdf PDF
EA-119S.pdf PDF
Revised Bid Schedule Seed Task Order.xlsx XLSX spreadsheet
SES-04.pdf PDF
SES-06.pdf PDF
EA-117S.pdf PDF
EA-118R.pdf PDF
SES-03.pdf PDF
SES-01.pdf PDF
EA-118D.pdf PDF
EA-120S.pdf PDF
EA-120D.pdf PDF
Revised Binding Rate.xlsx XLSX spreadsheet
EA-117D.pdf PDF
SES-10.pdf PDF
SES-02.pdf PDF
EA-117R.pdf PDF
EA-118S.pdf PDF
SES-11.pdf PDF
EA-119R.pdf PDF
W912WJ22R0011 Amendment 0002.pdf PDF
EA-120R.pdf PDF
EA-121R.pdf PDF
EA-121D.pdf PDF
SES-09.pdf PDF
SES-08.pdf PDF
Pre-design Investigation Report Part 1.pdf PDF
Pre-Design Investigation Report Part 2.pdf PDF
Final Design Analysis Report Part 1.pdf PDF
Final Design Analysis Report Part 2.pdf PDF
W912WJ22R0011 Amendment 0001.pdf PDF
Semi-Annual Sampling Report.pdf PDF
Final Decision Document.pdf PDF
Final Value Engineering Report.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED Performance Work Statement for Remedial Action Contract Seed Task Order

Former Nike Battery PR-58 And Disaster Village Training Area

Formerly Used Defense Site North Kingstown, Rhode Island

April 4, 2022 June 13, 2022

TABLE OF CONTENTS

1. CONTRACT PROCUREMENT OBJECTIVES AND OVERVIEW

2. TYPES OF SERVICES REQUIRED

3. CONTRACT TYPE

4. SITE BACKGROUND

5. TASK ORDER 1 (SEED TASK ORDER) - PERFORMANCE OBJECTIVES AND

STANDARDS

6. TASK ORDER CONTRACT REQUIREMENTS

6.1 Task 1– Project Management & Contract Administration

6.1.1 Task 1.1 – Project Management & Project Controls

6.1.2 Task 1.2 – Project Teleconferences & Meetings

6.1.3 Task 1.3 - Progress Invoices and Monthly Status Reports

6.1.4 Option Task 1.4 - Public Meetings

6.1.5 Option Task 1.5 - Project Repository

6.2 Task 2.0 – Site Walk Project Kick-off Meeting

6.3 Task 3 – Project Plans

6.3.1 Task 3.1 – Contractor Project Management Plan

6.3.2 Task 3.2 – Quality Control Plan

6.3.3 Task 3.3 - Accident Prevention Plan

6.4 Task 4.0 - Pre-Remediation Investigation

6.4.1 Task 4.1 – Combined Pre-Remediation Investigation Sampling & Analysis and Quality

Assurance Project Plan

6.4.2 Task 4.2 – Execute Combined Pre-Remediation Investigation Sampling & Analysis and

Quality Assurance Project Plan

6.5 Task 5.0 – ISTR Bench-Scale Testing Work Plan & Execution

6.5.1 Task 5.1 - ISTR Bench-Scale Testing Work Plan

6.5.2 Task 5.2 - ISTR Bench-Scale Testing Work Plan Execution

6.6 Option Task 6.0 – Phase 1 ISTR Thermal Conductive Heating Remedial Action Work Plan (RAWP) & Execution

6.6.1 Option Task 6.1 - ISTR TCH Phase 1 Remedial Action Work Plan

6.6.2 Option Task 6.2 – Execution ISTR TCH Phase 1 Work Plan

6.7 Option Task 7 – Technical Project Meeting

7. COORDINATION

8. SCHEDULE

9. ADDITIONAL REQUIREMENTS

9.1 Environmental Protection Requirements

9.2 Protection of Property

9.3 Health and Safety Requirements

9.4 Quality Control Testing

9.5 Electronic Data Deliverables

9.6 Chemistry Electronic Data Deliverables

9.7 Other Types of Electronic Non-Laboratory Chemistry Data Deliverables

9.8 Other Types of Data Not Currently Supported in FUDSChem

9.9 Project Repository and Administrative Record

9.10 Instructions for Submittals of Electronics Documents to the FUDS Records

Database/Deliverable Requirements

9.11 Procedure for the Retention & Digitization of Critical E-mails

9.12 Regulatory Involvement

9.13 Project Stakeholders

9.14 Deliverable Requirements

9.15 Expertise and Related Personnel

9.16 Certification and Approval of Project Performance Standards, Milestones, and Deliverables

9.17 Travel

9.18 USACE Furnished Resources

9.19 Rights of Entry

9.20 Contractor Furnished Resources

9.21 Government Rights

9.22 Stop Work Authority

9.23 Performance Evaluation

9.24 Sustainable Design Requirements

10. REFERNCES

11. ACRONYM & ABBREVIATIONS

ATTACHMENTS

Attachment A Attachment B Attachment C Attachment D Attachment E Attachment F Attachment G

1. CONTRACT PROCUREMENT OBJECTIVES AND OVERVIEW

This Seed Task Order is for Environmental Remediation Services in support of the US Army Corps of Engineers (USACE) at the for Former Nike Battery PR-58 and Disaster Village Training Area Formerly Used Defense Site (FUDS), Quonset Point Naval Air Station, North Kingstown, Rhode Island.

The Contractor shall perform all the necessary services required to successfully meet all performance objectives of this Performance Work Statement (PWS). The Contractor shall comply with all applicable Federal, State, and local laws and regulations to successfully complete all performance objectives of this PWS in a manner that is consistent with any applicable orders and permits and relevant Department of Defense (DOD) and Army policies for the duration of this Task Order. The Contractor shall also comply with comply with all applicable requirements of the Decision Document for the Former Nike Battery PR- 58 & DTVA FUDS dated June 2019, all applicable ASTM standards, USACE Engineering Manuals and Engineering Regulations. The Decision Document for the Former Nike Battery PR- 58 & DTVA FUDS has been provided with the Solicitation. as well as other Site-specific documents including, but not limited to: The following documents are provided with this Seed TO to provide background information on the FUDS. These documents are intended for informational purposes only:

• Final PR-58 Design Analysis Report, Former Nike Battery PR-58 & Disaster Village

Training Area, Quonset Point Naval Air Station, North Kingstown, Rhode Island, FUDS Project Number: D01RI0029 05. AECOM Environmental, December 28, 2021.

• Final Value Engineering Report, Former Nike Battery PR-58 & Disaster Village Training Area, Quonset Point Naval Air Station, North Kingstown, Rhode Island, FUDS Project Number: D01RI0029 05. AECOM Environmental, December 28, 2021.

• Final PR-58 Pre-Design Investigation Report, Former Nike Battery PR-58 & Disaster Village Training Area, Quonset Point Naval Air Station, North Kingstown, Rhode Island, FUDS Project Number: D01RI0029 05. AECOM Environmental, August 25, 2021.

• Groundwater and Surface Water Sampling at Former Nike Battery PR-58 & Disaster Village Training Area, Summer 2021 Semi-annual Sampling Report, FUDS Project Number: D01RI0029 05. Bluestone Environmental Group, December 8, 2021.

• Final Decision Document, Former Nike Battery PR-58 & Disaster Village Training Area, Quonset Point Naval Air Station, North Kingstown, Rhode Island, FUDS Project Number:D01RI0029 05. Stone Environmental, Inc., June 2019.

• Final Remedial Investigation/Feasibility Study Report, Former Nike Battery PR-58 & Disaster Village Training Area, Quonset Point Naval Air Station, North Kingstown, Rhode Island, FUDS Project Number: D01RI0029 05. Stone Environmental, Inc., June 2016.

• Report of Findings, Steam Enhanced Remediation Pilot Test, at the Former PR-58 Nike Site, North Kingstown, Rhode Island, FUDS Project Number: D01RI0029 05.

EA Engineering, Science, and Technology, Inc., January 2008.

2. TYPES OF SERVICES REQUIRED

This Task Order includes the following types of geotechnical and environmental services as authorized under the basic contract:

• Site Characterization/Investigation

• Studies and Reports

• Monitoring and Interim Operations

• Engineering for Remediation

• Remedial Action

3. CONTRACT TYPE

Cost Plus Fixed-Fee

X _Firm Fixed Price

Fixed Price with Award Fee

4. SITE BACKGROUND

The Nike PR-58 & Disaster Training Village Area (DTVA) Formerly Used Defense Site (FUDS) property (Site) is in North Kingstown, Washington County, Rhode Island. The Property, which comprises approximately 44 acres, is bounded by the former Perimeter Road (now a bike path) to the north, Seabee Avenue to the east, Newcomb Road to the west, and Babcock Road to the south. Most of the Property is currently owned by the Quonset Development Corporation (QDC), a special purpose subsidiary of the Rhode Island Economic Development Corporation (RIEDC), except for approximately 1.7 acres in the southwest corner of the Property that was purchased by Chipster, LLC in 2008. The Property is abutted on the North and West by residential areas. The parcel to the east and south of the Property is currently owned by the Navy and was previously occupied by the Davisville Naval Construction Battalion Center (NCBC). QDC has a Lease in Furtherance of Conveyance (Lease No. N62472-98-RP-00035). This parcel will transfer to QDC once there is a Record of Decision (ROD) for the Property and the remedial action has been implemented.

The Property was previously used by the U.S. Navy as a military camp from 1942 until the end of World War II, by the U.S. Army as the Nike Battery PR-58 from 1954 to 1962, by the U.S. Navy as the DVTA from 1964 to 1974, and by Peabody Clean Industries (PCI) for hazardous materials storage and treatment from 1980 to 1983. Historical operations conducted on the Property by these operations resulted in releases of hazardous materials and impacts to environmental media. In addition, multiple releases of contamination have been documented on sites located downgradient and unrelated to the Property. It is likely that plumes from these sites have commingled with the plume that is a result of activities performed on the Property. The various studies conducted on the Property have determined that releases of hazardous substances from Department of Defense (DOD) activities at the Property resulted in impacts to soil, groundwater, surface water, sediment, and soil gas from chlorinated volatile organics (CVOCs). The CVOCs observed in environmental media on the Property were 1,1,2,2-tetrachloroethane (TeCA), tetrachloroethene (PCE), trichloroethene (TCE), and their degradation products: 1,1,2-trichloroethane (TCA); 1,1-dichloroethene (DCE); cis-1,2-DCE; trans-1,2-DCE; and vinyl chloride (VC). Multiple lines of evidence suggest that the CVOCs were released on the Property in the form of dense non-aqueous phase liquid (DNAPL). Investigations indicate that residual DNAPL is still present in the deeper unconsolidated overburden deposits and bedrock fractures in an area approximately 1/3 acre in size beneath the Property, which is referred to as the “Source Area.”

Concentrations of total CVOCs in the Source Area exceed 70,000 µg/L in groundwater and 10,000 µg/kg in soil. A more dilute plume extends outward from the Source Area. In general, the plume increases in size with depth, covering a greater area in bedrock than in the shallow unconsolidated deposits. The plume has migrated the greatest distance in the bedrock to the east and south of the Source Area and to a lesser extent toward the north.

Historical operations on the former Davisville NCBC facility, which abuts the Property on the east and south, also resulted in releases of hazardous materials and impacts to environmental media. Multiple sites on the former NCBC facility, unrelated to the releases at the Property, have been or are engaged in independent environmental investigation and remediation activities. The footprint of the plume extending from the Source Area on the Property overlaps the plumes of similar types of CVOC contamination from Navy operations to the east and south.

The compounds TeCA; PCE; TCE; cis-1,2-DCE; trans-1,2- DCE; 1,1-DCE; 1,1,2-TCA; and VC were all identified above their Maximum Contaminant Levels (MCLs) or risk-based concentrations in the most recently sampled groundwater on the Property. The compounds TeCA and TCE exceeded the MCLs in the aquifer below the undeveloped portion of the land immediately north of the Property. PCE, 1,1,2-TCA, cis-1,2-DCE, and vinyl chloride were detected in one or more pore water samples collected from Hall Creek, and low concentrations of TCE were detected at one location near Davol Pond. Private drinking water wells to the north and northeast of the Property were sampled in 1997, 2006, 2009, and 2013, although the list of wells sampled in each timeframe varied. There were no detections of CVOCs in these wells, with the exception of trace levels (below MCLs) of PCE and 1,1,1-TCA (0.7 µg/L and 1.0 µg/L, respectively) in one well in 1997. Access to resample this well has not been granted in the numerous follow-on efforts. Not all existing residential wells have been sampled because not all residents granted access to USACE for sampling.

VOCs were detected in surface water samples collected from Hall Creek and Davol Ponds between 2008 and 2013, but at concentrations below the regulatory criteria. Sediment quality guidelines were marginally exceeded in the Hall Creek/Davol Ponds system at only one of six locations sampled. TCE was present in this sediment sample at 97.3 µg/kg as compared to the EPA Benchmark of 96.9 µg/kg.

In 1983, PCI performed a cleanup of contaminated soil related to their activities at and near the Property. This process included the excavation and removal of approximately 710 cubic yards of contaminated soils resulting from the oil/water separator constructed and operated by PCI and the disposal of four oil, water, and waste storage tanks. In addition, RIEDC removed a large concrete pad and a damaged wooden structure from the Property from the proximity of the known Source Area. There is little to no data or information related to these demolition and removal actions by RIEDC. From 2004 through 2005, a Steam Enhanced Remediation (SER) pilot study was conducted to assess the feasibility of using SER technology as a remediation alternative in the future. The test removed roughly 323 pounds of contaminant mass and reduced the levels of CVOCs in some of the Source Area wells as it was designed to do; however, it appears to have temporarily mobilized/redistributed DNAPL and increased the levels of CVOCs in some downgradient wells. One area where the plume of CVOC contamination appears to be increasing in concentrations is in the shallow overburden flowing southeast towards Davol Pond and Hall Creek. Because of the borderline risk associated with the data available in the RI as well as the potential increasing concentration migrating towards this groundwater discharge area, there is potential for unacceptable risk in the wetlands and surface waters of Hall Creek.

The Remedial Investigation/Feasibility Study report for the property was completed in 2016 and the proposed plan completed in 2018. The Proposed Plan’s preferred alternative for the property was the UU/UE alternative which includes thermal treatment in the contaminant Source Area, where the highest concentrations of chlorinated volatile organic compounds (CVOCs) are present in the soil, groundwater, and bedrock fractures; and reductive dechlorination in the downgradient groundwater plume(s) of dissolved CVOC contamination. This alternative was chosen because it provides both short and long-term protection of human health and the environment: reduces the TMV of contaminated groundwater through treatment, to the maximum extent practicable; utilizes permanent solutions; and uses land use restrictions to prevent unacceptable exposures during implementation of the remedy until RGs are attained. The Decision Document for the FUDS was completed in June 2019.

The Source Area has been defined as the area of the Site where chlorinated volatile organic compounds (CVOCs), primarily trichloroethene and tetrachloroethane, have been identified at concentrations greater than 10,000 ug/Kg in soil and/or 70,000 ug/L in groundwater.

Investigations indicate that residual DNAPL is still present in the deeper unconsolidated overburden deposits and bedrock fractures in an area approximately 1/3 acre in size beneath the Site. The exact vertical and horizontal extents of the Source Area are not currently well defined with the limited data available. The vertical extent consists of 25-45 feet of unconsolidated deposits underlain by approximately 40 feet of basal glacial till and weathered bedrock and at least 60 feet of competent bedrock with known contamination.

The total depth of the Source Area in the bedrock is not well defined at this time but it appears that the treatment zone will be extend no deeper than 100 feet below ground surface (bgs).

5. TASK ORDER 1 (SEED TASK ORDER) - PERFORMANCE OBJECTIVES AND

STANDARDS

This Task Order PWS is for a results-based contract with intent to successfully complete all performance objectives shown in Table 1. The Contractor shall furnish all labor, materials, and equipment necessary to successfully complete all performance objectives identified in this PWS and Table 1, Performance Requirements Summary. Achievement of the performance objectives is successfully attained upon the finalization of appropriate documentation certifying that the documents have been accepted by the USACE. USACE approval of the Performance Standards will be by the USACE Contracting Officer (KO) or Contracting Officer’s Representative (COR).

Table 1 – Performance Requirements Summary Performance Objective/Task Performance Standard Task 1.0 – Project Management & Contract Administration

Performance Standards provided by sub-task below.

Task 1.1 – Project Management & Control USACE approval of final monthly invoices.

Task 1.2 – Project Teleconferences & Meetings

USACE approval of final meeting minutes.

Task 1.3 – Progress Invoices & Monthly Status Reports

USACE approval of final monthly invoices.

Option Task 1.4– Public Meetings USACE approval of meeting materials and minutes and/or final stenographer submittal.

Option Task 1.5 – Project Repository Update

Repository confirmation/receipt from North Kingstown Free Library.

Task 2.0 – Project Kick-off Site Walk USACE approval of final meeting materials, field notes or minutes.

Task 3 – Project Plans Performance Standards provided by sub- task below.

Task 3.1 – Contractor Project Management Plan

USACE approval of Final Contractor Project Management Plan

Task 3.2 – Contractor Quality Control Plan USACE approval of Final Quality Control Plan

Task 3.3 - Accident Prevention Plan/Health& Safety Plan

USACE approval of Final APP/HASP

Task 4.0 – Pre-Remediation Investigation

Performance Standards provided by sub-task below.

Task 4.1 – Combined Sampling & Analysis and Quality Assurance Project Plan (SAP-

QAPP)

USACE approval of Final SAP-QAPP

Task 4.2 – Execute Combined Pre- Remediation Investigation

USACE approval of final Field Investigation Report

Task 5.0 – ISTR Bench-Scale Testing Work Plan & Execution

Performance Standards provided by sub-task below

Task 5.1 – ISTR Bench-Scale Testing Work Plan

USACE approval of final Bench-Scale Testing Work Plan

Task 5.2 – Execute ISTR Bench-Scale Testing Work Plan

USACE approval of final Bench-Scale Testing Report

Option Task 6.0 – ISTR TCH Phase 1 Work Plan & Execution

Performance Standards provided by sub-task below.

Option Task 6.1 – ISTR TCH Phase 1 Work Plan

USACE approval of final Phase 1 Work Plan

Option Task 6.2 – Execution of ISTR TCH Phase 1 Work Plan

USACE approval of final Phase 1 ISTR Completion Report

Option Task 7 – Technical Project Meeting USACE approval of final meeting minutes

Note - In the event that there may be multiple milestones and/or deliverables for each of the performance objective tasks, partial payments will be based on the successful completion of milestones. Final decisions regarding the adequacy of milestone and deliverable completion resides with the KO or COR.

6. TASK ORDER CONTRACT REQUIREMENTS

The Contractor shall furnish all necessary labor, equipment, materials, and supplies to complete the tasks listed in Table 1 above and defined in the following paragraphs. All work shall be conducted in a safe, secure, cost efficient, and environmentally acceptable manner conforming to existing Federal, State, and local regulations. Work shall be completed correctly in a professional, workmanlike manner, in accordance with approved work plans. Work is to be performed commensurate with the level of effort and quality intended, with appropriately qualified quality control (QC) representation (as part of the contractor’s overall QC Program) controlling the work.

6.1 Task 1– Project Management & Contract Administration

The performance-based TO approach requires careful coordination of project activities to ensure that all stakeholders are kept informed of the project status, existing or potential problems, and any changes that may be required to prudently manage the project and meet the needs of the project stakeholders and decision-makers.

The Contractor is responsible for ensuring that the quality of all work performed, and documents produced under this PWS meets USACE approval. The Contractor shall ensure that adequate project management resources are available and that project management tasks are completed in order to effectively execute this PWS on schedule.

6.1.1 Task 1.1 – Project Management & Project Controls

The Contractor shall provide all project management and project control activities for the duration of this Task Order pursuant to task requirements outlined in Task 1.0 – Project Management/Project Controls in Section 6.1 of the Base IDIQ Contract. Note, the initial draft fact sheet is due within 120 calendar days of award of this Seed Task Order and the initial draft Quarterly Project Summary is due within nine (9) months of award of this Seed Task Order.

Section 9.0 of this PWS provides additional information and requirements.

6.1.2 Task 1.2 – Project Teleconferences & Meetings

The Contractor is expected to regularly update USACE on project status, via telephone or electronic mail, including daily communication with the USACE Engineering Technical Lead during the execution of field activities or other critical periods of the project. In addition to this regular informal communication, the contractor shall prepare for and participate in bi-weekly status conference calls with USACE and potentially other stakeholders, which shall be held weekly during field activities.

The Contractor shall also prepare meeting and teleconference agendas which will include technical, budget and project schedule status, project risk updates and any other pertinent project updates.

The Contractor shall be responsible for the preparation and submission of all Meeting Minutes, and/or other required documentation, in electronic format within seven (7) calendar days following the meeting.

6.1.3 Task 1.3 - Progress Invoices and Monthly Status Reports

The Contractor shall develop and submit invoices monthly, unless otherwise approved by the COR/PM, based on milestone progress and successful achievement of the performance objectives defined in Table 1, above. Successful achievement of the performance objectives is attained upon receipt of the USACE’s approval of the relevant task documentation (as defined). In the event there are multiple milestones and/or deliverables for each of the performance objective tasks, partial payments will be based on the successful completion of milestones, if agreed upon ahead of time. Final decisions regarding the achievement of performance objectives including adequacy of milestone and deliverable completion resides with the USACE KO or COR.

With each invoice, the Contractor shall provide a Monthly Status Report in electronic format by the end of the first week of every month that reflects the activities completed by the Contractor the previous month, activities to be completed by the Contractor before the next monthly Status Report submittal, completion of the project risk tracking matrix (Attachment A) and an updated project schedule through completion of project tasks.

Prices shall be billed in a format consistent with the Contractor’s accepted proposal on an ENG Form 93. With the ENG Form 93, the Contractor shall provide a spreadsheet containing a work breakdown structure (WBS) which includes the following items:

• CLINs (Contract Line-Item Numbers),

• CEFMS PR&C and PR&C Line Number,

• Task/Subtask Name (note, tasks should follow the Task number system in the PWS),

• Budgeted Amount (Contract Amount),

• Total Earnings to Date (including current invoice),

• Percent Complete to Date (including current invoice),

• Total Retained to Date (including current invoice),

• Previously Earned to Date,

• Previously Retained to Date,

• Previously Paid to Date,

• Total Earnings this Period (Invoice Amount),

• Retainage Refunded This Period,

• Retainage Withheld This Period,

• Amount Due to Contractor,

• Contract Budget Remaining.

Section 9.0 of this PWS provides additional information and requirements.

6.1.4 Option Task 1.4 - Public Meetings

The Contractor shall support community involvement activities including attendance at public meetings, as required by USACE. For planning purposes, the Contractor shall assume the following:

1) Two employees will attend and provide support at each public meeting.

2) Public meetings will be held at TBD facilities in North Kingstown, Rhode Island.

3) It is highly likely the public meetings will be held in the early evening to encourage greater public participation; therefore, the Contractor shall assume one overnight stay for each meeting.

4) The Contractor shall be responsible for providing all graphics, materials, and audio-visual equipment to facilitate the meeting.

5) A licensed court stenographer may also be required.

6) The Contractor shall develop and submit Meeting Minutes in electronic format within seven (7) calendar days following the meeting for distribution to the USACE.

This Option Task will be multi-executable up to 4-times, and the price will be valid for a period of two (2) years from award of this task order.

6.1.5 Option Task 1.5 - Project Repository

The Contractor is responsible for updating, annually or after completion of a final document, the existing project repository for the FUDS, which has been established at the following location:

North Kingstown Free Library 100 Boone Street North Kingstown, Rhode Island 02852 Telephone: 401-294-3306

This Option Task will be multi-executable up to 4-times, and the price will be valid for a

6.2 Task 2.0 – Site Walk Project Kick-off Meeting

The Contractor shall facilitate and attend one formal kick-off meeting to be held at the project Site, within fifteen (15) business days following TO award. The kick-off meeting will be held to discuss the overall project objectives, methodologies, logistics and project schedule, and to attend a Site walk. The Contractor will provide an agenda and all necessary equipment and materials to facilitate the kick-off meeting. The objective of the Site walk includes, but is not limited to:

• Familiarization with project area,

• Evaluation of clearing and grubbing requirements,

• Evaluation of potential impacts to property owner(s), wetlands, etc., and

• Evaluation of mobile office and laydown area(s), if required.

As a component of this effort, the Contractor shall prepare an abbreviated Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA), in accordance with the relevant sections of EM 385-1-1, covering anticipated site walk activities. The draft abbreviated APP & AHA must be submitted within 7-working days from award and the final must be accepted by USACE prior to the meeting. Within seven (7) calendar days following the kick-off meeting, the Contractor shall develop and submit (in electronic format) Meeting Minutes including a Summary of Site Walk Observations and any outstanding questions or concerns identified regarding project implementation.

6.3 Task 3 – Project Plans

The Contractor shall prepare a draft and final Contractor Project Management Plan, Quality Control Plan and Accident Prevention Plan for this Task Order. The first draft of each plan shall be submitted within the calendar days from award as indicated in Sections 6.3.1, 6.3.2 and 6.3.3. Draft plans and subsequent revisions will be subject to USACE review and approval through the Contracting Officer’s Representative (COR). Revised and final plans will be due within fifteen (15) calendar days of comments received from the COR on the previous submittal. Unless otherwise noted, assume a Draft and Final plans with response to comments (RTCs) and response to comments letters (RCL) by the Contractor. Assume thirty (30) calendar days for government review of all submittals.

6.3.1 Task 3.1 – Contractor Project Management Plan

The Contractor shall develop a draft and final detailed Contractor Project Management Plan (CPMP) pursuant to task requirements outlined in Task 2.1 – Contractor Project Management Plan in Section 6.2.1 of the Base IDIQ Contract. The draft CPMP shall be submitted within 30 calendar days of Task Order award. The CPMP will specify the schedule, execution, and completion of the performance objectives.

6.3.2 Task 3.2 – Contractor Quality Control Plan

The Contractor shall submit a draft and final Quality Control Plan pursuant to task requirements outlined in Task 2.2 – Quality Control Plan in Section 6.2.2 of the Base IDIQ Contract. The draft shall be submitted within 45 calendar days of Task Order award.

6.3.3 Task 3.3 - Accident Prevention Plan

The Contractor shall prepare a draft and final Accident Prevention Plan (APP) specific to the activities being performed. The draft APP shall be submitted within 60 calendar days of Task Order award. The APP shall include an Activity Hazard Analysis (AHA) as described in 2 below. All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, most recent edition), and all applicable federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at Headquarters USACE website under publications using the following link:

https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_ 385-1- 1.pdf

The APP shall detail how safety and health will be managed during the project. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No. 52.236- 13 for Accident Prevention, which is added by reference. Special attention shall focus on the requirements of EM 385-1-1, specifically Section 01.A.12 through 01.A.17, Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). The APP shall be developed by a qualified person. The contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the APP has been reviewed by the Government Designated Authority (GDA) and deemed acceptable for use on the project.

APP Appendices

A. An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the contractor to discuss the AHA contents with all engaged in the activity. The preparatory meeting shall be conducted by the prime contractor and shall include all subcontractors and Government On-Site representatives. The AHA shall be continuously reviewed and revised to address changing Site conditions or operations as appropriate.

B. The contractor shall develop a Hazardous Energy Control Program (HECP) IAW EM

385-1- 1 Section 12 as well as all requirements of 29 CFR 1910.147, ANSI Z244.1, and ANSI A10.44. This HECP shall be submitted as part of their Accident Prevention https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf

Plan (APP) to the GDA for acceptance.

Competent Persons

A. Competent Persons are defined as one who can identify existing and predictable hazards in the working environment or working conditions that are dangerous to personnel and who has authorization to take prompt corrective measures to eliminate them. Activities under this TO are not anticipated to include tasks/efforts that require competently trained individuals from a health & safety perspective (e.g., confined space entry, crane and rigging, excavation, etc.). This may be updated if a change in PWS field activities require the need and designation of a competent person.

B. Site Safety and Health Officer (SSHO): The Contractor shall designate one individual as the SSHO who shall have the qualifications detailed below. Documentation of SSHO qualifications shall be submitted for approval prior to initiating work. The SSHO may have other duties in addition to Site safety and health but may not be the Contractor’s Site Superintendent.

1. A minimum of two years of experience in implementing safety and health programs at similar projects.

2. Working knowledge of construction safety procedures as well as Federal and state occupational safety and health regulations.

3. Ten (10) hour OSHA Construction Safety certification or as an equivalent, Ten (10) hours of formal construction safety and health training covering the subjects of the OSHA 10-hour course.

Safety Reporting

A. Safety Briefing and Equipment Inspection Documentation

The Contractor shall conduct a safety meeting at the project Site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work. All safety meetings shall be documented. A copy of a suggested weekly safety meeting form (Attachment B) will be provided by the Contracting Officer’s Representative.

Records of the safety briefings shall be submitted to the GDA weekly.

The Contractor shall submit to the GDA a current written safety inspection for all heavy equipment proposed for use on this contract. The Contractor, upon award of the contract, will be required to make available for suitability and safety compliance inspection all equipment proposed for use to perform the work of this contract. Equipment shall be made available for inspection by the GDA five working days prior to the start of work. Any additional equipment added during the prosecution of the work shall also be made available for inspection prior to its use on the project. Equipment not accepted by the GDA should be repaired or replaced by the Contractor.

Incident Reporting

All work-related incidents, to include injuries, illnesses, near misses, and property related accidents (excluding on the road- vehicle accidents), shall be immediately reported to the GDA and documented appropriately. All incidents shall be investigated to identify all root causes and recommended hazard control measures.

ENG Form 3394 (Attachment C)shall be completed for all OSHA recordable injuries or illnesses and property damage accidents, for which property damage exceeds $5,000.00. A Lessons Learned Document shall also be submitted separately within five days of the incident. All other incidents shall be reported using EITHER ENG 3394 or the Contractor’s internal incident reporting form.

Exposure Hour Reporting

The Contractor shall complete the “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (Attachment D) for prime and its subcontractors and forward the completed form to the GDA no later than close of business on the 5th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically.

6.4 Task 4.0 - Pre-Remediation Investigation

The Contractor shall be responsible for reviewing relevant project related files and develop and execute a Combined Sampling Analysis Plan (SAP) and Quality Assurance Project Plan (QAPP) to address all remedial design data gaps identified in the relevant project related files, data, and documents, etc., which are provided as a part of this Seed Task Order in order to support bench scale testing, development of the Phase I Treatment Work Plan and successfully complete the Phase 1 Treatment, and to identify and treat the entire vertical and horizontal extent of the overburden and bedrock Source Area. The Contractor shall specifically address data gaps described in the August 2021 Pre-Design Investigation Report, December 2021 Value Engineering(VE) Report and the December 2021 Design Analysis Report (DAR).

6.4.1 Task 4.1 – Combined Pre-Remediation Investigation Sampling & Analysis and Quality Assurance Project Plan

The Contractor shall prepare and submit a Draft and Final Combined Sampling & Analysis (SAP) and Uniform Federal Policy for Quality Assurance Project Plans (QAPP) to address all remedial design data gaps identified in the relevant project related files, data, and documents, etc., reviewed as a part of this Seed TO.

The SAP portion of the SAP-QAPP shall be prepared in accordance with the DoD Field Sampling Handbook dated 9 October 2013 (or subsequent revision) and should include a conceptual site model (CSM) for the project, which shall be prepared in accordance with EM 200-1-12, dated 28 December 2012 (or most recent subsequent revision). The UFP QAPP portion shall be prepared in accordance with the DoD Environmental Data Quality Group (EDQW) Environmental Field Sampling Handbook, dated 9 October 2013 (or subsequent revision), and the Optimized UFP- QAPP Worksheet Guidance (EPA/DOD/DOE, 2012). The Contractor shall include a Risk Assessment Work Plan in accordance with EP 200-1-15, as an appendix to the UFP QAPP. The Contractor shall also consider EM 200-1-12 and EM 200-1-2 in preparing the UFP QAPP.

The Contractor shall also develop an electronic QAPP (eQAPP) within FUDSChem as detailed in the Quality Control Testing and Electronic Data Deliverables sections, below (see Section 9.0).

Generally, the UFP QAPP and the eQAPP are developed in parallel since several QAPP worksheets may be automatically generated within FUDSChem.

Note: The Contractor shall assume implementing a quality control (QC) sampling program for each sample media including field duplicates collected at a frequency of 10%, MS/MSD at 5%, and frequencies of equipment blanks and trip blank depending on field sampling duration.

6.4.2 Task 4.2 – Execute Combined Pre-Remediation Investigation Sampling & Analysis and Quality Assurance Project Plan

Upon completion and approval of the final Combined Pre-Remediation Investigation Sampling & Analysis and Quality Assurance Project Plan (SAP-QAPP), the Contractor shall be responsible for mobilizing sufficient quantity and quality of all appropriate equipment, supplies, personnel, and sub-contractors to execute this task in accordance with the approved SAP-QAPP. The Contractor shall coordinate all utility clearance required with Dig Safe Systems, Inc. and/or other responsible entity prior to the execution of any intrusive activities at the Site. Prior to commencing any Site activities, the Contractor shall obtain approval from USACE Project Manager that all necessary and appropriate Health & Safety documents and plans have been received and approved by USACE’s Safety and Occupational Health Branch.

Additionally, the Contractor shall establish Site controls to ensure that any Site investigation activities do not further impact (temporarily or permanently) or contaminate the project Site or surrounding area. The Contractor shall be responsible to decontaminate all equipment and/or tools, implement soil erosion control measures, remove any temporary facilities, and restore all areas impacted by Site activities. The Contractor is wholly responsible for any and all investigation derived wastes (IDW), e.g., soils, water, etc., generated during Site field activities which shall be managed pursuant to all applicable pertinent Federal, State, and local regulations.

Upon completion of this Task, the Contractor shall prepare a draft and final Field Investigation Report which will present the findings of all activities completed, deviations from approved work plans as well as an updated CSM. Furthermore, the report shall provide ALL of the raw data collected and details as well as a figure showing sampling locations and a summary table of media exceedance (using validated data) of applicable regulatory criteria or applicable concentrations.

6.5 Task 5.0 – ISTR Bench-Scale Testing Work Plan & Execution

The Contractor shall be responsible for performing bench-scale tests to assess the mechanisms and efficacy of thermal treatment of the Site’s Source Area overburden soils weathered bedrock containing CVOCs, particularly but not limited to, TeCA and TCE. The bench-scale testing shall explore treatment of TeCA in soils that contain high total organic carbon (TOC), but it is up to the Contractor to determine, based on documents reviewed as part of this Seed Task Order, what other bench-scale testing may be required to meet the objective of this Seed Task Order. The Contractor will develop a work plan for the bench- scale testing and then execute the work plan once it has been approved by USACE.

Elements of the bench-scale test shall include, but are not limited to, evaluation of:

1) Mass recovery of TeCA after 1) achieving boiling temperatures and maintaining for a standard duration, 2) after maintaining boiling temperatures for an extended duration, and 3) after heating to the boiling point of TeCA (146°C at 1 atm) and maintaining for a nominal duration.

2) The role that soil TOC plays on contaminant recovery and duration of operation by using Site soils collected from the overburden and weathered bedrock (Task 4.2) with a range of TOC values representative of Site conditions.

3) The primary mechanisms of TeCA removal through monitoring the fraction of TCE and TeCA in recovered vapor and condensate over time. For instance, a higher ratio of TCE/TeCA in the recovered vapor and condensate relative to baseline soil results may indicate the relative contribution of hydrolysis in TeCA removal.

4) The changes in pH that occur over the course of thermal treatment, and how to enhance the rate and role of hydrolysis in TeCA treatment.

6.5.1 Task 5.1 - ISTR Bench-Scale Testing Work Plan

The Contractor shall prepare and submit a Draft and Final Bench-Scale Testing (bench study) Work Plan outlining the technical approach for the bench-scale treatability study.

This Work Plan shall be prepared in coordination with the SAP/QAPP to identify drilling activities and locations needed to collect soil samples for bench-scale testing collected under Task 4.2. Data quality for the bench-scale testing shall be governed by the data quality objectives for this work. The data quality shall conform with the final SAP-QAPP prepared under Task 4.1 of this PWS, unless DQOs indicate other quality assurance procedures, in which case the QAPP amended to address these procedures.

Requirements

1) Contractor shall track and report contaminant removal as a function of soil TOC and pH, and potentially other parameters, as necessary to optimize Source Area ISTR.

2) Contractor shall select a range of TOC plus TeCA locations including high TeCA locations to evaluate optimal Source Area ISTR: TOC ranging up to 500 mg/kg;

high TeCA should be > 50 mg/kg.

3) Contractor shall evaluate, at a minimum, three overburden locations. The highest

TOC values detected to date have been in the deep overburden at/near weathered bedrock.

4) Contractor shall identify number of samples needed to perform testing. Contractor shall indicate whether separate samples are required for the boiling and 146°C tests and any other tests Contractor identifies.

5) Contractor shall provide details on estimated sample volume required for testing and sample collection methodology.

6.5.2 Task 5.2 - ISTR Bench-Scale Testing Work Plan Execution

The Contractor shall complete bench-scale thermal treatment test(s) in accordance with the approved Final Bench-Scale Testing Work Plan to, at a minimum, identify extent of contaminant removal at both boiling (i.e., 100°C) and 146°C (i.e., the pure phase boiling point of TeCA). Results of the bench-scale testing will inform the thermal treatment approach for the Source Area ISTR (Option Task 6.0).

Requirements

1) Contractor shall track and report contaminant removal as a function of soil TOC and pH.

2) Contractor shall select a range of TOC plus high TeCA locations: TOC ranging up to

500mg/kg; high TeCA should be > 50 mg/kg.

3) Contractor shall evaluate, at a minimum, three overburden locations. The highest TOC values detected to date have been in the deep overburden at/near weathered bedrock.

4) Contractor shall identify number of samples needed to perform testing. Contractor shall indicate whether separate samples are required for the boiling and 146°C tests.

5) Contractor shall provide details on estimated sample volume required for testing and sample collection methodology.

Deliverables

1) The Contractor shall provide regular updates via progress memos to USACE regarding status, schedule, and interim results. At a minimum, progress memos will be submitted upon initiation of the testing; after the samples are heated to boiling temperatures; and upon achieving elevated temperature of (or near) 146°C.

2) The Contractor shall develop and submit a Bench-scale Test Report (Draft and

Final) summarizing the results, including recommendations and considerations for the updating the project CSM and Phase 1 remediation thermal treatment approach.

6.6 Option Task 6.0 – Phase 1 ISTR Thermal Conductive Heating Remedial Action Work Plan (RAWP) & Execution

NOTE – The Phase 1 ISTR shall be completed in compliance with all the requirements of Specification Section 02 61 18 (Attachment G), for the Phase 1 area only, and as defined below. Technical and schedule requirements in Task 6.0 that conflict with Specification Section 02 61 18, supersede the requirements of Specification Section 02 61 18 (which were written for the entire Source Area Remediation). Any references to other specifications called out in Specification Section 02 61 18 shall instead comply with the applicable sections in this PWS.

Contractor shall prepare a RAWP and execute the ISTR for the Phase 1 Thermal Treatment Zone (TTZ). The TTZ is a portion of the known and suspected PR-58 Source Area and contains CVOC contamination in both the overburden and bedrock. This Phase 1 ISTR will be the first phase of the Source Area remediation. The TTZ is depicted in modified Figure 10A from the DAR (Attachment E). The approximate dimensions of the Phase 1 TTZ are:

1) Area: 10,000 sq ft;

2) Treatment Depth: 0-55 ft bgs including bedrock and overburden. Depth of overburden is approximately 0-30 ft bgs; depth of bedrock approximately 30-55 ft bgs.;

3) Treatment Volume: 20,340 cy;

4) TTZ Perimeter: 430 ft.

Upon approval from USACE, the Contractor shall execute the Phase 1 ISTR in accordance with the final ISTR TCH RAWP, SAP-QAPP and all other relevant documents and guidelines identified in this PWS. Upon completion of the Phase 1 ISTR, the Contractor shall submit a Phase 1 ISTR Completion Report which presents the results of the Phase 1 remediation and lessons learned and recommendations for the subsequent phase(s) of the Source Area remediation.

Objectives of the Phase 1 ISTR

1) Achieve Site cleanup objectives (Attachment F) for overburden soil and bedrock groundwater.

2) Evaluate efficacy of, and lessons learned during, the Phase 1 ISTR.

3) Summarize results and make recommendations for subsequent phases of in situ thermal treatment. Including:

a. Establish requirements for subsequent completion of the Source Area remediation, including target temperature, energy and power demand, heating approach, and operational strategy for effective treatment of TeCA and TCE in overburden and bedrock.

b. Establish requirement(s) for and cost-effective method(s) to manage stormwater and mitigate infiltration in the vicinity of the ISTR thermal treatment zone for subsequent Source Area remediation phases.

6.6.1 Option Task 6.1 - ISTR TCH Phase 1 Remedial Action Work Plan

Note - Option Task 6.1 is a single execution Option Tasks that, if required, will be executed within eighteen (18) months of award of the Base Seed Task Order. If this Option Task is awarded, it will add 10-months to the Seed Task Order Period of Performance for this Task only.

The Contractor shall prepare and submit a Draft, Draft Final and Final Phase 1 ISTR TCH RAWP (Phase 1 RAWP) in accordance with the attached ISTR Specification Section 02 61 18 (Attachment G), Section 1.5, Remedial Action Work Plan, following the format requirements of the State of Rhode Island Rules and Regulations for the Investigation and Remediation of Hazardous Material releases (short title: Remediation Regulations). Data quality for the Phase 1 ISTR shall be governed by the data quality objectives for this work.

The data quality shall conform with the final SAP-QAPP prepared under Task 4.1 of this PWS, unless DQOs indicate other quality assurance procedures, in which case the SAP- QAPP shall be updated to include. The Contractor shall develop the Phase 1 RAWP upon substantial completion of the bench study (Task 5.2) to appropriately incorporate the results of the bench-scale testing into the Phase 1 ISTR design. The Phase 1 ISTR RAWP shall also be developed using hydrogeological and chemical testing results from previous investigation conducted at the Site as well as any additional relevant data collected during the execution of the Pre-Remediation Investigation (Task 4.2).

With this Phase 1 RAWP submittal, the contractor shall update the Project Schedule (per Task 2.0 of the IDIQ) to include detailed activities for Option Task 6, and update the APP in accordance with Section 6.3, above, as applicable, to include all activities being conducted during the Phase 1 ISTR.

In addition to the elements detailed in the ISTR Specification Section 02 61 18, the RAWP shall also include, but not be limited to, the following:

a) Heater well/electrode placement and design.

b) Groundwater monitoring well and soil sampling location placement and installation methods.

c) Summary of all permit requirements and applications. Permit status should be communicated during regular progress calls and reporting.

d) Develop and update as required a Temporary Site Facilities and ISTR Layout Plan, that includes, addresses and/or provides, but is not limited to, pertinent existing site features (roads, above and below ground utilities and infrastructure), TTZ, exclusion zone (if applicable), decontamination area, site trailer, cuttings and soil stockpile area (s), silt fence locations, environmentally or historically sensitive areas, buffer zones, IDW storage area (s), site access points, stormwater features, plan for traffic control and site security, etc.

e) Operation, maintenance, and monitoring (OM&M) plan for the ISTR system, that at a minimum, shall cover, include, or provide details on:

Purpose of the OM&M, ISTR system startup, shutdown and post…