Solicitation Amendment W912QR26RA0170001 SF 30.pdf

PDF 287 KB Posted

Attached to
Ft. Campbell Rectifier Replacement
Solicitation number
W912QR-26-R-A017
Issued by

About this file

This is a Standard Form 30 (SF 30) Amendment of Solicitation issued by the U.S. Army Corps of Engineers (USACE) on 3 April 2026. The amendment modifies solicitation W912QR26RA017, issued by the W072 ENDIST Louisville KO Contracting Division. The contracting officer is Thomas Nauert, reachable at thomas.s.nauert@usace.army.mil or (502) 315-6205.

The amendment makes three substantive changes to the solicitation: (1) extends the solicitation due date from 17 April 2026 to 24 April 2026; (2) adds a mandatory organized site visit scheduled for 15 April 2026 at 1300 hours at 95 Bastogne Ave, Fort Campbell, KY 42223, with participants required to meet at that location; and (3) incorporates FAR clause 52.236-27 Site Visit (Construction), Alternate I, which requires offerors and quoters to inspect the work site and indicates that clauses 52.236-2 (Differing Site Conditions) and 52.236-3 (Site Investigations and Conditions Affecting the Work) will be included in any resulting contract. All other terms and conditions of the original solicitation remain unchanged. Offerors must acknowledge receipt of this amendment prior to the extended due date by completing and returning items 8 and 15, acknowledging receipt on each copy of their offer, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.

View the file

Other files

File Type Posted
W912QR26RA017 Amendment 0003.pdf PDF
W912QR26RA017 Amendment 0002.pdf PDF
RFIs.pdf PDF
Site Visit Sheet.pdf PDF
Facility Plans .pdf PDF
Solicitation - W912QR26RA017 3.17.26.pdf PDF
2025.6.18 - FTC Rectifier PWS.pdf PDF
Wage Rates 12.25.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

J 1 3

0001 03 APR 2026

W912QR

W072 ENDIST LOUISVILLE

KO CONTRACTING DIVISION, 600 DR MARTIN LUTHER KING JR PL

LOUISVILLE, KY 40202-2230

UNITED STATES

THOMAS NAUERT, EMAIL: THOMAS.S.NAUERT@USACE.ARMY.MIL TELEPHONE:

(502) 315-6205

SCD: PAS:

W912QR26RA017

02 APR 2026

SEE CONTINUATION

Solicitation W912QR26RA017 is hereby modified as follows:

a. The Solicitation Due date has been extended from 17 April 2026 to 24 April 2026.

b. Site Visit has been added and date is set for 15 April 2026 at 1300 at 95 Bastogne Ave, Fort Campbell, KY 42223.

c. All other terms and conditions remain unchanged

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form Continuation

The following changes have been made:

Addendum to 52.212-1, Instructions to Offerors - Commercial Products and Commercial Services

Miscellaneous text in this section has been added to:

52.236-27 Site Visit (Construction). Alternate I

As prescribed in 36.523 , insert a provision substantially the same as the following:

Site Visit (Construction) (Feb 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(Feb 1995). If an organized site visit will be conducted, substitute a paragraph substantially the same as the following for paragraph (b) of the basic provision:

(b) An organized site visit has been scheduled for-

W912QR26RA0170001

15 April 2026 at 1300

(c) Participants will meet at-

95 Bastogne Ave, Fort Campbell, KY 42223

W912QR26RA0170001

File details come from the government source that posted it. Updated .