This document is a comprehensive Submittal Form for the Eglin AFB Medical Training Facility B3120 Design project, Amendment 0004. The solicitation is for a construction project involving a medical training facility, issued by the U.S. Army Corps of Engineers Engineering District Louisville under contract number W912QR-51061297. The submittal form covers an extensive range of technical specifications and requirements across multiple construction disciplines, including structural steel, aluminum windows, door hardware, and various building systems.

The document details specific submittal requirements for preconstruction documents, shop drawings, product data, samples, design data, test reports, certificates, and closeout submittals. Key areas of focus include safety requirements, structural components, architectural elements, mechanical and electrical systems, and quality control procedures. The submittal form provides a comprehensive framework for contractors to document compliance with technical specifications, with each section requiring detailed documentation on materials, fabrication methods, installation procedures, testing, and performance standards. The solicitation appears to be specifically targeted to Southeast Region MATOC (Multiple Award Task Order Contract) pool contract holders, with specification documents to be available by close of business on 24 April 2025.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912QR-51061297_CORRFinal_Specs-0004

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 68 PAGES

Eglin AFB Medical Training Facility B3120 Design - Amendment 0004

00 80 00.00 06 SD-01 Preconstruction Submittals

1.14 GLocal Agency Check

1.12SF1413 Statement and

Acknowledgement

1.32 GRadioactive Material/Equipment

SD-02 Shop Drawings

1.34 GMechanical/Electrical Room

Layout

SD-04 Samples

1.16 GEquipment Warranty Identification

Tags

SD-05 Design Data

1.37Progress Photographs

SD-07 Certificates

1.16Warranty of Construction

1.15 GNO ASBESTOS - CONTAINING

MATERIAL (ACM)

CERTIFICATION

1.15.2 GCertification for each individual

product installed and identified to contain mineral fibers that no asbestos-containing materials were installed

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 68 PAGES

00 80 00.00 06 1.15.2 GDocumentation to show that the products containing mineral fiber materials have been microscopically examined by an

AIHA- or NVLAP-certified laboratory and the lab has determined that the material does not contain asbestos

1.29Insurance

1.27Sales and Use Tax

SD-11 Closeout Submittals

1.7.4 GPreliminary (Working) As-Built

Drawings

1.7.1 GFinal As-Built Drawings

1.7.1.2 GCAD Working As-Built Drawings

1.9.1Equipment-in-Place List

1.9.1Maintenance and Parts Data

1.16 GWarranty Management Plan

01 32 01.00 06 SD-01 Preconstruction Submittals

1.3 GProject Scheduler Qualifications

3.4.1 GPreliminary Project Schedule

3.4.2 GInitial Project Schedule

3.6.2 GPeriodic Schedule Update

01 33 00 SD-01 Preconstruction Submittals

1.9 GSubmittal Register

01 33 29 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 68 PAGES

01 33 29 1.5.3.2 G SPreliminary High Performance and Sustainable Building Checklist

1.4.1 G SSustainability Action Plan

1.5.3.2 GPreliminary Sustainability

eNotebook

SD-11 Closeout Submittals

1.5.3.2 G SFinal High Performance and

Sustainable Building Checklist

1.5.3.2 GFinal Sustainability eNotebook

01 35 26.00 06 SD-01 Preconstruction Submittals

1.7Accident Prevention Plan (APP)

1.7Fatigue Management Plan

1.7Bloodborne Pathogen Plan

1.7Exposure Control Plan

1.7Automatic External Defibrillator

(AED) Program

1.7Site Layout Plan

1.7Access/Haul Road Plan

1.7Hearing Conservation Program

1.7Respiratory Protection Plan

1.7Health Hazard Control Program

1.7Hazard Communication Program

1.7Process Safety Management

Plan

1.7Lead Compliance Plan &

Specifications

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 68 PAGES

01 35 26.00 06 1.7Radiation Safety Program

1.7Abrasive Blasting Plan

1.7Heat Stress Monitoring Plan

1.7Cold Stress Monitoring Plan

1.7Indoor Air Quality Management

Plan

1.7Mold Remediation Plan

1.7Chromium (VI) Exposure

Evaluation

1.7Crystalline Silica Assessment

1.7Lighting Plan for Night Operations

1.7Traffic Control Plan

1.7Fire Prevention Plan

1.7Wild Land Fire Management Plan

1.7Arc Flash Hazard Analysis

1.7Assured Equipment Grounding

Control Program (AEGCP)

1.7Hazardous Energy Control Plan

1.7Standard Pre-Lift Plan (LHE)

1.7Critical Lift Plan - LHE

1.7Naval Architectural Analysis-LHE

(Floating)

1.7Floating Plant Inspection and

Certification

1.7Severe Weather Plan for Marine

Activities

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 68 PAGES

01 35 26.00 06 1.7Emergency Plan for Marine

Activities

1.7Man Overboard/Abandon Ship

Procedures

1.7Float Plan for Launches, Motorboats, Skiffs

1.7Fall Protection and Prevention

Plan

1.7Demolition/Renovation Plan (to include engineering survey)

1.7Rope Access Work Plan

1.7Excavation/Trenching Plan

1.7Fire Prevention & Protection Plan for Underground Construction

1.7Compressed Air Plan for

Underground Construction

1.7Erection and Removal Plan for

Formwork and Shoring

1.7PreCast Concrete Plan

1.7Lift-Slab Plans

1.7Masonry Bracing Plan

1.7Steel Erection Plan

1.7Explosives Safety Site Plan

(ESSP)

1.7Blasting Plan

1.7Dive Operations Plan

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 68 PAGES

01 35 26.00 06 1.7Safe Practices Manual for Diving

Activities

1.7Emergency Management Plan for

Diving

1.7Tree Felling/Maintenance

Program

1.7Aircraft/Airfield Construction

Safety & Phasing Plan (CSPP)

1.7Aircraft/Airfield Safety Plan

Compliance Document (SPCD)

1.7Site Safety and Health Plan

(HTRW)

1.7Confined Space Entry

Procedures

1.7Confined Space Program

1.8 G ROActivity Hazard Analysis (AHA)

1.5.1.1 G ROSite Safety and Health Officer

Qualifications(SSHO)

1.12.7 G ROProof of qualification for Crane

Operators

1.12.7 G ROCritical Lift Plan

SD-06 Test Reports

1.12Reports

1.12.1Accident Reports

1.12.3Monthly Exposure Reports

1.12.5Crane Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 68 PAGES

01 35 26.00 06 1.12.4Regulatory Citations and

Violations

SD-07 Certificates

1.12.8Confined Space Entry Permit

1.13Hot work permit

1.12.6Crane Certificate of Compliance

01 45 04.10 06 SD-01 Preconstruction Submittals

3.3 G ROConstruction Quality Control Plan

01 45 35 SD-01 Preconstruction Submittals

3.1 GProject Manual

SD-06 Test Reports

3.1Daily Reports

3.1Biweekly Reports

3.1.1Biweekly Reports

SD-07 Certificates

2.1AISC Certified Steel Fabricator

2.1Steel Truss Plant Quality

Assurance Program

2.1Certificate of Compliance

1.5 GSpecial Inspector of Record

Qualifications

1.5 GSpecial Inspector

SD-11 Closeout Submittals

3.1 GComprehensive Final Report

01 46 00.00 06 SD-01 Preconstruction Submittals

1.4 G DOCommissioning Specialists

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 68 PAGES

01 46 00.00 06 1.4.4 G DOCommissioning Specialists

1.9 G DOProject Schedule

SD-06 Test Reports

3.1.3 G DOConstruction Phase

Commissioning Plan

3.1.6.2 G DOBuilding Envelope Inspection

Checklists

3.1.6.2 G DOBuilding Envelope Inspection

Checklists

3.1.6.3 G DOPre-Functional Checklists

1.7Issues Log

3.1.6.6Trend Log Report

3.8.1Post-Construction Trend Log

Report

3.7 G DOCommissioning Report

3.8 G DOPost-Construction

Commissioning Report

SD-07 Certificates

1.8 G DOCertificate of Readiness

SD-10 Operation and Maintenance

Data

3.2 G DOSystems Training

3.3 G ROTraining Plan

3.3 G ROTraining Attendance Rosters

3.4 G DOSystems Manual

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 68 PAGES

01 46 00.00 06 3.8 G DOPost-Construction Systems

Manual

3.5 G DOMaintenance and Service Life

Plans

SD-11 Closeout Submittals

1.6 S DOFinal Commissioning Report

1.6 SFinal Construction Phase

Commissioning Plan

01 50 00 SD-01 Preconstruction Submittals

1.3 GConstruction Site Plan

3.4.1 GTraffic Control Plan

1.6.1.4 GContractor Computer

Cybersecurity Compliance

Statements

1.6.6 GContractor Temporary Network

Cybersecurity Compliance

Statements

SD-03 Product Data

1.4 GBackflow Preventers

SD-06 Test Reports

3.5Backflow Preventer Tests

SD-07 Certificates

1.4.1Backflow Tester

1.4Backflow Preventers

01 57 19.00 06 SD-01 Preconstruction Submittals

1.6.1Preconstruction Survey

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 68 PAGES

01 57 19.00 06 1.11 GSolid Waste Management Permit

1.6.2 GRegulatory Notifications

1.7 GEnvironmental Protection Plan

1.7.9.1 GDirt and Dust Control Plan

1.6.5 GEmployee Training Records

1.6.4 GEnvironmental Manager

Qualifications

3.17 GNotice of Soil Treatment

SD-06 Test Reports

3.7.2.1 GSolid Waste Management Report

SD-07 Certificates

1.6.5 GEmployee Training Records

1.6.5.1Certificate of Competency

SD-11 Closeout Submittals

3.7.1 GWaste Determination

Documentation

3.7.4.6 GDisposal Documentation for

Hazardous and Regulated Waste

1.6.5 GAssembled Employee Training

Records

1.11 GSolid Waste Management Permit

3.7.2.1 GSolid Waste Management Report

3.7.4.1 GHazardous Waste/Debris

Management

1.6.2 GRegulatory Notifications

3.7.2.1 GSales Documentation

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 68 PAGES

01 74 19 SD-01 Preconstruction Submittals

1.6 GConstruction Waste Management

Plan

SD-06 Test Reports

1.8.2Quarterly Reports

1.8.3Annual Report

SD-11 Closeout Submittals

1.9 SFinal Construction Waste

Diversion Report

01 78 23 SD-10 Operation and Maintenance

Data

3.1.1 GTraining Plan

3.1.3 GTraining Outline

3.1.2 GTraining Content

SD-11 Closeout Submittals

3.1.4 GTraining Video Recording

3.1.6 GValidation of Training Completion

02 41 00 SD-01 Preconstruction Submittals

1.2.2 GDemolition Plan

1.9Existing Conditions

SD-07 Certificates

1.6 GNotification

03 30 00 SD-01 Preconstruction Submittals

1.6.3.1Concrete Curing Plan

1.6.5 GQuality Control Program

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 68 PAGES

03 30 00 1.6.6 GQuality Control Personnel

Certifications

1.6.6Quality Control Organizational

Chart

1.6.8 GLaboratory Accreditation

SD-02 Shop Drawings

1.6.2.1 GReinforcing Steel

SD-03 Product Data

2.4.5Joint Sealants

2.4.4Joint Filler

2.1Formwork Materials

2.3.1Cementitious Materials

2.4.6Vapor Barrier

2.4.1Concrete Curing Materials

2.6Reinforcement

2.3.4Admixtures

2.6.4Reinforcing Fibers

2.6.2Mechanical Reinforcing Bar

Connectors

1.8.1Local/Regional Materials

2.2.2Biodegradable Form Release

Agent

1.6.3.2Pumping Concrete

2.4.2Nonshrink Grout

SD-05 Design Data

1.6.1.1 GConcrete Mix Design

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 68 PAGES

03 30 00 SD-06 Test Reports

1.6.1.1 GConcrete Mix Design

1.6.4.1Fly Ash

1.6.4.1Pozzolan

1.6.4.2Slag Cement

1.6.4.3Aggregates

1.6.4.4 GFiber-Reinforced Concrete

3.9.2.1Tolerance Report

3.13.3.3 GCompressive Strength Tests

3.13.3.5Unit Weight of Structural

Concrete

3.13.3.6Chloride Ion Concentration

3.13.3.4Air Content

3.13.3.1Slump Tests

2.3.2Water

SD-07 Certificates

2.6.1Reinforcing Bars

1.9Welder Qualifications

1.6.3.3VOC Content for Form Release

Agents, Curing Compounds, and

Concrete Penetrating Sealers

1.6.3.4Safety Data Sheets

1.8.2Forest Stewardship Council

(FSC) Certification

1.6.6.2Field Testing Technician and

Testing Agency

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 68 PAGES

03 30 00 SD-08 Manufacturer’s Instructions

2.4.5Joint Sealants

2.4.1Curing Compound

03 42 13.00 10 SD-01 Preconstruction Submittals

1.3.2.2Quality Control Procedures

SD-02 Shop Drawings

2.1.1 GStandard Precast Units

2.1.2 GCustom-Made Precast Units

3.2.4.3Special Finishes

SD-03 Product Data

2.1.1Standard Precast Units

2.1.3Proprietary Precast Units

3.1.3Embedded Items

2.2.6Accessories

SD-05 Design Data

2.1.2 GDesign Calculations

2.1.5.1Concrete Mix Proportions

SD-06 Test Reports

1.3.2.4Test Reports

SD-07 Certificates

1.3.2.2Quality Control Procedures

SD-11 Closeout Submittals

2.2.1 SRecycled content for fly ash and

pozzolan

2.2.1 SRecycled content for Ground Iron

Blast-Furnace Slag

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 68 PAGES

03 42 13.00 10 2.2.1 SRecycled content for Silica Fume

2.2.1 SRecycled content for Synthetic

Fiber Reinforcement

2.2.1 SRecycled content for steel

04 20 00 SD-02 Shop Drawings

GCut CMU

GDetail Drawings

SD-03 Product Data

1.5.1 GHot Weather Procedures

2.2.2 GClay or Shale Brick

2.3.1.2 GCement

2.3.1.1 GCementitious Materials

SD-04 Samples

GCMU Veneer

2.2.2 GClay or Shale Brick

SD-05 Design Data

2.1.1 GMasonry Compressive Strength

3.2.5 GBracing Calculations

SD-06 Test Reports

2.2.2.1.4Efflorescence Test

3.6.1.2Prism Tests

SD-07 Certificates

1.3.1Special Masonry Inspector

Qualifications

2.2.2Clay or Shale Brick

Concrete Masonry Units (CMU)

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 68 PAGES

04 20 00 2.2.4Precast Concrete Units

2.3.1.1Cementitious Materials

2.3.1.5Admixtures for Masonry Mortar

2.5.3Joint Reinforcement

SD-08 Manufacturer’s Instructions

2.3.1.5Admixtures for Masonry Mortar

SD-10 Operation and Maintenance

Data

3.8Take-Back Program

SD-11 Closeout Submittals

2.2.2.1.3 SClay Units

05 12 00 SD-01 Preconstruction Submittals

1.4.1.1 GErection and Erection Bracing

Drawings

SD-02 Shop Drawings

1.4.2 GFabrication Drawings

SD-03 Product Data

2.5.2Shop Primer

2.4.1Welding Electrodes and Rods

2.3.1.3Direct Tension Indicator Washers

2.4.2Non-Shrink Grout

2.3.2Tension Control Bolts

2.2.1 SRecycled Content for Structural

Steel

2.2.2 SRecycled Content for Structural

Steel Tubing

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 68 PAGES

05 12 00 2.2.3 SRecycled Content for Steel Pipe

SD-05 Design Data

1.4.3 GDesign Calculations for Steel

Connections

SD-06 Test Reports

2.5.2Class B Coating

2.3Bolts, Nuts, and Washers

3.6.2.1Direct Tension Indicator Washer

Inspection Reports

3.6.3.1Bolt Testing Reports

SD-07 Certificates

2.2Steel

2.3Bolts, Nuts, and Washers

AISC Structural Steel Fabricator

Quality Certification

AISC Structural Steel Erector

Quality Certification

1.4.4.1Welding Procedures and

Qualifications

2.4.1Welding Electrodes and Rods

3.6.1.1Certified Welding Inspector

3.4Welding Procedure Specifications

(WPS)

05 30 00 SD-02 Shop Drawings

1.3.4 GFabrication Drawings

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 68 PAGES

05 30 00 2.2Accessories

2.1Deck Units

2.1.3Galvanizing Repair Paint

2.2.12Mechanical Fasteners

2.1.3Touch-Up Paint

2.1 SRecycled Content of Steel

Products

SD-05 Design Data

2.1 GDeck Units

SD-07 Certificates

1.3.2Powder-Actuated Tool Operator

1.3.3.1Wind Storm Resistance

1.3.1Manufacturer's Certificate

05 40 00 SD-02 Shop Drawings

1.6.1 GFraming Components

SD-03 Product Data

2.1Studs, Joists

2.1 SRecycled Content of Steel

Products

SD-05 Design Data

1.6.2 GMetal Framing Calculations

SD-07 Certificates

1.4Load-Bearing Cold-Formed Metal

Framing

3.2.1Welds

05 50 13 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 68 PAGES

05 50 13 2.5 GExpansion Joint Covers

2.4 GCanopies

2.6 GAngles and Plates

SD-03 Product Data

2.5 GExpansion Joint Covers

2.4 GCanopies

2.1 SRecycled Content

SD-04 Samples

2.5Expansion Joint Covers

2.4 GCanopy Color Chip

SD-05 Design Data

2.4 GCanopy Calculations

SD-07 Certificates

2.1 GCertificates of Compliance

SD-11 Closeout Submittals

GCanopy Warranty

06 10 00 SD-02 Shop Drawings

2.4.1.1 GNailing Strips

SD-03 Product Data

1.8Fire-retardant Treatment

SD-06 Test Reports

1.4.3Preservative-treated

SD-07 Certificates

1.11.1Certificates of Grade

2.2.1 SCertified Sustainably Harvested

Framing Lumber

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 68 PAGES

06 10 00 2.3.1.1 SCertified Sustainably Harvested

Plywood for Other Uses

1.7Preservative Treatment

06 41 16.00 10 SD-02 Shop Drawings

2.9Shop Drawings

3.1Installation

SD-03 Product Data

2.1Wood Materials

2.9.7.3Finish Schedule

SD-04 Samples

2.3Plastic Laminates

2.6Cabinet Hardware

SD-07 Certificates

1.5.2Sustainable Design Certification

1.5Quality Assurance

3.1Laminate Clad Casework

06 61 16 SD-02 Shop Drawings

3.1 GInstallation

SD-03 Product Data

2.1.1 GSolid Polymer

2.2.2 SIndoor air quality for solid surface

seam and sealant products

SD-04 Samples

2.1 GMaterial

2.3.4 GCountertops

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 68 PAGES

06 61 16 2.1.1Test Report Results

SD-07 Certificates

1.4.1Qualifications

2.1.1 SIndoor Air Quality for solid

surface fabrication products

SD-10 Operation and Maintenance

Data

2.1.1 GSolid Polymer

07 21 13 SD-03 Product Data

1.3 GManufacturer's Standard Details

2.1 GBlock or Board Insulation

2.3 GAccessories

2.1.4 SRecycled Content for Block or

Board Insulation

SD-07 Certificates

2.1 GBlock or Board Insulation

1.8.2 GDraft Special Warranty

1.8.2 GFinal Special Warranty

2.1.5 SIndoor Air Quality For Block Or

Board Insulation

SD-08 Manufacturer’s Instructions

2.3.1Adhesive

2.1Block or Board Insulation

07 21 16 SD-03 Product Data

2.1 GBlanket Insulation

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 68 PAGES

07 21 16 2.1.1 SRecycled Content for Insulation

Materials

2.3Accessories

SD-07 Certificates

SIndoor Air Quality for Insulation

Materials

2.3.1 SIndoor Air Quality for Adhesives

SD-08 Manufacturer’s Instructions

3.3.1Insulation

07 22 00 SD-02 Shop Drawings

1.3 GInsulation Board Layout

1.3 GVerification of Existing Conditions

SD-03 Product Data

2.1 GInsulation

1.4 GCover Board

2.3 GFasteners

2.1.2 SRecycled Content For Insulation

SD-05 Design Data

1.7 GWind Resistance

SD-06 Test Reports

1.8.1 GFlame Spread Rating

SD-07 Certificates

1.6 GInstaller Qualifications

2.1.3 SIndoor Air Quality For Insulation

SD-08 Manufacturer’s Instructions

2.3 GFasteners

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 68 PAGES

07 22 00 2.1 GInsulation

07 27 10 SD-02 Shop Drawings

2.1 GAir Barrier System Shop

Drawings

SD-03 Product Data

2.1 GAir Barrier System Product Data

SD-04 Samples

3.1.2 GMock-Up

2.1 GMaterial Samples For Air Barrier

System

SD-05 Design Data

1.8 GDesign Data And Calculations

For The Air Barrier System

SD-06 Test Reports

1.8 GDesign Review Report

3.1.3 GTesting and Inspection

SD-07 Certificates

1.7 G ROAir Barrier Inspector

07 27 19.01 SD-01 Preconstruction Submittals

1.7.1 GQualifications of Manufacturer

1.7.2 GQualifications of Installer

SD-02 Shop Drawings

1.4.1 GSelf-adhering Air Barrier Shop

Drawings

SD-03 Product Data

2.1 GSelf-adhering Air Barrier

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 68 PAGES

07 27 19.01 2.2 GPrimers, Adhesives, and Mastics

1.4.2 GSafety Data Sheets

SD-04 Samples

1.4.3 GSelf-adhering Air Barrier System

Mockup

SD-06 Test Reports

1.7.3 GField Peel Adhesion Test

1.4.4 GFlame Propagation of Wall

Assemblies

GFlame Spread and Smoke

Developed Index Ratings

3.4.1 GSite Inspections and Testing

SD-08 Manufacturer’s Instructions

1.4.2 GSelf-adhering Air Barrier

Manufacturer's Printed Instructions

2.2 GPrimers, Adhesives, and Mastics

07 27 26 SD-01 Preconstruction Submittals

1.9.1 GQualifications of Manufacturer

1.9.2 GQualifications of Installer

SD-02 Shop Drawings

1.4.1 GFluid-Applied Membrane Air

Barrier Shop Drawings

SD-03 Product Data

1.4 GFluid-Applied Membrane Air

Barrier

2.3 GTransition Membrane

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 68 PAGES

07 27 26 2.2 GPrimers, Adhesives, and Mastics

2.6 GReinforcement

1.4.2 GSafety Data Sheets

SD-04 Samples

1.4.3 GMockup

SD-06 Test Reports

1.6 GCapillary Moisture Test

1.4.4 GField Peel Adhesion Test

1.4.4 GFlame Propagation of Wall

Assemblies

3.4.1 GSite Inspections

SD-08 Manufacturer’s Instructions

1.4 GFluid-Applied Membrane Air

Barrier

2.2 GPrimers, Adhesives, and Mastics

07 27 36 SD-01 Preconstruction Submittals

1.10.1 GQualification of Manufacturer

1.10.2 GQualification of Installer

1.11 GQuality Control Plan

1.11 GSafety Plan

1.9.1 GFire Prevention Plan

1.9.2 GRespiratory Protection Plan

SD-02 Shop Drawings

1.5.1Spray Foam Air Barrier System

Shop Drawings

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 68 PAGES

07 27 36 2.1.1 GClosed Cell

2.2 GTransition Membrane

2.3 GPrimers, Adhesives, and Mastics

2.5 GSealants

1.5.2 GSafety Data Sheets

2.1.1 GThermal Barrier Materials

2.1.1 GIgnition Barrier Coatings

2.1.1 GAccessories

2.1.2 SRecycled Content for Closed Cell

Spray Foam Air Barrier

SD-04 Samples

1.5.3 GSpray Foam Air Barrier Mockup

SD-06 Test Reports

1.5.4 GPeel Adhesion Test

3.4.5.1 GThermographic Test

1.8 GAir Barrier Test

1.5.4 GFire-Ratings Of Thermal/Ignition

Barrier Materials

1.5.4 GFlame Spread and Smoke

Developed Index Ratings of SPF

Products

1.5.4 GFlame Propagation of Wall

Assemblies

3.4.1 GSite Inspections

SD-07 Certificates

2.1.1 GClosed Cell

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 68 PAGES

07 27 36 2.2 GTransition Membrane

2.1.5 SIndoor Air Quality for Spray Foam

Air Barrier

SD-08 Manufacturer’s Instructions

1.6.1 GSPF Handling, Storage, and

Spray Procedures

3.2.1 GSubstrate Preparation

1.5.2 GThermal Barrier

1.12.3 GIgnition Barrier

2.2 GTransition Membrane

2.3 GPrimers, Adhesives, and Mastics

SD-09 Manufacturer’s Field

Reports

1.11 GCore Samples

3.3.3 GDaily Work Record

3.4.5 GVisual Inspection and Thermal

Scanning

07 60 00 SD-02 Shop Drawings

3.1.3 GExpansion Joints

3.1.1 GCounterflashing

2.1 SRecycled Content

SD-08 Manufacturer’s Instructions

1.4.3 GInstructions for Installation

3.5 GQuality Control Plan

SD-10 Operation and Maintenance

Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 68 PAGES

07 60 00 1.4.3 GCleaning and Maintenance

07 61 14.00 20 SD-02 Shop Drawings

1.2.5 GRoofing

GFlashing and Accessories

GGutter/Downspout Assembly

SD-03 Product Data

2.1 GRoofing Panels

2.6 GUnderlayment

2.1 SEnergy Star Label for Steel

Roofing Product

2.1.1 SRecycled Content for Steel

Roofing Product

2.3Attachment Clips

2.4.1Closures

2.4Accessories

2.4.2Fasteners

2.4.3Sealants

1.7 GWarranty

SD-04 Samples

2.1Panel

2.4Accessories

2.4.3Sealants

2.2Intermediate Support

SD-05 Design Data

1.5Design Calculations

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 68 PAGES

07 61 14.00 20 3.6Field Inspection

1.3.3Structural Performance

1.6.6Finish

SD-07 Certificates

1.6.3Manufacturer's Technical

Representative

1.6.4Installer's Qualifications

SD-08 Manufacturer’s Instructions

3.3 GInstallation

SD-11 Closeout Submittals

3.8Information Card

1.7Warranty

07 92 00 SD-03 Product Data

2.1 GSealants

2.2 GPrimers

2.3 GBond Breakers

2.4 GBackstops

SD-06 Test Reports

3.1 GField Adhesion

SD-07 Certificates

2.1.1 SIndoor Air Quality For Interior

Sealants

2.1.3 SIndoor Air Quality For Interior

Floor Joint Sealants

2.1.4 SIndoor Air Quality For Interior

Acoustical Sealants

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 68 PAGES

07 92 00 2.5 SIndoor Air Quality For Interior

Caulking

08 11 13 SD-02 Shop Drawings

2.1 GDoors

2.1 GDoors

2.4 GFrames

2.4 GFrames

2.2Accessories

SD-03 Product Data

2.1 GDoors

2.1 SRecycled Content for Steel Door

Product

2.4 GFrames

2.4 SRecycled Content for Steel Frame

Product

2.2Accessories

08 31 00 SD-03 Product Data

1.3 GAccess Doors And Panels

1.3.1 GHardware

2.2.5 GAccessories

2.1 SRecycled Content

08 41 13 SD-01 Preconstruction Submittals

1.2.1 GSample Warranty

1.2.1 GList of Product Installations

SD-02 Shop Drawings

3.3 GInstallation Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 68 PAGES

08 41 13 2.2 GFabrication Drawings

SD-03 Product Data

1.2.1 GManufacturer's Catalog Data

2.2.3 GFinish

2.1.1.2 SRecycled Content of Aluminum

Material

SD-04 Samples

1.2.1 GFinish and Color Samples

SD-06 Test Reports

1.2.1 GCertified Test Reports

1.4.3.3Deflection

1.4.3.1Air Infiltration

1.4.3.4Condensation Resistance and

Thermal Transmittance

1.4.3.5Water Infiltration

SD-08 Manufacturer’s Instructions

3.3Manufacturer's Instructions

SD-11 Closeout Submittals

3.6Manufacturer's Product Warranty

08 51 13 SD-02 Shop Drawings

2.1 GWindows

1.7Fabrication Drawings

SD-03 Product Data

2.1 GWindows

2.1 SRecycled Content of Aluminum

Windows

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 68 PAGES

08 51 13 2.2.2 GFasteners

1.8 GWindow Performance

2.3 GThermal-Barrier Windows

2.2.5 GAccessories

2.2.3Adhesives

1.8.4 GThermal Performance

SD-04 Samples

1.3.3.1Finish Sample

1.3.3.2Window Sample

SD-05 Design Data

2.1 GStructural Calculations for

Deflection

1.3.4 GDesign Analysis

SD-06 Test Reports

1.3.5Minimum Condensation

Resistance Factor

1.8.6Windborne-Debris-Impact

Performance

SD-10 Operation and Maintenance

Data

2.1 GWindows

1.5Plastic Identification

08 71 00 SD-02 Shop Drawings

1.3 GManufacturer's Detail Drawings

1.3 GVerification of Existing Conditions

1.5 GHardware Schedule

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 68 PAGES

08 71 00 2.3.5 GKeying System

SD-03 Product Data

2.3 GHardware Items

SD-08 Manufacturer’s Instructions

3.1Installation

SD-10 Operation and Maintenance

Data

1.5 GHardware Schedule

SD-11 Closeout Submittals

1.6.1Key Bitting

08 81 00 SD-03 Product Data

2.2 GInsulating Glass

1.3Glazing Accessories

2.3.3.1Sealants

2.3.4Joint Backer

SD-04 Samples

2.2 GInsulating Glass

SD-07 Certificates

2.2Insulating Glass

SD-08 Manufacturer’s Instructions

2.3Setting and Sealing Materials

3.2Glass Setting

SD-11 Closeout Submittals

1.7.1Insulated Glass Units

08 91 00 SD-02 Shop Drawings

1.4 GWall Louvers

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 68 PAGES

08 91 00 SD-03 Product Data

2.2 GMetal Wall Louvers

SD-04 Samples

1.5 GWall Louver Samples

09 22 00 SD-02 Shop Drawings

2.1 GMetal Support Systems

SD-03 Product Data

2.1Metal Support Systems

2.1 SRecycled Content for Metal

Support Systems

09 29 00 SD-03 Product Data

2.1.3Glass Mat Water-Resistant

Gypsum Tile Backing Board

2.1.2Water-Resistant Gypsum Backing

Board

2.1.4Glass Mat Covered or Reinforced

Gypsum Sheathing

2.1.4.1Glass Mat Covered or Reinforced

Gypsum Sheathing Sealant

2.1.8Accessories

2.1.1Gypsum Board

2.1.1 SRecycled Content for Gypsum

Board

2.1.1 SRecycled Content for Paper

Facing and Gypsum Cores

2.1.5 SVOC Content of Joint Compound

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 68 PAGES

09 29 00 SD-07 Certificates

2.1 GAsbestos Free Materials

2.1.1 SIndoor Air Quality for Gypsum

Board

2.1.7 SIndoor Air Quality for Non-aerosol

Adhesives

2.1.7 SIndoor Air Quality for Aerosol

Adhesives

SD-08 Manufacturer’s Instructions

2.1Safety Data Sheets

SD-10 Operation and Maintenance

Data

2.1Manufacturer Maintenance

Instructions

09 30 10 SD-02 Shop Drawings

3.2 GDetail Drawings

SD-03 Product Data

2.1.1 GPorcelain Tile

2.1.1 SRecycled Content for Porcelain

Tile

2.1.2 GGlazed Ceramic Wall Tile

2.1.2 SRecycled Content for Glazed

Ceramic Wall Tile

2.1 GTransition Strips

2.6.1 GTransition Strips

2.2 GSetting-Bed

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 68 PAGES

09 30 10 2.4 GMortar, Grout, and Adhesive

2.2.6Reinforcing Wire Fabric

SD-04 Samples

2.1 GTile

2.1 GAccessories

2.1 GTransition Strips

2.6.1 GTransition Strips

2.4.2 GGrout

SD-07 Certificates

2.4 SIndoor Air Quality for Adhesives

2.4.3 SIndoor Air Quality for Sealants

SD-08 Manufacturer’s Instructions

3.8Manufacturer's Approved

Cleaning Instructions

SD-10 Operation and Maintenance

Data

2.1.1 GPorcelain Tile

2.1.2 GGlazed Ceramic Wall Tile

09 51 00 SD-02 Shop Drawings

2.1 GDrawings

SD-03 Product Data

2.1 GAcoustical Ceiling System

2.2.1.1 SRecycled Content for Type IV

Ceiling Tiles

2.3 SRecycled Content for Suspension

Systems

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 68 PAGES

09 51 00 2.1.1 GAcoustical Performance

SD-04 Samples

2.2 GAcoustical Units

2.2.1.1 GAcoustical Ceiling Tiles

SD-07 Certificates

2.2.1.1 SIndoor Air Quality for Type IV

Ceiling Tiles

SIndoor Air Quality for Adhesives

SIndoor Air Quality for Sealants

09 65 00 SD-02 Shop Drawings

2.7 GResilient Flooring and

Accessories

SD-03 Product Data

2.7 GResilient Flooring and

Accessories

2.3Adhesives

2.1Luxury Vinyl Tile

2.1 SRecycled content for Luxury Vinyl

Tile

2.2Wall Base

SD-04 Samples

2.7 GResilient Flooring and

Accessories

SD-06 Test Reports

3.3 GMoisture, Alkalinity and Bond

Tests

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 68 PAGES

09 65 00 SD-07 Certificates

2.2 SIndoor Air Quality for Wall Base

2.3 SIndoor Air Quality for Adhesives

SD-08 Manufacturer’s Instructions

3.2Surface Preparation

3.1Installation

SD-10 Operation and Maintenance

Data

2.7 GResilient Flooring and

Accessories

09 68 00 SD-02 Shop Drawings

3.4 GInstallation Drawings

SD-03 Product Data

2.1 GCarpet

2.1.1 SRecycled Content for Carpeting

2.4 GMoldings

2.3 SIndoor Air Quality for Aerosol

Adhesives

2.3 SIndoor Air Quality for Non-Aerosol

Adhesives

2.3 SIndoor Air Quality for Concrete

Primer

SD-04 Samples

2.1 GCarpet

2.4 GMoldings

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 68 PAGES

09 68 00 3.2Moisture and Alkalinity Tests

SD-07 Certificates

2.1.2 SIndoor Air Quality for Carpet

SD-08 Manufacturer’s Instructions

3.1Surface Preparation

SD-10 Operation and Maintenance

Data

3.5Cleaning and Protection

3.7.2Maintenance Service

SD-11 Closeout Submittals

1.6Warranty

09 84 20 SD-02 Shop Drawings

2.2 GApproved Detail Drawings

SD-03 Product Data

3.2Installation

2.2 GAcoustical Wall Panels

SD-04 Samples

2.2 GAcoustical Wall Panels

SD-07 Certificates

2.2Acoustical Wall Panels

SD-11 Closeout Submittals

1.4Warranty

09 90 00 SD-02 Shop Drawings

3.8Piping Identification

SD-03 Product Data

2.1 GCoating

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 40 OF 68 PAGES

09 90 00 2.1Product Data Sheets

Sealant

SD-04 Samples

2.2 GColor

SD-07 Certificates

1.6.5.2 GQualification Testing

1.6.4Indoor Air Quality for Paints and

Primers

SD-08 Manufacturer’s Instructions

2.1Mixing

1.8.1Manufacturer's Safety Data

Sheets

SD-10 Operation and Maintenance

Data

2.1 GCoatings

10 14 00.20 SD-02 Shop Drawings

1.4.2 GDetail Drawings

SD-03 Product Data

2.1 GRoom Identification and

Directional Signage System

SD-04 Samples

1.4.1 GInterior Signage

1.3 GSoftware

2.1 GRoom Identification and

Directional Signage System

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 41 OF 68 PAGES

10 14 00.20 SD-10 Operation and Maintenance

Data

3.1 GApproved Manufacturer's

Instructions

3.1.2 GProtection and Cleaning

10 14 53 SD-03 Product Data

2.1Traffic Sign Posts

2.3Traffic Sign Retroreflective

Sheeting

10 26 00 SD-02 Shop Drawings

2.2 GCorner Guards

SD-03 Product Data

2.2 GCorner Guards

2.2.1 SRecycled content for aluminum

component of corner guards

SD-04 Samples

2.2 GCorner Guards

SD-06 Test Reports

2.1.1.2Fire Resistance Rating

SD-07 Certificates

2.4 SIndoor air quality for adhesives

10 28 13 SD-02 Shop Drawings

2.1 GProduct Schedule

SD-03 Product Data

2.1 SRecycled content for stainless

steel toilet accessories

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 42 OF 68 PAGES

10 28 13 2.1.3 GCombination Paper Towel

Dispenser/Waste Receptacle

2.1.4 GItem A5109

2.1.5 GItem A5200

2.1.6 GSoap Dispenser, Surface

Mounted

SD-10 Operation and Maintenance

Data

2.1.3 GCombination Paper Towel

Dispenser/Waste Receptacle

2.1.4 GItem A5109

2.1.5 GItem A5200

2.1.6 GSoap Dispenser, Surface

Mounted

10 44 16 SD-02 Shop Drawings

2.1.1 GFire Extinguishers

Part 2 GAccessories

Part 2 GCabinets

1.5 GSchedule

SD-03 Product Data

2.1.1 GFire Extinguishers

Part 2 GAccessories

Part 2 GCabinets

3.2.1 GReplacement Parts List

SD-04 Samples

1.3.1 GEquipment Samples

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 43 OF 68 PAGES

10 44 16 SD-07 Certificates

2.1.1 GFire Extinguishers Certifications

1.4 GManufacturer's Warranty with

Inspection Tag

12 21 00 SD-02 Shop Drawings

3.2Installation

SD-03 Product Data

2.1 GWindow Blinds

2.1 SRecycled Content for aluminum

components

SD-04 Samples

2.1 GWindow Blinds

SD-06 Test Reports

2.1Window Blinds

SD-07 Certificates

2.1 SIndoor Air Quality for window

blinds

2.1 SIndoor Air Quality for window

blinds

SD-08 Manufacturer’s Instructions

2.1 GWindow Blinds

SD-10 Operation and Maintenance

Data

2.1 GWindow Blinds

22 00 70 SD-02 Shop Drawings

3.11.1…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .