W912QR23R0024_NRP_PH2_VolB-0004.pdf
PDF 678 KB Posted
- Solicitation number
- W912QR23R0024
About this file
This document is a Scope of Work for a Design-Build task order under the National Roofing Program (NRP) Multiple Award Task Order Contract (MATOC) issued by the U.S. Army Corps of Engineers, Engineering District Louisville.
The task order requires the design and construction to replace roof systems at several facilities located in Hawaii, Indiana, and Pennsylvania. The work includes removing existing roof systems and installing new roof systems, such as EPDM, 3-ply modified bitumen, and PVC overlay systems. The contractor shall prepare complete construction documents, including drawings, specifications, and design analyses. The document provides detailed design requirements, milestones, and submittal distribution information. It also includes general construction requirements, such as site access, coordination with building occupants, and safety considerations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
National Roofing Program (NRP) FY24
Seed Projects
HI006, IN011, PA011
SECTION 01 11 50.00 06
CERTIFIED FINAL
AMENDMENT 0004
SECTION
01 11 50.00 06
Task Order SCOPE OF WORK
Amendment 0004
1. PROJECT INFORMATION
1.1. GENERAL
Design/Build: The Contractor shall provide all labor, equipment, supplies, and consultant services and all site investigations, surveys, analysis, sampling, testing and verification of existing field conditions as required for design and construction of the Roof Replacement Project at
HI006 to result in a complete and useable Facility. Contractor shall provide complete design analysis incorporating all engineering computations, analysis, test, and survey results, building code (including fire protection, life safety, environmental and accessibility) review as it pertains/affects/relates to this project, equipment and material data and documentation of existing conditions.
1.2. SCOPE OF WORK
Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base
MATOC contract Volume 1 of 2 shall apply to this Task Order. The work includes design and construction to replace the following roof systems located at HI006, IN011, PA011:
HI006, Building 1557
Section(s) Existing Roof System
1 Elastomeric Coating over standing seam metal roof over polyisocyanurate insulation between purlins over metal deck
HI006, Building 1556
Section(s) Existing Roof System
1 Elastomeric Coating over Structural Standing Seam Metal over batt insulation and structural metal purlins
2 Elastomeric Coating over Structural Standing Seam Metal over batt insulation and structural metal purlins
3 Single-ply PVC (full replacement)
HI006, Building 1558
Section(s) Existing Roof System
1 Elastomeric Coating over standing seam metal roof over polyisocyanurate insulation between purlins over metal deck
2 Elastomeric Coating over standing seam metal roof over polyisocyanurate insulation between purlins over metal deck
W912QR23R0024_NRP_PH2_VolB-0004
HI006, IN011, PA011
SECTION 01 11 50.00 06
CERTIFIED FINAL
AMENDMENT 0004
IN011
Building Section(s) Existing Roof System
USARC 1-5 Gravel Built Up Roof (BUR)
OMS 1-2 Gravel Built Up Roof (BUR)
PA011
Building Section(s) Existing Roof System
USARC 1-3 Low Slope Single Ply (EPDM)
OMS 1-2 Low Slope Single Ply (EPDM)
Design/Build: Design and construction shall comply with the requirements contained in this Task Order Request for Proposal (RFP). The design and technical criteria contained and cited in this RFP and the Unified
Facilities Guide Specifications (UFGS) establish minimum standards for design and construction quality. The Designers of Record shall use the
Unified Facilities Guide Specifications (UFGS) and the requirements contained in this RFP to fully develop the technical specifications and construction drawings. The objective of this solicitation is to obtain an energy efficient, durable, maintainable, and sustainable space.
Design/Build: The illustrations and exhibits included in this RFP illustrate the conceptual design of the project and are provided to define the scope of work and budget. The concepts provided shall be further developed by the Design/Build Contractor to comply with the customer’s functional needs.
All demolition required to construct the project is included as part of the work of this Contract.
1.3. SITE LOCATION
This projects are located at Ft Shafter Flats, Honolulu, HI, Ft Wayne, IN, and Brookville, PA.
1.4. EXISTING SITE UTILITIES
1.4.1. The contractor shall verify the location of all utilities serving the building. Upgrading the existing utilities, (unless noted otherwise) outside the limits of construction, is not a part of this project.
1.5. NOT USED
1.6. NOT USED
1.7. ATTACHMENTS
Design/Build: Information provided in the Attachments is intended to guide the completion of the design by establishing existing conditions, and the desired character, appearance, and function of the new construction. The
CERTIFIED FINAL
AMENDMENT 0004
following Attachments are included and shall be used and strictly adhered-to in completing the design and construction of the project.
IN011
a. ATTACHMENT A: Site Location
b. ATTACHMENT B: Building Layout Plans
c. ATTACHMENT C: Site Inspection Report, dated 8 October 2021 (FIO)
PA011
a. ATTACHMENT D: Site Location
b. ATTACHMENT E: Building Layout Plans
c. ATTACHMENT F: Site Inspection Report, dated 8 December 2021 (FIO)
HI006
a. ATTACHMENT G: Site Location
b. ATTACHMENT H: Building Layout Plans
c. ATTACHMENT I: Site Inspection Report, dated 8 September 2021 (FIO)
1.8. NOT USED
1.9. NOT USED
1.10. NOT USED
1.11. NOT USED
1.12. NOT USED
1.13. NOT USED
1.14. NOT USED
1.15. NOT USED
1.16. NOT USED
1.17. NOT USED
1.18. NOT USED
2. DESIGN REQUIREMENTS
2.1. GENERAL
The Contractor shall prepare complete construction documents for all work designed as required by the RFP. The construction documents to be prepared shall include, but are not limited to, construction drawings, specifications, submittals, and design analysis as required in Section 01
CERTIFIED FINAL
AMENDMENT 0004
33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD), Volume 1. Materials and equipment shall be limited to those specified except that where no specific material and equipment is specified or no basis of design is identified, the Contractor shall use materials and equipment accepted within the construction industry and in compliance with Design Criteria.
2.2. DESIGN
2.2.1. The Contractor shall prepare a 100% design for the project in accordance with the RFP using industry standard materials and efficient practices. The design of the materials selected shall be high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy, and coordination of all designs, drawings, specifications, and other documents or publications upon which the design and construction are based. It shall be the responsibility of the Design/ Build Contractor to verify the accuracy of the documents provided.
2.2.2. Design Milestone Schedule
HI006, Building 1556, 1557, 1558 - BASE
Notice to Proceed (NTP) Day 0
Design Quality Control Plan (DQCP) NTP + 14 Days
Design Kickoff Meeting (on-site) NTP + 45 Days
Charette Report (FIO) NTP + 60 Days
Final Submittal NTP + 140 Days
Final Plan in Hand Meeting (on-site) NTP + 165 Days
Corrected Final Submittal NTP + 185 Days
Certified Final Submittal NTP + 190 Days
IN011, USARC and OMS – OPTION 1
Design Kickoff Meeting (on-site) NTP + 60 Days
Charette Report (FIO) NTP + 75 Days
Final Submittal NTP + 155 Days
Final Plan in Hand Meeting (on-site) NTP + 180 Days
Corrected Final Submittal NTP + 200 Days
Certified Final Submittal NTP + 205 Days
PA011, USARC and OMS – OPTION 2
Design Kickoff Meeting (on-site) NTP + 90 Days
Charette Report (FIO) NTP + 105 Days
Final Submittal NTP + 185 Days
Final Plan in Hand Meeting (on-site)
NTP + 210 Days
CERTIFIED FINAL
AMENDMENT 0004
Corrected Final Submittal NTP + 230 Days
Certified Final Submittal NTP + 235 Days
2.3. REQUEST FOR PROPOSAL (RFP) INTENT
The intent of this RFP section is to describe the requirements for appearance, function, materials, and types of construction in sufficient detail to enable engineering and design to be completed by the Contractor.
2.4. Design Milestone Meetings
2.4.1. Charette / Kickoff Meeting
2.4.1.1. Shall be in person and on-site.
2.4.2. Final Design / Plan-in-hand Review Meeting
2.4.2.1. Shall be in person and on-site.
2.5. NOT USED
2.6. NOT USED
2.7. NOT USED
2.8. NOT USED
2.9. NOT USED
2.10. NOT USED
2.11. NOT USED
2.12. GOVERNMENT FURNISHED MATERIALS
2.12.1. GFM Handover
The GFM has been provided as part of the Solicitation package.
2.12.2. GFM File Formats
GFM are provided only in PDF format.
2.13. DESIGN SUBMITTAL DISTRIBUTION MATRIX
Submittal Reviewers & Mailing Addresses
U.S. Army Corps of Engineers
Ryan Fagan
RYAN.A.FAGAN@USACE.ARMY.MIL
LRL-ED-MA Room 414
600 Doctor Martin Luther King Junior Place
CERTIFIED FINAL
Louisville, KY 40202
Timothy M. McClellan, P.E., RRC
Timothy.M.McClellan@usace.army.mil
LRL-ED-MA Room 414
US Army Corps of Engineers – Wright Patterson Resident Office
John Hearn john.p.hearn@usace.army.mil
Supervisory Construction Control Rep, COR
LRL CDSO Chairman
OSHA SGE
2475 K Street Bldg 52
WPAFB OH 45433
Michael Brooks
Michael.s.brooks@usace.army.mil
LRL-CDR
Tim Ruhland timothy.j.ruhland@usace.army.mil
LRL-CDM-A
Jeffrey E. Bayers, P.E., P.M.P.
Jeffrey.E.Bayers@usace.army.mil
LRL-PM-R
Steve Coffey
USARC-ARIMD Engineering Branch
Program Manager: BUILDER, NRP, & FRP
Phone: 910-570-8961
Email: steven.w.coffey3.civ@army.mil
3. GENERAL CONSTRUCTION REQUIREMENTS
3.1. SUMMARY
3.1.1. The requirements include:
mailto:Timothy.M.McClellan@usace.army.mil mailto:Michael.s.brooks@usace.army.mil mailto:Jeffrey.E.Bayers@usace.army.mil
CERTIFIED FINAL
a. Construction considerations and use of the premises.
b. Protection of personnel and Government property.
c. Construction facilities and job site standards.
d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.
3.2. GENERAL INFORMATION
3.2.1. HI006 - Coordinate site access with Mark Bowling, Department of Public Works (DPW) at Fort Shafter Flats, Mark.J.Bowling4.mil@army.mil.
3.2.2. HI006 – Contractors without CAC cards to use
https://home.army.mil/hawaii/about/visitor-information to get visitor pass from US Army Garrison Hawaii (USAG-HI) for access to the site
3.2.3. HI006 – Operating hours are 0800-1600.
3.2.4. HI006, Building 1556, 1557, 1558 are 3-story buildings and require the use of lifts and/or cranes for roof installation.
3.2.5. IN011 – Operating hours are 0730-1630.
3.2.6. IN011 – No weekend work permitted due to the high number of units located at this facility.
3.2.7. PA011 – Operating hours are 0800-1630.
3.2.8. NOT USED
3.2.9. Coordinate all construction activities with:
a. Contracting Officer’s Representative
b. HI006: DPW – Fort Shafter Flats, Mark Bowling, Mark.J.Bowling4.mil@army.mil
c. Building Occupants
3.2.10. NOT USED
3.2.11. NOT USED
3.2.12. NOT USED
3.2.13. NOT USED
3.2.14. NOT USED
3.2.15. Project and Safety Signs. See 01 50 00, Paragraph 2.1.3.
3.3. DOCUMENTATION
mailto:Mark.J.Bowling4.mil@army.mil https://home.army.mil/hawaii/about/visitor-information mailto:Mark.J.Bowling4.mil@army.mil
CERTIFIED FINAL
3.3.1. NOT USED
3.3.2. NOT USED
3.4. NOT USED
3.5. NOT USED
3.6. NOT USED
4. NOT USED
5. CIVIL/ SITE WORK
5.1. HI006 - Trim existing foliage to provide a minimum of four feet of clearance between roof/building perimeter walls and trimmed foliage.
6. EXTERIOR EQUIPMENT
6.1. IN011 – Proper pipe supports and roof pads to be installed as necessary. Coordinate locations with COR.
6.2. IN011 – Remove large mechanical roof curb on roof section 1.
There is a structural support bridging the original curbing system. DOR to determine if removal is necessary.
6.3. IN011 – Remove four (4) abandoned penetration on roof section 2.
6.4. IN011 - Remove relief vents on the USARC and OMS buildings.
6.5. IN011 – Install OSHA Compliant Safety Guardrail system on the south side of the RTU-4 and RTU-6 Units on Roof section 2 close to the courtyard on the USARC building and near the basement entrance.
6.6. IN011 – replace weather head with current NEC code compliant weather head. Coordinate with Public Utility Company. Coordinate with
User if any outage is needed.
6.7. PA011 – Remove chimney from facility, pipes shall remain.
6.8. PA011 – Remove TV Antenna and associated equipment/lines for disposal.
Amendment 0003***************************************************************
6.9. DELETED
***************************************************************Amendment 0003
7. ARCHITECTURAL/BUILDING ENVELOPE
7.1. IN011 – Replace approximately 2,000 LF of wall expansion joints, joints around exterior doors and windows.
7.2. IN011 – Replace approximately 400 LF of wall sealant at control joints.
7.3. IN011 – Add approximately 100 LF of caulk around block windows on roof section 5.
7.4. IN011 – Repair/tuck point approximately 20 LF of brick on roof section 5 at ground level and window sills for block windows.
Coordinate with COR.
CERTIFIED FINAL
AMENDMENT 0004
7.5. IN011 – Replace roof hatch with an OSHA Approved roof hatch with steel ladder safety post for ease of egress.
7.6. IN011 – Caulk joints around facility (approximately 10 LF).
Coordinate with COR.
7.7. IN011 – OMS – replace all fascia per SMACNA details.
7.8. IN011 – replace 50 LF of two (2) expansion joints on the west side of the USARC. Coordinate location with COR.
7.9. HI006 – 1556, 1557, 1558 – Perform pull test and provide results to the COR.
8. NOT USED
9. NOT USED
10. NOT USED
11. NOT USED
12. NOT USED
13. NOT USED
14. ROOF SYSTEM
14.1. IN011, USARC Building
Sections 1-5: Design and install a new EPDM roof system.
14.2. IN011, OMS Building
Section 1: Design and install a new EPDM roof system.
14.3. PA011, USARC Building
Sections 1-3: Design and install a new 3-ply modified bitumen roof.
14.4. PA011, OMS Building
Sections 1 & 2: Design and install a new 3-ply modified bitumen roof.
14.5. HI006, Building 1557 OMS
14.5.1. Over existing SSMR system, design and install a PVC overlay system with insulated flute filler, coverboard, and PVC simulated ribs, for a 20 year No-Dollar-Limit Warranty. Install edge metal prior to installation of overlay system.
14.5.2. Repair or replace (estimated 10%) any heavily deteriorated metal panels prior to installing the flute-fill overlay.
14.5.3. PVC Color to match installation guidelines and must be approved by Contracting Officer’s Representative (COR)
CERTIFIED FINAL
14.5.4. All metal replaced, including, but not limited to gutters and flashings shall be copper to match installation guidelines and must be approved by COR.
14.5.5. Contractor to perform water testing on gutters and
downspouts, with results to be submitted with the Charrette Report.
14.6. HI006, Building 1556 USARC
14.6.1. Over existing SSMR system, design and install a PVC overlay
14.6.2. Repair or replace (estimated 10%) any heavily deteriorated
14.6.3. PVC Color to match installation guidelines and must be approved by COR.
14.6.4. All metal, including, but not limited to gutters and
flashings shall be aluminum to match installation guidelines and
14.6.5. Low Roof System, Section 3, is under an active roof
warranty, but should be replaced as it has ongoing leak problems, bringing all buildings into a newly reset warranty. This particular roof section should be removed down to the existing deck and replaced with new polyisocyanurate insulation, coverboard and new single-ply PVC system to include all flashings and sheet metal and to include the same 20-year No-Dollar-Limit Warranty as the steep slope areas.
14.7. HI006, Building 1558
Amendment 0004***************************************************************
14.7.1. Over existing SSMR system, design and install a PVC overlay
CERTIFIED FINAL
***************************************************************Amendment 0004
14.7.2. Repair or replace (estimated 10%) any heavily deteriorated
14.7.3. PVC Color to match installation guidelines and must be approved by COR.
14.7.4. All metal, including, but not limited to gutters and
flashings shall be aluminum to match installation guidelines and
--End of Section --
01 11 50.00 06
File details come from the government source that posted it. Updated .