This federal contract opportunity solicitation seeks construction services for a new aircraft maintenance hangar at Westover Air Reserve Base in Massachusetts. The proposed project includes constructing a high-bay hangar with reinforced concrete foundation and floor slab, masonry and metal exterior walls, electrically operated hangar doors, structural steel frame, fire protection and alarm systems, utilities, secure and non-secure communications, site improvements, and demolition of an existing building. The contract duration is estimated at 730 calendar days with a cost range between $25-100 million. NAICS code is 236220. This will be an unrestricted, full and open competition conducted by the Department of the Army Corps of Engineers Louisville District.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Regional ISO Maintenance Hangar Westover Air Reserve Base, MA
P2: 472183
Design Bid Build
Specifications Vol. 4 of 4 Certified Final Submittal
11 August 2020
W912QR20R0059
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR20R0059-0001
This page was intentionally left blank for duplex printing.
Westover Air Reserve Base, MA
Project Number: YTPM099001B P2#: 472183
Certified Final Submittal
Specifications
Volume IV
July 2020
BMcD PN 109519
Louisville District
Westover Air Reserve Base, MA
Project Number: YTPM099001B
P2#: 472183
July 2020 Burns & McDonnell 9400 Ward Parkway
Kansas City, MO 64114
CERTIFICATION PAGE
CIVIL STRUCTURAL ARCHITECTURAL
FIRE PROTECTION MECHANICAL ELECTRICAL
07/31/2020
07/31/2020 07/31/2020
07/31/2020
C5: 109519; ISO HANGAR
Westover AFRB, MA
109519
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
VOLUME I of IV
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 00.00 06 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01.00 06 PROJECT SCHEDULE
01 33 00.00 06 SUBMITTAL PROCEDURES
01 33 29.00 06 SUSTAINABILITY REPORTING
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.10 06 CONTRACTOR QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 46 00.00 06 TOTAL BUILDING COMMISSIONING (CONTRACTOR CxA)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 06 TEMPORARY ENVIRONMENTAL CONTROLS AND PERMITS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 00 ASBESTOS REMEDIATION
02 83 13.00 06 LEAD IN CONSTRUCTION
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 51 33 METAL LADDERS
05 52 00 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
PROJECT TABLE OF CONTENTS Page 2
06 61 16 SOLID SURFACING FABRICATIONS
VOLUME II of IV
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 11 13 BITUMINOUS DAMPPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 27 19.01 SELF-ADHERING AIR BARRIERS
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 13 METAL WALL PANELS
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 72 13 PREFABRICATED ROOF CURBS
07 84 00 FIRESTOPPING
07 92 00.00 06 JOINT SEALANTS
07 95 00 EXPANSION CONTROL
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 33 13 COILING COUNTER DOORS
08 34 16.10 STEEL SLIDING HANGAR DOORS
08 34 19.10 20 ROLLING SERVICE AND FIRE DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.16 FUEL RESISTIVE RESINOUS FLOORING, 5-COAT SYSTEM
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES
DIVISION 10 - SPECIALTIES
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 14 53 TRAFFIC SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 13 WIRE MESH PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
PROJECT TABLE OF CONTENTS Page 3
DIVISION 11 - EQUIPMENT
11 01 50 RIGID RAIL FALL PROTECTION SYSTEMS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 36 00 COUNTERTOPS
12 50 00.13 10 FURNITURE AND FURNITURE INSTALLATION
12 59 00 SYSTEMS FURNITURE
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 20 PRE-ENGINEERED METAL FUELING CANOPIES
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
21 13 18.00 10 PREACTION SPRINKLER SYSTEMS, FIRE PROTECTION
21 13 25.00 10 HIGH EXPANSION FOAM (HI EX. HEF) FIRE PROTECTION SYSTEM
21 30 00 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 52 00 HEATING BOILERS
23 64 26 HEATING WATER PIPING SYSTEMS
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
VOLUME III of IV
DIVISION 25 - INTEGRATED AUTOMATION
25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END
AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 13 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
PROJECT TABLE OF CONTENTS Page 4
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 56 00 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00.00 06 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 01 16.71 COLD MILLING ASPHALT PAVING
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS PAVEMENTS
32 11 23 GRADED CRUSHED AGGREGATE AND AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 ASPHALT PAVING FOR AIRFIELDS
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES
32 92 19 SEEDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERAGE
33 40 00 STORM DRAINAGE UTILITIES
33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION
33 52 10 FUEL SYSTEMS PIPING (SERVICE STATION)
33 52 23.15 POL SERVICE PIPING WELDING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.15 BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT
46 25 14 COALESCING OIL-WATER SEPARATORS
PROJECT TABLE OF CONTENTS Page 5
VOLUME IV of IV
APPENDIX A DRAFT SWPPP
APPENDIX B ENVIRONMENTAL REPORTS
APPENDIX C BUILDING 2426 PROJECT REFERENCE DOCUMENTS
APPENDIX D OWNER'S PROJECT REQUIREMENTS DOCUMENT
APPENDIX E BASIS OF DESIGN Cx
-- End of Project Table of Contents --
APPENDIX A
Draft SWPPP
Stormwater Pollution Prevention Plan
Louisville District U.S. Army Corps of Engineers
Project No. 109519
May 2019
Stormwater Pollution Prevention Plan prepared for
Louisville District U.S. Army Corps of Engineers
Chicopee, Massachusetts
Project No. 109519
May 2019 prepared by
Burns & McDonnell Engineering Company, Inc.
Kansas City, Missouri
COPYRIGHT © 2019 BURNS & McDONNELL ENGINEERING COMPANY, INC.
Stormwater Pollution Prevention Plan Operator Certification
Regional ISO Maintenance Hangar Project
“I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information contained therein. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information contained is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.”
Authorized Official Title
Signature Date
CONTRACTOR NOTIFICATION
“I understand the terms and conditions of this Stormwater Pollution Prevention Plan and the associated regulations that authorize the discharge of stormwater from construction activities associated with the Project.”
Signature For Responsible for
(Name)
(Position)
(Signature)
(Date)
(Company)
(Street / P.O. Box)
(City, State, Zip)
(Phone)
(Activity)
Stormwater Pollution Prevention Plan Table of Contents
USACOE TOC-1 Burns & McDonnell
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION ............................................................................................... 1-1
1.1 Project Description and Location ......................................................................... 1-2
1.2 Project Owner and Operator ................................................................................ 1-2
1.3 Stormwater Team ................................................................................................. 1-2
1.4 SWPPP Certification ............................................................................................ 1-3
1.5 Standard Permit Conditions ................................................................................. 1-3
1.5.1 Duty to Comply with Permit Conditions .............................................. 1-3
1.5.2 Notice of Permit Coverage Posting Requirements ............................... 1-4
1.5.3 Modification of NOI ............................................................................. 1-4
1.5.4 SWPPP Modifications .......................................................................... 1-4
1.5.5 Final Stabilization and Termination of Coverage ................................. 1-4
1.5.6 Retention of Records............................................................................. 1-5
2.0 CONSTRUCTION ACTIVITIES AND SITE DESCRIPTION .............................. 2-1
2.1 Nature of Construction Activity........................................................................... 2-1
2.2 Planned Sequence of Major Construction Activities ........................................... 2-1
2.3 Site Maps ............................................................................................................. 2-1
2.4 Soils...................................................................................................................... 2-1
2.5 Potential Pollutants .............................................................................................. 2-2
2.6 Receiving Waters ................................................................................................. 2-2
2.7 Threatened and Endangered Species ................................................................... 2-3
2.8 Cultural Resources ............................................................................................... 2-3
3.0 CONTROLS - STRUCTURAL PRACTICES ..................................................... 3-1
3.1 Temporary Erosion and Sediment Control Practices ........................................... 3-1
3.1.1 Construction Entrance ........................................................................... 3-1
3.1.2 Silt Fence .............................................................................................. 3-1
3.1.3 Inlet Protection ...................................................................................... 3-2
3.1.4 Concrete Washout ................................................................................. 3-2
3.2 Permanent Stormwater Management Practices ................................................... 3-2
3.2.1 Check Dams .......................................................................................... 3-2
3.2.2 Infiltration Basin ................................................................................... 3-3
4.0 CONTROLS - STABILIZATION PRACTICES .................................................. 4-1
4.1 Stabilization Practices .......................................................................................... 4-1
4.1.1 Seeding .................................................................................................. 4-1
4.1.2 Mulching ............................................................................................... 4-1
4.1.3 Fertilizer ................................................................................................ 4-2
4.2 Final Stabilization ................................................................................................ 4-2
5.0 OTHER CONTROLS ......................................................................................... 5-1
USACOE TOC-2 Burns & McDonnell
5.1 Dust Control ......................................................................................................... 5-1
5.2 Street Sweeping ................................................................................................... 5-1
5.3 Waste Materials ................................................................................................... 5-1
5.4 Sanitary Waste ..................................................................................................... 5-1
5.5 Hazardous Waste ................................................................................................. 5-2
6.0 MAINTENANCE AND INSPECTION ................................................................ 6-1
6.1 Inspection Procedures .......................................................................................... 6-1
6.1.1 Areas Requiring Inspection................................................................... 6-1
6.1.2 Inspection Requirements ....................................................................... 6-1
6.1.3 Inspection Report .................................................................................. 6-2
6.2 SWPPP Staff Training ......................................................................................... 6-3
6.3 Corrective Action ................................................................................................. 6-3
6.4 Distribution List ................................................................................................... 6-4
7.0 SPILL PREVENTION AND CONTROL ............................................................. 7-1
7.1 Materials Management Practices ......................................................................... 7-1
7.1.1 Non-Petroleum Products ....................................................................... 7-2
7.1.2 Petroleum Products ............................................................................... 7-2
7.2 Spill Response ...................................................................................................... 7-2
APPENDIX A – GENERAL PERMIT
APPENDIX B – PERMIT AUTHORIZATION
APPENDIX C – FIGURES
APPENDIX D – NOTICE OF PERMIT COVERAGE
APPENDIX E – EROSION AND SEDIMENT CONTROL PLAN
APPENDIX F – BMP SPECIFICATIONS
APPENDIX G – FORMS
APPENDIX H – SPILL REPORT FORM
APPENDIX I – TRAINING RECORDS
USACOE TOC-3 Burns & McDonnell
LIST OF TABLES
Page No.
Table 1-1: Stormwater Team ................................................................................................... 1-3 Table 6-1: Stormwater Inspector Identification List ................................................................ 6-1 Table 6-2: Distribution List ..................................................................................................... 6-4
Stormwater Pollution Prevention Plan List of Abbreviations
USACOE i Burns & McDonnell
LIST OF ABBREVIATIONS
Abbreviation Term/Phrase/Name
ARB Air Reserve Base
BMPs best management practices
Burns & McDonnell Burns & McDonnell Engineering Company, Inc.
CFR Code of Federal Regulations
EPA U.S. Environmental Protection Agency
ESC Plan Erosion and Sediment Control Plan
ISO Isochronal inspection
MS4 Municipal Separate Storm Sewer System
NeT NPDES eReporting Tool
NOI Notice of Intent
NOT Notice of Termination
NPDES National Pollutant Discharge Elimination System
Permit EPA General Permit MAR100000
Project Regional ISO Maintenance Hangar Project
SDS Safety Data Sheet
SPCC Plan Spill Prevention, Control, and Countermeasure Plan
SWPPP Stormwater Pollution Prevention Plan
USACE Louisville District U.S. Army Corps of Engineers
USFWS U.S. Fish and Wildlife Service
Stormwater Pollution Prevention Plan Introduction
USACOE 1-1 Burns & McDonnell
1.0 INTRODUCTION
The U.S. Environmental Protection Agency (EPA) requires a National Pollutant Discharge Elimination
System (NPDES) Permit for stormwater discharges from construction activities that disturb 1 or more acres of land or from smaller sites that are part of a larger, common plan of development or sale which will disturb a cumulative total of 1 or more acres. For the purpose of the NPDES program, construction activities are defined as clearing, grading, excavation, and other construction-related activities that could lead to the generation of pollutants.
In the State of Massachusetts, Region 1 of the EPA is the permitting authority for the NPDES program.
Construction projects that will disturb 1 or more acres of land are issued a certificate of permit coverage under EPA General Permit MAR100000 (Permit), which authorizes the discharge of stormwater associated with construction activities into State waters. Stormwater discharges from construction activities associated with the Regional Isochronal Inspection (ISO) Maintenance Hangar Project (Project) for the Louisville District U.S. Army Corps of Engineers (USACE) are authorized under the Permit. The
Permit is issued pursuant to the Clean Water Act as amended (33 U.S.C. 1251 et. seq.). A copy of the
Permit is provided in Appendix A.
Coverage under the Permit is obtained by developing a Stormwater Pollution Prevention Plan (SWPPP) and then submitting a Notice of Intent (NOI) through the EPA’s NPDES eReporting Tool (NeT) at http://www.epa.gov/npdes/stormwater-discharges-construction-activities#ereporting. The NOI authorization will be included in Appendix B once received. The SWPPP described herein establishes a plan to manage the quality of stormwater runoff from construction activities associated with the Project.
This SWPPP has been developed in accordance with requirements and guidelines specified in Part 7 of the Permit. The SWPPP was also written with the assistance of and information from the EPA’s 2007
Developing Your Stormwater Pollution Prevention Plan: A Guide for Construction Sites.
This SWPPP must be used by onsite construction personnel to reduce soil erosion and to minimize the potential for sediment and other onsite pollutants to leave the Project site and enter waters of the State of
Massachusetts. The SWPPP identifies a set of best management practices (BMPs) to be implemented on the Project site; however, BMPs may need to be moved, added, or redesigned to control erosion and sedimentation to the extent practicable. The SWPPP must be updated and revised when stormwater control measures are modified due to a change in design, construction method, operation, maintenance procedure, etc.
USACOE 1-2 Burns & McDonnell
1.1 Project Description and Location
The Project will consist of the construction of a new C-5 ISO Maintenance Hangar facility at the
Westover Air Reserve Base. This project is located to along the eastern aircraft apron and will require some repaving of the existing apron. The site work includes new access drives, a parking lot, sidewalks, new security fencing, and all utilities to support the new hangar. A new fuel station will be constructed in a new location to replace the existing airside fuel station. The project also includes work to demolish an existing facility on-site, Building 2426. A General Vicinity Map showing the location of the Project can be found in Appendix C. The Project is located in Chicopee, Hampden County, Massachusetts
(42.193313, -72.545387). Construction is scheduled to begin in January 2020 and be completed by
January 2022.
Approximately 6.5 acres of the 8.2-acre site will be disturbed. Based on an evaluation of the Project site, the pre-development percent imperviousness for the Project is 64 percent, and the post-development percent imperviousness is expected to increase to 74 percent. This SWP3 has been developed to address all construction activities associated with the Project.
1.2 Project Owner and Operator
Contact information for the Project owner, USAF Westover Air Reserve Base, is provided below.
USAF Westover Air Reserve Base Rick Colburn 975 Patriot Avenue Chicopee, MA 01022 (413)-557-2433
An operator is any person associated with the Project that has operational control over the construction plans and specifications, including the ability to make modifications to the plans and specifications, and any person who has day-to-day operational control over the construction activities and can make necessary decisions to maintain compliance with Permit conditions. Where there are multiple operators associated with the same project, all operators are required to obtain Permit coverage. All operators must submit an NOI and sign the Operators Certification form, provided at the front of this SWPPP, in accordance with Appendix J of the Permit. Contact information for the Project operator(s) will be added to this SWPPP when available.
USACOE 1-3 Burns & McDonnell
Table 1-1: Stormwater Team
Name/Title Company/Address Phone/Email Role (Area of Control)
USAF Westover Air
Reserve Base
57 Patriot Avenue
Chicopee, MA 01022
(413)-557-2433
Owner’s
Representative
Onsite SWPPP implementation
SWPPP maintenance and modification
Installation and maintenance of
BMPs
Employee training
Corrective action oversight
1.4 SWPPP Certification
By signing the Contractor Notification form (located near the front of this document, copy as needed), the contractor and subcontractors signify they have read, understand, and will adhere to the SWPPP before conducting any construction work that will result in land disturbance. The signed certification confirms that USACE has notified the contractor or subcontractors that a SWPPP has been prepared for the Project, and the contractor and subcontractors must perform the necessary actions identified to comply with the
SWPPP and the Permit. To maintain compliance with the Permit, it may be necessary for the contractor or subcontractor responsible for erosion and sediment control to implement additional stormwater BMPs and pollution prevention measures that may not be indicated in this SWPPP.
1.5 Standard Permit Conditions
This section discusses Federal penalties for noncompliance with the Permit, as well as standard Permit conditions. The staff responsible for implementation of the SWPPP must be familiar with the requirements of the SWPPP and the Permit.
1.5.1 Duty to Comply with Permit Conditions
The EPA has substantial penalties for noncompliance with the Permit. USACE has a duty to comply with
Permit conditions. Failure to comply with Permit conditions is a violation of the Permit and statutes under which it was issued and is grounds for enforcement action including terminating Permit coverage, modification of Permit coverage, or denial of the Permit renewal application, as well as potential criminal, USACOE 1-4 Burns & McDonnell civil, and administrative penalties. Those responsible for SWPPP implementation must be familiar with the SWPPP and Permit requirements.
The EPA, or an authorized representative of the EPA, must be allowed onto the Project site and any location where records are kept under the conditions of the Permit. The EPA must also be allowed to inspect the Project site, sample or monitor stormwater discharges, and access and copy any required records. USACE must comply with any corrective actions required by the EPA as a result of Permit violations discovered during an inspection.
1.5.2 Notice of Permit Coverage Posting Requirements
A Notice of Permit Coverage (Appendix D) must be posted at the entrance to the Project site. It must be visible from a public road, and the font must be large enough to be readily viewed from the public right-of-way.
1.5.3 Modification of NOI
If a modification to the NOI is necessary, due to changes to the Project (e.g., the extent of disturbance has increased), a Change NOI must be submitted using EPA’s NeT. The amendment must include the
Project’s assigned permit number and the requested change. The SWPPP must be updated to reflect the modification(s).
1.5.4 SWPPP Modifications
This SWPPP must be modified, including site maps, within 7 days of any of the following conditions:
• A new operator becomes active onsite; changes are made to construction plans and erosion and sediment control BMPS; or other activities onsite are no longer accurately reflected in this
SWPPP.
• Operational control over areas of the Project site have transferred to another operator.
• State or Federal officials determine SWPPP modifications are necessary for Permit compliance, following onsite inspections.
• The EPA decides to impose additional requirements on the stormwater discharge.
• Revisions to applicable Federal, State, or local requirements affect the stormwater control measures implemented at the Project site.
1.5.5 Final Stabilization and Termination of Coverage
For any areas not covered by permanent structures, final stabilization is met when the Project has been seeded or planted to establish a uniform perennial vegetative cover that will provide a density of 70
USACOE 1-5 Burns & McDonnell percent of the native background vegetative cover for the area. In addition, construction materials, equipment, and waste have been removed from the Project site, and pollutant generating activities associated with construction activities have ceased.
Permit coverage is terminated by submitting a Notice of Termination (NOT) via the EPA’s NeT within 30 calendar days of final stabilization and completeness of the Project.
1.5.6 Retention of Records
The SWPPP and a copy of the authorized NOI must be maintained at the appropriate Project construction office from the date of Project initiation to the date of Project completion. Records must be maintained for dates when major grading occurs, construction activities temporarily or permanently cease, stabilization measures are initiated, and final stabilization is achieved. The following records must be retained for a minimum period of 3 years from the date that Permit coverage expires or is terminated:
• The SWPPP and any amendments to the SWPPP
• A copy of the Permit, the signed and certified NOI submitted to the EPA, and the acknowledgement letter from the EPA’s NeT assigning the NPDES identification number
• Data used to complete the NOI
• Reports and actions required by the Permit
• Site inspection records
• Corrective action reports
• Contractor certifications
• Clearance letters from the U.S. Fish and Wildlife Service (USFWS), Massachusetts Department of Fish and Game, Massachusetts State Historic Preservation Office, the U.S. Army Corps of
Engineers, and any other agency providing clearance
• A copy of the NOT submitted to the EPA
Stormwater Pollution Prevention Plan Construction Activities and Site Description
USACOE 2-1 Burns & McDonnell
2.0 CONSTRUCTION ACTIVITIES AND SITE DESCRIPTION
The following sections include a description of the construction activities that will take place for the
Project as well as information regarding the natural resources in and adjacent to the Project site.
2.1 Nature of Construction Activity
The Project will construct a new C-5 ISO Maintenance Hangar as well as new associated access drives, parking lot, sidewalk, fencing, fuel station, and utilities. This work will also include repaving of a portion of the existing aircraft apron. In addition to the new construction, the demolition of Building 2426, an existing facility onsite, is included in this Project. Construction activities are scheduled to begin January
2020 and end in January 2022. Major ground-disturbing activities associated with the Project include demolition/removal of nearby building and grading for the new hangar and associated facilities.
2.2 Planned Sequence of Major Construction Activities
The following is a chronological list of the planned sequence of activities and implementation of temporary BMPs for Project construction:
1. Install erosion and sediment control measures and temporary construction fence.
2. Demolish Building 2426 and existing airside fuel station.
3. Install additional inlet protection and silt fencing.
4. Construct new C-5 ISO Hangar facility and airside fueling station, including all site work (access drives, parking lot, access apron, fencing, associated utilities, and revised grading).
5. Convert sediment basin to infiltration basin.
6. Seed and/or sod the Project site.
7. Upon achievement of final stabilization, return staging area to existing conditions and submit the
NOT via EPA’s NeT.
2.3 Site Maps
The Vicinity Map, Soils Map, and Topographic Map are provided in Appendix C. The Erosion and
Sediment Control Plan (ESC Plan) is provided in Appendix E.
2.4 Soils
According to the U.S. Department of Agriculture, Natural Resources Conservation Service, Soil Survey of Hampden County, Massachusetts (http://websoilsurvey.nrcs.usda.gov/app/WebSoilSurvey.aspx., accessed April 23, 2019) one soil type, Urban land is located within the Project area. The Urban land soil
USACOE 2-2 Burns & McDonnell type is commonly associated with areas of previous development. A Soils Map is provided in Appendix
C.
2.5 Potential Pollutants
The primary pollutant sources on the Project site will be disturbed soils and subsequent stormwater runoff caused by grading and site excavation operations, vehicle tracking, soil stockpiling, and debris from demolition work. BMPs must be used on the Project site to control erosion and minimize offsite sedimentation. Erosion and sediment control BMPs are discussed in further detail in Chapter 3.0 of this
SWPPP. BMPs for product specific practices are discussed in Chapters 5.0 and 7.0.
Non-stormwater discharges from active construction sites are authorized if the discharge complies with
Part 1.2.2 of the Permit. During Project construction, the following discharges may occur:
• Fire hydrant flushings
• Discharges from emergency fire-fighting activities
• Water used to wash vehicles and equipment, provided there is no discharge of soaps, solvents, or detergents
• Landscape irrigation
• Water used to control dust
• Uncontaminated and non-turbid discharges of groundwater or spring water
• Potable water, including uncontaminated waterline flushing
• Routine external building washdown, provided there is no discharge of soaps, solvents, or detergents and the external surfaces do not contain hazardous substances
• Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred
(unless all spilled material has been removed) and where soaps, solvents, or detergents have not been used
• Foundation or footing drains where flows are not contaminated with process materials such as solvents
• Construction dewatering water discharges in accordance with Part 2.4 of the Permit
• Uncontaminated air conditioning or compressor condensate
2.6 Receiving Waters
Stormwater runoff will drain to the Westover ARB Municipal Separate Storm Sewer System (MS4). Inlet protection and other BMPS will be installed during construction to collect sediment and other construction-related pollutants before they enter the storm sewer system.
USACOE 2-3 Burns & McDonnell
2.7 Threatened and Endangered Species
According to the USFWS Information for Planning and Consultation (https://ecos.fws.gov/ipac/ accessed on April 25, 2019), two federally listed threatened species, the northern long-eared bat (Myotis septentrionalis) and the small whorled pogonia (Isotria medeoloides), are listed as potentially occurring near the Project site. As per coordination with base environmental personnel, no impacts to threatened and endangered species are expected.
2.8 Cultural Resources
According to the National Register of Historic Places
(https://www.nps.gov/maps/full.html?mapId=7ad17cc9-b808-4ff8-a2f9-a99909164466, accessed on April
25, 2019), no historic properties are located on or within 1,000 feet the of Project site. Additionally, no architectural properties are listed on or nominated for inclusion in the National Register of Historic
Places. While cultural resources are not anticipated in the area of disturbance, workers must stop work immediately and notify USACE and the construction office upon discovery of items with potential historical significance, including but not limited to arrowheads, bones, old bottles or building materials, building foundations, and suspected gravesites. If human remains are unearthed during excavation work, then the area must be secured, and the local law enforcement agency must be contacted immediately.
Stormwater Pollution Prevention Plan Controls - Structural Practices
USACOE 3-1 Burns & McDonnell
3.0 CONTROLS - STRUCTURAL PRACTICES
The following sections detail the structural erosion and sediment control BMPs that must be implemented prior to the start of major earth-disturbing activities on the Project site.
3.1 Temporary Erosion and Sediment Control Practices
Erosion and sediment control BMPs must be in place prior to soil-disturbing activities and must be maintained throughout construction. To limit the potential for sediment leaving the Project site, erosion and sediment control BMPs may be required in other locations of the Project site as work progresses.
These BMPs must be evaluated by the contractor/owner’s representative in the field; if measures are changed, then the SWPPP must be modified in accordance with Chapter 6.0 of this document. The minimum temporary erosion and sediment control BMPs that will be used for the Project are discussed in the following subsections.
3.1.1 Construction Entrance
Offsite tracking of soils must be limited by utilizing an appropriately designed construction entrance. The construction entrance installed on the Project site must be maintained throughout the duration of construction. If necessary, a culvert will be installed to allow stormwater to pass under the construction entrance. The amount of sediment that is transported onto a public road surface or other paved areas by construction equipment or vehicles must be limited and cleaned up at the end of each work day. The location and installation details for the construction entrance are provided in Appendix E and F, respectively.
3.1.2 Silt Fence
Silt fence will be used to intercept and retain sediment carried by sheet flow from disturbed areas and to limit sediment-laden runoff from leaving the Project site during construction. Silt fence should be placed perpendicular to the direction of water flow and as close to topographic contours as possible, with the ends extending upslope. Silt fence should also be placed downslope of disturbed areas where sheet or rill erosion would occur and around soil stockpiles. Silt fence must be inspected and maintained on a regular basis, and sediment buildup must be removed when sediment reaches 50 percent of the height of the barrier. Silt fence may be installed with an additional wire backing to provide extra strength in locations that may receive higher stormwater runoff volumes. Location and installation details are provided in
Appendix E and F, respectively.
USACOE 3-2 Burns & McDonnell
3.1.3 Inlet Protection
Inlet protection is used to remove sediment from stormwater before it enters storm sewers. Inlet protection is typically constructed of washed gravel, crushed stone, geotextile fabrics, or other materials.
Storm drain inlet protection consists of several different types of inlet filters and traps, depending on the type of inlet. It will be up to the contractor to determine which types of inlet protection are most suitable for the specific type of storm drain inlet. Common types of inlet protection include Gutterbuddies®, Sediment Fence, Block & Gravel, Gravel & Wire Mesh, and Silt Saver®. Other types of inlet protection include rice wattles, rock socks, and coconut logs. It may be necessary to remove inlet protection in freezing weather and/or prior to snowfall. See location and typical implementation details in Appendices
E and F, respectively.
3.1.4 Concrete Washout
A concrete washout area is either a prefabricated unit or a designed measure to contain concrete washout.
These systems are typically used to contain washout water when chutes and hoppers are rinsed following concrete delivery and are implemented to reduce the discharge of pollutants through consolidation of solids and retention of liquids. Uncured concrete and associated liquids are highly alkaline. Without containment measures, these materials could leach into the soil and contaminate groundwater or discharge to a surface waterbody or wetland. If concrete washouts will be utilized onsite, the installation locations must be shown on the ESC Plan located in Appendix E. Installation specifications for concrete washouts are provided Appendix F.
3.2 Permanent Stormwater Management Practices
Permanent stormwater management BMPs are those that are left in place after construction is finished and the site is stabilized to manage stormwater flow, volume, and/or quality. An infiltration basin for stormwater collection has been designed as a permanent stormwater management feature for the Project site.
3.2.1 Check Dams
Check dams are to be installed in existing or construction-related channels/drainages to reduce runoff velocity, filter concentrated flows, and limit the amount of sediment that travels downstream. Check dams are generally used in concentrated flow areas, such as ditches and swales. These barriers must be placed so that the elevation of the outside channel edge is higher than the top of the barrier in the middle of the channel. The proposed check dams will be composed of washed gravel and will be installed as part of the forebay berm to convey water to the infiltration basin. Check dams must be maintained to remain
USACOE 3-3 Burns & McDonnell effective, and sediment must be removed from behind the device on a regular basis. For more information, refer to the locations and design details in Appendices E and F, respectively.
3.2.2 Infiltration Basin
An infiltration basin is designed to hold stormwater runoff and infiltrate the water slowly to avoid downstream flooding and stream erosion. The practice is an extremely effective water quality and peak discharge reduction measure. The infiltration basin will initially be utilized as temporary sediment basin during construction activities. Upon completion of construction activities, the infiltration basin will be cleaned out and converted to a permanent facility. The infiltration basin is designed to treat runoff from a local 2-year, 24-hour storm. Location and installation details for the infiltration basin are provided in
Appendix E and F, respectively.
Stormwater Pollution Prevention Plan Controls - Stabilization Practices
USACOE 4-1 Burns & McDonnell
4.0 CONTROLS - STABILIZATION PRACTICES
The following sections detail the stabilization practices to be implemented during and after Project construction activities.
4.1 Stabilization Practices
Stabilization measures must be initiated immediately whenever earth-disturbing activities have permanently or temporarily ceased on any portion of the Project site and will not resume for a period exceeding 14 calendar days. Temporary and permanent stabilization activities must be completed as soon as practicable, but no later than 14 calendar days after the initiation of stabilization.
As soon as practicable, but no later than 14 calendar days after the initiation of soil stabilization measures, the contractor is required to have completed:
1. For vegetative stabilization, all activities necessary to initially seed or plant the area to be stabilized; and/or
2. For non-vegetative stabilization, the installation or application of all such non-vegetative measures.
4.1.1 Seeding
The contractor or subcontractor is responsible for labor, materials, tools, equipment, and other related items required for preparing ground, sowing seeds, fertilizing, mulching and top dressing, and other soil management practices. It will be the contractor’s or subcontractor’s responsibility to check that the soil seedbed is not blown, washed, or otherwise removed from the site. The contractor or subcontractor must make repairs, including replacement of lost topsoil and mulch, to the seedbed preparation site in the event of heavy rain, wind, or other natural events that cause damage. Seeding and planting practices must adhere to the specifications provided in Appendix F.
4.1.2 Mulching
Mulching must be used in conjunction with seeding practices to enhance the success of vegetation establishment by providing erosion protection prior to the onset of vegetative growth. Mulch must be free of noxious and undesirable seed and other materials and must be crimped into the ground by means of a mechanical spreader or other approved methods. Mulching should be completed within 24 hours following the seeding operation and must be completed in accordance with requirements in Appendix F.
Stormwater Pollution Prevention Plan Controls - Stabilization Practices
USACOE 4-2 Burns & McDonnell
4.1.3 Fertilizer
Disturbed soil may need supplementation from fertilizer, and soil tests may be necessary to determine the most appropriate fertilizer for each location. Once applied, the fertilizer must be worked into the soil to limit exposure to stormwater. Fertilizer spills must be cleaned up immediately, and fertilizer must not be applied along or in a waterway. Fertilizing procedures must adhere to the specifications provided in
Appendix F.
4.2 Final Stabilization
The Project is considered finally stabilized when all soil-disturbing activities have been completed and a uniform (i.e., evenly distributed, without large bare areas) perennial vegetative cover with a density of 70 percent of the native background vegetative cover for the area has been established on all unpaved areas.
For those areas not covered by permanent vegetation control measures, an equivalent permanent stabilization measure (e.g., riprap, gabions, or geotextiles) must be used.
Stormwater Pollution Prevention Plan Other Controls
USACOE 5-1 Burns & McDonnell
5.0 OTHER CONTROLS
The following sections detail other controls to be implemented during Project construction activities to limit the potential for pollutants and sediment to reach the municipal storm sewer system or waters of the
State.
5.1 Dust Control
Preventative measures must be taken during periods of extreme drought or heavy winds when exposed soil is susceptible to wind erosion. In areas where bare soil is exposed, water or other approved and acceptable dust palliatives will be applied to the soil to limit wind erosion. Precautions should be taken not to over-water and erode soils. In addition, appropriate speed limits should be established within the
Project site to limit the generation of dust. Spoil piles should be temporarily stabilized or covered to limit wind erosion.
5.2 Street Sweeping
If sediment is observed leaving the Project site through tracking and is deposited on paved public or private roads, then it must be removed immediately through dry sweeping and not flushing.
5.3 Waste Materials
Solid and liquid waste (including sediment, asphalt, concrete millings, floating debris, paper, plastic, fabric, and construction and demolition debris) must be disposed of in accordance with applicable disposal requirements and regulations. Solid or liquid wastes must not be disposed of onsite (e.g., buried or poured), but must be taken offsite for proper disposal. Waste containers must be inspected regularly, and waste stored onsite must be protected from stormwater exposure. All waste materials, including those associated with the demolition of Building 2426, must be properly disposed of.
5.4 Sanitary Waste
The contractor and subcontractors must comply with applicable portable toilet regulations. Each contractor and subcontractor must provide sanitary facilities for its crews on the Project site for the duration of construction activities. Facilities must not be placed in low-lying areas or near a waterbody and must be positioned so they are secure and cannot be tipped over. Sanitary facilities must be used by construction personnel and must be serviced regularly by a licensed contractor. Once any facilities are brought to site, their locations should be added to the Erosion and Sediment Control Plan in Appendix E.
Stormwater Pollution Prevention Plan Other Controls
USACOE 5-2 Burns & McDonnell
5.5 Hazardous Waste
Hazardous or toxic waste must be separated from construction and domestic waste and must be stored in sealed containers constructed of suitable materials to avoid leakage or corrosion. These containers should be stored within appropriately sized secondary containment. Hazardous waste material must be disposed of in the manner specified by the manufacturer and by local, State, and Federal regulations. These regulations often include testing of materials to identify what hazards may be present and obtaining manifests or receipts to document proper disposal of materials. Spills must be cleaned up immediately and in accordance with protocols outlined in Chapter 7.0. Site personnel must be made aware of these requirements.
In areas where potential hazards are likely to be encountered, such as asbestos during demolition activities or hydrocarbon-contaminated soils near the runway, precautions should be taken to minimize the potential for further contamination prior to commencing ground-disturbing activities.
Stormwater Pollution Prevention Plan Maintenance and Inspection
USACOE 6-1 Burns & McDonnell
6.0 MAINTENANCE AND INSPECTION
Routine maintenance and inspection of BMPs is essential to minimizing erosion and sedimentation on the
Project site and protecting the water quality of receiving streams.
6.1 Inspection Procedures
A qualified person knowledgeable in the principles and practice of erosion and sediment control BMPs and pollution prevention, and who possesses the skills to assess construction site conditions that could impact water quality, is responsible for conducting regular inspections. Table 6-1 will identify personnel responsible for performing inspections prior to the start of construction, and a copy will be kept onsite.
The Project site must be inspected at a minimum, once every 7 calendar days and within 24 hours of the end of a storm event 0.5-inch or greater, or the occurrence of runoff from snowmelt sufficient to cause a discharge. Total rainfall measured for that day must be recorded in accordance with Part 4.7.1d.
Table 6-1: Stormwater Inspector Identification List
Personnel Title Contact Responsibility
6.1.1 Areas Requiring Inspection
The following areas must be routinely inspected:
• Areas that have been cleared, graded, or excavated and have not yet achieved final stabilization
• Stormwater controls, including pollution prevention measures
• Material, waste, borrow, or equipment storage and maintenance areas
• Areas where stormwater typically flows within the site, including drainages designed to divert, convey, and/or treat stormwater
• Points of discharge
• Locations where stabilization measures have been implemented
6.1.2 Inspection Requirements
During site inspections, the inspector must complete the following actions:
USACOE 6-2 Burns & McDonnell
• Verify erosion and sediment controls and pollution prevention controls are installed and operational, and determine if controls require replacement, repair, or maintenance.
• Determine the presence of conditions, if any, that could lead to spills, leaks, or other accumulations of pollutants.
• Identify locations where new or modified stormwater controls are necessary to meet the requirements of Parts 2 and 3 of the Permit.
• Check discharge points and banks of any surface waters flowing within the Project boundaries or adjacent areas for signs of visible erosion and sedimentation that are attributable to site discharge;
if discharge points are not accessible, check nearby downstream locations to the extent practicable.
• Identify incidents of noncompliance.
• If discharge is occurring at the time of an inspection:
o Identify all points of the Project site from which a discharge occurs.
o Observe and document the visual quality of the discharge (color, odor, oils, suspended solids, and other stormwater pollutants).
o Document whether stormwater controls are operating effectively, and note controls that are not operating effectively.
• Inspect locations where vehicles enter or exit the Project site for evidence of offsite sediment tracking along paved roadways.
In areas of the Project site where construction activities have permanently or temporarily ceased and will not resume for a period exceeding 14 calendar days, stabilization measures must be initiated immediately.
The inspection frequency may be reduced to once per month in areas where seeding has been completed, appropriate non-vegetative cover (e.g., hydromulch, erosion control blankets) has been provided, or…