This is Attachment D to Request for Proposals No. DACA27-1-27-0015900, containing installation and property information for an Enhanced Use Lease opportunity at Blue Grass Army Depot (BGAD) in Richmond, Kentucky. The document provides a comprehensive overview of BGAD, a critical component of the Army's Organic Industrial Base established in 1941, which encompasses approximately 14,532 acres and operates the full spectrum of ammunition lifecycle operations including receipt, storage, distribution, maintenance, renovation, and demilitarization of conventional munitions. The installation features over 1,000 facilities, 902 earth-covered magazines, and 3.4 million square feet of covered storage capacity, with strategic location five minutes from Interstate 75, thirty minutes from Interstate 64 and Blue Grass Airport, and direct rail connectivity via CSX.
The available property for lease is Parcel 11, comprising approximately 358 acres located along BGAD's southern boundary outside primary ammunition mission areas and in proximity to existing infrastructure corridors. The parcel consists of rolling pasture, woodland, and intermittent drainage features with private rural and residential properties adjoining the southern perimeter. Electricity is available via a 69-kV transmission line and active substation on the eastern boundary; however, no natural gas, potable water, wastewater collection, or fiber infrastructure currently serves the property. Key considerations include karst limestone geology with potential subsurface voids, no active RCRA hazardous waste management units within the parcel, potential archaeological findings requiring Phase 1 surveys and Kentucky State Historic Preservation Office consultation, minor seasonal wetlands requiring coordination with USACE and Kentucky Division of Water, and bat habitat and avian species considerations affecting clearing and construction timing. The property is subject to Exclusive Federal Legislative Jurisdiction, and offerors should address civil matter enforcement through choice of law provisions.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment D Request for Proposals No. DACA27-1-27-0015900
BLUE GRASS ARMY DEPOT
MADISON COUNTY
RICHMOND, KENTUCKY
Installation Summary:
Established in 1941, Blue Grass Army Depot (BGAD) is a critical component of the Army's Organic Industrial Base and a premier conventional munitions Installation supporting Joint Force readiness. Located near Richmond, Kentucky, BGAD executes the full spectrum of ammunition lifecycle operations, including the receipt, storage, distribution, maintenance, renovation, and demilitarization of conventional munitions in support of Combatant Commands and military services worldwide.
BGAD encompasses approximately 14,532 acres of land and includes more than 1,000 facilities, 902 earth-covered magazines, and over 3.4 million square feet of covered storage capacity. The Installation's extensive land holdings, robust infrastructure, and required explosive safety quantity-distance buffers provide significant opportunities for mission growth, industrial partnerships, and strategic development while preserving operational readiness and safety.
The Installation's primary operational area, known as the Restricted Area, comprises approximately 13,175 acres of land and supports large-scale ammunition storage, maintenance, and demilitarization operations. BGAD also houses a state-of-the-art Consolidated Shipping Center, one of the most modern munitions shipping and receiving facilities within the Department of War, serving as a benchmark for efficiency and modernization across the Organic Industrial Base.
Strategically located in the eastern United States, BGAD offers exceptional access to national transportation networks. It is located five minutes from Interstate 75, thirty minutes from Interstate 64, and thirty minutes from Blue Grass Airport in Lexington, Kentucky. The Installation also maintains direct rail connectivity, enabling efficient movement of military and commercial freight while providing rapid access to major defense, manufacturing, and logistics corridors throughout the region.
As a secure federal Installation, BGAD maintains a robust physical security posture, including controlled access points, advanced surveillance systems, and dedicated protective forces. Combined with its strategic location, transportation infrastructure, available acreage, and long-term federal ownership, BGAD offers a uniquely secure and attractive environment for Enhanced Use Lease opportunities that support both Army objectives and private-sector investment.
Available Property:
The Property available for lease is approximately 358 acres of land referred to as Parcel 11.
Parcel Identifier Acreage
Parcel 11 358
Total 358
Parcel 11 is located along the Installation's southern boundary. It is located outside the Installation's primary ammunition mission areas and in proximity to existing infrastructure corridors.
Maps Identifying the Property:
The green and black perimeter line identifies the BGAD Installation boundary.
Multicolored arcs in the northern sector depict explosive safety distance (ESD) requirements associated with demolition-range facilities. The tan-shaded western area represents the open detonation range and its operational safety footprint.
Land Usage of the Property:
The Property consists of rolling pasture, woodland, and intermittent drainage features.
Private rural and residential properties adjoin the southern perimeter. Development planning should assess visual and lighting impacts, construction traffic, noise, stormwater runoff, and any necessary buffers or community coordination.
Utilities at Blue Grass Army Depot:
Electricity: KU and Blue Grass Energy Cooperative are identified as regional providers. A 69-kV transmission line crosses the Parcel. An active substation is located along the eastern boundary, and an easement to EKPC encumbers the Parcel.
Natural Gas: No natural-gas distribution line is identified within Parcel 11. Any gas-dependent generation or heating concept would require coordination with Delta Natural Gas or other potential providers.Water: Fort McCoy owns and operates its own well field and water treatment plant. There is no water infrastructure serving the Property.
Wastewater: No sanitary collection system or septic facilities are identified within Parcel 11. BGAD’s existing wastewater treatment plant has acceptance limitations.
Water: No potable or process-water distribution lines currently extend into Parcel 11.
Fiber: High-speed fiber service exists at BGAD but has not been extended to Parcel 11.
Considerations of the Property:
a. Parcel 11 is outside operational explosive safety arcs.
b. Parcel 11 lies within BGAD’s exterior security perimeter.
c. BGAD’s Main Gate supports approximately 500 personnel per day and has demonstrated throughput above 1,300 per day.
d. No known glint or glare constraints for Parcel 11 including lighting, reflective surfaces or rooftop equipment.
e. The area has regional karst limestone geology with potential subsurface voids.
f. In accordance with official BGAD environmental records and Kentucky Division of Waste Management (KDWM) Permit documentation (EPA ID KY8-213-820-105 / Permit KY0020737), there are currently no active, permitted RCRA hazardous waste management units (HWMUs), Solid Waste Management Units (SWMUs), or Areas of Concern (AOCs) located within Parcel 11.
g. Phase I reconnaissance identifies artifact scatters and potential Section 106 consultation with Kentucky State Historic Preservation Office. The eastern half of Parcel 11 has never been surveyed and would require a Phase 1 archaeological survey.
h. Minor seasonal wetlands and non-jurisdictional intermittent drainage features exist along southern swales and creek borders within the Parcel footprint; any required civil site modifications can be fully mitigated on-site in coordination with USACE regulatory guidelines. While the wetlands mitigation is within the jurisdiction of BGAD’s federal partner, USACE, can’t fully mitigate all concerns. Some level of coordination with KDOW will still be necessary.
i. Bat habitat monitoring, avian species considerations, and seasonal tree-clearing windows are identified. Species surveys and agency coordination may affect clearing limits, construction timing, and habitat mitigation requirements.
j. BGAD has a CSX-connected rail spur and approximately 41 miles of government-owned track. Rail may support selected construction or industrial logistics.
Legislative Jurisdiction of Blue Grass Army Depot:
The Property is subject to Exclusive Federal Legislative Jurisdiction. Exclusive legislative jurisdiction exists when the federal government acquires all of the state’s judicial, legislative and administrative authority, and the state concerned has not reserved to itself the right to exercise any of the authority concurrently with the federal government, except the right to serve state civil or criminal process for activities that occurred outside of the area. Since there are no federal general municipal laws, the state law in effect at the time such exclusive jurisdiction is acquired generally governs with respect to civil matters. The criminal laws of the state are generally adopted within areas of exclusive federal jurisdiction under 18 U.S.C. § 13 (the Assimilative Crimes Statute). As a result, laws governing both criminal offenses and certain civil matters may be ambiguous or non-existent in some cases. Offerors should therefore familiarize themselves with jurisdictional matters to best determine how to address the enforcement of civil matters on the Property, such as enforcement of contractual obligations, which may be addressed through choice of law provisions.