W912QR23B0014_Specs_Vol3-0000.pdf
PDF 2 MB Posted
- Attached to
- Fort Knox Toilet/Shower Facility
- Solicitation number
- W912QR23B0014
About this file
This invitation for bid solicits offers for a toilet and shower facility project at Fort Knox, Kentucky. The project has an estimated construction cost between $5 million and $10 million. Bids are due by a specified date and must be submitted electronically, as facsimile bids will not be accepted. This procurement is set aside exclusively for small businesses. The soliciting agency is the Department of the Army Corps of Engineers Louisville District. The project location is Fort Knox, and the NAICS code listed is 236220, indicating the work involves commercial and institutional building construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Opening Results.pdf | ||
| W912QR23B0014-0003.pdf | ||
| W912QR23B0014_Specs-0002.pdf | ||
| W912QR23B0014_Plans-0001.pdf | ||
| W912QR23B0014_Specs-0001.pdf | ||
| W912QR23B0014_Plans-0000.pdf | ||
| W912QR23B0014_Specs_Vol1-0000.pdf | ||
| W912QR23B0014_Specs_Vol2-0000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Consolidated Shower Facility, Fort Knox, KY
P2: 499990
Design-Bid-Build
Specifications - Vol. 3 of 3 Certified Final Design
13 June 2023
W912QR23B0014
ARIMS: 200A Disposition: Maintain for 15yrs after construction.
W912QR23B0014_Specs_Vol3-0000
499990 Consolidated Shower Facility Fort Knox, KY
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
APPENDIX A: CONSTRUCTION PROJECT SIGN DETAILS
APPENDIX B: SUBMITTAL REGISTER
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01.00 06 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29.00 06 SUSTAINABILITY REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
APPENDIX A: SCHEDULE OF SPECIAL INSPECTIONS
APPENDIX B: STATEMENT OF SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
APPENDIX A: SWPPP
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 BOARD AND BLOCK INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
PROJECT TABLE OF CONTENTS Page 1
CERTIFIED FINAL
08 11 13 STEEL DOORS AND FRAMES
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 67 23.13 STANDARD RESINOUS FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 SEISMIC CONTROL FOR MISCELLANEOUS EQUIPMENT
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 48.19 SEISMIC BRACING FOR HVAC
23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 30 00 HVAC AIR DISTRIBUTION
23 80 20.00 10 GAS-FIRED HEATING EQUIPMENT
23 82 46.00 40 ELECTRIC UNIT HEATERS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DIVISION 32 - EXTERIOR IMPROVEMENTS
PROJECT TABLE OF CONTENTS Page 2
32 05 33 LANDSCAPE ESTABLISHMENT
32 15 00 AGGREGATE SURFACING
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 31 23.00 10 SANITARY SEWER FORCE MAIN PIPING
33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS
33 40 00 STORMWATER UTILITIES
33 51 15 NATURAL-GAS GAS DISTRIBUTION PIPELINES
33 63 14 EXTERIOR BURIED PUMPED CONDENSATE RETURN
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
SECTION TABLE OF CONTENTS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
SECTION 23 05 48.19
SEISMIC BRACING FOR HVAC
05/18, CHG 2: 08/20
PART 1 GENERAL
1.1 REFERENCES
1.2 SYSTEM DESCRIPTION
1.2.1 General Requirements
1.2.2 Mechanical Equipment
1.2.3 Mechanical Systems
1.2.4 Contractor Designed Bracing
1.2.5 Items Not Covered By This Section
1.2.5.1 Items Requiring No Seismic Restraints
1.3 SUBMITTALS
PART 2 PRODUCTS
2.1 GENERAL DESIGN REQUIREMENTS
2.2 EQUIPMENT RESTRAINT
2.2.1 Rigidly (Base and Suspended) Mounted Equipment
2.2.2 Nonrigid or Flexibly-Mounted Equipment
2.3 BOLTS AND NUTS
2.4 FLEXIBLE JOINTS
2.4.1 Braided Hose Expansion Joint
2.4.1.1 Corrugated Hose
2.4.1.2 Flexible Hose Expansion Loops
2.4.2 Double Ball Flexible Expansion Joint
2.4.2.1 Internal Surfaces
2.4.2.2 Exterior Surfaces
2.4.3 Double Ball Flexible Expansion Joint Gravity Drain
(Non-Pressurized)
2.5 SWAY BRACING MATERIALS
PART 3 EXECUTION
3.1 COUPLING AND BRACING
3.2 BUILDING DRIFT
3.3 FLEXIBLE COUPLINGS OR JOINTS
3.3.1 Building Piping
3.4 PIPE SLEEVES
3.5 SPREADERS
3.6 SWAY BRACES FOR PIPING
3.6.1 Transverse Sway Bracing
3.6.2 Longitudinal Sway Bracing
3.6.3 Vertical Runs
3.6.4 Clamps and Hangers
3.7 SWAY BRACES FOR DUCTS
3.7.1 Braced Ducts
3.7.2 Unbraced Ducts
SECTION 23 05 48.19 Page 1
3.8 EQUIPMENT
3.8.1 General
3.8.2 Controls
3.9 ANCHOR BOLTS
3.9.1 Cast-in-Place Anchor Bolts
3.9.2 Drilled-In Anchor Bolts
3.9.2.1 Wedge Anchors, Heavy-Duty Sleeve Anchors, and Undercut
Anchors
3.9.2.2 Cartridge Injection Adhesive Anchors
3.9.2.3 Capsule Anchors
3.10 ANCHOR BOLT TESTING
3.10.1 Torque Wrench Testing
-- End of Section Table of Contents --
SECTION 23 05 48.19 Page 2
SECTION 23 05 48.19
SEISMIC BRACING FOR HVAC
05/18, CHG 2: 08/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 355.2 (2007) Qualification of Post-Installed Mechanical Anchors in Concrete and Commentary
ACI 355.4 (2011) Qualification of Post-Installed Adhesive Anchors in Concrete (ACI 355.4) and Commentary
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
AISC 325 (2017) Steel Construction Manual
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 7-16 (2017; Errata 2018; Supp 1 2018) Minimum Design Loads and Associated Criteria for Buildings and Other Structures
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C105/A21.5 (2018) Polyethylene Encasement for Ductile-Iron Pipe Systems
AWWA C116/A21.16 (2015) Protective Fusion-Bonded Coatings for the Interior and Exterior Surfaces of Ductile-Iron and Gray Iron Fittings
AWWA C153/A21.53 (2019) Ductile-Iron Compact Fittings for Water Service
AWWA C213 (2022) Fusion-Bonded Epoxy Coatings and Linings for Steel Water Pipe and Fittings
ASTM INTERNATIONAL (ASTM)
ASTM A36/A36M (2019) Standard Specification for Carbon Structural Steel
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
SECTION 23 05 48.19 Page 3
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A325 (2014) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
ASTM A490 (2014a) Standard Specification for Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength
ASTM A500/A500M (2021a) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
ASTM A563 (2015) Standard Specification for Carbon and Alloy Steel Nuts
ASTM A603 (2019) Standard Specification for Zinc-Coated Steel Structural Wire Rope
ASTM D1785 (2015; E 2018) Standard Specification for Poly(Vinyl Chloride) (PVC), Plastic Pipe, Schedules 40, 80, and 120
ASTM D2665 (2014) Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings
ASTM F891 (2016) Standard Specification for Coextruded Poly (Vinyl Chloride) (PVC) Plastic Pipe with a Cellular Core
ASTM F1554 (2020) Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength
FEDERAL EMERGENCY MANAGEMENT AGENCY (FEMA)
FEMA P-414 (January 2004) Installing Seismic Restraints for Duct and Pipe
METAL FRAMING MANUFACTURERS ASSOCIATION (MFMA)
MFMA-4 (2004) Metal Framing Standards Publication
NSF INTERNATIONAL (NSF)
NSF/ANSI 61 (2020) Drinking Water System Components - Health Effects
SECTION 23 05 48.19 Page 4
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1981 (2008) Seismic Restraint Manual Guidelines for Mechanical Systems, 3rd Edition
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-301-01 (2019, with Change 1, 2022) Structural Engineering
UFC 4-010-01 (2018; with Change 1, 2020) DoD Minimum Antiterrorism Standards for Buildings
VIBRATION ISOLATION AND SEISMIC CONTROL MANUFACTURERS ASSOCIATION
(VISCMA)
VISCMA 412 (2014) Installing Seismic Restraints for Mechanical Equipment
1.2 SYSTEM DESCRIPTION
1.2.1 General Requirements
Apply the requirements for seismic protection measures described in this section and on the drawings to the mechanical equipment and mechanical systems both inside and outside of the building along with exterior utilities and systems listed below. Where there is a conflict between the specifications and the drawings, the specifications will take precedence.
Accomplish resistance to lateral forces induced by earthquakes without consideration of friction resulting from gravity loads.
1.2.2 Mechanical Equipment
Mechanical equipment to be seismically protected must include the following items to the extent required on the drawings or in other sections of these specifications:
Equipment/Components with Ip = 1.0
Storage Tanks for Water
Water Heaters
Valves and Fittings for Piping
Air Handling Units
SECTION 23 05 48.19 Page 5
Pumps with Motors
Unit Heaters
Exhaust, Return and Misc. Fans
Pumps
Instrumentation and Control for HVAC
1.2.3 Mechanical Systems
Mechanical systems to be seismically protected must include the following items to the extent required on the drawings or in this or other sections of these specifications:
Mechanical systems with Ip = 1.0
a. All Piping and Ducts Inside the Building Except as Specifically Stated Below Under "Items Not Covered By This Section".
c. Gas and Fuel Piping Outside of Buildings.
1.2.4 Contractor Designed Bracing
Submit copies of the design calculations with the drawings. Calculations must be approved, certified, stamped and signed by a registered Professional Structural Engineer. Calculations must verify the capability of structural members to which bracing is attached for carrying the load from the brace. Design the bracing in accordance with UFC 3-301-01 , , UFC 4-010-01 and additional data furnished by the Contracting Officer.
Resistance to lateral forces induced by earthquakes must be accomplished without consideration of friction resulting from gravity loads.
UFC 3-301-01 uses parameters for the building, not for the equipment in the building; therefore, corresponding adjustments to the formulas must be required. Loadings determined using UFC 3-301-01 are based on strength
SECTION 23 05 48.19 Page 6 design; therefore, AISC 325 Specifications must be used for the design.
The bracing for the mechanical equipment designated in paragraph 1.2.2 and systems designated in paragraph 1.2.3 must be developed by the Contractor.
1.2.5 Items Not Covered By This Section
1.2.5.1 Items Requiring No Seismic Restraints
Seismic restraints are not required for the following items:
a. Gas piping less than 1 inch nominal pipe size.
b. Piping in boiler and mechanical equipment rooms less than 1-1/4 inches nominal pipe size.
c. All other piping equal to or less than 3inches nominal pipe size.
d. Rectangular air handling ducts less than 6 square feet in cross sectional area.
e. Round air handling ducts less than 28 inches in diameter.
f. Piping suspended by individual hangers 12 inches or less in length from the top of pipe to the bottom of the supporting structural member where the hanger is attached, except as noted below.
g. Ducts suspended by hangers 12 inches or less in length from the top of the duct to the bottom of the supporting structural member, except as noted below.
In exemptions f. and g. all hangers must meet the length requirements. If the length requirement is exceeded by one hanger in the run, brace the entire run. Seismically protect interior piping and ducts not listed above in accordance with the provisions of this specification.
Non-critical items may require seismic restraints if adjacent to critical equipment or systems that must remain operational after an earthquake and could be compromised by impact with non-critical adjacent components.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Coupling and Bracing
Flexible Couplings or Joints
Equipment Restraint
Contractor Designed Bracing; G , AE
SECTION 23 05 48.19 Page 7
SD-03 Product Data
Coupling and Bracing; G , AE
Flexible Couplings Or Joints; G , AE
Equipment Restraint; G , AE
Contractor Designed Bracing; G , AE
Snubbers
Anchor Bolts
Vibration Isolators
SD-05 Design Data
Design Calculations
SD-06 Test Reports
Anchor Bolts; G , AE
PART 2 PRODUCTS
2.1 GENERAL DESIGN REQUIREMENTS
Submit detailed seismic restraint drawings for mechanical equipment, duct systems, piping systems and any other mechanical systems along with calculations, catalog cuts, templates, and erection and installation details, as appropriate, for the items listed below. Indicate thickness, type, grade, class of metal, and dimensions; and show construction details, reinforcement, anchorage, and installation with relation to the building construction. Calculations must be stamped, by a registered structural engineer, and verify the capability of structural members to which bracing is attached for carrying the load from the brace. Include drawing for Mission Critical Equipment indicating the equipment location in the facility sufficient to be used for the installation. Design must be based on actual equipment and system layout. Design must include calculated dead loads, static seismic loads and capacity of materials utilized for the connection of the equipment or system to the structure.
Analysis must detail anchoring methods.
2.2 EQUIPMENT RESTRAINT
Equipment must be rigidly or flexibly mounted as indicated in the specifications and/or drawings depending on vibration isolation requirements as follows below.
Roof mounted equipment such as cooling towers and condensers, both vibration isolated and nonisolated, must have support members designed and anchored to building structural steel or concrete as required for seismic restraint and wind loads.
SECTION 23 05 48.19 Page 8
2.2.1 Rigidly (Base and Suspended) Mounted Equipment
HVAC equipment furnished under this contract must be rigidly mounted, rigidly mounted using cast-in-place anchor bolts or post-installed anchors that are qualified for earthquake loading in accordance with ACI 355.2 and ACI 355.4 . Anchor bolts must conform to ASTM F1554. For any rigid equipment which is rigidly anchored, provide flexible joints for piping, ductwork, electrical conduit, etc., that are capable of accommodating displacements equal to the full width of the joint in both orthogonal directions. Suspended equipment bracing attachments should be located just above the center of gravity to minimize swinging. Use the ratio of the overturning moment from seismic forces to the resisting moment due to gravity loads to determine if overturning forces need to be considered in the sizing of anchor bolts. Provide calculations to verify the adequacy of the anchor bolts for combined shear and overturning.
2.2.2 Nonrigid or Flexibly-Mounted Equipment
Select vibration isolation devices so that the maximum movement of equipment from the static deflection point is 1/4 inch. Equipment flexibly mounted on vibration isolators must have a bumper restraint or snubber in each horizontal direction and vertical restraints must be provided where required to resist overturning. Isolator housing and restraints must be constructed of ductile materials. A viscoelastic pad or similar material of appropriate thickness must be used between the bumper and components to limit the impact load. Restraints must be designed to resist the calculated horizontal lateral and vertical forces.
Spring vibration isolators must be seismically rated, restrained isolators for equipment subject to load variations and large external forces. The seismically rated housing must be sized to meet or exceed the force requirements applicable to the project and meet the required isolation criteria. Spring vibration isolator manufacturer's will be a member of VISCMA. Design force, Fp, must be doubled for vibration isolators with an air gap greater than 0.25 inches as specified in ASCE 7-16 , Chapter 13.
Housed springs must not be used for seismic restraint applications because they cannot resist uplift.
2.3 BOLTS AND NUTS
Hex head bolts, and heavy hexagon nuts must be ASTM A325 or ASTM A490 bolts and ASTM A563 nuts. Provide bolts and nuts galvanized in accordance with ASTM A153/A153M when used underground or exposed to weather.
2.4 FLEXIBLE JOINTS
Flexible joints must have same pressure and temperature ratings as adjoining pipe. Braided hoses must not be used where there is torsional or axial movement unless manufacturer allows it.
2.4.1 Braided Hose Expansion Joint
Braided hose expansion joint(s) must be installed in the locations indicated on the drawings and as required to accommodate any thermal expansion, contraction or seismic movement of the piping system. Joints must consist of two parallel sections of corrugated metal hose, compatible braid, and 180 degree return bend with inlet and outlet connections. Field
SECTION 23 05 48.19 Page 9 fabricated loops are not acceptable. Braided hose expansion joint(s) must be installed in the locations indicated on the drawings and as required to accommodate any thermal expansion, contraction or seismic movement of the piping system. Joints must consist of two parallel sections of corrugated metal hose, compatible braid, and 180 degree return bend with inlet and outlet connections. Field fabricated loops must not be acceptable.
Braided hose in a 60 degree flexible V loop arrangement must be used for small diameter pipe connections to coils in variable-air-volume (VAV)terminal units and fan coil units installed in suspended ductwork whether braced or unbraced.
All braided hose expansion joints must be manufactured in accordance with the documented manufacturers weld procedure specifications. The procedure qualification record must be used to document the execution of this procedure and must follow the general "guidelines" of ASME Section IX.
Each individual welder must conform to the in-house procedure qualification record and be qualified prior to each production lot. The testing of each individual welder must be documented in a welding procedure qualification record.
2.4.1.1 Corrugated Hose
Corrugated hose must be bronze. Braid must be bronze for any bronze hose.
Fittings materials of construction and end fitting type must be consistent with pipe material and equipment/ pipe connection fittings. Copper fittings must not be attached to stainless steel hose.
2.4.1.2 Flexible Hose Expansion Loops
Flexible hose expansion loops must have a factory supplied, hanger / support lug located at the bottom of the 180deg return. Flexible hose expansion loop(s) must be furnished with a plugged FPT to be used for a drain or air release vent. Flexible hose expansion loop(s) must be rated with an operating pressure which is the same as the adjoining pipe. The operating pressure must be based on burst pressure with a 4 to 1 safety factor.
2.4.2 Double Ball Flexible Expansion Joint
Install flexible expansion joints manufactured of ductile iron conforming to the material requirements of ASTM A536 and AWWA C153/A21.53 in the locations indicated on the drawings. Provide foundry certification of material upon request. Each flexible expansion joint must be pressure tested prior to shipment against its own restraint to a minimum of 350 psi (250 psi for flexible expansion joints 2 inch and 30 inches diameter and larger.) A minimum 2:1 safety factor, determined from the published pressure rating, must apply. Factory Mutual Approval for the 3 inch through 12 inch sizes is required. Each flexible expansion joint must consist of an expansion joint designed and cast as an integral part of a ball and socket type flexible joint, having a minimum per ball deflection of: 20º, 2" - 12"; 15º, 14" - 36"; 12º, 42"-48" and 4-inches minimum expansion. Additional expansion sleeves must be available and easily added or removed at the factory or in the field. Both standardized mechanical joint and flange end connections must be available.
2.4.2.1 Internal Surfaces
Line all internal surfaces (wetted parts) with a minimum of 15 mils of fusion bonded epoxy conforming to the applicable requirements of AWWA C213.
SECTION 23 05 48.19 Page 10
Sealing gaskets must be constructed of EPDM. The coating must meet
NSF/ANSI 61 .
2.4.2.2 Exterior Surfaces
Coat exterior surfaces with a minimum of 6 mils of fusion bonded epoxy conforming to the applicable requirements of AWWA C116/A21.16 . Include appropriately sized polyethylene sleeves, meeting AWWA C105/A21.5 , for direct buried applications.
2.4.3 Double Ball Flexible Expansion Joint Gravity Drain (Non-Pressurized)
Flexible expansion joints gravity drain must be installed in the locations indicated on the drawings and must be manufactured of pvc. All connections whether solvent weld or mechanical must be restrained to allow movement to be transferred to expansion joint. Each ball must allow up to 15 degrees deflection.
End connection outside diameters must be compatible with ASTM D1785, ASTM D2665 and ASTM F891 PVC pipe and are to be solvent welded.
2.5 SWAY BRACING MATERIALS
Material used for members listed in this section, must be structural steel conforming with the following:
a. Plates, rods, and rolled shapes, ASTM A36/A36M.
b. Wire rope, ASTM A603 pre-stretched. Class B galv coating Ferrule clamps must be qualified by testing for use in seismic applications per VISCMA 412 . A minimum of two clamps are required on each end of wire rope.
c. Tubes, ASTM A500/A500M , Grade B.
d. Pipes, ASTM A53/A53M, Grade B.
e. Angles, ASTM A36/A36M.
f. Channels (Struts) with in-turned lips and associated hardware for fastening to channels at random points conforming to MFMA-4
PART 3 EXECUTION
3.1 COUPLING AND BRACING
a. Submit detail drawings, as specified here and throughout this specification, along with catalog cuts, templates, and erection and installation details, as appropriate, for the items listed.
Submittals must be complete in detail; must indicate thickness, type, grade, class of metal, and dimensions; and must show construction details, reinforcement, anchorage, and installation with relation to the building construction.
b. Provide coupling installation conforming to the details shown on the drawings. Provisions of this paragraph apply to all piping within a 5 foot line around outside of building unless buried in the ground.
Piping grouped for support on trapeze-type hangers must be braced at the most frequent interval as determined by applying the requirements
SECTION 23 05 48.19 Page 11 of this specification to each piping run on the common support.
c. Size bracing components as required for the total load carried by the common supports. Bracing rigidly attached to pipe flanges, or similar, must not be used where it would interfere with thermal expansion of piping.
d. Adjust isolators and restraints after piping systems has been filled and equipment is at its operating weight, following the manufacturer's written instructions.
e. Install cables at a 45-degree slope. Where interference is present, the slope may be minimum of 30 degrees or a maximum of 60 degrees per
VISCMA 412 .
3.2 BUILDING DRIFT
Provide joints capable of accommodating seismic displacements for vertical piping between floors of the building, where pipes pass through a building seismic or expansion joint, or where rigidly supported pipes connect to equipment with vibration isolators. Provide horizontal piping across expansion joints to accommodate the resultant of the drifts of each building unit in each orthogonal direction. For threaded piping, provide swing joints made of the same piping material. For piping with manufactured ball joints the seismic drift must be 0.015 feet per foot of height above the base where the seismic separation occurs; this drift value must be used in place of the expansion given in the manufacturer's selection table.
3.3 FLEXIBLE COUPLINGS OR JOINTS
3.3.1 Building Piping
Provide flexible couplings or joints in building piping at bottom of all pipe risers for pipe larger than 3-1/2 inches in diameter. Laterally brace flexible couplings or joints without interfering with the action of the flexible coupling or joint. Cast iron waste and vent piping need only comply with these provisions when caulked joints are used. Flexible bell and spigot pipe joints using rubber gaskets may be used at each branch adjacent to tees and elbows for underground waste piping inside of building to satisfy these requirements.
3.4 PIPE SLEEVES
Size pipe sleeves in interior non-fire rated walls as indicated on the drawings to provide clearances that will permit differential movement of piping without the piping striking the pipe sleeve. Pipe sleeves in fire rated walls must conform to the requirements in Section 07 84 00
FIRESTOPPING.
3.5 SPREADERS
Provide spreaders between adjacent piping runs to prevent contact during seismic activity whenever pipe or insulated pipe surfaces are less than 4 inches apart. Apply spreaders at same interval as sway braces at an equal distance between the sway braces. If rack type hangers are used where the pipes are restrained from contact by mounting to the rack, spreaders are not required for pipes mounted in the rack. Apply spreaders to surface of bare pipe and over insulation on insulated pipes utilizing high-density
SECTION 23 05 48.19 Page 12 inserts and pipe protection shields in accordance with the requirements of Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS.
3.6 SWAY BRACES FOR PIPING
Provide sway braces to prevent movement of the pipes under seismic loading. Provide braces in both the longitudinal and transverse directions, relative to the axis of the pipe. Provide sufficient braces for equipment to resist a horizontal force as specified in UFC 3-301-01 without exceeding safe working stress of bracing components. Provide bracing that does not interfere with thermal expansion requirements for the pipes as described in other sections of these specifications. For seismic analysis of horizontal pipes, the equivalent static force should be considered to act concurrently with the full dead load of the pipe, including contents.
3.6.1 Transverse Sway Bracing
Provide transverse sway bracing for steel and copper pipe at intervals not to exceed those shown on the drawings. All runs (length of pipe between end joints) must have a minimum of transverse bracing at each end.
Provide transverse sway bracing for pipes of materials other than steel and copper at intervals not to exceed the hanger spacing as specified in Section 22 00 00 PLUMBING, GENERAL PURPOSE.
3.6.2 Longitudinal Sway Bracing
Provide longitudinal sway bracing at 40 foot intervals unless otherwise indicated. All runs (length of pipe between end joints) must have one longitudinal brace minimum. Construct sway braces in accordance with the drawings. Do not use branch lines, walls, or floors as sway braces.
3.6.3 Vertical Runs
Run is defined as length of pipe between end joints. Do not brace vertical runs of piping no more than 10 foot vertical intervals. Braces for vertical runs must be above the center of gravity of the segment being braced. Flexible couplings should be provided at the bottoms of risers for pipes larger than 3.5 in. (89 mm) in diameter. Flexible couplings and expansion joints should be braced laterally and longitudinally unless such bracing would interfere with the action of the couplings or joints. When pipes enter buildings, flexible couplings should be provided to allow for relative movement between the soil and building. Construct all sway braces in accordance with the drawings. Attach sway braces to the structural system. Do not connect to branch lines, walls, or floors.
3.6.4 Clamps and Hangers
Apply clamps or hangers on uninsulated pipes directly to pipe. Insulated piping must have clamps or hangers applied over insulation in accordance with Section 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS.
Hanger rod stiffener angle or strut bracing must be securely attached by a series of attachment clamps manufactured from a one piece metal stamping and must include all require attachment hardware and locking nuts.
Attachment clamps made from aluminum or cast iron must not be used in seismic applications. Do not weld vertical braces to hanger rods.
SECTION 23 05 48.19 Page 13
3.7 SWAY BRACES FOR DUCTS
3.7.1 Braced Ducts
Provide bracing details and spacing for rectangular and round ducts in accordance with SMACNA 1981. However, the design seismic loadings for these items must not be less than loadings obtained using the procedures in UFC 3-301-01 . Bracing must not attach to duct joints. Use shortest screws possible when penetrating ductwork to minimize airflow noise inside duct.
3.7.2 Unbraced Ducts
Attach hangers for unbraced ducts to the duct within 2 inches of the top of the duct with a minimum of two #10 sheet metal screws in accordance with FEMA P-414 . Use shortest screws possible when penetrating ductwork to minimize airflow noise inside duct. Install unbraced ducts with a 6 inch minimum clearance to vertical ceiling hanger wires.
3.8 EQUIPMENT
3.8.1 General
Ensure housekeeping pads have adequate space to mount equipment and seismic restraint devices allowing adequate edge distance and embedment depth for restraint anchor bolts. Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Do not drill holes in concrete or masonry until concrete, mortar, or grout has achieved full design strength. Install neoprene grommet washers or till the gap with epoxy on equipment anchor bolts where clearance between anchor and equipment support hole exceeds 0.125 inches.
3.8.2 Controls
Ensure that controls for critical equipment that must remain operational after an earthquake are certified per paragraph 3.11 SPECIAL TESTING FOR SEISMIC-RESISTING EQUIPMENT and are served by emergency power as required.
3.9 ANCHOR BOLTS
3.9.1 Cast-in-Place Anchor Bolts
Use templates to locate cast-in-place bolts accurately and securely in formwork. Anchor bolts must have an embedded straight length equal to at least 12 times nominal diameter of the bolt. Anchor bolts that exceed the normal depth of equipment foundation piers or pads must either extend into concrete floor or the foundation or be increased in depth to accommodate bolt lengths.
3.9.2 Drilled-In Anchor Bolts
Drill holes with rotary impact hammer drills Drill bits must be of diameters as specified by the anchor manufacturer. Unless otherwise shown on the Drawings, all holes must be drilled perpendicular to the concrete surface. Where anchors are permitted to be installed in cored holes, use core bits with matched tolerances as specified by the manufacturer.
Properly clean cored hole per manufacturer's instructions. Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Exercise care in coring or drilling to avoid damaging
SECTION 23 05 48.19 Page 14 existing reinforcing or embedded items. Notify the COR if reinforcing steel or other embedded items are encountered during drilling. Take precautions as necessary to avoid damaging prestressing tendons, electrical and telecommunications conduit, and gas lines. Unless otherwise specified, do not drill holes in concrete or masonry until concrete, mortar, or grout has achieved full design strength. Perform anchor installation in accordance with manufacturer instructions.
3.9.2.1 Wedge Anchors, Heavy-Duty Sleeve Anchors, and Undercut Anchors
Protect threads from damage during anchor installation. Heavy-duty sleeve anchors must be installed with sleeve fully engaged in part to be fastened. Set anchors to manufacturer's recommended torque, using a torque wrench. Following attainment of 10% of the specified torque, 100% of the specified torque must be reached within 7 or fewer complete turns of the nut. If the specified torque is not achieved within the required number of turns, the anchor must be removed and replaced unless otherwise directed by the Engineer.
3.9.2.2 Cartridge Injection Adhesive Anchors
Where approved for seismic application, clean all holes per manufacturer instructions to remove loose material and drilling dust prior to installation of adhesive. Inject adhesive into holes proceeding from the bottom of the hole and progressing toward the surface in such a manner as to avoid introduction of air pockets in the adhesive. Follow manufacturer recommendations to ensure proper mixing of adhesive components.
Sufficient adhesive must be injected in the hole to ensure that the annular gap is filled to the surface. Remove excess adhesive from the surface. Shim anchors with suitable device to center the anchor in the hole. Do not disturb or load anchors before manufacturer specified cure time has elapsed.
3.9.2.3 Capsule Anchors
Where approved for seismic application, perform drilling and setting operations in accordance with manufacturer instructions. Clean all holes to remove loose material and drilling dust prior to installation of adhesive. Remove water from drilled holes in such a manner as to achieve a surface dry condition. Capsule anchors must be installed with equipment conforming to manufacturer recommendations. Do not disturb or load anchors before manufacturer specified cure time has elapsed.
Observe manufacturer recommendations with respect to installation temperatures for cartridge injection adhesive anchors and capsule anchors.
3.10 ANCHOR BOLT TESTING
Test in place expansion and chemically bonded anchors not more than 24 hours after installation of the anchor, conducted by an independent testing agency; testing must be performed on random anchor bolts as described below.
3.10.1 Torque Wrench Testing
Perform torque wrench testing on not less than 50 percent of the total installed applied torque expansion anchors and at least one anchor for every piece of equipment containing more than two anchors. The test torque must equal the minimum required installation torque as required by
SECTION 23 05 48.19 Page 15 the bolt manufacturer. Calibrate torque wrenches at the beginning of each day the torque tests are performed. Recalibrate torque wrenches for each bolt diameter whenever tests are run on bolts of various diameters. Apply torque between 20 and 100 percent of wrench capacity. Reach the test torque within one half turn of the nut, except for 3/8 inch sleeve anchors which must reach their torque by one quarter turn of the nut. If any anchor fails the test, test similar anchors not previously tested until 20 consecutive anchors pass. Failed anchors must be retightened and retested to the specified torque; if the anchor still fails the test it must be replaced.
-- End of Section --
SECTION 23 05 48.19 Page 16
SECTION TABLE OF CONTENTS
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
SECTION 23 05 93.00 06
TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
08/16
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 SIMILAR TERMS
1.3.1 Work Description
1.4 TAB STANDARD
1.5 QUALIFICATIONS
1.5.1 TAB Firm
1.5.2 TAB Specialist
1.6 TAB SPECIALIST RESPONSIBILITIES
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 DESIGN REVIEW
3.2 TAB RELATED HVAC SUBMITTALS
3.3 TAB SCHEMATIC DRAWINGS AND REPORT FORMS
3.4 TAB Procedures
3.5 Calibrations
3.6 Systems Readiness Check
3.7 TESTING, ADJUSTING, AND BALANCING
3.7.1 Preliminary Procedures
3.7.2 TAB Field Work
3.8 TAB Report
3.8.1 Draft TAB Report
3.8.2 Final TAB Report
3.9 TAB Verification
3.10 Marking of Setting
3.11 Identification of Test Ports
-- End of Section Table of Contents --
SECTION 23 05 93.00 06 Page 1
SECTION 23 05 93.00 06
TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC
08/16
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASSOCIATED AIR BALANCE COUNCIL (AABC)
AABC MN-1 (2002; 6th ed) National Standards for Total System Balance
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB PROCEDURAL STANDARDS (2005) Procedural Standards for Testing, Adjusting and Balancing (TAB) of Environmental Systems
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1780 (2002) HVAC Systems - Testing, Adjusting and Balancing, 3rd Edition
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with LRL Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
TAB Schematic Drawings and Report Forms; G, AE
Submit TAB Schematic Drawings and Report Forms no later than 21 calendar days prior to the start of TAB field work. Submit three hard copies and an electronic copy.
SD-03 Product Data
TAB Related HVAC Submittals
Submit an electronic copy of a list of the TAB Related HVAC Submittals, no later than 7 calendar days after the approval of the TAB Specialist.
SECTION 23 05 93.00 06 Page 2
TAB Procedures; G, AE
Submit TAB Procedures concurrent with the TAB Schematic Drawings and Report Forms. Submit three hard copies and an electronic copy.
Calibrations; G, Submit Calibration concurrent with the TAB Schematic Drawings and Report Forms. Submit three hard copies and an electronic copy.
Systems Readiness Check
Submit proposed date and time to begin the Systems Readiness Check, no later than 7 calendar days prior to the start of the Systems Readiness Check.
TAB Field Work; G, Submit proposed date and time to begin TAB field work concurrent with the Systems Readiness Check Report.
TAB Verification; G, Submit proposed date and time to begin the TAB Verification, concurrent with the Draft TAB Report.
SD-06 Test Reports
Design Review Report; G, AE
Submit the Design Review Report no later than 14 calendar days after approval of the TAB Firm and the TAB Specialist. Submit one hard copy and an electronic copy.
Systems Readiness Check Report; G, Submit the Systems Readiness Check Report at least 14 calendar days prior to the start of TAB Field Work. Submit three hard copies and an electronic copy.
Draft TAB Report; G, AE
Submit completed Draft TAB Report electronically no later that 7 calendar days after completion of all TAB field work. Submit one hard copy and an electronic copy.
Final TAB Report; G, AE
Submit three hard copies and an electronic copy of the Final TAB Reports no later that 7 calendar days after successful completion of TAB Verification. Submit three hard copies and an electronic copy.
SD-07 Certificates
SECTION 23 05 93.00 06 Page 3
TAB Firm; G, Submit certification of the proposed TAB Firm's qualifications by either AABC, NEBB, or TABB to perform the duties specified herein and in other related Sections, no later than 21 calendar days after the Notice to Proceed. The documentation shall include the date that the Certification was initially granted and the date that the current Certification expires. Submit three hard copies and one electronic copy.
TAB Specialist; G, Submit certification of the proposed TAB Specialist's qualifications by either AABC, NEBB, or TABB to perform the duties specified herein and in other related Sections, no later than 21 calendar days after the Notice to Proceed. The documentation shall include the date that the Certification was initially granted and the date that the current Certification expires.
Submit three hard copies and an electronic copy.
1.3 SIMILAR TERMS
In some instances, terminology differs between the Contract and the TAB Standard primarily because the intent of this Section is to use the industry standards specified, along with additional requirements listed herein to produce optimal results. The following table of similar terms is provided for clarification only. Contract requirements take precedent over the corresponding AABC, NEBB, or TABB requirements where differences exist.
SIMILAR TERMS
Contract Term AABC Term NEBB Term TABB Term
TAB Standard National Standards for Procedural Standards SMACNA's Testing and Balancing for Testing, Adjusting, Procedures Heating, Ventilating, and Balancing of and Air Conditioning Environmental Systems.
Systems
TAB Specialist TAB Engineer TAB Supervisor TAB Supervisor
Systems Construction Phase Field Readiness Field Readiness Inspection Check & Preliminary Readiness Check Field Procedures. Check & Prelim.
Field Procedures
1.3.1 Work Description
Perform Testing, Adjusting, and Balancing (TAB) of the new heating, ventilation, and cooling (HVAC) air and water distribution systems.
SECTION 23 05 93.00 06 Page 4
1.4 TAB STANDARD
Perform TAB in accordance with the requirements of the TAB procedural standard recommended by the TAB trade association that approved the TAB Firm's qualifications, i.e. AABC MN-1, NEBB PROCEDURAL STANDARDS, or SMACNA 1780 as supplemented and modified by this specification section.
Comply with all recommendations and suggested practices contained in the TAB procedural standards. Use the provisions of the TAB Standard, including checklists, report forms, etc., as nearly as practical, to satisfy the Contract requirements. The TAB Standard shall be used for all aspects of TAB, including qualifications for the TAB Firm and Specialist and calibration of TAB instruments. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the TAB Standard, adhere to the manufacturer's recommendations.
All quality assurance provisions of the TAB Standard such as performance guarantees are part of this contract. For systems or system components not covered in the TAB Standard, TAB procedures must be developed by the TAB Specialist. Where new procedures, requirements, etc., applicable to the Contract requirements have been published or adopted by the body responsible for the TAB Standard used (AABC, NEBB, or TABB), the requirements and recommendations contained in these procedures and requirements are mandatory.
1.5 QUALIFICATIONS
1.5.1 TAB Firm
The TAB Firm must be either a member of AABC or certified by the NEBB or the TABB and certified in all categories and functions where measurements or performance are specified on the plans and specifications, including TAB of environmental systems and the measuring of sound and vibration in environmental systems.
The certification must be maintained for the entire duration of duties specified herein. If, for any reason, the firm loses subject certification during this period, immediately notify the Contracting Officer and submit another TAB Firm for approval. Any firm that has been the subject of disciplinary action by either the AABC, the NEBB, or the TABB within the five years preceding Contract Award is not eligible to perform any duties related to the HVAC systems, including TAB. All work specified in this section and in other related sections to be performed by the TAB Firm is invalid if the TAB Firm loses its certification prior to Contract completion and must be performed by an approved successor.
These TAB services are to assist the prime Contractor in performing the quality oversight for which it is responsible. The TAB Firm must be a subcontractor of the prime Contractor and shall be financially and corporately independent of the mechanical subcontractor, and shall report to and be paid by the prime Contractor.
1.5.2 TAB Specialist
The TAB Specialist must be either a member of AABC, an experienced technician of the Firm certified by the NEBB, or a Supervisor certified by the TABB. The certification must be maintained for the entire duration of duties specified herein. If, for any reason, the Specialist loses subject certification during this period, immediately notify the Contracting Officer and submit another TAB Specialist for approval. Any individual
SECTION 23 05 93.00 06 Page 5 that has been the subject of disciplinary action by either the AABC, the NEBB, or the TABB within the five years preceding Contract Award is not eligible to perform any duties related to the HVAC systems, including TAB. All work specified in this section and in other related sections performed by the TAB Specialist is invalid if the TAB Specialist loses its certification prior to Contract completion and must be performed by the approved successor.
1.6 TAB SPECIALIST RESPONSIBILITIES
All TAB work specified herein and in related sections must be performed under the direct guidance of the TAB Specialist. The TAB specialist is required to be onsite on a daily basis to direct TAB efforts. The TAB Specialist shall participate in the commissioning process specified in LRL Section 01 46 00.00 06 TOTAL BUILDING COMMISSIONING (CONTRACTOR CxA).
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 DESIGN REVIEW
The TAB Specialist must review the Contract Plans and Specifications and identify, in a Design Review Report, any deficiencies that would prevent the effective and accurate TAB of the system. In the Design Review Report, the TAB Specialist shall individually list each deficiency and the corresponding proposed corrective action necessary for proper system operation. State that no deficiencies are evident if that is the case.
3.2 TAB RELATED HVAC SUBMITTALS
The TAB Specialist must prepare a list of the submittals from the Contract Submittal Register that relate to the successful accomplishment of all HVAC TAB. Accompany the submittals identified on this list shall be accompanied by a letter certifying that submitted equipment will allow proper testing, adjusting, and balancing of the HVAC systems. The letter must be signed and dated by the TAB Specialist when submitted to the Government. The TAB Specialist must also ensure that the location and details of ports, terminals, connections, etc., necessary to perform TAB are identified on the submittals.
3.3 TAB SCHEMATIC DRAWINGS AND REPORT FORMS
Provide TAB Schematic Drawings showing each system component, including balancing devices, for each system. Include the following on TAB Schematic Drawings:
a. Location of all air terminal devices including supply, return, exhaust, and transfer devices.
b. A unique number or mark for each piece of equipment or terminal cross-referenced to the report forms and procedures.
c. Locations of air balancing dampers.
d. Air quantities at each air terminal.
e. Air quantities and temperatures in air handling unit schedules.
SECTION 23 05 93.00 06 Page 6
f. Intended location of all traverse, static pressure readings, and other testing points with a keying scheme cross-referenced to the TAB report forms and procedures.
g. Water quantities and temperatures in thermal energy transfer equipment schedules.
h. Water quantities and heads in pump schedules.
i. Water flow measurement fittings and balancing fittings.
Provide TAB Report Forms intended for use in preparing the TAB Report.
Include the following information in the TAB Report Forms:
a. Design data obtained from contract drawings, specifications, and approved submittals.
b. Notations detailing additional data to be obtained from the contract site by the TAB Specialist.
c. Designate the actual data to be measured.
d. Identifiers for each measured item and piece of equipment or terminal cross-referenced from TAB Schematic Drawings.
e. Provide a list of the types of instruments, and the measuring range of each, which are anticipated to be used. By means of a keying scheme, specify on each TAB report form submitted, which instruments will be used for measuring each item. If selection of which instrument to use will be made in the field, specify from which instruments the choice will be made. Place the instrument key number in the blank space where the measured data would be entered.
3.4 TAB Procedures
Provide step by step procedures for each measurement required during TAB.
Provide a separate section for each system. Include measures to ensure that each system performs as specified in all operating modes, interactions with other components (such as exhaust fans, kitchen hoods, fume hoods, relief vents, etc.) and systems, and with all seasonal operating differences, diversity, simulated loads, and pressure relationships required.
3.5 Calibrations
Provide a list of each instrument to be used during TAB, stating calibration requirements required or recommended by both the TAB Standard and the instrument manufacturer and the actual calibration history of the instrument, submitted with the TAB Procedures. The calibration history shall include dates calibrated, the qualifications of the calibration laboratory, and the calibration procedures used.
3.6 Systems Readiness Check
The TAB Specialist must inspect each system to ensure that it is complete, including installation and operation of controls, and that all aspects of the facility that have any bearing on the HVAC systems, including installation of ceilings, walls, windows, doors, and partitions, are complete in accordance with the applicable TAB…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .