W912QR-51061297_CertFinal_Specs_Vol2-0008.pdf
PDF 8 MB Posted
- Solicitation number
- W912QR-51061297
About this file
This document is a detailed specification section (Section 01 46 00.00 06) for Total Building Commissioning for a Medical Training Facility project at Eglin Air Force Base. The project involves constructing an addition to Building B3120, including a 1,778 square foot new area and 975 square feet of converted covered drive space, with comprehensive architectural, structural, mechanical, and electrical systems.
The specification outlines comprehensive commissioning requirements for multiple systems including HVAC, building automation, lighting, power distribution, and building envelope. Key requirements include developing a Construction Phase Commissioning Plan, conducting detailed functional performance testing, creating pre-functional checklists, performing seasonal tests, providing systems training, and preparing final commissioning reports and systems manuals. The commissioning process involves multiple team members including a Lead Commissioning Specialist, Government Commissioning Specialist, Designer of Record, and various contractors, with rigorous documentation and testing protocols to ensure systems meet design and operational requirements.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Multiple Award Task Order Contracts U.S. Army Corps of Engineers Great Lakes and Ohio River Division Mission Boundaries Addition Repair Component Medical Training Facility B3120, Duke AFS, Eglin AFB
P2: 513409
Design-Build Specifications - Vol. 2 of 3(Div 00 - 07) Certified Final Design 15 July 2025
W912QR-51061297-0008
MATOC
W912QR21D0049 thru 21D0055 All requirements of the base MATOC Volume 1 of 2 shall apply to this Task Order unless noted otherwise.
RRS-A: 1200A Disposition: Permanent
W912QR-51061297_CertFinal_Specs_Vol2-0008
DEPARTMENT OF THE ARMY
LOUISVILLE DISTRICT, CORPS OF ENGINEERS
P.O. BOX 59
LOUISVILLE,KENTUCKY 40201-0059
REPLY TO
ATTENTION OF
Contracting Division 1 July 2024
Bill W. Jarrett Construction Company, Inc.
Butts Construction Company, Inc.
Howard W. Pence, Inc.
PEM-Jarkins JV LLP Southeastern Industrial Barlovento JV-2, LLC Zodiac-Poettker HBZ Joint Venture, LLC ESA South, Inc.
Dear MATOC Contractors:
Reference is made to your Indefinite Delivery Contracts, Numbers W912QR21D0049 - W912QR21D0055, IDIQ Design Build and Design Bid Build Multiple Award Task Order Contracts (MATOC) to support the military construction (MILCON) and operations and maintenance (O&M) funded construction requirements for the U.S. Army Reserves, U.S. Air Force Reserves, U.S. Air Force, and U.S. Army programs in the Southeast Region.
Amendment 000 for solicitation number W912QR-51061297 for the Addition/Repair of the Component Medical Training Facility, B3120, located on Eglin Air Force Base, FL, is hereby issued and incorporates the following changes.
SUMMARY OF CHANGES:
ALL SPECIFICATIONS and DRAWINGS have been replaced in their entirety with the
CERTIFIED FINAL.
The proposal due date and time has changed to July 2025 at 2:00 PM ET.
Proposals not received by the stated date/time will not be considered. Please acknowledge receipt of this amendment by signing below in the space provided and returning to Charity Mansfield at charity.a.mansfield@usace.army.mil .
If you have contractual questions, please contact Charity Mansfield at charity.a.mansfield@usace.army.mil . If an Offeror believes that the requirements in the RFP contain an error, omission, or are otherwise unsound; the offeror shall immediately notify the Contract Specialist in writing with supporting rationale. All Offerors is reminded that the Government reserves the right to award this RFP based on the initial proposals, as received, without discussion.
Sincerely, Adam M. Wantland Contracting Officer
ACKNOWLEDGEMENT OF AMENDMENT:
(Signature) (Date)
(Printed Name)
(Firm Name)
This page was intentionally left blank for duplex printing.
USACE
Addition Repair Component
Medical Training Facility B3120 Duke AFS Eglin AFB
W912QR-21-D-0070
PN163486
June 2025
SPECIFICATION
CERTIFICATION PAGE
CIVIL STRUCTURAL ARCHITECTURAL
FIRE PROTECTION MECHANICAL PLUMBING
TELECOMMUNICATIONS ELECTRICAL
This page was intentionally left blank for duplex printing.
P2 #513409 Medical Training Facility B3120 Design Duke Field, Eglin AFB FL
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 04/21 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01.00 06 10/23 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 5: 08/23 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
BELOW GRADE CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 08/23 BOARD AND BLOCK INSULATION
07 21 16 08/23 MINERAL FIBER BLANKET INSULATION
PROJECT TABLE OF CONTENTS
CERTIFIED FINAL
07 22 00 08/23 ROOF AND DECK INSULATION
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 27 19.01 08/23 SELF-ADHERING AIR BARRIERS
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 08/23 SPRAY FOAM AIR BARRIERS
07 60 00 08/23 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 00 08/22 SCHEDULES FOR FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC AND PORCELAIN TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 68 00 11/17, CHG 2: 08/20 CARPETING
09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 08/20 INTERIOR SIGNAGE
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS
DIVISION 22 - PLUMBING
22 00 70 05/20 PLUMBING FOR HEALTHCARE FACILITIES
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING
(TAB) OF HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
PROJECT TABLE OF CONTENTS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - HVAC DDC
25 05 11.02 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - LIGHTING CONTROL
DIVISION 26 - ELECTRICAL
26 05 73 08/23 POWER SYSTEM STUDIES
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 07/18 EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE
PAVING
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 92 23 04/06, CHG 1: 08/21 SODDING
DIVISION 33 - UTILITIES
33 40 00 11/21 STORMWATER UTILITIES
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS
SECTION 00 80 00.00 06
SPECIAL PROVISIONS
04/21
PART 1 GENERAL
Attachments to this specification are as follows:
Construction Project Sign Details Project Submittal Register
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1153 (2015) Standard Practice for Location of Wet Insulation in Roofing Systems Using Infrared Imaging
U.S. ARMY (DA)
AR 530-1 Operation Security
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Occupational Health (SOH) Requirements
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926.59 Hazard Communication
1.2 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Local Agency Check; G
SF1413 Statement and Acknowledgement
Radioactive Material/Equipment; G
SD-02 Shop Drawings
DOCUMENT 00 80 00.00 06 Page 1
Mechanical/Electrical Room Layout; G
SD-04 Samples
Equipment Warranty Identification Tags; G
SD-05 Design Data
Progress Photographs
SD-07 Certificates
Warranty of Construction
NO ASBESTOS - CONTAINING MATERIAL (ACM) CERTIFICATION; G
Construction Phase:
Certification for each individual product installed and identified to contain mineral fibers that no asbestos-containing materials were installed; G
Documentation to show that the products containing mineral fiber materials have been microscopically examined by an AIHA- or NVLAP-certified laboratory and the lab has determined that the material does not contain asbestos; G
Insurance
Sales and Use Tax
SD-11 Closeout Submittals
Preliminary (Working) As-Built Drawings; G
Final As-Built Drawings; G
CAD Working As-Built Drawings; G
Equipment-in-Place List
Maintenance and Parts Data
Warranty Management Plan; G
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. Refer to clause 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 00 for the amount of Liquidated Damages for the project.
b. Refer to clause 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for a notification of significant contract dates.
c. After approval of the required bonds, the Government will issue an Administrative Notice-to-Proceed (NTP) to allow for preconstruction activities to be initiated in accordance with the contract requirements. The contract period of performance specified in Contract Clause 52.211-10 will begin upon issuance of Administrative
DOCUMENT 00 80 00.00 06 Page 2
NTP. No physical onsite work will be permitted during the Administrative NTP period. All required preconstruction activities and submittals must be submitted and accepted by the Government, where applicable, within the Administrative NTP period of 45 days. The Government will issue a Construction NTP to allow commencement of all other contract work after the Administrative NTP period, or after the contractor's completion of all work specified in the Administrative NTP. Failure to complete all required preconstruction activities may result in the contract being terminated for default in accordance with Contract Clause 52.249-10 Default (Fixed-Price Construction).
1.3.1 Additional Requirements/Clarifications of Work Included Within the Contract
a. The time stated in clause 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for completion shall include installation of Government-furnished furniture, if required, as well as as-built drawings, O&M manuals, operational tests/reports/training/instructions, equipment lists.
b. Those areas of the building receiving Government-furnished furniture and IT/Telecom equipment shall be made available for Government installation to begin no less than 45 calendar days prior to the contractor's accepted scheduled Construction Completion Date updated in accordance with clause 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00. The Contractor shall participate in a Furniture Pre-Installation Building Inspection, Daily Furniture Installation Building Inspections, and a Final Furniture Installation Building Inspection along with the furniture installation supervisor and a Government representative.
c. If the Contractor fails to meet the requirements in paragraph "Requirements for Completion of Designated Areas Prior to Furniture Installation", by the Contractor's accepted scheduled Furniture Installation Start Date,the Contractor shall pay separate liquidated damages to the Government in the amount of $1,900 for each seven calendar days of the delay until the requirement is fulfilled. The liquidated damages contained in this paragraph are independent of and in addition to those references in clause 52.211-12 "Liquidated Damages - Construction" in Section 00 70 00. Changes to the Contractor's Scheduled Furniture Installation Start Date and Construction Completion Date must be received and accepted no later than forty-nine (49) calendar days prior to the Contractor's current Scheduled Furniture Installation Start Date in order to avoid liquidated damages associated with the furniture installation.
Commencement of furniture installation on or after the Contractor's scheduled Furniture Installation Start Date prior to the fulfillment of these requirements does not relieve the Contractor of their liquidated damages obligation.
1.3.2 Requirements for Completion of Designated Areas Prior to Furniture Installation
a. The Contractor is responsible for access to the building, security and ownership during the furniture and IT/Telecom equipment installation.
Facility operation and maintenance during the furniture and IT/Telecom equipment installation is the responsibility of the Contractor.
b. The Government will be installing IT/Telecom equipment, including the
DOCUMENT 00 80 00.00 06 Page 3 telephone switch and individual telephone sets, during the furniture installation period.
c. The Contractor shall be responsible for coordination with its subcontractors and the Government furniture and IT/Telecom installation contractors, as necessary, to accommodate the furniture and IT/Telecom equipment installation.
d. The exterior roads, parking areas, walks, and building entrances shall be sufficiently complete to support the delivery of furniture products by semi-tractor trailers and made available for use to the Government furniture and IT/Telecom installation contractors.
e. All interior building finishes of areas receiving furniture, including all furniture entries, pathways, staging, and storage areas shall be complete. Completed building finishes shall include all flooring materials and base, interior walls, ceilings, lighting, HVAC systems and controls, doors, doorframes, and trim. All areas are to be cleaned, vacuumed, and an initial waxing applied as appropriate for the installation of furniture.
f. All utilities and systems serving the building shall be fully operational prior to furniture installation. The HVAC system(s) must be in operation, fully balanced and commissioned. The elevator(s) shall be operable and certified for use by the approving agency prior to the delivery of the furniture package and must be made available, at no additional cost, for use by the furniture and IT/Telecom equipment installation contractors.
g. The pre-final building punch inspections shall be performed and punch list items corrected by the Contractor prior to the Government Furniture and IT/Telecom installations.
h. During installation of the furniture and IT/Telecom, the Contractor shall participate in inspections as noted above in subparagraph (b) of the paragraph entitled "Additional Requirements/Clarifications of Work Included Within the Contract". Repairs to any damaged areas shall be performed at no additional cost to the Government by the appropriate party as determined by the Government during these inspections.
i. The Contractor shall be responsible for the electrical hookup of the power feed(s) and phone/data wiring to-as well as providing all data/com faceplates and jacks for-all powered modular systems furniture. This work shall be coordinated with the Government Furniture and IT/Telecom installation contractors to occur while they continue their installations.
j. The Contractor shall perform the final buffing and waxing of areas that are receiving furniture after the furniture and IT/Telecom installation contractors have indicated either installation in those areas is complete or that the final buffing and waxing shall be performed in certain areas prior to the placement of furniture. The final buffing and waxing of corridors and other areas not receiving furniture shall be performed by the Contractor after the furniture and IT/Telecom installation contractors have indicated installation is complete for the building.
k. After furniture and IT/Telecom installation by the Government, the Contractor shall perform a complete Final Cleaning in all impacted
DOCUMENT 00 80 00.00 06 Page 4 areas, as defined in the paragraph entitled "Final Cleaning" in this specification. Final Inspection and Acceptance may occur only after all furniture and IT/Telecom installation by the Government is complete.
1.4 NOT USED
1.5 NOT USED
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
In addition to DFARS 252.236-7001 "Contract Drawings and Specifications" in Section 00 70 00 the following will apply:
a. After Award or no later than Notice to Proceed (NTP), the Government will furnish the Contractor all technical contract documents in electronic media only. This will include a complete set of drawing files and technical specification files which have all amendments included, and will contain drawing files in PDF format along with technical specifications in PDF format. These PDF files are the contract documents that represent the construction requirements of the contract, and are being provided for the Contractor's use in printing paper copies of contract documents.
b. In addition, native CAD files(this includes, but not limited to, all source files, models, custom fonts and linestyles, plot files, and images used to create the contract drawings) are provided in accordance with the "AS-BUILT DOCUMENTS" paragraph for the Contractor's use in maintaining and preparing as-built plans. If another CAD Program is used other than the Using Agency's System, all native CAD files that were generated with that software and all support files will also be included. Only native files are to be used for As-Built preparation and information.
c. Native files are to be used for As-Built preparation only. The PDF files are the contract documents that represent the construction requirements of the contract.
1.7 AS-BUILT DOCUMENTS FOR DESIGN BID BUILD PROJECTS
1.7.1 General
This section covers the completion of final as-built drawings, as a requirement of the contract. The Contractor is responsible for maintaining paper copy working as-built drawings during the construction phase. These paper copy drawings will be used by the Contractor to prepare, maintain and submit the final as-built drawings.
1.7.1.1 As-Built Drawings
An as-built drawing is a contract construction drawing revised to reflect the final as-built conditions of the project because of modifications, changes, corrections to the project design required during construction, submittals and extensions of design. The terms "drawings," "contract drawings," "drawing files," "working as-built drawings" and "final as-built drawings" refer to contract drawings that are revised to be used for the "RECORD DRAWING AS-BUILTS".
DOCUMENT 00 80 00.00 06 Page 5
1.7.1.2 Government-Furnished Files
a. The Contractor will be provided electronic files at the beginning of construction for use during the construction phase which are to be maintained during construction for the preparation of as-builts. The Contractor shall be responsible to print two full size paper copies.
The Contractor shall enter changes and corrections on two sets of paper full size construction plans on a weekly basis in accordance with Paragraph "Maintenance of Working As-Built Drawings" in this section.
b. The Contractor is required to prepare final as-built drawings utilizing the native files provided by the Government. If translation is required, the original design models (BIM or CAD) shall be updated to As-Built conditions and then appropriately translated. Updating translated drawings will not be accepted. The contractor shall update the CAD working as-built drawings, in accordance with paragraph "Maintenance of Working As-Built Drawings", on a quarterly basis and submit them to the COR for independent Government review. Both paper and electronic documents shall be available at all times and shall be provided promptly to the Contracting Officer's Representatives when requested. The Contractor shall be responsible for backup of electronic files during construction and for controlling release of information.
1.7.2 Withholding
Maintenance of working as-builts is considered part of the value of the facilities being constructed and will not be paid for as a separate line item. All costs in conjunction with periodic as-built maintenance and final preparation shall be considered a subsidiary obligation of the Contractor.
1.7.2.1 Failure to Maintain
If the Contractor fails to maintain the working as-built drawings as specified herein, the Contracting Officer will deduct from the monthly progress payment an amount up to 10% or which, in the Contracting Officer's judgment, represents the estimated cost of bringing the as-built documents up to date. This monthly deduction will continue until an agreement can be reached between the Contracting Officer and the Contractor regarding the accuracy and completeness of working as-built documents. This includes conversion of submittals and other miscellaneous documents.
1.7.2.2 As-Builts Prepared by Contractor
The Contractor is required to prepare and provide final as-built drawings. The Contractor shall include an activity in the cost-loaded schedule for the final As-Built drawing submittal in the amount defined in the following paragraph. See Section 01 32 01.00 06, PROJECT SCHEDULE, para "Basis for Payment and Cost Loading". This amount shall be withheld and not paid until the final As-Built drawing submittal has been accepted by the Government.
Withholding for the final as-built drawing submittal shall be in the amount of: 1% for contract awards less than $5,000,000; $50,000 for contracts awarded from $5,000,000 to $10,000,000; or $100,000 for contracts awarded greater than $10,000,000. Withholding shall be withheld
DOCUMENT 00 80 00.00 06 Page 6 until the final as-built drawing submittal has been approved and accepted by the Government.
1.7.3 Maintenance of Working As-Built Drawings
The Contractor shall revise two (2) sets of paper drawings by red-line process to show the as-built conditions during the prosecution of the project. These as-built marked drawings shall be kept current on a weekly basis and available on the jobsite at all times. Changes in the work from the contract or additional information which is uncovered in the course of construction shall be accurately and neatly recorded as they occur by means of details and notes. Changes must be reflected on all sheets that the change affects . The working as-built marked drawings will be jointly reviewed for accuracy and completeness by the Contracting Officer and the Contractor before submission of each monthly pay estimate. The working as-built drawings shall show the following information if applicable to the project, but not be limited thereto:
a. The actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, the as-built drawings shall show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction. Valves, splice boxes and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.
b. The location and dimensions of any changes within the building structure.
c. The correct alignments, grade elevations, typical cross section, earthwork, structures or utilities if any changes were made from contract plans.
d. Additional as-built information that exceeds the detail shown on the Contract Drawings. These as-built conditions include those that reflect structural details, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment foundations and layouts, equipment, sizes, mechanical and electrical room layouts and other extensions of design, that were not shown in the original contract documents because the exact details were not known until after the time of approved shop drawings. It is recognized that the shop drawing submittals (revised showing as-built conditions) will serve as the as-built record without actual incorporation into the contract drawings. The final as-built construction drawing shall reference the shop drawing file that includes the as-built information. In turn, the shop drawing shall reference the applicable construction as-built drawing. All such shop drawing submittals must include the paper copy and PDF of the drawings.
e. The invert elevations and grades of any drainage structures or ditches installed or affected as part of the project construction.
f. Changes or modifications which result from the final inspection.
g. Contour map of the final borrow pit or spoil area with spot elevations as necessary if: borrow material is from sources on Government property; Government property is used as a spoil area; or, if
DOCUMENT 00 80 00.00 06 Page 7 excavated soil materials are placed in approved locations other than a landfill.
h. Where contract drawings present options, only the option selected for construction shall be shown on the final as-built drawings.
i. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarms, fire sprinklers, fire protection, fire detection and irrigation systems and other related systems in this project, shall be incorporated into the as-built drawings to include detailed information for all aspects of the systems including wiring, piping, and equipment drawings.
j. Room numbers shown on the contract drawings are selected for design convenience and may not represent the actual numbers intended for use by the end user. Final as-built drawings shall reflect actual room numbers adopted by the end user.
k. Contract modification (change order price) shall include the Contractor's cost to change working and final as-built drawings to reflect modifications and compliance with the following procedures (See "Markings and Indicators"):
(1) Directions in the modification for posting descriptive changes shall be followed.
(2) A Revision Triangle shall be placed at the location of each deletion.
(3) For new details or sections which are added to a drawing, a Revision Triangle shall be placed by the detail or section title.
(4) For minor changes, a Revision Triangle shall be placed by the area changed on the drawing (each location).
(5) For major changes to a drawing, a Revision Triangle shall be placed by the title of the affected plan, section, or detail at each location.
(6) For changes to schedules or drawings, a Revision Triangle shall be placed either by the schedule heading or by the change in the schedule.
1.7.4 Preliminary (Working) As-Built Drawings
Six (6) weeks before Contract Completion Date, the Contractor shall submit one (1) set of the original paper working as-built drawings to the Contracting Officer for review and approval. These working as-built marked drawings shall be neat, legible and accurate. The review by Government personnel will be expedited to the maximum extent possible. If upon review, the working as-built drawings are found to contain errors and/or omissions, they will be returned to the Contractor for corrections. The Contractor shall complete the corrections and return the working as-built marked drawings to the Contracting Officer within fourteen (14) calendar days. Upon approval, the working as-built drawings will be returned to the Contractor for use in preparation of final as-built drawings.
DOCUMENT 00 80 00.00 06 Page 8
1.7.5 Preparation of Final As-Built Drawings
The contract drawings shall be modified as may be necessary to correctly show the features of the project as it has been constructed by bringing the contract drawings into agreement with approved working as-built drawings, adding such additional drawings as may be necessary.
These final as-built drawings are part of the permanent records of the project and the Contractor shall be responsible for the protection and safety thereof until returned to the Contracting Officer. Any drawings damaged or lost by the Contractor shall be satisfactorily replaced by the Contractor at no expense to the Government.
When electronic CAD files are a part of the as-built process, a set of files shall be provided to the Government as a part of the Final As-Built submittal for a review to verify the correctness of the as-built markups and that all changes have been incorporated into the electronic files.
This review will require the electronic model files in Revit version 2022, AutoCAD Civil 3D 2022 and AutoCAD 2022, all the files needed to reproduce the contract drawings, a full size set of contract drawings in PDF format and all the shop drawings in PDF format, a scanned set of the paper markups and the paper markups. Should errors be determined, the Contractor shall update the files and provide a corrected set of files within fourteen (14) calendar days of receipt of comments. An independent Government review, by the Louisville district As-Built Coordinator (CELRL-CDM-Q), will be made on the accepted files to determine compliance with the As-Built requirements of this section, National CAD Standards, and the AEC CAD Standards; and to verify graphic changes were done properly in preparing the electronic files. This review will require submission of electronic files, containing all the files needed to reproduce the contract drawings, a full size set of contract drawings in PDF format, all shop drawings in PDF format, a scanned set of the paper markups and the paper markups. Upon receipt of any comments from this independent review, the contractor shall update the electronic files and provide a corrected set of files within fourteen (14) calendar days of receipt of the comments.
When BIM models are a part of the as-built process, the models shall be provided to the Government as a part of the Final As-Built submittal for a review to verify the correctness of the as-built markups and confirm that all changes have been incorporated into the models. Should errors be determined, the contractor shall update the files and provide a corrected set of files within fourteen (14) calendar days of receipt of comments. An independent Government review, by the Louisville district As-Built Coordinator (CELRL-CDM-Q), will be made on the accepted files to determine compliance to the As-Built requirements and to verify graphics changes were done properly. This review will require the electronic model files, all the files needed to reproduce the contract drawings, a full size set of contract drawings in PDF format and all the shop drawings in PDF format, a scanned set of the paper markups and the paper markups. Upon receipt of any comments from this independent review, the contractor shall update the electronic model files and provide a corrected set of files within fourteen (14) calendar days of receipt of the comments.
In the event the Contractor accomplishes additional work which changes the as-built conditions of the facility, after submission and approval of the working as-built drawings, the Contractor shall be responsible for the addition of these changes to the working as-built drawings and also to the final as-built documents and electronic models.
DOCUMENT 00 80 00.00 06 Page 9
1.7.6 Markings and Indicators
Changes shall be annotated in accordance with ERDC/ITL TR-12-1 "A/E/C Graphics Standard_Release 2.0" at the following locations:
a. Bottom of the revised detail.
b. Right hand and bottom border aligned with the revised detail.
c. The revision block of the title block.
Separate markings shall be made for each modification negotiated into the contract.
1.7.7 Construction Contract Specifications
Submit final PDF file record construction contract specifications, including revisions thereto, with submission of final as-built drawings.
1.7.8 Preparation of Other As-Built Documents
All other non-electronic documents which may include, for example, design analysis, catalog cuts, or certification documents that are not available in native electronic format shall be scanned and provided in an organized manner in Adobe PDF format.
1.7.9 Submittal of Final As-Built Documents
Within fourteen (14) calendar days of Final Acceptance meeting of the project, Final As-Built documents shall be provided to the Contracting Officer in the formats described in paragraph "Electronic File Use". The final as-built document submittal shall also include the approved preliminary paper working as-built drawings.
1.7.10 Partial Occupancy
For projects where portions of construction are to be occupied or activated before overall project completion, including portions of utility systems, as-built drawings for those portions of the facility being occupied or activated shall be supplied at the time the facility is occupied or activated. This same as-built information previously furnished must also be shown on the final set of as-built drawings at project completion.
1.7.11 Electronic File Use
Only personnel proficient in the preparation of CAD drawings shall be employed to modify the electronic contract drawings or prepare additional new electronic drawings. Additions and corrections to the contract drawings shall be equal in quality to that of the originals. Line work, line weights, lettering, layering conventions, and symbols shall be the same as the original line work, line weights, lettering, layering conventions, and symbols. If additional drawings are required, they shall be prepared using the specified electronic file format applying the same guidance specified for original drawings. Three dimensional (3D) elements shall be placed in files in their proper locations when using 3D files with spatially correct elements. If the Designer of Record used a different software than that requested by the Using Agency, the Designer of Record's files will be used for as-built purposes and then translated and/or exported, by the Contractor, to the Using Agency's system. The
DOCUMENT 00 80 00.00 06 Page 10 title block and drawing border to be used for any new final as-built drawings shall be identical to that used on the contract drawings.
Additions and corrections to the contract drawings shall be accomplished using CAD media files supplied by the Government. All work by the Contractor shall be done on files in the format in which they are provided. Translation of files to a different format, for the purpose of As-Built production, and then retranslating back to the format originally provided, will not be acceptable. The original electronic files provided by the Government will be provided in the format compatible with the Using Agency. The Using Agency uses Revit version 2022, AutoCAD Civil 3D 2022 and AutoCAD 2022. The Contractor shall be responsible for providing all program files and hardware necessary to prepare final as-built drawings.
The Contracting Officer will review final as-built drawings for accuracy and the Contractor shall make all required corrections, changes, additions, and deletions.
a. When final revisions have been completed, the cover sheet drawing shall show the wording "RECORD DRAWING AS-BUILT" followed by the name of the Contractor in letters at least 5 mm 3/16 inch high. All other contract drawings shall be marked in the bottom right-hand corner of each drawing either "AS-BUILT" drawing denoting no revisions on the sheet, or "REVISED AS-BUILT" denoting one or more revisions. As-Built drawings shall be dated with the Contract Completion Date in the revision block.
b. After receipt by the Contractor of the approved working as-built drawings and the original contract drawings files the Contractor shall, within thirty (30) calendar days, make the final as-built submittal. This submittal shall consist of 2 sets of completed final as-built drawings on separate media consisting of both CAD files (compatible with the Using Agency's system on electronic storage media identical to that supplied by the Government) and a full size set in PDF format and the return of the approved marked up working as-built drawings. They shall be complete in all details and identical in form and function to the contract drawing files supplied by the Government.
Any translations or adjustments necessary to accomplish this are the responsibility of the Contractor. The Government reserves the right to reject any drawing files it deems incompatible with its CAD system.
All paper drawings, drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final as-built drawing files and marked drawings as specified shall be cause for withholding any payment due the Contractor under this contract. Approval and acceptance of final as-built drawings shall be accomplished before final payment is made to the Contractor.
1.8 NOT USED
1.9 EQUIPMENT DATA, O&M, & REPAIR MANUALS WITH FIELD TRAINING REQUIREMENTS
1.9.1 Real Property Equipment
OPTION #1 Equipment-in-Place Data
Contractor shall be required to make an Equipment-in-Place list of all installed equipment furnished under this contract. This list shall include all information usually listed on manufacturer's name plate. The Form is part of SPECIAL PROVISIONS and is included following the SPECIAL PROVISIONS, so to positively identify the piece of property. The list shall also include the cost of each piece of installed property F.O.B.
DOCUMENT 00 80 00.00 06 Page 11 construction site. For each of the items which are specified herein to be guaranteed for a specified period from the date of acceptance thereof, the following information shall be given: The name, serial and model number address of equipment supplier, or manufacturer originating the guaranteed item. The Contractor's guarantee to the Government of these items will not be limited by the terms of any manufacturer's guarantee to the Contractor. Furnish the list in as one (1) reproducible and three (3) copies, and in electronic format on CD to the Contracting Officer thirty
(30) calendar days before completion of any segment of the contract work which has an incremental completion date.
Maintenance and Parts Data The Contractor will be required to furnish a brochure, catalog cut, parts list, manufacturer's data sheet or other publication which will show detailed parts data on all other equipment subject to repair and maintenance procedures not otherwise required in Operations and Maintenance Manuals specified elsewhere in this contract. Distribution of directives shall follow the same requirements as listed in paragraph above.
1.9.2 O&M and Repair Manuals
OPTION #1 Withholding & Copies
The Contractor shall provide 6 complete copies of the Equipment Operating, Maintenance, and Repair Manuals unless the Technical Specification indicates otherwise. The manuals shall be prepared electronically in PDF format containing bookmarks for each table of contents item. The PDF file shall be referenced in a separate column or linked worksheet in the equipment data excel spreadsheet. Separate manuals shall be provided for each utility system as defined per the Technical Specification.
Operations and Maintenance manuals shall be accepted/approved before field training or ninety (90) calendar days before substantial completion (whichever occurs earlier). An amount of $10,000 shall be withheld until submittal and acceptance/ approval of O&M manuals is complete. A draft outline and table of contents shall be submitted for acceptance/ approval at 50% contract completion See paragraph "EQUIPMENT DATA, O&M, & REPAIR MANUALS WITH FIELD TRAINING REQUIREMENTS" for detail O&M and Repair Manual format.
1.9.3 Field Training
1.9.3.1 Training Course
Contractor shall conduct a training course for the operating staff for each particular component and system. Where the training period is not identified by the technical specification, a minimum of 1 hour of training shall be provided for that component or system. Training shall only occur after the Manuals have been approved/ accepted by the Government and during normal working time, and shall start after the system or component is functionally completed. The field instructions shall cover all of the items contained in the Equipment Operating, Maintenance and Repair Manuals as identified per individual Technical Specifications. The training will include both classroom and "hands-on" training. The Contractor shall submit a lesson plan outlining the information to be discussed during training periods. This lesson plan will be submitted ninety (90) calendar days before contract completion and accepted/approved before the field training occurs. Training shall be documented by the Contractor and a list of attendees shall be furnished to the Government.
DOCUMENT 00 80 00.00 06 Page 12
1.9.3.2 Training Recording
The Contractor shall provide all equipment, materials, and trained personnel required to visually and audibly record all site operations and maintenance (O&M) training sessions. The video technician/trainer shall be employed by a video production company that has been in business for a minimum of 2 years. The Contractor shall submit for acceptance by the Government, the resume of the technician/trainer and the video production company, and the proposed video format. The video format shall be one in wide use, and any software necessary to view the video shall be provided to the Government. Video shall be provided to the Government on DVD.
Audio shall be adjusted, filtered or otherwise controlled to ensure the presenter can be understood at all times. Each system or piece of equipment shall be covered on a single DVD or set of DVDs, which shall be identified with a type written label showing the name of the project, equipment or system, and contract number. This same information shall be provided as an introduction on each DVD. When two or more DVDs are provided for a single system or piece of equipment, they shall be packaged as a set in an appropriate storage case. Provide three copies of each DVD(s) for each training session. Training DVDs shall be furnished to the Government within ten (10) working days following training.
1.10 AVAILABILITY OF UTILITIES
a. Availability and Use of Utility Services
The Government will not furnish any utilities or sanitary facilities to the contractor for their use even if available at the work site. The contractor is responsible for procuring and/or providing these items themselves or obtaining them from a private entity (utility company).
During furniture and IT/Telecom equipment installation and until the facility is turned over to the Government, the Contractor shall maintain electric service to the construction site for the operation of HVAC, lighting and electrical power.
1.10.1 Alterations to Utilities
Where changes and relocations of utility lines are noted to be performed by others, the Contractor shall give the Contracting Officer at least thirty (30) calendar days written notice in advance of the time that the change or relocation is required. In the event that, after the expiration of thirty (30) calendar days after the receipt of such notice by the Contracting Officer, such utility lines have not been changed or relocated and delay is occasioned to the completion of the work under contract, the Contractor may be entitled to a time extension equal to the period of time lost by the Contractor after the expiration of said thirty (30) calendar day period.
1.10.2 Interruptions of Utilities
a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.
b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) working days before date of proposed interruption. The request shall give the following information:
DOCUMENT 00 80 00.00 06 Page 13
(1) Nature of Utility. (Gas, L.P. or H.P., Water, etc.)
(2) Size of line and location of shutoff.
(3) Buildings and services affected .
(4) Hours and date of shutoff.
(5) Estimated length of time services will be interrupted.
c. Services shall not be shut off until receipt of approval of the proposed hours and date from the Contracting Officer.
d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency without any additional cost to the Government.
e. Operation of valves on water mains will be by persons of that utility. Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.
f. Flow in gas mains which have been shut off shall not be restored until the Government inspector has determined that all items serviced by the gas line have been shut off.
1.11 NOT USED
1.12 PERFORMANCE OF WORK BY THE CONTRACTOR
a. For Full and Open Procurement, the requirements found in Section 00 70 00, clause 52.236-1 "Performance of Work By the Contractor" apply, unless the awardee is a certified HUBZone small business concern, in which case the requirements found in Section 00 70 00, clause 52.219-4 "Notice of Price Evaluation Preference for HUBZone Small Business Concerns" shall apply.
b. For purposes of Section 00 70 00, clause 52.236-1, only, "WORK BY THE CONTRACTOR" is defined as prime Contractor direct contract labor (including testing and layout personnel), exclusive of other general condition or field overhead personnel, material, equipment, or subcontractors. The "TOTAL AMOUNT OF WORK" is defined as total direct contract labor (including testing and layout personnel), exclusive of other general condition or field overhead personnel, material, or equipment.
c. Within seven calendar days after the award of any subcontract at any tier, either by himself or a subcontractor, the Contractor shall submit to the Contracting Officer a completed Standard Form SF1413 Statement and Acknowledgement (available at the GSA Forms Library, https://www.gsa.gov/reference/forms#). The form shall include the subcontractor's acknowledgement of the inclusion in his subcontract of the clauses in Section 00 70 00 of this contract entitled 52.222-4 "Contract Work Hours and Safety Standards - Overtime Compensation"; 52.222-8 "Payrolls and Basic Records"; 52.222-7 "Withholding of Funds"; 52.222-14 "Disputes Concerning Labor Standards"; 52.222-13 "Compliance with Construction Wage Rate Requirements and Related Regulations"; 52.222-6 "Construction Wage Rate Requirements" (formerly named "Davis-Bacon Act");
52.222-9 "Apprentices and Trainees"; 52.222-10 "Compliance with Copeland Act Requirements"; 52.222-11 "Subcontracts (Labor Standards); 52.222-12
DOCUMENT 00 80 00.00 06 Page 14
"Contract Termination - Debarment"; 52.222-15 "Certification of Eligibility". Nothing contained in this contract shall create any contractual relation between any subcontractor and the Government.
d. Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts
In addition to complying with the requirements outlined in Subpart 22.13, provision 52.222-38, clause 52.222-35, clause 52.222-37, DFARS Subpart
222.13 and United States Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
(1) U.S. Department of Labor Veterans' Employment and Training Service (VETS): https://www.dol.gov/vets/
(2) Federal veteran employment information:
https://www.fedshirevets.gov/
(3) Veterans Opportunity to Work (VOW) Program:
https://benefits.va.gov/vow/
(4) U.S. Army Warrior Transition Command Employment Index:
http://wct.army.mil/modules/employers/index.html
(5) Hiring Our Heroes:
https://www.uschamberfoundation.org/hiring-our-heroes
1.13 SUPERINTENDENCE OF SUBCONTRACTORS
a. The Contractor shall be required to furnish the following, in addition to the superintendence required by clause 52.236-6 - "Superintendence By The Contractor" in Section 00 70 00.
(1) If more…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .