W912QR24R0044_Specs_Vol2-0000.pdf
PDF 3 MB Posted
- Solicitation number
- W912QR24R0044
About this file
This document is the specifications for the Energy Resilience and Conservation Investment Program (ERCIP) Microgrid project at the Ramey Army Reserve Center (ARC) in Aguadilla, Puerto Rico. The solicitation number is W912QR24R0044 and the estimated price range is between $10,000,000 and $25,000,000. The North American Industrial Classification System (NAICS) code is 237130 - Power and Communication Line and Related Structures Construction, with a size limitation of $45,000,000.
The specifications cover the technical requirements for the microgrid system, including HVAC, controls, electrical, and mechanical components. Key requirements include energy-efficient equipment, cybersecurity measures, testing and commissioning, and maintenance documentation. The project calls for the design-bid-build delivery method. Contractors must be registered in the System for Award Management (SAM) database and comply with HUBZone price evaluation requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Energy Resilience and Conservation Investment Program (ERCIP) Microgrid, Ramey Army Reserve Center (ARC), Aguadilla, PR
P2: 503254
Design-Bid-Build
Specifications - Vol. 2 of 2 (DIV 23 - 33) Certified Final Design
23 April 2024
W912QR24R0044
ARIMS: 200A Disposition: Maintain for 15yrs after construction.
W912QR24R0044_Specs_Vol2-0000
THIS PAGE INTENTIONALLY LEFT BLANK
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
P2#503254, PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 04/21 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 32 01.00 06 10/23 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29.00 06 11/17 SUSTAINABILITY REPORTING
01 35 26.00 06 04/20 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 11/16, CHG 2: 08/19 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 04.10 06 04/20 CONTRACTOR QUALITY CONTROL
01 45 35 11/20 SPECIAL INSPECTIONS
01 46 00.00 06 04/20 TOTAL BUILDING COMMISSIONING
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 06 04/20 TEMPORARY ENVIRONMENTAL CONTROLS AND
PERMITS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 27 36 05/17, CHG 3: 02/23 SPRAY FOAM AIR BARRIERS
07 57 12 09/23 LIQUID APPLIED ELASTOMERIC SILICONE
WALL COATING
07 57 16 09/23 LIQUID APPLIED ELASTOMERIC ACRYLIC
ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
DIVISION 09 - FINISHES
DOCUMENT PROJECT Page 1 Certified Final
ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
ERCIP Microgrids
09 90 00 02/21 PAINTS AND COATINGS
09 97 13.16 05/11, CHG 2: 08/19 INTERIOR COATING OF WELDED STEEL WATER
TANKS
09 97 13.27 02/21, CHG 1: 08/22 HIGH PERFORMANCE COATING FOR STEEL
STRUCTURES
DOCUMENT PROJECT Page 2 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.26 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS UTILITY CONTROL SYSTEM
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 19.00 10 11/22 INSULATED WIRE AND CABLE
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 23 00 05/15, CHG 2: 11/19 LOW-VOLTAGE SWITCHGEAR
26 28 00.00 10 08/22 MOTOR CONTROL CENTERS, SWITCHBOARDS
AND PANELBOARDS
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 31 00 11/21 FACILITY-SCALE SOLAR PHOTOVOLTAIC (PV)
SYSTEMS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 33 53 05/19 STATIC UNINTERRUPTIBLE POWER SUPPLY
(UPS)
26 33 61 08/23 STATIC BATTERY ENERGY STORAGE SYSTEM
(BESS)
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00.00 48 10/20 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 31 - EARTHWORK
31 00 00.00 06 07/18 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 10 00 02/21 SITE CLEARING
31 11 00 11/18 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/21 CHAIN LINK FENCES AND GATES
32 31 13.56 12/23 BLAST-RESISTANT GATES
32 92 23 04/06, CHG 1: 08/21 SODDING
DIVISION 33 - UTILITIES
33 01 50.31 02/20 LEAK DETECTION FOR FUELING SYSTEMS
33 05 23.13 11/19 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 40 00 11/21 STORMWATER UTILITIES
33 52 23.15 11/18 FUEL AND DIESEL EXHAUST FLUID (DEF)
SERVICE PIPING WELDING
33 52 40 11/18, CHG 2: 11/20 FUEL AND DIESEL EXHAUST FLUID (DEF)
SYSTEMS PIPING
33 52 43.11 08/18 FUEL AND DIESEL EXHAUST FLUID (DEF)
MECHANICAL EQUIPMENT
33 52 80 08/22 LIQUID FUELS PIPELINE COATING SYSTEMS
33 56 10 05/19, CHG 1: 11/20 FACTORY-FABRICATED FUEL STORAGE TANKS
33 57 55 11/18, CHG 1: 11/20 FUEL AND DIESEL EXHAUST FLUID (DEF)
SYSTEM COMPONENTS
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00.00 48 04/20 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
DOCUMENT PROJECT Page 3 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
SECTION 23 81 00
DECENTRALIZED UNITARY HVAC EQUIPMENT
05/18, CHG 1: 02/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI 350 (2015) Sound Rating of Non-Ducted Indoor Air-Conditioning Equipment
AHRI 390 (2003) Performance Rating of Single Package Vertical Air-Conditioners and Heat Pumps
AHRI DCAACP (Online) Directory of Certified Applied Air-Conditioning Products
ANSI/AHRI 640 (2005) Performance Rating of Commercial and Industrial Humidifiers
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 15 & 34 (2013) ASHRAE Standard 34-2016 Safety Standard for Refrigeration Systems/ASHRAE Standard 34-2016 Designation and Safety Classification of Refrigerants-ASHRAE Standard 34-2016
ASHRAE 52.2 (2012) Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size
ASHRAE 90.1 - IP (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME BPVC SEC IX (2017; Errata 2018) BPVC Section IX-Welding, Brazing and Fusing Qualifications
ASME BPVC SEC VIII D1 (2019) BPVC Section VIII-Rules for Construction of Pressure Vessels Division 1
AMERICAN WELDING SOCIETY (AWS)
AWS Z49.1 (2021) Safety in Welding and Cutting and
SECTION 23 81 00 Page 1 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
Allied Processes
ASTM INTERNATIONAL (ASTM)
ASTM B117 (2019) Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM D520 (2000; R 2011) Zinc Dust Pigment
ASTM D522/D522M (2017) Mandrel Bend Test of Attached Organic Coatings
ASTM D3363 (2005; E 2011; R 2011; E 2012) Film Hardness by Pencil Test
ASTM E84 (2023) Standard Test Method for Surface Burning Characteristics of Building Materials
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA MG 1 (2021) Motors and Generators
NEMA MG 2 (2014) Safety Standard for Construction and Guide for Selection, Installation and Use of Electric Motors and Generators
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 90A (2024) Standard for the Installation of Air Conditioning and Ventilating Systems
UNDERWRITERS LABORATORIES (UL)
UL 1995 (2015; Reprint Aug 2022) UL Standard for Safety Heating and Cooling Equipment
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Spare Parts
Posted Instructions
Coil Corrosion Protection; G
Training; G
Inventory
Supplied Products; G
SECTION 23 81 00 Page 2 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
Manufacturer's Standard Catalog Data; G
Humidifier
System Performance Tests; G
SD-06 Test Reports
Refrigerant Tests, Charging, and Start-Up; G
System Performance Tests; G
SD-07 Certificates
Service Organizations
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G
SD-11 Closeout Submittals
Ozone Depleting Substances; S
1.3 QUALITY ASSURANCE
Carefully investigate the plumbing, fire protection, electrical, structural and finish conditions that would affect the work to be performed and arrange such work accordingly, furnishing required offsets, fittings, and accessories to meet such conditions. Submit drawings consisting of:
a. Equipment layouts which identify assembly and installation details.
b. Plans and elevations which identify clearances required for maintenance and operation.
c. Wiring diagrams which identify each component individually and interconnected or interlocked relationships between components.
d. Foundation drawings, bolt-setting information, and foundation bolts prior to concrete foundation construction for equipment indicated or required to have concrete foundations.
e. Details, if piping and equipment are to be supported other than as indicated, which include loadings and type of frames, brackets, stanchions, or other supports.
f. Automatic temperature control diagrams and control sequences.
g. Installation details which includes the amount of factory set superheat and corresponding refrigerant pressure/temperature.
h. Equipment schedules
1.4 DELIVERY, STORAGE, AND HANDLING
Protect stored items from the weather, humidity and temperature
SECTION 23 81 00 Page 3 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
variations, dirt and dust, or other contaminants. Properly protect and care for all material both before and during installation. Submit an inventory of all the stored items. Replace any materials found to be damaged, at no additional cost to the Government. During installation, cap piping and similar openings capped to keep out dirt and other foreign matter.
1.5 ENVIRONMENTAL REQUIREMENTS
For proper Indoor Environmental Quality, maintain pressure within the building as indicated. Meet or exceed filter media efficiency as tested in accordance with ASHRAE 52.2 .
1.6 WARRANTY
Provide equipment with the 5 year manufacturer's warranty.
PART 2 PRODUCTS
2.1 ENERGY EFFICIENCY REQUIREMENTS
42 USC 8259b requires the procurement of energy efficient products in product categories covered by the Energy Star program or the Federal Energy Management Program for designated products. A list of covered product categories is available from the Federal Energy Management Web site at http://energy.gov/eere/femp/covered-product-categories.
Submit Material, Equipment, and Fixtures List of all supplied products within a covered product category, including manufacturer's catalog numbers, specification and drawing reference number, warranty information, fabrication site, and energy performance data. For product categories covered by the Federal Energy Management Program, submit documentation that the product meets or exceeds FEMP-designated efficiency requirements.
2.2 MATERIALS
Provide Manufacturer's standard catalog data, at least 5 weeks prior to the purchase or installation of a particular component, highlighted to show material, size, options, performance charts and curves, etc. in adequate detail to demonstrate compliance with contract requirements.
Data includes manufacturer's recommended installation instructions and procedures. If vibration isolation is specified for a unit, include vibration isolator literature containing catalog cuts and certification that the isolation characteristics of the isolators provided meet the manufacturer's recommendations. Submit data for each specified component. Minimum efficiency requirements must be in accordance with
ASHRAE 90.1 - IP .
2.2.1 Standard Products
Provide materials and equipment that are standard products of a manufacturer regularly engaged in the manufacturing of such products, which are of a similar material, design and workmanship. The standard products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2 year use includes applications of equipment and materials under similar circumstances and of similar size.
The 2 years' experience must be satisfactorily completed by a product which has been sold or is offered for sale on the commercial market
SECTION 23 81 00 Page 4 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
through advertisements, manufacturer's catalogs, or brochures. Products having less than a 2 year field service record will be acceptable if a certified record of satisfactory field operation, for not less than 6000 hours exclusive of the manufacturer's factory tests, can be shown.
Products must be supported by a service organization. Ensure system components are environmentally suitable for the indicated geographic locations.
2.2.2 Product Sustainability Criteria
2.2.2.1 Energy Efficient Equipment
Provide equipment meeting the efficiency requirements as stated within this section and provide documentation in conformance with Section 01 33 29.00 06 SUSTAINABILITY REQUIREMENTS AND REPORTING paragraph ENERGY
EFFICIENT EQUIPMENT.
2.2.2.2 Electrical Equipment / Motors
Provide electrical equipment, motors, motor efficiencies, and wiring.
Electrical motor driven equipment specified must be provided complete with motors, motor starters, and controls. Electrical characteristics must be as shown, and unless otherwise indicated, all motors of 1 horsepower and above with open, dripproof, totally enclosed, or explosion proof fan cooled enclosures, must be the premium efficiency type in accordance with NEMA MG 1. Field wiring must be in accordance with manufacturer's instructions. Each motor must conform to NEMA MG 1 and NEMA MG 2 and be of sufficient size to drive the equipment at the specified capacity without exceeding the nameplate rating of the motor. Motors must be continuous duty with the enclosure specified. Motor starters must be provided complete with thermal overload protection and other appurtenances necessary for the motor control indicated. Motors must be furnished with a magnetic across-the-line or reduced voltage type starter as required by the manufacturer. Motor duty requirements must allow for maximum frequency start-stop operation and minimum encountered interval between start and stop. Motors must be sized for the applicable loads. Motor torque must be capable of accelerating the connected load within 20 seconds with 80 percent of the rated voltage maintained at motor terminals during one starting period. Motor bearings must be fitted with grease supply fittings and grease relief to outside of enclosure. Manual or automatic control and protective or signal devices required for the operation specified and any control wiring required for controls and devices specified, but not shown, must be provided.
2.2.2.3 Ozone Depleting Substances
Unitary air conditioning equipment must not use CFC-based refrigerants.
Refrigerant may be an approved alternative refrigerant in accordance with EPA's Significant New Alternative Policy (SNAP) listing. Provide documentation in conformance with Section 01 33 29.00 06 SUSTAINABILITY REQUIREMENTS AND REPORTING paragraph OZONE DEPLETING SUBSTANCES.
2.2.3 Nameplates
Major equipment including compressors, condensers, receivers, heat exchanges, fans, and motors must have the manufacturer's name, address, type or style, model or serial number, and catalog number on a plate secured to the item of equipment. Plates must be durable and legible throughout equipment life and made of stainless steel. Fix plates in
SECTION 23 81 00 Page 5 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
prominent locations with nonferrous screws or bolts.
2.2.4 Safety Devices
Exposed moving parts, parts that produce high operating temperature, parts which may be electrically energized, and parts that may be a hazard to operating personnel must be insulated, fully enclosed, guarded, or fitted with other types of safety devices. Safety devices must be installed so that proper operation of equipment is not impaired. Welding and cutting safety requirements must be in accordance with AWS Z49.1 .
2.3 EQUIPMENT
2.3.1 Packaged Terminal Air Conditioners
2.3.1.1 Packaged Terminal Unit
Provide a vertical, through-the-wall, wall hung heavy-duty commercial grade, factory assembled and precharged air conditioner unit in accordance with AHRI 390 and UL 1995 . Provide units listed in AHRI DCAACP. Provide unit with a noise rating in accordance with AHRI 350 that does not exceed 85 dB while the entire unit is operating at any fan or compressor speed.
Provide Air Conditioners with a minimum energy efficiency ratio (EER) of 11.0, and
2.3.1.2 Compressor
Provide a hermetically sealed scroll type Compressor. Provide compressor with permanent split capacitor motor, overload protection, and vibration isolators. Protect compressor against high discharge pressure, loss of charge, low voltage, and short cycling.
2.3.1.3 Air to Refrigerant Coils
Provide evaporator and condenser coils with copper or aluminum tubes of 3/8 inch minimum diameter with copper or aluminum fins that are mechanically bonded or soldered to the tubes. Protect coil in accordance with paragraph COIL CORROSION PROTECTION. Provide casing of galvanized steel or aluminum. Avoid contact of dissimilar metals. Test coils in accordance with ASHRAE 15 & 34 at the factory and ensure they are suitable for the working pressure of the installed system. Dehydrate and seal each coil after testing and prior to evaluation and charging. Provide each unit with a factory operating charge of refrigerant and oil. Provide a condensate removal system.
2.3.1.4 Fans
Provide direct driven, statically and dynamically balanced, centrifugal type fans. Design the outdoor fan so that condensate will evaporate without drip, splash, or spray on building exterior. Provide indoor fan with a minimum two-speed motor with built-in overload protection. Fan motors must be the inherently protected, permanent split-capacitor type.
2.3.1.5 Air Filters
Provide standard filter on all packaged terminal units; 2 inch inch MERV 8, throwaway filter capable of filtering the entire air supply.
SECTION 23 81 00 Page 6 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
2.3.1.6 Primary/Supplemental Heat
Provide heating unit with internal thermal insulation having a fire hazard rating not to exceed 25 for flame spread and 50 for smoke developed as determined by ASTM E84.
2.3.1.7 Cabinet Construction
Provide cabinet free of visible fasteners, sharp protuberances and edges.
Enclosure sheet metal must be a minimum of 18 gauge steel with a protective coating. Provide removable face panels and allow full access to unit appurtenances. Access to controls must be without removal of the face panel. Discharge conditioned air through adjustable louvers.
Thermally and acoustically insulate the cabinet with materials which conform to NFPA 90A. Furnish units with a prewired subbase that has leveling screws with provisions for remote unit control. Subbase must be of 18 gauge galvanized steel construction with a protective coating to match that of the room cabinet. Paint and finishes must comply with the requirements specified in paragraph EQUIPMENT AND COMPONENTS FACTORY COATING. Provide exposed components and cabinet with coatings suitable for salt laden environment.
2.3.1.8 Wall Sleeve
Provide water and airtight completely insulated assembly, with weather-resistant protective coating.
2.3.1.9 Unit Controls
Controls must include an on-off switch, high and low selector switch for the cooling mode, multiple speed fan cooling mode, room air fan switch, and an adjustable cooling thermostat. Function and temperature controls must be remotely mounted as indicated or as accepted by the Contracting Officer.
Controls must include a control system interface to a BACnet or LonWorks control system, whichever is used by the control syste.
2.4 UNITARY EQUIPMENT ACCESSORIES AND MISCELLANEOUS EQUIPMENT
2.4.1 Humidifier
Provide humidifiers that meet the requirements of ANSI/AHRI 640
2.4.1.1 Refrigerant Signs
Refrigerant signs must be a medium-weight 304 stainless steel type with a baked enamel finish. Signs must be suitable for indoor or outdoor service. Signs must have a white background with red letters not less than
0.5 inches in height.
2.4.1.1.1 Installation Identification
Provide each new refrigeration system with a refrigerant sign which indicates the following as a minimum:
a. Contractor's name.
b. Refrigerant number and amount of refrigerant.
SECTION 23 81 00 Page 7 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
c. The lubricant identity and amount.
d. Field test pressure applied.
2.5 FINISHES
2.5.1 Coil Corrosion Protection
Provide coil with a uniformly applied high-performance epoxy-silane type coating to all coil surface areas without material bridging between fins.
Submit product data on the type coating selected, the coating thickness, the application process used, the estimated heat transfer loss of the coil, and verification of conformance with the salt spray test requirement. Coating must be applied at either the coil or coating manufacturer's factory. Coating process must ensure complete coil encapsulation. Coating must be capable of withstanding a minimum 1,000 hours exposure to the salt spray test specified in ASTM B117 using a 5 percent sodium chloride solution.
2.5.2 Equipment and Components Factory Coating
Unless otherwise specified, equipment and component items, when fabricated from ferrous metal, must be factory finished with the manufacturer's standard finish, except that items located outside of buildings must have weather resistant finishes that will withstand 6000 hours exposure to the salt spray test specified in ASTM B117 using a 5 percent sodium chloride solution. Immediately after completion of the test, the specimen must show no signs of blistering, wrinkling, cracking, or loss of adhesion and no sign of rust creepage beyond 1/8 inch on either side of the scratch mark. Cut edges of galvanized surfaces where hot-dip galvanized sheet steel is used must be coated with a zinc-rich coating conforming to ASTM D520, Type I.
Where stipulated in equipment specifications of this section, coat finned tube coils of the affected equipment as specified below. Apply coating at the premises of a company specializing in such work. Degrease and prepare for coating in accordance with the coating applicator's procedures for the type of metals involved. Completed coating must show no evidence of softening, blistering, cracking, crazing, flaking, loss of adhesion, or "bridging" between the fins.
2.5.2.1 High Performance Epoxy-Silane Coating
Apply coating using an airless fog nozzle. For each coat, make at least two passes with the nozzle. Materials to be applied are as follows:
a. Total Dry Film Thickness: 1.0 to 1.5 mils thick.
b. Cross Hatch Adhesion ASTM D522/D522M: 4B-5B.
c. Pencil Hardness ASTM D3363: 2H-4H.
d. Heat Transfer Reduction: Less than 1 percent as applied for heat transfer components.
2.5.3 Factory Applied Insulation
Refrigeration equipment must be provided with factory installed insulation
SECTION 23 81 00 Page 8 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
on surfaces subject to sweating including the suction line piping. Where motors are the gas-cooled type, factory installed insulation must be provided on the cold-gas inlet connection to the motor in accordance with manufacturer's standard practice. Factory insulated items installed outdoors are not required to be fire-rated. As a minimum, factory insulated items installed indoors must have a flame spread index no higher than 75 and a smoke developed index no higher than 150. Factory insulated items (no jacket) installed indoors and which are located in air plenums, in ceiling spaces, and in attic spaces must have a flame spread index no higher than 25 and a smoke developed index no higher than 50. Flame spread and smoke developed indexes must be determined by ASTM E84.
Insulation must be tested in the same density and installed thickness as the material to be used in the actual construction. Material supplied by a manufacturer with a jacket must be tested as a composite material.
Jackets, facings, and adhesives must have a flame spread index no higher than 25 and a smoke developed index no higher than 50 when tested in accordance with ASTM E84.
2.6 TESTS, INSPECTIONS, AND VERIFICATIONS
All manufactured units must be inspected and tested, and documentation provided to demonstrate that each unit is in compliance with ANSI/AHRI and UL requirements and that the minimum efficiency requirements of ASHRAE 90.1 - IP have been met.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with all details of the work, perform Verification of Dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.
3.2 INSTALLATION
Perform work in accordance with the manufacturer's published diagrams, recommendations, and equipment warranty requirements. Where equipment is specified to conform to the requirements of ASME BPVC SEC VIII D1 and ASME BPVC SEC IX , the design, fabrication, and installation of the system must conform to ASME BPVC SEC VIII D1 and ASME BPVC SEC IX .
3.2.1 Equipment
Provide refrigeration equipment conforming to ASHRAE 15 & 34 . Provide necessary supports for all equipment, appurtenances, and pipe as required, including frames or supports for compressors, pumps, cooling towers, condensers, and similar items. Isolate compressors from the building structure. If mechanical vibration isolators are not provided, provide vibration absorbing foundations. Each foundation must include isolation units consisting of machine and floor or foundation fastenings, together with intermediate isolation material. Other floor-mounted equipment must be set on not less than a 6 inch concrete pad doweled in place. Concrete foundations for floor mounted pumps must have a mass equivalent to three times the weight of the components, pump, base plate, and motor to be supported. In lieu of concrete pad foundation, concrete pedestal block with isolators placed between the pedestal block and the floor may be provided. Concrete pedestal block must be of mass not less than three times the combined pump, motor, and base weights. Isolators must be selected and sized based on load-bearing requirements and the lowest
SECTION 23 81 00 Page 9 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
frequency of vibration to be isolated. Isolators must limit vibration to 20-40 percent at lowest equipment rpm. Equipment must be properly leveled, aligned, and secured in place in accordance with manufacturer's instructions.
3.2.2 Field Applied Insulation
Apply field applied insulation to match manufacturer of equipment recommendations for salt laden environment.
3.2.3 Field Painting
Painting required for surfaces not otherwise specified, and finish painting of items to match manufacturer of equipment recommendations for salt laden environment.
3.3 CLEANING AND ADJUSTING
Equipment must be wiped clean, with all traces of oil, dust, dirt, or paint spots removed. Temporary filters must be provided for all fans that are operated during construction, and new filters must be installed after all construction dirt has been removed from the building. System must be maintained in this clean condition until final acceptance. Bearings must be properly lubricated with oil or grease as recommended by the manufacturer. Belts must be tightened to proper tension. Control valves and other miscellaneous equipment requiring adjustment must be adjusted to setting indicated or directed. Fans must be adjusted to the speed indicated by the manufacturer to meet specified conditions.
3.4 TRAINING
Conduct a training course for the operating staff as designated by the Contracting Officer. The training period must consist of a total 8 hours of normal working time and start after the system is functionally completed but prior to final acceptance tests.
a. Submit a schedule, at least 2 weeks prior to the date of the proposed training course, which identifies the date, time, and location for the training.
b. Submit the field posted instructions, at least 2 weeks prior to construction completion, including equipment layout, wiring and control diagrams, piping, valves and control sequences, and typed condensed operation instructions. The condensed operation instructions must include preventative maintenance procedures, methods of checking the system for normal and safe operation, and procedures for safely starting and stopping the system. The posted instructions must be framed under glass or laminated plastic and be posted where indicated by the Contracting Officer.
c. The posted instructions must cover all of the items contained in the approved operation and maintenance manuals as well as demonstrations of routine maintenance operations. Submit 3 complete copies of an operation manual in bound 8-1/2 by 11 inch booklets listing step-by-step procedures required for system startup, operation, abnormal shutdown, emergency shutdown, and normal shutdown at least 4 weeks prior to the first training course. The booklets must include the manufacturer's name, model number, and parts list. The manuals must include the manufacturer's name, model number, service manual, SECTION 23 81 00 Page 10 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
and a brief description of all equipment and their basic operating features.
d. Submit 3 complete copies of maintenance manual in bound 8-1/2 by 11 inch booklets listing routine maintenance procedures, possible breakdowns and repairs, and a trouble shooting guide. The manuals must include piping and equipment layouts and simplified wiring and control diagrams of the system as installed.
3.5 REFRIGERANT TESTS, CHARGING, AND START-UP
Packaged refrigerant systems which are factory charged must be checked for refrigerant and oil capacity to verify proper refrigerant levels in accordance with manufacturer's recommendations. Following charging, packaged systems must be tested for leaks with a halide torch or an electronic leak detector. Submit 3 copies of each test containing the information described below in bound 8-1/2 by 11 inch booklets.
Individual reports must be submitted for the refrigerant system tests.
a. The date the tests were performed.
b. A list of equipment used, with calibration certifications.
c. Initial test summaries.
d. Repairs/adjustments performed.
e. Final test results.
3.5.1 Refrigerant Leakage
If a refrigerant leak is discovered after the system has been charged, the leaking portion of the system must immediately be isolated from the remainder of the system and the refrigerant pumped into the system receiver or other suitable container. Under no circumstances must the refrigerant be discharged into the atmosphere.
3.5.2 Contractor's Responsibility
Take steps, at all times during the installation and testing of the refrigeration system, to prevent the release of refrigerants into the atmosphere. The steps must include, but not be limited to, procedures which will minimize the release of refrigerants to the atmosphere and the use of refrigerant recovery devices to remove refrigerant from the system and store the refrigerant for reuse or reclaim. At no time must more than 3 ounces of refrigerant be released to the atmosphere in any one occurrence. Any system leaks within the first year must be repaired in accordance with the requirements herein at no cost to the Government including material, labor, and refrigerant if the leak is the result of defective equipment, material, or installation.
3.6 SYSTEM PERFORMANCE TESTS
Before each refrigeration system is accepted, conduct tests to demonstrate the general operating characteristics of all equipment by a registered professional engineer or an approved manufacturer's start-up representative experienced in system start-up and testing, at such times as directed. Three copies of the report provided in bound 8-1/2 by 11 inch booklets. The report must document compliance with the specified performance criteria upon completion and testing of the system. The report must indicate the number of days covered by the tests and any conclusions as to the adequacy of the system.
SECTION 23 81 00 Page 11 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
For equipment providing cooling the system performance tests must be performed during the cooling seasons.
a. Submit a schedule, at least 2 weeks prior to the start of related testing, for the system performance tests. The schedules must identify the proposed date, time, and location for each test. Tests must cover a period of not less than 48 hours for each system and must demonstrate that the entire system is functioning in accordance with the drawings and specifications.
b. Make corrections and adjustments, as necessary, tests must be re-conducted to demonstrate that the entire system is functioning as specified. Prior to acceptance, install and tighten service valve seal caps and blanks over gauge points. Replace any refrigerant lost during the system startup.
c. If tests do not demonstrate satisfactory system performance, correct deficiencies and retest the system. Conduct tests in the presence of the Contracting Officer. Water and electricity required for the tests will be furnished by the Government. Provide all material, equipment, instruments, and personnel required for the test.
d. Submit 3 copies of the field test report provided in bound 8-1/2 by 11 inch booklets. The report must document compliance with the specified performance criteria upon completion and testing of the system. The report must indicate the number of days covered by the tests and any conclusions as to the adequacy of the system. Submit the report including the following information (where values are taken at least three different times at outside dry-bulb temperatures that are at least 5 degrees F apart):
(1) Date and outside weather conditions.
(2) The load on the system based on the following:
(a) The refrigerant used in the system.
(b) Condensing temperature and pressure.
(c) Suction temperature and pressure.
(d) Ambient, condensing and coolant temperatures.
(e) Running current, voltage and proper phase sequence for each phase of all motors.
(3) The actual on-site setting of operating and safety controls.
(4) Thermostatic expansion valve superheat - value as determined by field test.
(5) Subcooling.
(6) High and low refrigerant temperature switch set-points
(7) Low oil pressure switch set-point.
(8) Defrost system timer and thermostat set-points.
(9) Moisture content.
(10) Capacity control set-points.
SECTION 23 81 00 Page 12 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
(11) Field data and adjustments which affect unit performance and energy consumption.
(12) Field adjustments and settings which were not permanently marked as an integral part of a device.
3.7 MAINTENANCE
3.7.1 EXTRA MATERIALS
Submit spare parts data for each different item of equipment specified, after approval of detail drawings and not later than 2 months prior to the date of substantial completion. Include in the data a complete list of parts and supplies, with current unit prices and source of supply, a recommended spare parts list for 1 year of operation, and a list of the parts recommended by the manufacturer to be replaced on a routine basis.
3.7.2 Maintenance Service
Submit a certified list of qualified permanent service organizations, which includes their addresses and qualifications, for support of the equipment. The service organizations must be reasonably convenient to the equipment installation and be able to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.
-- End of Section --
SECTION 23 81 00 Page 13 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 23 81 00 Page 14 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
SECTION 25 05 11.26
CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS UTILITY CONTROL SYSTEM
05/21
PART 1 GENERAL
Many subparts in this Section contain text in curly braces ("{" and "}") indicating which cybersecurity control and control correlation identifier (CCI) the requirements of the subpart relate to. The text inside these curly braces is for Government reference only and enables coordination of the requirements of this Section with the RMF process throughout the design and construction process. Text in curly braces are not contractor requirements.
This Section refers to Security Requirements Guide (SRGs) and Security Technical Implementation Guide (STIGs). STIGs and SRGs are available online at the Information Assurance Support Environment (IASE) website at https://public.cyber.mil/stigs/downloads/ and an SRG/STIG Applicability Guide and Collection Tool is available at https://public.cyber.mil/stigs/SCAP/ . Not all control system components have applicable STIGs or SRGs. The "Control Systems SRG" does not apply to work performed under this Section; all requirements within this section to apply applicable SRGs DO NOT include the "Control Systems SRG".
1.1 CONTROL SYSTEM APPLICABILITY
There are multiple versions of this Section associated with this project.
Different versions have requirements applicable to different control systems. This specific Section applies only to the following control systems: Microgrid Control System (MCS).
1.2 RELATED REQUIREMENTS
This section does not contain sufficient requirements to procure a control system and must be used in conjunction with other Sections which specify control systems. This Section adds cybersecurity requirements to the control systems specified in other Sections, and as these requirements are conditioned on the control system being provided, there may be requirements in this Section that will not apply to this project. All Sections containing facility-related control systems or control system components are related to the requirements of this Section. Review all specification sections to determine related requirements.
In cases where a requirement is specified in both this Section and in another Section, the more stringent requirement must be met. In cases where a requirement in this Section conflicts with the requirements of another Section such that both requirements cannot be met at the same time, request direction from the Contracting Officer Representative to determine which requirement applies to the project.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
SECTION 25 05 11.26 Page 1 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 802.1x (2010) Local and Metropolitan Area Networks - Port Based Network Access Control
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST FIPS 140-2 (2001) Security Requirements for Cryptographic Modules
U.S. DEPARTMENT OF DEFENSE (DOD)
DODI 8551.01 (2014) Ports, Protocols, and Services Management (PPSM)
DTM 08-060 (2008) Policy on Use of Department of Defense (DoD) Information Systems - Standard Consent Banner and User Agreement
1.4 DEFINITIONS
1.4.1 Administrator Account
An administrator account is an account with full permissions to a device, application, or operating system, including the ability to create and modify other user accounts.
Note that the operating system Administrator Account may be different than Administrator Accounts for applications hosted on that operating system.
Also, most controllers will not have any support for accounts and will therefore not have an 'Administrator Account'.
1.4.2 Computer
A computer is one of the following:
a. a device running a non-embedded desktop or server version of Microsoft Windows
b. a device running a non-embedded version of MacOS
c. a device running a non-embedded version of Linux
d. a device running a version or derivative of the Android Operating System, where Android is considered separate from Linux
e. a device running a version of Apple iOS
Unless otherwise indicated or clear from context use of the word "device" in this Section includes computers.
1.4.3 Controller
A device other than a computer or Ethernet switch.
1.4.4 Mission Space
Mission space is shown on the drawings.
SECTION 25 05 11.26 Page 2 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
1.4.5 Network
A network is a group of two or more devices that can communicate using a network protocol. Network protocols must provide a method for addressing devices on the network; a communication method that does not provide an addressing scheme is not a networked form of communication. Devices that communicate using a method of communication that does not support device addressing are not using a network.
1.4.6 Network Connected
A component is network connected (or "connected to a network") only when the device has a network transceiver which is directly connected to the network and implements the network protocol. A device lacking a network transceiver (and accompanying protocol implementation) can never be considered network connected. Note that (unlike many IT definitions of "Network Connected") a device connected to a non-IP network is still considered network connected (an IP connection or IP address is not required for a device to be network connected).
1.4.6.1 Wireless Network Connected
Any device that supports wireless network communication is network connected to a wireless network, regardless of whether the device is communicating using wireless. Unless physically disabled, devices with wireless transceivers support wireless, it is not sufficient to disable the wireless in software.
1.4.7 Network Media
The thing that provides the communication channel between the devices on a network. Typically wire, but might include wireless, fiber optic, or even power line (some network protocols allow sending network signals over power wiring).
1.4.8 User Account Support Levels
The support for user accounts is categorized in this Section as one of three levels:
1.4.8.1 FULLY Supported
Device supports configurable individual accounts. Accounts can be created, deleted, modified, etc. Privileges can be assigned to accounts.
These devices support user-based (as opposed to role-based) authentication.
1.4.8.2 MINIMALLY Supported
Device supports a small, fixed number of accounts (perhaps only one).
Accounts cannot be modified. A device with only a "User" and an "Administrator" account would fit this category. Similarly, a device with two PINs for logon - one for restricted and one for unrestricted rights would fit here (in other words, the accounts do not have to be the traditional "username and password" structure). These devices typically only support role-based authentication.
Examples of devices which MINIMALLY support accounts are a) a variable frequency drive with a single account which requires a PIN for access to
SECTION 25 05 11.26 Page 3 Certified Final
P2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R. ERC. .
ERCIP MicrogridsP2#503428, ERCIP Microgrid, Pesquera ARC, Juana Diaz P.R ER.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.P2#503254, ERCIP MicrogridsERCIP Microgrid, Ramey ARC, Aguadilla P.R.ERCIP Microgrid, Ramey ARC, Aguadilla P.R.
configuration; and b) a room lighting control touchpad interface that has a single account.
1.4.8.3 NOT Supported
Device does not support any Access Enforcement therefore the whole concept of "account" is meaningless.
1.4.9 Manual Local Input
Manual Local Inputs are system analog or binary inputs that are adjustable by a person but are, by intrinsic hardware design, very limited in potential capabilities.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .