W912QR23R0024_NRP_PH2_VolA-0005.pdf

PDF 807 KB Posted

Attached to
National Roofing Program (NRP) Design/Build Construction Services MATOC
Solicitation number
W912QR23R0024
Issued by

About this file

This document is an amendment to a solicitation for an Indefinite Delivery Indefinite Quantity (IDIQ), Design-Build Multiple Award Task Order Contract (MATOC) for building envelope, roof repair, and replacement construction in support of the U.S. Army Reserves National Roofing Program (NRP), Army, and Air Force Reserve Sections. The amendment revises two specification sections: 01 45 04.10 06 Contractor Quality Control and 01 50 00 Temporary Construction Facilities and Controls. Key details include:

The Design Quality Control Plan (DQCP) must identify a Design Quality Control Project Manager (DQCPM) who is a licensed professional engineer or registered architect, or an RRC/RBEC with 10+ years' experience as a design PM. The Construction Quality Control Plan (CQCP) must identify a CQC System Manager with specific qualifications and responsibilities. The contract includes temporary project safety fencing, dumpsters, and provisions for traffic control and Condition of Readiness during high wind events. The government will not provide utilities unless specified in the Task Order. Offers must acknowledge receipt of this amendment prior to the specified due date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

IDIQ Design Build Multiple Aw ard Task Order Contract (MATOC) for Building Envelope, Roof Repair and Replacement Construction in Support of U.S. Army Reserve National Roofing Program (NRP), Army, and Air Force Reserves Sections is hereby amended as follows:

See continuation Page

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR23R0024

X 9B. DATED (SEE ITEM 11)

22-Feb-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05 - Aug-2024

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912QR23R0024_NRP_PH2_VolA-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0005

The following SPECIFICATION SECTIONS have been revised and replaced in their entirety:

1. Base MATOC Vol 1 (A) – 01 45 04.10 06

2. Base MATOC Vol 1 (A) – 01 50 00

All other information remains the same.

(End of Summary of Changes)

FY24 National Roofing Program (NRP)

Large MATOC

P2 509137

Section 01 45 04.10 06 Page 1

Certified Final

Amendment 0005

SECTION 01 45 04.10 06

CONTRACTOR QUALITY CONTROL

08/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 3740 (2004a) Standard Practice for Minimum

Requirements for Agencies Engaged in the

Testing and/or Inspection of Soil and Rock as

Used in Engineering Design and Construction

ASTM E 329 (2007) Standard Specification for Agencies

Engaged in Construction Inspection and/or

Testing

1.2 PAYMENT

Separate payment will not be made for providing and maintaining an effective

Quality Control program, and all costs associated therewith shall be included in the applicable unit prices or lump-sum prices contained in the

Bidding Schedule.

1.3 SUBMITTALS

Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor

Quality Control approval, or for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with LRL Section 01 33 00.00 06 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Design Quality Control Plan; G (If Task Order Scope of Work is

Design-Build)

Construction Quality Control Plan; G, RO

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx

P2 509137

Section 01 45 04.10 06 Page 2

3.1 GENERAL REQUIREMENTS

The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with FAR 52.246-

12 - Inspection of Construction. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The system shall cover all design and construction operations, both onsite and offsite, and shall be keyed to the proposed construction sequence. The site project superintendent will be held responsible for the quality of work on the job and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. The site project superintendent in this context shall be the highest level manager responsible for the overall construction activities at the site, including quality and production. The site project superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the Contracting Officer, and shall be responsible for all construction and construction related activities at the site.

3.2 DESIGN QUALITY CONTROL PLAN (DQCP)

A DQCP is required for all projects where the Task Order Scope of Work is for a design-build project. All documents shall be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product shall not perform the independent technical review (ITR). The plan must identify the Independent Technical

Review Team and their qualifications. The Contractor shall correct errors and deficiencies in the design documents prior to submitting them to the

Government.

Amendment 0005***************************************************************

The DQC Plan shall be implemented by a Design Quality Control Project

Manager (DQCPM) who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual shall be a person who has verifiable engineering or architectural design experience and is a licensed professional engineer or registered architect and can be one of the DESIGNERS OF RECORD. The DQCPM may also be an RRC (registered roofing consultant) or RBEC (registered building enclosure consultant) with a minimum of 10 years of experience as a design

PM but cannot serve as a DESIGNER OF RECORD. The Contractor shall notify the

Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position. The Design Quality Control

Project Manager (DQCPM) and the Design Project Manager can be the same person.

***************************************************************Amendment 0005

In addition to these requirements, the design firm shall have a Design

Project Manager (PM), who shall coordinate and manage the design for all disciplines and serve as the point of contact on all design related issues.

The Design PM shall be a registered Architect or licensed Engineer, with a minimum of ten years overall designer experience (including PM experience) and a minimum of two years Design PM experience.

P2 509137

Section 01 45 04.10 06 Page 3

The Contractor shall include the design schedule in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. This should be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. The schedule shall include review and correction periods associated with each item. This should reflect calendar days and not dates for each activity. If the schedule is changed, the Contractor shall submit a revised schedule reflecting the change within 7 calendar days. The Contractor shall include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal.

The Contractor shall furnish for review by the government, not later than 10 days after Notice to Proceed, the Contractor Design Quality Control Plan for the design portion of the contract. The professional quality, technical accuracy and the coordination of all design documents and other services to be provided by the prime Contractor and subcontractor/ consultants is of major importance. A logical and functional quality control program requiring technical and interdisciplinary reviews to eliminate errors and deficiencies in the design documents is required. As a minimum, the DQCP will address the following elements:

Management Approach - Define the specific management-methodology to be followed during the design phase of the work including the relationship between prime contractor and subcontractors/consultants. Address coordination, quality control, communications and lines of responsibility.

The DQCP must also cover the process of review and acceptance of construction submittals as specified in LRL Section 01 33 00.00 06 SUBMITTAL

PROCEDURES.

Management Structure - Delineate the organizational structure and interrelationship of management and the design team including all subcontractor and consultants. Identify the key design and review team members showing their specific responsibilities. Either the designer or the reviewer must be a licensed professional for the Architectural, Civil, Structural, Mechanical and Electrical disciplines.

List submittals required, dates for submittal, dates for completion of

Government review and products required to be submitted. Technical review comments provided by the ITR Team must be submitted with each design submittals. The approved complete checklists shall be submitted at each design phase as part of the project documentation.

Designer of Record (DOR) - The licensed professional Engineer, or registered Architect ultimately responsible and liable for adequacy and safety of the design. DOR review is required on all submittals and DOR approval is required on all submittals of extensions of design and submittals of critical materials. See LRL Section 01 33 00.00 06 SUBMITTAL

PROCEDURES for definitions of these type submittals.

3.2.1 Acceptance of Plan

Acceptance of the Contractor's Quality Control Plan for Design is required prior to the start of design. Acceptance is conditional and will be predicated on satisfactory performance during the preparation of design documents. The Government reserves the right to require the Contractor to

W912QR23R0024_NRP_PH2_VolA-0005 file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx

P2 509137

Section 01 45 04.10 06 Page 4 make changes in his CQC Plan for Design, and operations including removal of personnel, as necessary, to obtain the quality specified.

3.3 CONSTRUCTION QUALITY CONTROL PLAN (CQCP)

The Contractor shall furnish for review by the Government, not later than 30 days after receipt of notice to proceed, the Contractor Construction Quality

Control (CQC) Plan proposed to implement the requirements of FAR 52.246-12 -

Inspection of Construction. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. The Government will consider an interim plan for the first 30 days of operation.

Construction will be permitted to begin only after acceptance of the CQC

Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the features of work included in an accepted interim plan will not be permitted to begin until acceptance of a

CQC Plan or another interim plan containing the additional features of work to be started.

3.3.1 Content of the CQC Plan

The CQC Plan shall include, as a minimum, the following to cover all construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff shall implement the three phase control system for all aspects of the work specified. The staff shall include a CQC

System Manager who shall report to the Project Manager/Project

Executive or President of the Company

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. The CQC System Manager shall issue letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities. Copies of these letters shall also be furnished to the Government.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures shall be in accordance with LRL Section 01 33 00.00 06 SUBMITTAL PROCEDURES.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities will be approved by the Contracting Officer.)

file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx

P2 509137

Section 01 45 04.10 06 Page 5

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. These procedures shall establish verification that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

3.3.2 Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.3.3 Notification of Changes

After acceptance of the CQC Plan, the Contractor shall notify the

Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.4 COORDINATION MEETING

After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, the Contractor shall meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. The CQC Plan shall be submitted for review a minimum of 30 calendar days prior to the Coordination Meeting.

During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting shall be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the

Contractor.

P2 509137

Section 01 45 04.10 06 Page 6

3.4.1 Subcontractor CQC Orientation

Before a Subcontractor begins work on the jobsite, the CQC System Manager will train the Subcontractor and answer any questions pertaining to quality control operations. This requirement is waived only if a Subcontractor attended the initial coordination meeting described above. A record of the orientation shall be documented in the QC Report.

3.5 CONSTRUCTION QUALITY CONTROL ORGANIZATION

3.5.1 Personnel Requirements

a. The requirements for the CQC organization are a CQC System Manager and sufficient number of additional qualified personnel to ensure safety and contract compliance. A Site Safety Health Officer (SSHO) will be required for this contract. See LRL Section 01 35 26.00 06 GOVERNMENT SAFETY

REQUIREMENTS for the SSHO qualifications and duties.

b. Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff shall maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff shall be subject to acceptance by the Contracting Officer. The Contractor shall provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC, and safety/health organization. Complete records of all letters, material submittals, shop drawing submittals, schedules and all other project documentation shall be promptly furnished to the CQC organization by the Contractor. The CQC organization shall be responsible to maintain these documents and records at the site at all times and made available to the SSHO, except as otherwise acceptable to the Contracting Officer.

3.5.2 CQC System Manager Qualifications and Duties

a. The Contractor shall identify as CQC System Manager an individual within the onsite work organization who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be either a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years construction experience on construction similar to this contractor a construction person with a minimum of 10 years in related quality management work. b. This CQC System Manager shall be employed by the Prime Contractor and be on the site at all times during construction. Alternate(s) for the CQC System Manager shall be identified in the CQC Plan to serve in the event of the CQC

System Manager's absence. The requirements for the alternates shall be the same as for the designated CQC System Manager.

AMDT004**********************************************************************

b. This CQC System Manager shall be employed by the Prime Contractor and file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2035%2026.00%2006.docx

P2 509137

Section 01 45 04.10 06 Page 7 be on the site at all times during construction. Alternate(s) for the

CQC System Manager shall be identified in the CQC Plan to serve in the event of the CQC System Manager's absence. The requirements for the alternates shall be the same as for the designated CQC System Manager.

c. The CQC System Manager shall be: assigned other duties as the SSHO or the superintendent.

**********************************************************************AMDT004

3.5.3 CQC Personnel

3.5.3.1 CQC for Design-Build Task Orders

a. The Design Quality Control Manager (DQCM) has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated, and will ensure that all services required by the D-B contract are performed and provided in a manner that meets professional architectural and engineering quality standards. For required qualifications refer to the experience matrix below. Project design personnel shall include those personnel listed in the RFP submission by the contractor for this MATOC. Any changes of these personnel requires a review and approval of new design personnel by the Contracting Officer. Qualifications of any new personnel must meet or exceed personnel they are replacing on the design team.

b. In addition to CQC personnel specified elsewhere in the contract, the

Contractor shall provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas identified per Experience Matrix Table. These individuals may be employees of the prime or subcontractor. These individuals identified per the Experience Matrix

Table, shall be responsible to the CQC System Manager; be physically present at the construction site when needed during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein. These individuals in the

Experience Matrix Table may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan.

c. The word "graduate" below indicates an individual possessing a four-year college degree accredited in the respective field listed-with experience obtained following graduation in the type of work being performed on the project.

Experience Matrix Table

Area Qualifications

a. DQCM (person not required Licensed Architect or to be on site at all times) Professional Engineer

b. Mechanical Graduate Mechanical Engineer with 2 yrs related experience or person with 5 yrs related experience

P2 509137

Section 01 45 04.10 06 Page 8

c. Electrical Graduate Electrical

Engineer with 2 yrs related experience or person with 5 yrs related experience

d. Structural Graduate Structural

Engineer with 2 yrs related experience or person with

5 yrs related experience

e. Architectural Graduate Architect with 2 yrs related experience or person with 5 yrs related

f. Environmental Graduate Environmental

Engineer with 3 yrs related

g. Roofing UFC 3-110-03 Change 3 Paragraph

1-8.11 requires a Registered

Roof Consultant (RRC) on the quality control staff of the design team for buildings above

15,000 SF of roof area.

RCI Registered Roof Observer

(Construction)

Amendment 0005***************************************************************

3.5.3.2 Registered Roof Observer

The Registered Roof Observers will perform daily oversight and quality control on all roof work to assure compliance with the projects plans and specifications. The RRO will supply recommendations and reports to the

Government for review and shall create initial update Asset Management Data file using commercially available industry standard software that is compatible with that used by USAR-IMCOM. The Government will supply the format of the file. The RRO shall provide daily reports per CQC requirements, number of squares of roof placed and the contractor's compliance with specifications and details. The RRO shall take daily color photographs (a minimum 24 photos total for the project) of every type of activity performed that shall include (but not limited to) insulation attachment, application of roofing membrane and flashings, sheet metal installation, kettle operation, material storage/handling and compliance with safety requirements. Photos may be digital but one hard color copy shall be made daily and kept on site. The Registered Roof Observer shall submit all plans, schedules, reports, and documentation directly to the

Contracting Officer's Representative concurrent with submission to the CQC

System Manager. The RRO shall have direct communication with the

Contracting Officer's Representative regarding all elements of the roofing installation process.

P2 509137

Section 01 45 04.10 06 Page 9

***************************************************************Amendment 0005

3.5.4 Additional Requirement

In addition to the above experience and/or education requirements the CQC

System Manager and Alternate(s) shall have completed and passed the course entitled "Construction Quality Management For Contractors" within the last 5 years. A copy of the certification shall be provided with the CQCP. This course is periodically offered by the Associated Builders and Constructors, Inc., or Associated General Contractor, Inc., and the U.S. Army Corps of

Engineers.

3.5.5 Organizational Changes

The Contractor shall maintain the CQC staff at full strength at all times.

When it is necessary to make changes to the CQC staff, the Contractor shall revise the CQC Plan to reflect the changes and submit the changes to the

Contracting Officer for acceptance.

3.6 SUBMITTALS AND DELIVERABLES

Submittals, if needed, shall be made as specified in LRL Section 01 33 00.00

06 SUBMITTAL PROCEDURES. The CQC organization shall be responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When LRL Section 01 46 00.10 06 and/or LRL Section

01 46 00.00 06 TOTAL BUILDING COMMISSIONING is included in the contract, the submittals required by those sections shall be coordinated with LRL Section

01 33 00.00 06 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.

3.7 CONTROL

Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control shall be conducted by the CQC System Manager for each definable feature of work as follows:

3.7.1 Preparatory Phase

This phase shall be performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase shall include:

a. A review of each paragraph of applicable specifications, reference codes, and standards. A copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field shall be made available by the Contractor at the preparatory inspection. These copies shall be maintained in the field and available for use by Government personnel until final acceptance of the work.

b. A review of the contract drawings.

file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx file://///lrd.ds.usace.army.mil/org/ED/Public/EDM/ED-MA/Projects/MATOCs%202019/Design%20Build%20MATOC/Volume%201/Phase%201%20Div%2000%20and%2001/01%2033%2000.00%2006.docx

P2 509137

Section 01 45 04.10 06 Page 10

c. A check to assure that all materials and/or equipment have been tested, submitted, and approved.

d. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

e. A physical examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

f. A review of the appropriate activity hazard analysis to assure safety requirements are met.

g. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

h. A check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

i. Resolve all differences.

j. Discussion of the initial control phase.

k. Review of provisions that have been made to provide required control inspection and testing.

l. Review of the CQC plan, specifically its organization chart and delegation letters. Insure all required members of the CQC organization for this feature of work are qualified, have been appointed, accepted and have requisite authority delegated.

m. The Government shall be notified at least 272 hours in advance of beginning the preparatory control phase. This phase shall include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. The results of the preparatory phase actions shall be documented by separate minutes prepared by the CQC System Manager and attached to the daily CQC report. The Contractor shall instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.7.2 Initial Phase

This phase shall be accomplished at the beginning of a definable feature of work. The following shall be accomplished:

a. A check of work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance.

Verify required control inspection and testing.

P2 509137

Section 01 45 04.10 06 Page 11

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government shall be notified at least 72 hours in advance of beginning the initial phase. Separate minutes of this phase shall be prepared by the CQC System Manager and attached to the daily CQC report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.

g. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.7.3 Follow-up Phase

Daily checks shall be performed to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. The checks shall be made a matter of record in the CQC documentation. Final follow-up checks shall be conducted and all deficiencies corrected prior to the start of additional features of work which may be affected by the deficient work. The Contractor shall not build upon nor conceal non-conforming work.

3.7.4 Additional Preparatory and Initial Phases

Additional preparatory and initial phases shall be conducted on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

3.8 TESTS

3.8.1 Testing Procedure

The Contractor shall perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, the Contractor shall furnish to the

Government duplicate samples of test specimens for possible testing by the

Government. Testing includes operation and/or acceptance tests when specified. For QC testing of construction materials including soil, rock, aggregate, asphalt, concrete, and steel, the Contractor shall procure the services of a Corps of Engineers (COE) validated testing laboratory or establish a COE validated testing laboratory at the project site. Technical specifications included in the contract that require materials testing by an approved commercial testing laboratory shall be intended to mean by a COE

P2 509137

Section 01 45 04.10 06 Page 12 validated laboratory. The Contractor shall perform the following activities and record and provide the following data:

a. Verify that testing procedures comply with contract requirements.

b. Verify that facilities and testing equipment are available and comply with testing standards.

c. Check test instrument calibration data against certified standards.

d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

e. Results of all tests taken, both passing and failing tests, shall be recorded on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test shall be given. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken.

An information copy of tests performed by an offsite or commercial test facility shall be provided directly to the Contracting

Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.

3.8.2 Testing Laboratories

3.8.2.1 Capability Check

The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel shall meet criteria detailed in ASTM D 3740 and

ASTM E 329.

3.8.2.2 Capability Recheck

If the selected laboratory fails the capability check, the Contractor will be assessed a charge of $1,375.00 to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor.

3.8.3 Onsite Laboratory

The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the

Contractor's testing procedures, techniques, and test results at no additional cost to the Government.

3.8.4 Furnishing or Transportation of Samples for Testing

Costs incidental to the transportation of samples or materials shall be borne by the Contractor. Samples of materials for test verification and

P2 509137

Section 01 45 04.10 06 Page 13 acceptance testing by the Government shall be delivered to the Corps of

Engineers Division Laboratory, f.o.b., at the following address:

For delivery by mail:

Geotechnical & Structures Laboratory

Material Testing Center (GS-E)

U.S. Army Engineer Research and Development Center

3909 Halls Ferry Road

Vicksburg, MS 39180-6199

Coordination for each specific test, exact delivery location, and dates will be made through the Area Office.

3.9 COMPLETION INSPECTION

3.9.1 Punch-Out Inspection

Near the end of the work, or any increment of the work established by a time stated in the SPECIAL CLAUSES FAR 52.211-10 - Commencement, Prosecution, and

Completion of Work, or by the specifications, the CQC System Manager shall conduct an inspection of the work. A punch list of items which do not conform to the approved drawings and specifications shall be prepared and included in the CQC documentation, as required by paragraph DOCUMENTATION.

The list of deficiencies shall include the estimated date by which the deficiencies will be corrected. The CQC System Manager or staff shall make a second inspection to ascertain that all deficiencies have been corrected.

Once this is accomplished, the Contractor shall notify the Government that the facility is ready for the Government Pre-Final inspection.

3.9.2 Pre-Final Inspection

The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch

List may be developed as a result of this inspection. The Contractor's CQC

System Manager shall ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Any items noted on the Pre-Final inspection shall be corrected in a timely manner. These inspections and any deficiency corrections required by this paragraph shall be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

3.9.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting

Officer's Representative shall be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notice shall be given to the Contracting Officer at least 14 days prior to the final acceptance inspection and shall include the

Contractor's assurance that all specific items previously identified to the

Contractor as being unacceptable, along with all remaining work performed

P2 509137

Section 01 45 04.10 06 Page 14 under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the

Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with FAR 52.246-12 - Inspection of

Construction.

3.10 DOCUMENTATION

The Contractor shall maintain current records providing factual evidence that required quality control activities and/or tests have been performed.

These records shall include the work of subcontractors and suppliers and shall be on an acceptable form that includes, as a minimum, the following information:

a. Contractor/subcontractor and their area of responsibility.

b. Operating plant/equipment with hours worked, idle, or down for repair.

c. Work performed each day, giving location, description, and by whom.

When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

d. Test and/or control activities performed with results and references to specifications/drawings requirements. The control phase shall be identified (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.

e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.

g. Offsite surveillance activities, including actions taken.

h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

i. Instructions given/received and conflicts in plans and/or specifications.

j. Contractor's verification statement.

k. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one copy of these records in report form shall be furnished to the Government daily within 24 hours after the date covered by the report. All calendar days shall be accounted for throughout the life of the contract. Reports shall be signed and dated by the CQC System

P2 509137

Section 01 45 04.10 06 Page 15

Manager. The report from the CQC System Manager shall include copies of test reports and copies of reports prepared by all subordinate quality control personnel.

l. Deficiency Tracking System. The Contractor shall maintain a cumulative list of deficiencies identified for the duration of the project. Deficiencies to be listed include those failures, Government oral observations and Notifications of Noncompliance.

The list shall be maintained at the project site. Copies of updated listings shall be submitted to the Government at least every 30 days.

3.11 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. The Contractor shall take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

-- End of Section --

P2 509137

Section 01 50 00 Page 1

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

05/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C511 (2017) Reduced-Pressure Principle Backflow

Prevention Assembly

FOUNDATION FOR CROSS-CONNECTION CONTROL AND HYDRAULIC RESEARCH

(FCCCHR)

FCCCHR List (continuously updated) List of Approved

Backflow Prevention Assemblies

FCCCHR Manual (10th Edition) Manual of Cross-Connection

Control

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2; TIA

17-3; TIA 17-4; TIA 17-5; TIA 17-6; TIA 17-7;

TIA 17-8; TIA 17-9; TIA 17-10; TIA 17-11; TIA

17-12; TIA 17-13; TIA 17-14; TIA 17-15; TIA

17-16; TIA 17-17) National Electrical Code

NFPA 241 (2013; Errata 2015) Standard for Safeguarding

Construction, Alteration, and Demolition

Operations

Amendment 0005**************************************************************

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety and Health Requirements Manual

Amendment 0005**************************************************************

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and

Lighting

Section 01 50 00 Page 2

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2015) Manual on Uniform Traffic Control

Devices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval (Design Build) or information only (Design Bid Build). When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33

29 SUSTAINABILITY REPORTING. Submit the following in accordance with

Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Site Plan; G

Traffic Control Plan; G

1.3 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

1.4 NOT USED

1.5 DOD CONDITION OF READINESS (COR)

DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots (60mph or 95 km/hr) or greater. Contact the

Contracting Officer for the current COR setting.

Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident

Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.

Unless otherwise directed by the Contracting Officer, comply with:

a. Condition FOUR (Sustained winds of 50 knots or greater expected within

72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less

Section 01 50 00 Page 3 than 4 feet high. Remove all debris, trash, or objects that could become missile hazards.

b. Condition THREE (Sustained winds of 50 knots or greater expected within

48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings.

Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.

c. Condition TWO (Sustained winds of 50 knots or greater expected within

24 hours): Curtail or cease routine activities until securing operation is complete. Reinforce or remove form work and scaffolding.

Secure machinery, tools, equipment, materials, or remove from the jobsite. Expend every effort to clear all missile hazards and loose equipment from general base areas.

d. Condition ONE. (Sustained winds of 50 knots or greater expected within

12 hours): Secure the jobsite, and leave Government premises.

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

Within one calendar day of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the

Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the

Contracting Officer. Coordinate requirements herein with 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS.

2.1.2 Not Used

2.1.3 Warning Signs

Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM

385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site. Correct the data required by safety signs daily.

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 NOT USED

2.2.2 NOT USED

2.3 FENCING

Section 01 50 00 Page 4

Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic. Specific fencing requirements are as described herein. All fencing will meet the requirements of EM 385-1-1.

2.3.1 Polyethylene Mesh Safety Fencing

Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches. Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.

2.3.2 Chain Link Panel Fencing

Temporary panel fencing must be galvanized steel chain link panels 6feet high unless specified…