W912QR24R0048_FIO_V4a_Specs-0000.pdf
PDF 4 MB Posted
- Solicitation number
- W912QR24R0048
About this file
This document is a pre-solicitation notice for a full and open federal contract opportunity for the Construction of Rough River Dam Safety Modification Phase II: New Outlet Works and Cutoff Wall Project. The proposed work involves specialized equipment and capabilities to construct a new outlet works and install a cutoff wall based on site-specific geology. The contractor must have the ability to meet construction deadlines and ensure continuity of the cutoff wall segments. The contract type will be Firm Fixed Price, awarded based on best value tradeoff, and the method of payment will be Electronic Funds Transfer. The solicitation is anticipated to be released in late November, with a draft solicitation released in mid-September. This project requires a HubZone 10% price evaluation, and large businesses must submit a subcontracting plan. The North American Industry Classification System (NAICS) code for this procurement is 237990.
View the file
Other files
Show 40 more
Latest 50 of 73 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Rough River Dam Safety Modification Project Phase II - New Outlet Works and Cutoff Wall
P2: 145870
Design-Bid-Build
Specifications Vol. 4a (Div. 00-06)
For Information Only
23 September 2024
W912QR24R0048
ARIMS: 1200
Disposition: Permanent
W912QR24R0048_FIO_V4a_Specs-0000
145870 Rough River Dam For Information Only BCOES Review DSM Phase 2: New Outlet Works and Cutoff Wall
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 31 19.23 06 5/24 WEATHER AND WATER STAGE
DATA/RESTRICTIONS
00 31 31.13 06 08/24 SUBSURFACE INVESTIGATION INFORMATION
00 80 00.00 06 04/21, CHG 1: 06/23 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 5/24 SUMMARY OF WORK
01 31 00 08/24 DATA MANAGEMENT
01 32 01.00 06 10/23 PROJECT SCHEDULE
01 32 23 SURVEY CONTROL, LiDAR, ORTHOIMAGERY
AND BATHYMETRY
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 16.00 08 8/24 CONTRACTOR SUBMITTALS REQUIRING
ENGINEERING AFTER AWARD
01 35 00.00 06 5/24 SPECIAL PROCEDURES
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 02/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 52 13.20 06 05/2024 GOVERNMENT FACILITIES
01 52 13.30 08 08/24 LABORATORY TESTING FACILITIES
01 57 19.00 06 11/21 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 6/24 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 32 00 5/24 ADDITIONAL INVESTIGATIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 00 00 6/24 GENERAL CONCRETE REQUIREMENTS
03 15 00 11/21 BRIDGE CONCRETE ACCESSORIES
03 23 00 11/21 POST TENSIONED REINFORCING
03 30 00 02/19 CAST-IN-PLACE CONCRETE OUTLET WORKS
03 37 13 11/21 SHOTCRETE
03 37 29 11/21 CONCRETE FOR CUTOFF WALL
03 70 00 11/21 MASS CONCRETE
DIVISION 04 - MASONRY
04 20 00 08/21 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE ANCHORS
05 12 10 08/21 ELASTOMERIC BEARING PADS
05 12 23 08/21 GENERAL STRUCTURAL STEEL
PROJECT TABLE OF CONTENTS Page 1
05 12 33 08/21 STRUCTURAL STEEL BRIDGES
05 14 00.13 11/19 WELDING STRUCTURAL ALUMINUM
05 21 00 05/21 STEEL JOIST FRAMING
05 30 00 08/21 STEEL DECKS
05 40 00 08/21 COLD-FORMED METAL FRAMING
05 50 13 08/21 MISCELLANEOUS METAL FABRICATIONS
05 50 15 08/21 CIVIL WORKS FABRICATIONS: GATE BONNETS
05 51 33 08/21 METAL LADDERS
05 52 00 08/21 METAL RAILINGS
05 59 20 11/21 FABRICATION OF HYDRAULIC STEEL
STRUCTURES
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/21 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 02/21 BOARD AND BLOCK INSULATION
07 27 10.00 10 08/21 BUILDING AIR BARRIER SYSTEM
07 60 00 08/21 FLASHING AND SHEET METAL
07 61 14.00 20 08/21 STEEL STANDING SEAM ROOFING
07 81 00 02/21 SPRAY-APPLIED FIREPROOFING
07 84 00 05/21 FIRESTOPPING
07 92 00 08/21 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/21 STEEL DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/21 OVERHEAD COILING DOORS
08 51 13 08/21 ALUMINUM WINDOWS
08 71 00 02/21 DOOR HARDWARE
08 81 00 05/21 GLAZING
08 91 00 08/21 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/21 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/21 GYPSUM BOARD
09 90 00 05/21 PAINTS AND COATINGS
09 97 02 02/21 PAINTING: HYDRAULIC STRUCTURES
DIVISION 10 - SPECIALTIES
10 14 00.10 08/21 EXTERIOR SIGNAGE
10 14 00.20 08/21 INTERIOR SIGNAGE
10 28 13 08/21 TOILET ACCESSORIES
10 44 16 08/21 FIRE EXTINGUISHERS
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 11/21 METAL BUILDING SYSTEMS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 13 05/21 ELECTRIC TRACTION FREIGHT ELEVATORS
DIVISION 22 - PLUMBING
PROJECT TABLE OF CONTENTS Page 2
22 14 29.00 40 05/21 SUMP PUMPS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS
23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 07/21 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 20 00 02/21 INTERIOR DISTRIBUTION SYSTEM
26 28 00.00 10 08/21 MOTOR CONTROL CENTERS AND PANELBOARDS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 00.00 10 08/21 AUTOMATIC TRANSFER SWITCH AND
BY-PASS/ISOLATION SWITCH
26 41 00 08/21 LIGHTNING PROTECTION SYSTEM
26 51 00 05/21 INTERIOR LIGHTING
26 56 00 05/21 EXTERIOR LIGHTING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/21 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 5/24 EARTHWORK
31 05 22 11/21 NON-WOVEN GEOTEXTILE FILTER FABRIC
31 09 13.00 06 INSTRUMENTATION AND MONITORING
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 06 5/24 CONTROL OF WATER AND DEWATERING
31 23 05.00 06 09/21 MASS EXCAVATION
31 23 17.00 06 09/21 UNDERWATER BLASTING
31 23 18.00 06 09/21 BLASTING - SURFACE
31 32 23.00 06 6/24 SLURRY CONTROL DRILLING AND GROUTING
31 41 16 11/21 METAL SHEET PILING
31 56 10.00 06 5/24 CUTOFF WALL CONSTRUCTION
31 60 00.00 06 6/24 FOUNDATION PREPARATION
31 68 13 06/24 ROCK SLOPE REINFORCEMENT AND PERMANENT
ROCKFALL PROTECTION
31 71 16.00 06 09/21 ROCK TUNNELING
31 73 00 10/21 TUNNEL GROUTING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 00 10/13 MISCELLANEOUS CONSTRUCTION
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 10 02/21 OPEN GRADED AGGREGATE FOR DRAINAGE
32 11 16.16 11/11 KYTC CRUSHED STONE BASE CONSTRUCTION
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16 11/21 HOT-MIX ASPHALT (HMA) FOR ROADS
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 18 16.13 08/17 PLAYGROUND PROTECTIVE SURFACING
32 31 13 11/21 CHAIN LINK FENCES AND GATES
PROJECT TABLE OF CONTENTS Page 3
32 31 13.15 06 06/01 GUARDRAIL
32 91 18.00 06 04/21 HIGH PERFORMANCE TURF REINFORCED MAT
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 92 23 04/06, CHG 1: 08/21 SODDING
DIVISION 33 - UTILITIES
33 01 30.16 11/21, CHG 1: 02/24 TV INSPECTION OF SEWER LINES
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 46 13 03/24 FOUNDATION DRAINAGE SYSTEM
33 46 16 05/18 SUBDRAINAGE PIPING
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 01 70.13 05/21 WIRE ROPE AND RIGGING FOR OPERATING
DEVICES
35 05 40.14 10 08/21 HYDRAULIC POWER SYSTEMS FOR CIVIL
WORKS STRUCTURES
35 20 14 08/22 STOPLOGS
35 20 16.54 08/21 CAST IRON SERVICE DOOR
35 42 37.00 06 4/24 RIP RAP STONE PROTECTION
35 59 15.00 06 10/20 MARINE SAFETY BOOM
35 73 13 05/21 EMBANKMENT FOR EARTH AND ROCKFILL DAMS
DIVISION 40 - PROCESS INTERCONNECTIONS
40 05 13 08/21 PIPELINES, LIQUID PROCESS PIPING
40 05 13.96 05/21 WELDING PROCESS PIPING
40 33 33 08/21 KNIFE GATE VALVES
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.14 08/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP
RUNNING
41 22 23.19 05/21 MONORAIL JIB CRANE HOISTS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 31 19.23 06
WEATHER AND WATER STAGE DATA/RESTRICTIONS
5/24
PART 1 GENERAL
1.1 SCOPE
1.1.1 Water Control Advisory Panel (W.C.A.P.)Coordination
1.1.2 Anticipated High Water And Unusually Severe Weather
1.2 WEATHER DATA
1.3 WORK RESTRICTIONS ASSOCIATED WITH POOL LEVEL
1.4 HYDROLOGIC CONDITIONS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 31 19.23 06 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 31 19.23 06 Page 2
SECTION 00 31 19.23 06
WEATHER AND WATER STAGE DATA/RESTRICTIONS
5/24
PART 1 GENERAL
1.1 SCOPE
This section contains weather and water stage data for construction at Rough River Lake Dam. Rough River Dam is intended for flood control therefore the pool and tailwater will fluctuate based on rainfall, inflows into the reservoir, reservoir levels, and downstream channel conditions. In spring of 2023 a pool restriction was implemented at the project. The "Normal Summer Pool" of 495 NGVD29 was lowered implementing a "Restricted Summer Pool" of 490 NGVD29. The Restricted Summer Pool will be the summer pool target elevation for work completed on the outlet works and cutoff wall. When the general term "Summer Pool" is used in this Contract, the Restricted Summer Pool of 490 NGVD29 is inferred. The Normal Summer Pool may be re-instated after acceptance of the outlet works AND cutoff wall.
The winter pool targets a pool of 470 NGVD29 in the winter.
The Geotechnical Interpretive Report (GIR), available in Volume 6 of the technical package, includes both the target pools listed on the Seasonal Guide Curve for the months when the summer pool and winter pools are targeted. The GIR also includes the Stage Frequency Curves which provide a summary of the probability to exceed any given reservoir stage in a given year. Hydrographs for the reservoir and the tailwater are included in the Volume 1 Plans with additional electronic resources included herein. This information is provided to the Contractor for review and interpretation to understand how the reservoir levels vary and how best to sequence work at the project. Reference is made to Specification 01 11 00 SUMMARY OF WORK for an overview of the project.
1.1.1 Water Control Advisory Panel (W.C.A.P.)Coordination
A Water-Control Assessment Panel (W.C.A.P.) will be formed from the USACE Louisville District Personnel and representatives for the Contractor. The W.C.A.P. will include the Dam Safety Modification Lead Engineer, The Project Manager, The Dam Safety Program Manager (DSPM), Water Management Team Lead, Resident Engineer, the Lake Manager, Contractor's SSHO, and the Contractor's QC Manager. The W.C.A.P. will convene at regular intervals when the reservoir is approaching the 510 elevation to make assessments of the current ongoing work and the impacts that the projected weather forecast may have for the dam. During construction, the W.C.A.P. will make recommendations to the Contracting Officer whether to proceed with work, to complete elements that have already started, to abandon elements that have already been started, and to recommend additional emergency measures related to pool levels as required to maintain Dam Safety during construction activities. Dam Safety and the integrity of the dam shall remain the number one priority for the project during construction.
The Water-Control Assessment Panel (W.C.A.P.) will also convene and make recommendations regarding evacuation of the spillway that may be utilized by the Contractor as a haul route. The concrete spillway control sill shall be protected from damage during hauling operations. If the reservoir rises to a high pool scenario that will likely result in uncontrolled spillway
DOCUMENT 00 31 19.23 06 Page 3 flow, the Contractor must remove any haul road material to below the concrete sill elevation (524), and any noticeable damage to the sill repaired by the Contractor within 36 hours.
Any work required to access the stilling basin and discharge conduit outlet works functioning as the primary means of flow conveyance must not disrupt normal releases more than 8 consecutive hours at any given time. This includes the time to dewater and the mobilization/demobilization of any equipment or personnel entering the structure. The Contractor is responsible for handling dewatering activities from sandbagging or cofferdams, gate leakage, or other sources as required to complete operations at normal or elevated pools. Following periods of shutdown or at the discretion of the Contracting Officer, the outlet works shall be cleared of any obstructions to allow controlled releases by USACE.
If a shutdown of releases from the project lasting more than 8 continuous hours is required at any time, USACE shall be notified in writing at least 7 days in advance and the contractor shall provide means for a continuous water bypass of at least 50 cfs. This may be accomplished through stilling basin dewatering, pumping of gate leakage, pumping from the reservoir, or any combination of these alternatives. The design and operation of the bypass system is the responsibility of the Contractor and shall be submitted to the Government for approval as part of the work plan.
The new outlet works shall be fully functioning, been placed in service a minimum of 30 days, and re-inspected by the Government for approval prior to abandoning the existing conduit or initiating work in Critical Area A.
Any time the stilling basin or tailwater is dewatered for either outlet works structure, the Contractor shall be responsible for removing fish from the tailwater and stilling basin for relocation downstream of any required cofferdam for dewatering. When dewatering of a stilling basin occurs, the Contactor shall coordinate with the Kentucky Department of Fish & Wildlife a minimum of 14 calendar days in advance, for approval and supervision of fish removal. Dewatering will not be allowed to occur without prior approval from the KY Department of Fish and Wildlife and a representative from said agency present during relocation operations. This dewatering requirement shall not apply to the new stilling basin should it be submerged by high water prior to being connected to the new retreat channel. No separate payment will be made for removal and relocation of fish.
1.1.2 Anticipated High Water And Unusually Severe Weather
Unusually Severe Weather Days are evaluated in accordance with Specification 00 80 00.00 06, paragraph 1.20, TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. In order to qualify for an Unusually Severe Weather Day related to high water, the following criteria must be met in addition to the requirements of Specification 00 80 00.00 06:
Control Tower: Work must cease in the area protected by the Cofferdam when the reservoir reaches elevation 521. The reserovoir rate of rise will vary based on rainfall. The Contractor must be prepared to remove all personnel, equipment, and materials from the area within a period of 48 hours of the reservoir surpassing the 510 elevation during an extreme event.
Cutoff Wall Construction on the Dam: Cutoff Wall excavation and grouting activities in the designated critical areas must cease when the reservoir reaches elevation 510. See special requirements contained herein relative to the cutoff wall.
DOCUMENT 00 31 19.23 06 Page 4
Stilling Basin Construction: Work in the protected area must cease when the tailwater reaches an elevation of 450. The Contractor must be prepared to remove all personnel, equipment, and materials from the area within a period of 48 hours of the reservoir surpassing the 445 elevation or a projected spillway flow event.
Spillway Haul Road: The upstream spillway haul road will be flooded prior to reaching the 521 elevation. No sandbagging, barricades, or other means of maintaining spillway haul road access are permitted and operations on the spillway haul road must stop when the road is covered by water.
Requirements for restoring the spillway prior to a flood event are contained herein and in the Volume 1 Plans. Aggregate surfacing for the haul road within the spillway above the 524 elevation must be 3 inch sized aggregate or smaller.
The Contractor must assume that two (2) high water events are expected to impact the project during construction exceeding the thresholds defined above. Each singular high water event is anticipated to impact all scenarios listed above as part of the that flood event. All demobilization from flooded areas, preparatory work, clean-up, and remobilization are incidental to GENERAL MOBILIZATION AND DEMOBILIZATION. In no instance will payment be made for time expended between normally required set-up, for delayed production due to concrete curing times, and the time required for equipment movements. This item does not include scheduled drawdowns of the reservoir as detailed in the plans and specifications or curing times associated with concrete. Links to hydraulic, meteorological, and hydrographs are provided herein with additional hydrographs provided in the Volume 1 Plans.
1.2 WEATHER DATA
The climatological data listed below was obtained from the website https://www.ncdc.noaa.gov/cdo-web/datatools/normals. It is maintained by the US Department of Commerce, National Oceanic and Atmospheric Administration. This data pertains to station "Rough River Lake, KY US" for the period 1991-2020. Note that updated information from the NOAA discussing climate changes for the period 1991-2020 is available here:
https://www.ncei.noaa.gov/news/noaa-delivers-new-us-climate-normals.
Month Precip (in)
Average Min. Temp (F)
Average Temp (F)
Average Max. Temp (F)
January 3.60 24.4 34.0 43.6
February 3.85 26.3 37.4 48.6
March 4.46 33.6 45.9 58.2
April 5.30 42.9 56.4 70.0
May 6.00 52.9 65.7 78.5
June 4.78 61.6 74.1 86.6
July 4.20 65.4 77.8 90.2
August 3.24 63.3 76.5 89.8
DOCUMENT 00 31 19.23 06 Page 5
September 3.48 56.1 69.9 83.6
October 4.06 44.4 58.1 71.9
November 3.84 34.3 46.5 58.6
December 4.66 27.9 37.8 47.7
1.3 WORK RESTRICTIONS ASSOCIATED WITH POOL LEVEL
Work shall be restricted based on pool level and calendar as described herein. The below criteria may be revised by the Contracting Officer, upon recommendation from the W.C.A.P., after completion of demonstration areas and test sections to more accurately reflect construction sequences, scheduled time of completion, and the calendar year to occur:
a. Outlet Works Construction: Releases during this phase shall be controlled by the existing outlet works. The Contractor shall construct a cofferdam to Elevation 525 with a controlled overtopping zone 50 feet long at Elevation 524 along the left cofferdam abutment.
At reservoir Elevation 510, the W.C.A.P. and Contractor Site Safety Health Officer (SSHO) shall convene to assess reservoir loading, seasonal uncertainty, cofferdam performance, spillway evacuation, and upcoming weather forecasts to determine if working conditions are safe to proceed. At pools above 510 the Contractor shall provide at least 1 dedicated individual to monitor performance of the Cofferdam 24 hours per day until a history of satisfactory performance is obtained, or at any point personnel, equipment, and completed work are threatened by cofferdam performance issues such as slope instability, sandboils, or embankment cracking. Above Elevation 515 the W.C.A.P. must meet at least bi-weekly, or as needed, to assess risks for any potential spillway flow event.
Additionally, blasting operations shall cease within 250 feet of the Control tower cofferdam when the reservoir exceeds Elevation 515.
Exceptions may be granted from the Contracting Officer in writing for instances where no personnel, equipment, or permanent work are placed at risk from potential inundation of the excavation. At a reservoir level of 521, or upon the direction of the Contracting Officer or SSHO, no personnel are permitted to enter the control tower excavation behind the cofferdam. The Contractor must remove all personnel, equipment, and materials from the protected area if reservoir levels are projected to reach an elevation of 521.
In the stilling basin and for the tunnel, all work in the area must be evacuated by the time the tailwater reaches the 450 elevation. The W.C.A.P. may recommend ceasing work sooner based on weather forecasts and the amount of seepage entering the excavation.
b. Underwater Excavation: See Specification Section 31 23 05.00 06 MASS EXCAVATION paragraphs for measurement and payment for underwater reservoir level limitations specific to underwater dredging/excavation and underwater blasting. Note that blasting within 25 feet of water shall only be conducted when the reservoir is below elevation 490.
DOCUMENT 00 31 19.23 06 Page 6
Gradual drawdown of the reservoir normally begins on 15 October and is scheduled for completion to an elevation of 470 on 1 December. The rate of drawdown is dependent on rainfall and inflow conditions. There are years in the historical record where heavy rainfall prevented the drawdown for the reservoir from reaching winter pool. On any given year requiring underwater blasting, the Contractor can request that the maximum drawdown rate be initiated on October 1st. The maximum amount the reservoir can be drawn down is 0.75 feet per day and is contingent upon rainfall and project inflows. Submit requests in writing to the Contracting Officer at least 120 days in advance. Submitting a request is no guarantee that such request will be approved by the Contracting Officer. In the event of heavy rains, the reservoir can rise very quickly. The Contractor is solely responsible for planning and sequencing the operation around reservoir fluctuations. Appropriate length spuds, evacuation plans, temporary mooring to allow for significant pool rise, and proper planning/sequences of work based on available weather forecasts are required.
c. Upstream Cofferdam Construction and Grout Curtain: The Stage 1 cofferdam allows for construction of the main cofferdam and required foundation treatment to occur in the dry. The Contractor may request an early drawdown beginning on September 1 on any given year but such request must be received in writing by the Contracting Officer at least 120 days in advance. Requests will be accepted or rejected by the Contracting Officer within 45 days of receiving the request.
d. Existing Conduit Abandonment: After the new outlet works has been in operation for 30 days, re-inspected, and formally approved by the Government,the W.C.A.P. shall convene to assess reservoir loading, seasonal uncertainty, and upcoming weather forecasts to determine when the existing conduit abandonment may proceed. The work shall be sequenced to occur during a time period where minimum releases from the new outlet works shall not result in reservoir levels above 515 or associated releases will not flood the Contractor's downstream operation at the stilling basin. Prior to approval of the new outlet works, the Contractor may elect to sandbag the existing stilling basin end sill up to elevation 438 and remove any fish trapped in the existing stilling basin. Alternative methods for earth or steel cofferdams must be approved by the Contracting Officer at least 30 days in advance. After approval of the new outlet works, the Contractor must execute procedures to abandon the existing outlet works detailed on Contract Drawings CTW-CG-502 through CTW-CG-506. The Contractor shall be responsible for evacuating the conduit/stilling basin of all manpower, equipment, and materials in a timely manner in the event heavy rainfall occurs with the potential to overtop the downstream cofferdam. Additionally, the Contracting Officer may direct evacuation of all personnel, materials, and equipment from the conduit and stilling basin upon recommendation from the W.C.A.P.
e. Cut-off Wall Critical Area A from Station 22+40 to Station 22+70 - Work related to excavation at the conduit, demolition of the conduit, and severing the conduit shall not be initiated if there is high water or forecasts for high water at the reservoir. The reservoir must be drawn down to a minimum pool of 500 before work will be permitted to proceed by the Government. Historically, the months of July through December have proven to have less fluctuations compared to the months of January through June. To avoid risks of high water during construction, work associated with placement of the Special Panel/Secants shall occur in continuous shifts until completion. If
DOCUMENT 00 31 19.23 06 Page 7 necessary, the Contracting Officer may halt operations and direct emergency backfilling procedures upon recommendation from the W.C.A.P.
f. Cut-off wall construction in critical areas: The W.C.A.P. will advise the Contracting Officer as to whether to proceed with the current element(s) under construction or to abandon the element(s) by placing low strength concrete or by adding cement to the slurry with the intention of returning to the element and reworking the area. No new excavations shall begin at pools above 510 without approval from the Contracting Officer.
g. Retreat Channel Construction: Rough River is a flood control reservoir with releases from the reservoir into the tailwater area governed by inflows into the reservoir, reservoir levels, and downstream channel conditions. The Government is not permitted to deviate from authorized operations. The outlet works alignment between Stations 25+30 and 30+70 must contend with fluctuating tailwater levels while allowing for continued operation of the flood control project.
The area between approximate Stations 25+30 to 27+00 supports the existing stilling basin access road. This area must be excavated last and cannot be removed until alternative access roads to the existing stilling basin are provided for USACE Staff. The area between Stations 27+00 and 30+70 is located within the existing retreat channel that is required to remain functional for the existing outlet works to make releases. The area between Station 25+30 and 30+70 has special restrictions and requirements that must be followed as indicated in specification 31 23 05.00 06 MASS EXCAVATION. The Contractor must submit written notification to the Contracting Officer at least 45 days in advance for intent to complete the tailwater work for any given phase so that coordination with W.C.A.P. can be established. For worker safety, no work must be permitted if releases exceed 1,600 cfs or the tailwater pool exceeds an elevation of 439.5.
The Contractor can access the Daily Lake Report at https://www.lrl-wc.usace.army.mil/reports/lkreport.html.
The area between Stations 27+00 and 30+70 is best completed during the summer months (July-September)which greatly reduces risks for high water but is no guarantee to the Contractor that favorable conditions will exist during this period. Work stoppages related to high tailwater or high releases do not constitute a delay by the Government. The work must be completed at any point before the control tower, tunnel, and stilling basin are fully functional. Therefore multiple working seasons exist to perform the work during optimal weather conditions and off the critical path schedule.
1.4 HYDROLOGIC CONDITIONS
The reservoir elevation varies throughout the year. The yearly Rough River Lake Report from 1983 to 2024 is available at the following website:
https://www.lrl-wc.usace.army.mil/reports/yearly/Rough%20River%20Lake.html.
Typicall, elevation 442 (or stage 42 per the USGS datum) at the end sill is only surpassed as the result of high releases from the reservoir, not from back flooding downstream. Information for the tailwater stage data from 1999 to 2024 is available at the following link:
https://waterdata.usgs.gov/ky/nwis/uv/?site_no=03318010&PARAmeter_cd=00065,00060.
Monthly tailwater hydrogrpahs from 1983 to 2024 are contained in the Volume 1 Plans. Hydrographs detailing the relationship between the pool, tailwater, and rainfall are also included in the Volume 1 plans. A stage
DOCUMENT 00 31 19.23 06 Page 8 frequency curve for the reservoir and tailwater are available in the Geotechnical Interpretive Report.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
-- End of Section --
DOCUMENT 00 31 19.23 06 Page 9
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 31 19.23 06 Page 10
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 31 31.13 06
SUBSURFACE INVESTIGATION INFORMATION
08/24
PART 1 GENERAL
1.1 GEOTECHNICAL DOCUMENTS PROVIDED
1.1.1 Contractor Required Investigations
1.1.2 Contractor Installed Instruments
1.2 INSPECTION OF GEOLOGIC SAMPLES
1.3 REFERENCE INFORMATION ON SUBSURFACE CONDITIONS
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 Disclaimer
-- End of Section Table of Contents --
DOCUMENT 00 31 31.13 06 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 31 31.13 06 Page 2
SECTION 00 31 31.13 06
SUBSURFACE INVESTIGATION INFORMATION
08/24
PART 1 GENERAL
1.1 GEOTECHNICAL DOCUMENTS PROVIDED
Subsurface exploratory borings have been obtained by the Government to determine the general character of the subsurface materials within the project area. During 2018 and 2019 a subsurface investigation was conducted in support of the outlet works construction consisting of 39 borings advanced in soil and/or bedrock and 13 test pits advanced in soil. The subsurface investigation techniques included augering soil with hollow-stem augers, soil samples obtained via standard penetration testing and undisturbed sampling methods, rock drilling using rotary diamond core tooling, down-hole televiewer surveys, logged rock core, and specific soil and rock testing. The boring location plans and boring logs are included in the Volume 1 Plans. Boring logs and subsurface information for the exploration is generally located in the Geotechnical Interpretive Report (GIR). Information specific to tunnels is included in the Geotechnical Baseline Report (GBR) and Geotechnical Data Report (GDR).
Project specific subsurface information including previous investigations, previous construction activities, previous laboratory test results and boring logs are included For Information Only (FIO) in the GIR contained in Volume 6 of the Contract Documents. The GIR Appendix includes a comprehensive set of boring locations plans along with an index of previous investigations, borings, and locations. While the borings are generally representative of subsurface conditions at their respective locations, localized variations of characteristics of the subsurface materials should be anticipated. Groundwater elevations, shown on the boring logs, are those encountered at the time when the borings were taken and will fluctuate due to factors such as rainfall, lake, and/or river stages.
The Phase IB Exploratory Drilling and Grouting Construction Completion Report is also included in Volume 6 For Information Only (FIO). The Phase IB Boring and televiewer logs are made available in a stand-alone document also in Volume 6: Phase IB Boring Logs. The Government assumes no responsibility for any interpretations made by the Contractor from FIO boring logs, data, or reports.
The tunnel specific Geotechnical Baseline Report (GBR) is a contractual document contained in Volume 5 of the Contract Documents. The GBR provides design data and other key information that shall be the basis of the Contractor's bid for the tunnel. The Geotechnical Data Report (GDR) contains tunnel specific subsurface information data, including boring logs and laboratory testing, that is the basis of the GBR interpretations and is also available in Volume 5 of the Contract Package.
1.1.1 Contractor Required Investigations
See Specification Section 02 32 00 ADDITIONAL INVESTIGATIONS. All soil drilling, rock drilling, interfaces, and backfilling shall be in accordance with ER 1110-1-1807 Drilling and Invasive Activities at Dams and Levees and EM 1110-1-1804 Geotechnical Investigations. A Drilling and Invasive
DOCUMENT 00 31 31.13 06 Page 3
Activities Program Plan (DIPP) shall be completed by the Contractor and accepted by the Government. It is the Contractor's responsibility to obtain information required for inclusion in the drilling plan.
1.1.2 Contractor Installed Instruments
During the Contract duration the contractor shall install instrumentation to monitor the work platform, cofferdam, and to augment existing instrumentation in the dam area as indicated on the Contract Drawings and per Specification 31 09 13.00 06 INSTRUMENTATION AND MONITORING, A Drilling Plan shall meet the requirements of ER 1110-1-1807.
1.2 INSPECTION OF GEOLOGIC SAMPLES
Samples taken during geologic investigations by the Government are available to Contractors and bidders for examination. This data represents the best subsurface information available; however, variations may exist in the subsurface between boring locations. Contractors and bidders may inspect these cores and samples during the solicitation period as follows:
Louisville Repair Station Warehouse 2605 Shippingport Drive Louisville, KY 40212
Select soil samples and rock core are available for viewing by appointment from 09:00 to 14:00 EST, Monday through Thursday during the two week period identified on SAM.GOV. Any request for viewing shall be by appointment only. Requests for all viewings are to be submitted by sending an e-mail to robert.e.wheeler@usace.army.mil and STEVEN.A.HITE@USACE.ARMY.MIL with SUBJECT: "ROUGH RIVER PHASE II NEW OUTLET WORKS AND CUT-OFF WALL - your company name. Requests are to include the information required by FAR 52.236-27 SITE VISIT." All appointments will only be issued to Prime Contractor’s/JV’s; the prime is responsible to coordinate the visit date and time with subcontractors.
Each Prime Contractor will be limited to what rock core can be examined during an 8-hour time period. Prime Contractor’s are limited to a maximum inspection time of 16 hours. Bidders must indicate the stationing involved for the cores which they would like to inspect during viewing. The Government will pull the requested pallets out into the warehouse bay. The Contractor must provide any required laborers and/or specialty equipment required to lay the core out. The Contractor must take precautions to protect the core. The Contractor shall provide laborers to lay out the specimens, rebox the specifimens, and re-stack the specimens when finished. Prospective offerors are encouraged to avail themselves of all existing information before preparation of their offer. Reservations must be confirmed with the Government 14 days in advance.
1.3 REFERENCE INFORMATION ON SUBSURFACE CONDITIONS
Reference information on subsurface conditions at the project site is contained in the following reports:
USACE Louisville District, Rough River Dam (KY03012) Geotechnical Data Report for Tunnel Construction (Volume 5).
DOCUMENT 00 31 31.13 06 Page 4
USACE Louisville District, Rough River Dam (KY03012) Geotechnical Baseline Report for Tunnel Construction (Volume 5).
USACE Louisville District, Rough River Dam (KY03012) Geotechnical Interpretive Report for Rough River Dam Safety Modification Phase II (Volume 6).
Advanced Construction Techniques, ACT Inc., Rough River Dam Phase IB - Exploratory Drilling and Grouting Completion Report – Rough River Dam, Grayson County KY, prepared for USACE Louisville District, August 2017 (Volume 6).
Rough River Phase IB Drilling LFoundaton and Materials Completion Report (USACE) (Volume 6).
Phase IB Drilling Logs (Volume 6).
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 Disclaimer
Geotechnical data is provided for information and convenience of bidders.
The Government disclaims responsibility for interpretation of the provided data by others, or faulty interpretation of data on behalf of the Contractor, with the exception of data contained in the plans, specifications and GBR.
-- End of Section --
DOCUMENT 00 31 31.13 06 Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 31 31.13 06 Page 6
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 80 00.00 0
SPECIAL PROVISIONS
04/21, CHG 1: 06/23
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.3.1 Additional Requirements/Clarifications of Work Included Within the Contract
1.4 NOT USED
1.5 NOT USED
1.6 CONTRACT DRAWINGS AND SPECIFICATIONS
1.7 AS-BUILT DOCUMENTS FOR DESIGN BID BUILD PROJECTS
1.7.1 General
1.7.1.1 As-Built Drawings
1.7.1.2 Government-Furnished Files
1.7.2 Withholding
1.7.2.1 Failure to Maintain
1.7.2.2 As-Builts Prepared by Contractor
1.7.3 Maintenance of Working As-Built Drawings
1.7.3.1 Digital CAD/BIM Files
1.7.4 Preliminary (Working) As-Built Drawings
1.7.5 Preparation of Final As-Built Drawings
1.7.6 Markings and Indicators
1.7.7 Construction Contract Specifications
1.7.8 Preparation of Other As-Built Documents
1.7.9 Submittal of Final As-Built Documents
1.7.10 Partial Occupancy
1.7.11 Electronic File Use
1.8 NOT USED
1.9 EQUIPMENT DATA, O&M, & REPAIR MANUALS WITH FIELD TRAINING
REQUIREMENTS
1.9.1 Real Property Equipment
1.9.2 O&M and Repair Manuals
1.9.3 Field Training
1.9.3.1 Training Course
1.9.3.2 Training Recording
1.10 AVAILABILITY OF UTILITIES
1.10.1 Alterations to Utilities
1.10.2 Interruptions of Utilities
1.11 QUANTITY SURVEYS
1.12 PERFORMANCE OF WORK BY THE CONTRACTOR
1.13 SUPERINTENDENCE OF SUBCONTRACTORS
1.14 IDENTIFICATION OF EMPLOYEES
1.15 NO ASBESTOS - CONTAINING MATERIAL (ACM) CERTIFICATION
1.15.1 Not Used
1.15.2 Construction Phase
1.16 WARRANTY OF CONSTRUCTION
DOCUMENT 00 80 00.00 06 Page 1
1.17 SALVAGE MATERIALS AND EQUIPMENT
1.18 NOT USED
1.19 PROJECT SIGN
1.20 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.21 INTERFERENCE WITH TRAFFIC AND PUBLIC AND PRIVATE PROPERTY
1.22 AIRSPACE/FAA FORM 7460-1
1.23 GOVERNMENT FIELD OFFICE FACILITIES AND SERVICES.
1.24 COMPLIANCE WITH POST/BASE REGULATIONS
1.25 COST PRINCIPLES AND PROCEDURES FOR MODIFICATION
1.26 ENGLISH-SPEAKING REPRESENTATIVE
1.27 SALES and USE TAX
1.28 CONTRACTOR SECURITY TRAINING/FACILITY ACCESS REQUIREMENTS
1.28.1 Critical Infrastructure
1.28.2 Supplemental Security Requirements
1.28.3 For All Louisville District Contracts
1.28.4 For Contractors Requiring DOD Common Access Card (CAC)
1.28.5 Foreign Nationals
1.29 INSURANCE--WORK ON A GOVERNMENT INSTALLATION
1.30 AVAILABILITY OF SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)
1.31 HAUL ROADS
1.32 RADIOACTIVE MATERIAL/EQUIPMENT
1.33 CONSTRUCTION HAZARD COMMUNICATION
1.34 NOT USED
1.35 RED ZONE MEETING
1.36 PARTNERING
1.37 PROGRESS PHOTOGRAPHS
1.38 DAMAGE TO WORK
1.39 SIGNAL LIGHTS
1.40 LAKE OPERATION
1.41 NOT USED
1.42 RESPONSIBILITY OF THE CONTRACTOR FOR DESIGN ELEMENTS
1.43 REGISTRATION OF DESIGNERS
1.44 DESIGN CONFERENCES
1.45 FINAL CLEANING
1.46 BASIS FOR SETTLEMENT OF PROPOSALS
1.47 NOT USED
1.48 PROTECTION OF HISTORIC PROPERTIES
1.49 Sub Title
1.50 NOT USED
1.51 FIRE PROTECTION DURING CONSTRUCTION
1.52 AVAILABILITY OF SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)
1.53 WAGE RATES
1.54 NOT USED
1.55 SEQUENCE OF WORK
1.56 NOT USED
1.57 NOT USED
1.58 NOT USED
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION NOT USED
-- End of Section Table of Contents --
DOCUMENT 00 80 00.00 06 Page 2
SECTION 00 80 00.00 06
SPECIAL PROVISIONS
04/21, CHG 1: 06/23
PART 1 GENERAL
Attachments to this specification are as follows:
Construction Project Sign Details Project Submittal Register Outlet Works Operability Checklist
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-600-01 (2016; with Change 5, 2020) Fire Protection Engineering for Facilities
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY (DA)
AR 530-1 Operation Security
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Health Requirements Manual
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926.59 Hazard Communication
33 CFR 81 International Navigation Rules
33 CFR 84-90 Inland Navigation Rules
1.2 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
DOCUMENT 00 80 00.00 06 Page 3
SD-01 Preconstruction Submittals
Local Agency Check; G
SF1413 Statement and Acknowledgement
Radioactive Material/Equipment; G
Contour Map of Pre-developed Disposal Areas; G, DO
Pre-Construction Site Survey; G, DO
SD-02 Shop Drawings
SD-04 Samples
Equipment Warranty Identification Tags; G
SD-05 Design Data
Progress Photographs; G,DO
Stilling Basin Dewatering and Maintenance System; G, DO
SD-07 Certificates
Warranty of Construction; G
NO ASBESTOS - CONTAINING MATERIAL (ACM) CERTIFICATION; G
Construction Phase:
Certification for each individual product installed and identified to contain mineral fibers that no asbestos-containing materials were installed; G
Documentation to show that the products containing mineral fiber materials have been microscopically examined by an AIHA- or NVLAP-certified laboratory and the lab has determined that the material does not contain asbestos; G
Insurance; G
Sales and Use Tax
Labor, Equipment, and Material Report
SD-10 Operation and Maintenance Data
OUTLET WORKS APPROVAL, DEMONSTRATION, AND ACCEPTANCE; G, DO
Procedures and requirements for Completion of Outlet Works Prior to Operation
SD-11 Closeout Submittals
Preliminary (Working) As-Built Drawings; G, DO
DOCUMENT 00 80 00.00 06 Page 4
Final As-Built Drawings; G, DO
CAD Working As-Built Drawings; G, DO
CAD/BIM Working Digital 3D Model Monthly Updates; G, DO
Final CAD/BIM Digital 3D Model; G, DO
Warranty Management Plan; G
Contour Map of the Final Disposal Areas; G, DO
Post-Construction Site Survey; G, DO
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
Refer to clause 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 00 for the amount of Liquidated Damages for the project.
Refer to clause 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for a notification of significant contract dates.
1.3.1 Additional Requirements/Clarifications of Work Included Within the Contract
a. The time stated in clause 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 00 for completion shall include installation of Government-furnished furniture, if required, as well as as-built drawings, O&M manuals, operational tests/reports/training/instructions, equipment lists.
b. Requirements for Outlet Works Demonstration and Acceptance.
The Contractor is responsible to maintain access and security to the control tower and new construction facilities for the life of the Contract. The Contractor shall maintain ownership of all property and equipment provided during the life of the contract until property has been turned over to the Government. Prior to completion of the contract, the new outlet works will be put into service in order to allow decommissioning of the existing outlet works. The process of approval for the new outlet works requires a Government Pre-Operational Inspection, a 30 day demonstration period, and a Government Post-Operational Inspection. This process will be paid for under OUTLET WORKS APPROVAL, DEMONSTRATION, AND ACCEPTANCE with the Pre-Inspection designated as PI #1A and the Post-Inspection designated PI#1B. All incidental costs associated with the performance of work in this section are included in the contract price for items b-d below. The Government will make no additional separate payment for items included herein or by reference.
In order for the Contractor to request the Pre-Operational inspection the following criteria must be met:
1. The control tower, conduit, stilling basin, and retreat channel were constructed in accordance with the plans and specifications with no known defects or operational issues.
2. The Contractor must have independently verified that all mechanical and electrical systems are functioning as designed and that all required bulkheads, screens, and other operational equipment fit
DOCUMENT 00 80 00.00 06 Page 5 within the designated slots.
3. All interior building components and finishes necessary for successful operation of the outlet gates and by-pass systems shall be complete and tested by the Contractor prior to first operational discharge. Non-critical interior finishes may be completed after the control works are placed into service but before final contract completion and transfer of property to the Government.
4. All areas are to be cleaned as appropriate for access and operation.
5. All utilities and systems serving the building shall be fully operational.
6. The HVAC system(s) must be in operation, demonstrated, and fully balanced.
7. The elevator(s) shall be operable and certified for use by the approving agency and must be made available, at no additional cost, for use by the project staff.
8. The Contractor must notify the Government in writing at least 30 days in advance of intent to proceed with the Pre-Operational Inspection. The request must include verification that the above criteria have been met. The actual inspection schedule and dates will be provided from the Contracting Officer.
b1. Government Pre-Operational Inspection.
The new outlet works shall be inspected and approved by the Contracting Officer, in writing, for initial operability acceptance. The Contractor shall anticipate 5 days of inspections lasting up to 8 hours each day to assist Government Dam Safety Inspectors to fully verify the system is operable and fit to be placed into service. These inspections must take priority over all other work activities ongoing around the project and the Contractor will manage the site and schedule to minimize disruptions. The Contractor shall provide support to include labor to operate machinery and equipment, labor and equipment to accompany the inspections, and the resources to quickly correct any deficiencies noted. The Contractor must support the inspections as follows:
1. The Government Dam Safety Inspectors will be divided into 5 teams (Structures, Mechanical, Electrical, Geotech/Geology, and Hydraulics).
At least one representative from the Contractor shall accompany each team.
2. All mechanical, electrical, and structural equipment must be operated, tested, and documented by the Government Inspectors.
3. Hydraulic steel structures will be set and removed by the Contractor in sequence so each gate, screen, or bulkhead can be inspected by the Government Inspectors. The service and emergency gates, bypass valves, and maintenance and bypass bulkheads, and stilling basin stoplogs, must be operated and inspected. Acceptance criteria for these items are detailed herein.
4. Air monitoring equipment, lifts, ladders, scaffolds, boats etc.
must be provided by the Contractor as required to inspect each area.
DOCUMENT 00 80 00.00 06 Page 6
Each Government Inspector will provide their own specialty hand tools and equipment.
5. An OUTLET WORKS OPERABILITY CHECKLIST must be completed and approved by the Government Inspectors verifying the structure is fit for operation. The inspection checklist is attached to this specification. Any deficiencies noted must be corrected and reinspected/approved by the Government Inspectors before the Contracting Officer will certify the post-inspection is acceptable.
6. Any noted concrete repairs that were required as part of Section 03 70 00 MASS CONCRETE, Section 03 30 00, CAST-IN-PLACE CONCRETE OUTLET WORKS, or Section 31 73 00 TUNNEL GROUTING must be fully inspected and evaluated prior to placing the outlet works into service. Cracked or spalled areas may require additional repairs by the Contractor before the outlet works is placed into service. The cost required concrete repairs is the responsibility of the Contractor.
7. Written acceptance for the Pre-Operational Inspection will be provided from the Contracting Officer.
8. The Contractor is responsible for facilitating and maintaining safe access to all required locations in accordance with EM 385-1-1 including air monitoring, fall protection, and confined space entry.
b2. 30-Day Operability Demonstration.
Once the structure is deemed operable by the Contracting Officer, the new outlet works shall be placed into service to demonstrate performance for a period of 30 days. The Contractor will maintain ownership of equipment (mechanical, electrical, and hydraulic) during this operational demonstration period. During this period, Louisville District Operations personnel shall be required to make gate operations to regulate the reservoir. The Contractor and Government Construction personnel shall accompany LRL Operations in the Control Tower for required gate operations to regulate the reservoir, or any other routine Dam Safety activity. Such requirements during the 30 day operability period shall be coordinated between LRL Operations, LRL Construction, and the Contractor through the Water Control Advisory Panel. The Contractor shall furnish all utilities, including lighting and electrical power,during this operability period at no additional cost to the Government. At the completion of the demonstration period the outlet works will be inspected per the requirements of Section b3.
UNDER NO INSTANCE SHALL THE CONTRACTOR OR CONSTRUCTION PERSONNEL MAKE
ANY ADJUSTMENTS TO THE CONTROL TOWER FLOOD CONTROL SETTINGS DURING THIS
PERIOD.
b3. Government Post-Operational Inspection.
After the 30 day operability demonstration is complete, a Government Post-Operability Inspection shall be completed by the Government with the same labor, equipment, and time commitments from the Contractor as indicated for the Pre-Operational Inspection contained above. The Contractor must fully dewater the stilling basin, tunnel and install all three emergency bulkheads, bypass bulkheads in the tower to facilitate inspections. In addition to any operability deficiencies noted during the operations period, the post-inspection checklist must be filled out to verify no detrimental changes have occurred to the structures or equipment. Deficiencies noted shall be provided in writing from the Contracting Officer. Repairs to any damaged areas identified prior to and during the demonstration period shall be
DOCUMENT 00 80 00.00 06 Page 7 performed at no additional cost to the Government by the appropriate party as determined by the Contracting Officer.
Any repair/defect noted during the operability demonstration period for which subsequent repairs require the outlet works, or any portion of the outlet works, to recieve a structural or mechanical repair requires an additional operability demonstration as defined by the…