This document provides details on a federal contract solicitation for repair work at the New Bedford Hurricane Barrier. The U.S. Army Corps of Engineers, New England District is seeking bids for repairs to the Fairhaven side sector gate, including replacement of 23 damaged fenders and a steel gate guide and strut. The period of performance is 125 days with an estimated budget between $500,000 and $1,000,000. The NAICS code is 237990 and the opportunity is set aside for small businesses. The response due date was extended to January 22, 2021. Repair work includes underwater inspection and debris removal, removal and replacement of fenders and gate components, and demonstration of repairs upon completion. Questions may be directed to the specified Contract Specialist by email.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidAbstract.pdf | ||
| Snap Sheet.pdf | ||
| W912WJ21B0004-0002.pdf | ||
| Virtual SIte Visit_no video.pptx | PPTX presentation | |
| Allision Repairs_Virtual Site Visit.mp4 | MP4 file | |
| Drawings.pdf | ||
| Specifications.pdf | ||
| W912WJ21B0004-Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is necessary to extend the bid opening date to 22 January 2021, provide the site visit attendee list, the site visit presentation and requests for information. All other aspects remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ21B0004
X 9B. DATED (SEE ITEM 11)
16-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Jan-2021
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912WJ21B0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
REQUESTS FOR INFORMATION
1. What is the percentage required for the Bid Bond? The percentage required for the Bid Bond is 20%.
2. Part BID GUARANTEE Under Section 00100 calls for wet stamped Bid Bonds to be delivered prior to the Bid Opening. Can you confirm this is in fact required and will confirmation of receipt be sent to the bidder, if so? Yes, this is a requirement. Confirmation of receipt will be sent to the bidder upon request.
3. Can you just confirm that a surety bond in the amount of 20% of the total contract price is the correct amount? Yes, the bond should be in the amount of 20% of the total contract price.
SITE VISIT ATTENDEES
1. Gaelen Magee – MAS Building& Bridge, Inc
2. Jonah Mikutowicz – AGM Marine Contrators, Inc
3. Mark Timmerman - AGM Marine Contrators, Inc
4. Russ Heinke – Mohawk Northeast, Inc
5. James Nichols – Underwater Construction
6. Phil Bower – Underwater Construction
7. John Macpherson – USACE
8. Adam Stewart – USACE
9. Heather Skorik - USACE
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 15-Jan-2021 01:00 PM to 22-Jan-2021 01:00 PM.
(End of Summary of Changes)