This solicitation is for repair and renovation work at the Repair Aircraft Maintenance Building 1455 for MH-139 Beddown at Maxwell Air Force Base in Alabama. The estimated construction cost is between $5 million and $10 million. The solicitation will utilize full and open competition with a best value tradeoff source selection process. The project requires compliance with the HUBZone price evaluation preference. Site visits will be held on January 10, 2023 at 9:30 AM Central Time, with personal information required to be submitted by January 4, 2023 for base access.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Repair Aircraft Maintenance B1455 for MH-139, Maxwell AFB, AL
P2: 496395
Design-Bid-Build
Specifications - Vol 2 of 3 Certified Final Design
29 December 2022
W912QR23R0003
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR23R0003_Specs_Vol2-0000
496395 Repair Aircraft Maintenance B1455 for MH-139 Maxwell AFB, AL
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 32 01.00 06 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 00 METAL STAIRS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 21 13 BOARD AND BLOCK INSULATION
PROJECT TABLE OF CONTENTS Page 1
CERTIFIED FINAL DESIGN SUBMITTAL
VOLUME 1 - SPECIFICATIONS
VOLUME 2 - SPECIFICATIONS
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 42 13.19 INSULATED CORE METAL WALL PANELS
07 54 23 THERMOPLASTIC POLYOLEFIN (TPO) ROOFING
07 60 00 FLASHING AND SHEET METAL
07 81 00 SPRAY-APPLIED FIREPROOFING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 68 00 CARPETING
09 69 13 RIGID GRID ACCESS FLOORING
09 84 20 ACOUSTICAL WALL PANELS
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
DIVISION 22 - PLUMBING
PROJECT TABLE OF CONTENTS Page 2
CERTIFIED FINAL DESIGN SUBMITTAL
VOLUME 3 - SPECIFICATIONS
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 48.19 SEISMIC BRACING FOR HVAC
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.01 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 30 00 HVAC AIR DISTRIBUTION
23 52 00 HEATING BOILERS
23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 81 23 COMPUTER ROOM AIR CONDITIONING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.21 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS, FIRE
AND LIFE SAFETY SYSTEMS
25 05 11.23 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS, ENERGY
MANAGEMENT CONTROL SYSTEM
25 05 11.26 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS,
UTILITY CONTROL SYSTEM
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND
INTEGRATION
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
PROJECT TABLE OF CONTENTS Page 3
CERTIFIED FINAL DESIGN SUBMITTAL
27 51 16 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 31 21 13
EARTHWORK RADON
MITIGATION
PROJECT TABLE OF CONTENTS Page 4
CERTIFIED FINAL DESIGN SUBMITTAL
-- End of Project Table of Contents --
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 32 11 23 32 11 23.23 32 12 13 32 12 16.16 32 16 19 32 31 13 32 92 23
LANDSCAPE ESTABLISHMENT
AGGREGATE BASE COURSES
BASE COURSE DRAINAGE LAYERS
BITUMINOUS TACK AND PRIME COATS
ROAD-MIX ASPHALT PAVING
SIDEWALKS
CHAIN LINK FENCES AND GATES
SODDING
DIVISION 33 - UTILITIES
33 30 00 33 40 00 33 82 00
SANITARY SEWERAGE
STORM DRAINAGE UTILITIES
TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
ATTACHMENT
TECHNICAL SCOPE AMRS METER SPECIFICATION
THIS PAGE INTENTIONALLY LEFT BLANK
Repair Aircraft Maintenance B1455 for MH-139
SECTION 02 41 00
DEMOLITION
05/10, CHG 2: 02/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI Guideline K (2009) Guideline for Containers for Recovered Non-Flammable Fluorocarbon Refrigerants
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
CARPET AND RUG INSTITUTE (CRI)
CRI 104 (2015) Carpet Installation Standard for Comnmercial Carpet
CRI 105 (2015) Carpet Installation Standard for Residential Carpet
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviationengineering/HazInfo/
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures
MIL-STD-129 (2014; Rev R; Change 1 2018; Change 2 2019) Military Marking for Shipment and Storage
02 41 00 Page 1 Certified Final Design Submittal
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 82 Protection of Stratospheric Ozone
49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.
1.2.1.2 Deconstruction
Deconstruction is the process of taking apart a facility with the primary goal of preserving the value of all useful building materials.
1.2.1.3 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, and airfield lighting, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Structural PE and Contracting Officer prior to work beginning.
1.2.3 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the building on airfield pavements. The work includes demolition, deconstruction, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed.
Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, 02 41 00 Page 2 perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements or pavements to remain.
Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, and debris from work areas daily.
1.3.2 Weather Protection
For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3.3 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, the Government will disconnect and seal utilities serving each area of alteration or removal upon written request from the Contractor.
1.3.4 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless directed otherwise by the Contracting Officer.
Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.
02 41 00 Page 3
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted
1.5 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan
Existing Conditions
SD-07 Certificates
Notification
SD-11 Closeout Submittals
Receipts
1.6 QUALITY ASSURANCE
Submit timely notification of demolition , deconstruction , and renovation projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M. Notify the State's environmental protection agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris to occupied portions of the building and onto airfield pavements and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.
1.7 PROTECTION
1.7.1 Traffic Control Signs
Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind, jet or prop blast. Notify the Contracting Officer prior to beginning such work.
02 41 00 Page 4
1.7.2 Protection of Personnel
Before, during and after the demolition and deconstruction work continuously evaluate the condition of the structure being deconstructed and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.8 FOREIGN OBJECT DAMAGE (FOD)
Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such materials that may appear on operational aircraft pavements due to the Contractor's operations. If necessary, the Contracting Officer may require the Contractor to install a temporary barricade at the Contractor's expense to control the spread of FOD potential debris. The barricade shall include a fence covered with a fabric designed to stop the spread of debris. Anchor the fence and fabric to prevent displacement by winds or jet/prop blasts.
Remove barricade when no longer required.
1.9 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.10 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.
Fill material shall be waste products from demolition or deconstruction until all waste appropriate for this purpose is consumed.
02 41 00 Page 5
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.
Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.
Materials shall be designated for reuse onsite whenever possible.
3.1.1 Structures
a. Remove existing structures indicated to be removed to top of foundation unless otherwise indicated . Interior walls, other than retaining walls and partitions, shall be removed to top of concrete slab unless otherwise indicated . Remove sidewalks, curbs, gutters and street light bases as indicated.
b. Deconstruct structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.
Deconstruct concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.
c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities, as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area.
3.1.3 Paving and Slabs
Remove sawcut concrete and asphaltic concrete paving and slabs including aggregate base to a depth of 12 inches below existing adjacent grade.
Provide neat sawcuts at limits of pavement removal as indicated. Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense.
02 41 00 Page 6
3.1.4 Masonry
Sawcut and remove masonry so as to prevent damage to surfaces to remain, to removed materials being salvaged and to facilitate the installation of new work. Where new masonry adjoins existing, the new work shall abut or tie into the existing construction as indicated. Provide square, straight edges and corners where existing masonry adjoins new work and other locations.
3.1.5 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch . Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete.
3.1.6 Structural Steel
Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Salvage for reuse or recycle structural steel, steel joists, girders, angles, plates, columns and shapes. Flame-cutting torches are only permitted when other methods of dismantling are not practical. Transport steel joists and girders as whole units and not dismantled. Transport structural steel shapes to a designated storage area , recycling facility , or area as directed by the Contracting Officer, stacked according to size, type of member and length, and stored off the ground, protected from the weather.
3.1.7 Miscellaneous Metal
Salvage shop-fabricated items such as access doors and frames, steel gratings, metal ladders, wire mesh partitions, metal railings, metal windows and similar items as whole units. Salvage light-gage and cold-formed metal framing, such as steel studs, steel trusses, metal gutters, roofing and siding, metal toilet partitions, toilet accessories and similar items. Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.
3.1.8 Carpentry
Chip or shred and recycle salvaged wood unfit for reuse, except stained, painted, or treated wood. Remove windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories.
Brace the open end of door frames to prevent damage.
3.1.9 Carpet
Remove existing carpet for reclamation in accordance with manufacturer recommendations and as follows. Remove used carpet in large pieces, roll tightly, and pack neatly in a container. Remove adhesive according to recommendations of the Carpet and Rug Institute (CRI). Adhesive removal solvents shall comply with CRI 104 / CRI 105 . Recycle removed carpet cushion.
02 41 00 Page 7
3.1.10 Acoustic Ceiling Tile
Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, priority shall be given to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material.
3.1.11 Patching
Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:
a. Concrete and Masonry: Completely fill holes and depressions, caused by previous physical damage or left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions.
b. Where existing partitions have been removed leaving damaged or missing resilient tile flooring, patch to match the existing floor tile.
c. Patch acoustic lay-in ceiling where partitions have been removed. The transition between the different ceiling heights shall be affected by continuing the higher ceiling level over to the first runner on the lower ceiling and closing the vertical opening with a painted sheet metal strip.
3.1.12 Air Conditioning Equipment
Recover all refrigerants prior to removing air conditioning, refrigeration, and other equipment containing refrigerants and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.13 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.14 Locksets on Swinging Doors
Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal.
3.1.15 Mechanical Equipment and Fixtures
Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Salvage each item of equipment and fixtures as a whole unit;
listed, indexed, tagged, and stored. Salvage each unit with its normal
02 41 00 Page 8 operating auxiliary equipment. Transport salvaged equipment and fixtures, including motors and machines, to a designated storage area as directed by the Contracting Officer. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse.
3.1.15.1 Preparation for Storage
Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned.
Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease.
3.1.15.2 Piping and Radiant Heaters
Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage.
Disconnect heaters and related appurtenances including gas piping, burner, vacuum pumps, and radiant pipe. Store salvaged piping according to size and type. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property.
Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type. Wrap sprinkler heads individually in plastic bags before boxing. Classify piping not designated for salvage, or not reusable, as scrap metal.
3.1.15.3 Ducts
Classify removed duct work as scrap metal.
3.1.15.4 Fixtures, Motors and Machines
Remove and salvage fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Salvage, box and store auxiliary units and accessories with the main motor and machines. Tag salvaged items for identification, storage, and protection from damage. Classify broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor.
3.1.16 Electrical Equipment and Fixtures
Salvage motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Salvage wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.16.1 Fixtures
Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured
02 41 00 Page 9 prior to 1978, boxed and tagged for identification, and protected from breakage.
3.1.16.2 Electrical Devices
Remove and salvage switches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.
3.1.16.3 Wiring Ducts or Troughs
Remove and salvage wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.
3.1.16.4 Conduit and Miscellaneous Items
Salvage conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
3.1.17 Elevators and Hoists
Remove elevators, hoists, and similar conveying equipment and salvage as whole units, to the most practical extent. Remove and prepare items for salvage without damage to any of the various parts. Salvage and store rails for structural steel with the equipment as an integral part of the unit.
3.1.18 Items With Unique/Regulated Disposal Requirements
Remove and dispose of items with unique or regulated disposal requirements in the manner dictated by law or in the most environmentally responsible manner.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin
02 41 00 Page 10 demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.2 Reuse of Materials and Equipment
Remove and store materials and equipment indicated to be reused or relocated to prevent damage and reinstall as the work progresses. Capture re-use of materials in the diversion calculations for the project.
3.3.3 Salvaged Materials and Equipment
Remove materials and equipment that are indicated and specified to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site, as directed.
a. Salvage items and material to the maximum extent possible.
b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. Capture salvaged materials in the diversion calculations for the project.
c. Remove salvaged items to remain the property of the Government in a manner to prevent damage, and packed or crated to protect the items from damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items. Properly identify the contents of containers.
d. Remove historical items in a manner to prevent damage. Deliver the following historical items to the Government for disposition: Corner stones, contents of corner stones, and document boxes wherever located on the site.
e. The Government will remove and capture Class I ODS refrigerants. To view the web site for ODS, link to:
https://www.osd.mil/denix/Public/News/DLA/ODS/sect1.html
3.3.4 Disposal of Ozone Depleting Substance (ODS)
Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS shall be removed from Government property and disposed of in accordance with 40 CFR 82 .
Products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) shall be disposed of in accordance with 40 CFR 82 . Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia.
3.3.4.1 Special Instructions
No more than one type of ODS is permitted in each container. A warning/hazardous label shall be applied to the containers in accordance with Department of Transportation regulations. All cylinders including
02 41 00 Page 11 but not limited to fire extinguishers, spheres, or canisters containing an ODS shall have a tag with the following information:
a. Activity name and unit identification code
b. Activity point of contact and phone number
c. Type of ODS and pounds of ODS contained
d. Date of shipment
e. National stock number (for information, call (804) 279-4525).
3.3.4.2 Fire Suppression Containers
Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used to cover exposed actuation mechanisms and discharge ports on these special cylinders.
3.3.5 Transportation Guidance
Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .
3.3.6 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable combustible material off the site.
3.4 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified off the site center.
3.5.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
3.5.3 Removal to Spoil Areas on Government Property
Transport noncombustible materials removed from demolition and deconstruction structures to designated spoil areas on Government property.
3.5.4 Removal from Government Property
Transport waste materials removed from demolished and deconstructed
02 41 00 Page 12 structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.
3.6 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before installation. Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --
02 41 00 Page 13
THIS PAGE INTENTIONALLY LEFT BLANK
02 41 00 Page 14
SECTION 02 82 00
ASBESTOS REMEDIATION
11/18, CHG 1: 11/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP Z9.2 (2018) Fundamentals Governing the Design and Operation of Local Exhaust Ventilation Systems
ASTM INTERNATIONAL (ASTM)
ASTM C732 (2017; R 2022 Standard Test Method for Aging Effects of Artificial Weathering on Latex Sealants
ASTM D4397 (2016) Standard Specification for Polyethylene Sheeting for Construction, Industrial, and Agricultural Applications
ASTM E84 (2020) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM E96/E96M (2021) Standard Test Methods for Gravimetric Determination ofWater Vapor Transmission Rate of Materials
ASTM E119 (2020) Standard Test Methods for Fire Tests of Building Construction and Materials
ASTM E736/E736M (2017) Standard Test Method for Cohesion/Adhesion of Sprayed Fire-Resistive Materials Applied to Structural Members
ASTM E1368 (2014) Visual Inspection of Asbestos Abatement Projects
COMPRESSED GAS ASSOCIATION (CGA)
CGA G-7 (2014) Compressed Air for Human Respiration; 6th Edition
INTERNATIONAL SAFETY EQUIPMENT ASSOCIATION (ISEA)
ANSI/ISEA Z87.1 (2020) Occupational and Educational Personal Eye and Face Protection Devices
02 82 00 Page 1
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 701 (2019) Standard Methods of Fire Tests for Flame Propagation of Textiles and Films
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH NMAM (2016; 5th Ed) NIOSH Manual of Analytical Methods
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 340/1-90/018 (1990) Asbestos/NESHAP Regulated Asbestos Containing Materials Guidance
EPA 560/5-85-024 (1985) Guidance for Controlling Asbestos-Containing Materials in Buildings (Purple Book)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)
29 CFR 1926.51 Sanitation
29 CFR 1926.59 Hazard Communication
29 CFR 1926.103 Respiratory Protection
29 CFR 1926.200 Accident Prevention Signs and Tags
29 CFR 1926.1101 Asbestos
40 CFR 61-SUBPART A General Provisions
40 CFR 61-SUBPART M National Emission Standard for Asbestos
40 CFR 763 Asbestos
42 CFR 84 Approval of Respiratory Protective Devices
49 CFR 107 Hazardous Materials Program Procedures
49 CFR 171 General Information, Regulations, and Definitions
49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements
49 CFR 173 Shippers - General Requirements for
02 82 00 Page 2
Shipments and Packagings
U.S. NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)
ND OPNAVINST 5100.23 (2005; Rev G) Navy Occupational Safety and Health (NAVOSH) Program Manual
UNDERWRITERS LABORATORIES (UL)
UL 586 (2009; Reprint Dec 2017) UL Standard for Safety High-Efficiency Particulate, Air Filter Units
1.2 DEFINITIONS
1.2.1 ACM
Asbestos Containing Materials.
1.2.2 Amended Water
Water containing a wetting agent or surfactant with a maximum surface tension of 0.00042 psi .
1.2.3 Area Sampling
Sampling of asbestos fiber concentrations which approximates the concentrations of asbestos in the theoretical breathing zone but is not actually collected in the breathing zone of an employee.
1.2.4 Asbestos
The term asbestos includes chrysotile, amosite, crocidolite, tremolite asbestos, anthophyllite asbestos, and actinolite asbestos and any of these minerals that has been chemically treated or altered. Materials are considered to contain asbestos if the asbestos content of the material is determined to be at least one percent.
1.2.5 Asbestos Control Area
That area where asbestos removal operations are performed which is isolated by physical boundaries which assist in the prevention of the uncontrolled release of asbestos dust, fibers, or debris.
1.2.6 Asbestos Fibers
Those fibers having an aspect ratio of at least 3:1 and longer than 5 micrometers as determined by National Institute for Occupational Safety and Health (NIOSH) Method 7400.
1.2.7 Asbestos Permissible Exposure Limit
0.1 fibers per cubic centimeter of air as an 8-hour time weighted average measured in the breathing zone as defined by 29 CFR 1926.1101 or other Federal legislation having legal jurisdiction for the protection of workers health.
02 82 00 Page 3
1.2.8 Authorized Person
Any person authorized by the Contractor and required by work duties to be present in the regulated areas.
1.2.9 Background
The ambient airborne asbestos concentration in an uncontaminated area as measured prior to any asbestos hazard abatement efforts. Background concentrations for other (contaminated) areas are measured in similar but asbestos free locations.
1.2.10 Competent Person (CP)
A person meeting the requirements for competent person as specified in 29 CFR 1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which meet the criteria of EPA's Model Accreditation Plan ( 40 CFR 763 ) for project designer or supervisor, or its equivalent. The competent person must have a current State of Alabama asbestos contractors or supervisors license.
1.2.11 Contractor
The Contractor is that individual, or entity under contract to perform the herein listed work.
1.2.12 Disposal Bag
A 6 mil thick, leak-tight plastic bag, pre-labeled in accordance with 29 CFR 1926.1101 , used for transporting asbestos waste from containment to disposal site.
1.2.13 Disturbance
Activities that disrupt the matrix of ACM, crumble or pulverize ACM, or generate visible debris from ACM. Disturbance includes cutting away small amounts of ACM, no greater than the amount which can be contained in one standard sized glovebag or waste bag, not larger than 60 inches in length and width in order to access a building component.
1.2.14 Encapsulation
The abatement of an asbestos hazard through the appropriate use of chemical encapsulants.
1.2.15 Encapsulants
Specific materials in various forms used to chemically or physically entrap asbestos fibers in various configurations to prevent these fibers from becoming airborne. There are four types of encapsulants as follows which must comply with performance requirements as specified herein.
a. Removal Encapsulant (can be used as a wetting agent)
b. Bridging Encapsulant (used to provide a tough, durable surface coating to asbestos containing material)
02 82 00 Page 4
c. Penetrating Encapsulant (used to penetrate the asbestos containing material encapsulating all asbestos fibers and preventing fiber release due to routine mechanical damage)
d. Lock-Down Encapsulant (used to seal off or "lock-down" minute asbestos fibers left on surfaces from which asbestos containing material has been removed).
1.2.16 Friable Asbestos Material
A term defined in 40 CFR 61-SUBPART M and EPA 340/1-90/018 meaning any material which contains more than 1 percent asbestos, as determined using the method specified in 40 CFR 763 , Polarized Light Microscopy (PLM), that when dry, can be crumbled, pulverized, or reduced to powder by hand pressure.
1.2.17 Glovebag Technique
Those asbestos removal and control techniques put forth in 29 CFR 1926.1101 .
1.2.18 Government Consultant (GC)
That qualified person employed directly by the Government to monitor, sample, inspect the work or in some other way advise the Contracting Officer. The GC is normally a private consultant, but can be an employee of the Government.
1.2.19 HEPA Filter Equipment
High efficiency particulate air (HEPA) filtered vacuum and exhaust ventilation equipment with a filter system capable of collecting and retaining asbestos fibers. Filters must retain 99.97 percent of particles
0.3 microns or larger as indicated in UL 586 .
1.2.20 Model Accreditation Plan (MAP)
USEPA training accreditation requirements for persons who work with asbestos as specified in 40 CFR 763 .
1.2.21 Negative Pressure Enclosure (NPE)
That engineering control technique described as a negative pressure enclosure in 29 CFR 1926.1101 .
1.2.22 NESHAP
National Emission Standards for Hazardous Air Pollutants. The USEPA NESHAP regulation for asbestos is at 40 CFR 61-SUBPART M .
1.2.23 Nonfriable Asbestos Material
Material that contains asbestos in which the fibers have been immobilized by a bonding agent, coating, binder, or other material so that the asbestos is well bound and will not normally release asbestos fibers during any appropriate use, handling, storage or transportation. It is understood that asbestos fibers may be released under other conditions such as demolition, removal, or mishap.
02 82 00 Page 5
1.2.24 Permissible Exposure Limits (PELs)
1.2.24.1 PEL-Time Weighted Average(TWA)
Concentration of asbestos not in excess of 0.1 fibers per cubic centimeter of air (f/cc) as an 8-hour time weighted average (TWA).
1.2.24.2 PEL-Excursion Limit
An airborne concentration of asbestos not in excess of 1.0 f/cc of air as averaged over a sampling period of 30 minutes.
1.2.25 Personal Sampling
Air sampling which is performed to determine asbestos fiber concentrations within the breathing zone of a specific employee, as performed in accordance with 29 CFR 1926.1101 .
1.2.26 Private Qualified Person (PQP)
That qualified person hired by the Contractor to perform the herein listed tasks.
1.2.27 Qualified Person (QP)
A Registered Architect, Professional Engineer, Certified Industrial Hygienist, consultant or other qualified person who has successfully completed training and is therefore accredited under a legitimate State Model Accreditation Plan as described in 40 CFR 763 as a Building Inspector, Contractor/Supervisor Abatement Worker, and Asbestos Project Designer; and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The QP must be qualified to perform visual inspections as indicated in ASTM E1368. The QP must be appropriately licensed in the State of Alabama .
1.2.28 TEM
Refers to Transmission Electron Microscopy.
1.2.29 Time Weighted Average (TWA)
The TWA is an 8-hour time weighted average airborne concentration of asbestos fibers.
1.2.30 Transite
A generic name for asbestos cement wallboard and pipe.
1.2.31 Wetting Agent
A chemical added to water to reduce the water's surface tension thereby increasing the water's ability to soak into the material to which it is applied. An equivalent wetting agent must have a surface tension of at most 0.00042 psi .
1.2.32 Worker
Individual (not designated as the Competent Person or a supervisor) who
02 82 00 Page 6 performs asbestos work and has completed asbestos worker training required by 29 CFR 1926.1101 , to include EPA Model Accreditation Plan (MAP) "Worker" training; accreditation, if required by the OSHA Class of work to be performed or by the state where the work is to be performed. The worker must be appropriately licensed in the State of Alabama .
1.3 REQUIREMENTS
1.3.1 Description of Work
The work covered by this section includes the handling and control of asbestos containing materials and describes some of the resultant procedures and equipment required to protect workers, the environment and occupants of the building or area, or both, from contact with airborne asbestos fibers. The work also includes the disposal of any asbestos containing materials generated by the work. More specific operational procedures must be outlined in the Asbestos Hazard Abatement Plan called for elsewhere in this specification. If asbestos-containing materials are discovered during demolition, provide negative pressure enclosure techniques as outlined in this specification. The work area will be evacuated during the asbestos abatement work. A competent person must supervise asbestos removal work as specified herein.
1.3.2 Unexpected Discovery of Asbestos
Notify the Contracting Officer if any previously untested building components suspected to contain asbestos are impacted by the work.
1.3.3 Medical Requirements
Provide medical requirements including but not limited to medical surveillance and medical record keeping as listed in 29 CFR 1926.1101 .
1.3.3.1 Medical Examinations
Before exposure to airborne asbestos fibers, provide workers with a comprehensive medical examination as required by 29 CFR 1926.1101 or other pertinent State or local directives. This requirement must have been satisfied within the 12 months prior to the start of work on this contract. The same medical examination must be given on an annual basis to employees engaged in an occupation involving asbestos and within 30 calendar days before or after the termination of employment in such occupation. Specifically identify x-ray films of asbestos workers to the consulting radiologist and mark medical record jackets with the word
"ASBESTOS."
1.3.3.2 Medical Records
Maintain complete and accurate records of employees' medical examinations, medical records, and exposure data for a period of 50 years after termination of employment and make records of the required medical examinations and exposure data available for inspection and copying to:
The Assistant Secretary of Labor for Occupational Safety and Health (OSHA), or authorized representatives of them, and an employee's physician upon the request of the employee or former employee.
1.3.4 Employee Training
Submit certificates, prior to the start of work but after the main
02 82 00 Page 7 abatement submittal, signed by each employee indicating…