W912QR20R0027_Specs_Vol1-0000.pdf
PDF 11 MB Posted
- Attached to
- Ft McCoy Training Barracks
- Solicitation number
- W912QR20R0027
About this file
This solicitation is for the design, bid, and construction of new transient training barracks at Fort McCoy in Wisconsin. The project has an estimated construction cost between $10-25 million under NAICS code 236220. The solicitation will use the HUBZone 10% price evaluation preference and funds are not presently available, with no contract award until appropriations. Interested parties must register in the System for Award Management at www.sam.gov which houses the Central Contractor Registration and Online Representations and Certifications Application. Technical questions should be submitted through the Bidder Inquiry function on ProjNet at http://projnet.org/projnet. The soliciting agency is the Department of the Army Corps of Engineers Louisville District. The solicitation number is W912QR20R0027 and responses are due through sealed bids, with the terms "bid," "bidder," "offer," and "offeror" used interchangeably throughout.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Transient Training Barracks Ft McCoy Wisconsin
P2: 476377
Design-Bid-Build
Specifications Volume 1 of 2 Div 00 - 09
CERTIFIED FINAL
07 August 2020
W912QR20R0027
ARIMS: 200A
Disposition: Maintain for 15yrs after completion of project
W912QR20R0027-0000
Design/Bid/Build for the Construction of Transient Training Barracks at Ft McCoy, WI.
Estimated Construction Cost is betw een $10,000,000.00 and $25,000,000.00.
NAICS Code is 236220. Size Determination is $39.5M. Please note that business size in SAM is determined by the NAICS code. If the vendor size is not listed correctly for a particular NAICS code in SAM the business w ill be considered other than a small business.
This is a full and open procurement. In accordance w ith Federal Acquisition Regulation 19.1307, this project requires the HUBZone 10% price evaluation.
Funds are not presently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available.
Central Contractor Registration and ORCA are available through the System for Aw ard Management (SAM), available at w w w .sam.gov.
Please see Section 00 10 00, SF1442 BLOCK 10 CONTINUATION for further instructions.
Technical inquiries and questions relating to the proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://projnet.org/projnet. Please see Section 00 21 00, ProjNet Instructions for further guidance.
LEVI R SPETH 502.315.6199
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Aug-2020
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________780 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________6 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time __0______ _S_e_p _2_0_2_0___ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
502.315.6195 OR 6193FAX:TEL: 502.315.6172 TEL: FAX:
W912QR20R0027 46
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912QR20R0027
Section 00 10 00 - Solicitation
BLOCK 10 CONTINUATION PAGE
Offerors must comply with the requirements of 52.204-7, 52.204-8, 52.232-33, and any other CCR/ORCA requirements in this solicitation through SAM. PLEASE NOTE: SAM is completely free of charge for both registrants and users.
Please see FAR 52.236-27 ALT 1 for Site Visit information.
The term bid and proposal are used interchangeably in industry and may be used interchangeably throughout this solicitation.
Please note, page numbering in this document may not be accurate.
All days are to be considered calendar days unless otherwise noted.
PRICE BREAKOUT SCHEDULE
PRICE BREAKOUT SCHEDULE
PROJECT : ORTC Transient Training Barracks
LOCATION : Ft McCoy – Ft, McCoy, Wisconsin
PROPOSER’S NAME :
BASE PROPOSAL
Item No. Description Unit Amount
0001 Primary Facilities JOB $ ____________
0002 Project Site Work JOB $ ____________
0003 Xcel Energy JOB $ 50,000.00
BASE PROPOSAL SUBMITTAL $ ____________
OPTION ITEMS
0004 Optional Item ‘A’ – Operations and Maintenance, Army Reserve (OMAR) Funded Equipment JOB $ ____________
0005 Optional Item ‘B’ – Operations and Maintenance, Army Reserve (OMAR) Funded Equipment JOB $ ____________
0006 Optional Item ‘C’ – Concrete Sidewalk JOB $ ____________
TOTAL BASE PROPOSAL + OPTION ITEMS $ ____________
Description of Base Proposal Items
(a) Item No. 0001 “Primary Facilities – Barracks Building” includes all Base Proposal construction work required within a line five feet outside of the building, except that work covered by Items No. 0003 0004, 0005 and 006.
(b) Item No. 0002 “Project Site Work”, includes all Base Proposal construction work required beyond a line five feet outside the building, except that work covered by Item Nos. 003 and 006. Includes stone base material for option sidewalks as indicated on the Sheet CP 102.
(c) Item No. 0003 “Xcel Energy”, include all Base Proposal construction work required to pay Xcel Energy to route and install gas and electrical infrastructure including pipeline, conduits, wiring and equipment including manholes and handholds from the utility main to the building.
Description of Option Items
(d) Item No. 0004 “Option ‘A’ – “Bona Fide Need” Operations, Maintenance – Army Reserve (OMAR) Funded Laundry Equipment Items” includes all work required to furnish and install “OMAR Funded Laundry Equipment Items” as noted below, which are items that are not permanently attached to the construction.
OMAR laundry equipment is to be contractor provided and contractor installed (CFCI).
CFCI OMAR Funded Laundry Equipment Items Consist of:
1. Washers at Laundry Rooms 126, 226, 326, 426
2. Dryers at Laundry Rooms 126, 226, 326, 426
***NOTE: This option may be exercised within 450 calendar days from Notice to Proceed.
(e) Item No. 0005 “Option ‘B’ – “Bona Fide Need” Operations, Maintenance – Army Reserve (OMAR)” Funded
Equipment Items” includes all work required to furnish and install “OMAR Funded Equipment Items” which are items that are not permanently attached to the construction. OMAR equipment is to be contractor provided and contractor installed (CFCI).
CFCI “Bona Fide Need” OMAR Funded Equipment Items consist of:
1. Metal Shelving at Janitor Rooms 114, 214, 314. 414
2. Fire Extinguishers as indicated by FEC on enlarged architecture plans.
3. Window Blinds ‘S3’’ at all Exterior Windows as indicated by Finish Plan Interior Design Note 5 on sheet I-602
***NOTE: This option may be exercised within 450 calendar days from Notice to Proceed.
(f) Item No. 0006 “Option ‘C’ – Concrete Sidewalk” See Sheet CP102 for location of new sidewalks.
***NOTE: This option may be exercised within 120 calendar days from Notice to Proceed.
Section 00 21 00 - Instructions
PROJNET INSTRUCTIONS
OFFEROR'S QUESTIONS AND COMMENTS
Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.
To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.
The Solicitation Number is: W912QR20R0027 The Bidder Inquiry Key is: J4G7ZQ-25E55N Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret
Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Select Continue. A page will then open asking you to enter the answer to your
SecretQuestion.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
From this page you may view all bidder inquiries or add an inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
NOTES:
1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.
2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.
3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled ten (10) calendar days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within five (5) calendar days prior to the closing date stated in the solicitation.
SUBMISSION INSTRUCTIONS
Proposals: ALL SUBMISSIONS TO THIS PROPOSAL ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY THROUGH DOD SAFE. No paper copies, CD-ROMs or facsimile submissions will be accepted. Electronic Proposal Submission is required through the Army’s Electronic File Sharing Service, DOD SAFE (https://safe.apps.mil). The DOD SAFE Application is used to send large files to individuals that would normally be too large to send via email. There are no user accounts for SAFE. Authentication is handled via email.
Anyone has access to DOD SAFE, and the application is available for use by anyone. The SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php). Instructions for uploading are as follows:
1. Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your proposal. This will need to be completed five (5) business days prior to proposal due date.
a. Levi Speth, Contract Specialist at Levi.R.Speth@usace.army.mil
b. Emily Moore, Contracting Officer at Emily.A.Moore@usace.army.mil
2. You will receive an email with the link to submit your drop-off. The link will be provided no later than two
(2) business days prior to the proposal due date.
3. Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter
W912QR20R0027-FIRMNAME.
4. Click Upload button to send documents. Note: all files should be uploaded at the same time as the link only allows one upload occurrence.
5. Guest users will need to check their email to verify their email address before the recipients will be notified. (Government-issued Common Access Cards (CACs) are not required).
File Size Limitations: Offerors are advised to follow the DOD SAFE instructions for uploading files. DOD SAFE supports delivery up to 8GB. If needed, Offerors are advised to break the files down into smaller sections in order to upload it to the system. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
File Naming Convention: To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:
W912QR20R0027-FIRMNAME-VOLUME I
W912QR20R0027-FIRMNAME-VOLUME II
Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description.
Please see examples above.
File Organization: Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger. Pages shall be letter sized (larger page sizes (such as 11x17 fold-outs, etc.) will be counted as two pages. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Information pertaining to more than one evaluation factor should be repeated in the each section for each factor.
Upload Completion & Deadline: Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of proposal receipt will be the upload completion / delivery time & date recorded within DOD SAFE site. Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Offerors are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 15.208.
Electronic Files: Files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications. Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked).
Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to Offerors – Competitive Acquisition (Jan 2017),” subparagraph (e), which is found in 00 21 00 Instructions of the RFP. The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.
“For Official Use Only” Source Selection Information See FAR 2.101 and 3.104 Page 1
Section 00 22 12
PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION CRITERIA
1. Overview.
1.1 The intent of this solicitation is to select one contractor for the Construction of a four-story Transient
Training (TT) Enlisted Barracks at Fort McCoy. The basis of award is the Best Value Trade-Off process.
The Government will evaluate the proposals in accordance with the criteria described herein. The
Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source
Selection Authority (SSA) determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. The Government reserves the right to accept other than the lowest priced offer or to reject all offers.
1.2 This project is for the construction of a four-story Transient Training (TT) Enlisted Barracks at Fort
McCoy. This project is for the construction of a four-story Transient Training (TT) Enlisted Barracks for
Major Exercises, Annual Training, Battle Assembly, and Mobilization training at Fort McCoy, WI. This work includes, but is not limited to, construction of a barracks to house 400-soldiers approximately
60,000 SF. Buildings will be of permanent construction with reinforced concrete foundations, concrete floor slabs, structural steel frames, steel stud infill with drywall, masonry veneer walls, prefinished standing seam metal roofing, Heating, Ventilation, and Air Conditioning (HVAC), plumbing, mechanical systems and electrical systems. Supporting facilities include land clearing, paving, general site improvements, and utility connections. Anti-Terrorism/Force Protection (ATFP) and physical security measures have been incorporated into design including maximum standoff distance from roads and parking areas. Sustainability/Energy measures are included.
1.3 The project contains bid options such as: Concrete Sidewalks, Mow Strip along Building Perimeter, and OMAR Funded Bona Fide Need Items.
1.4 The target ceiling for contract award is $22,526,000.00 based on the funds made available for this project.
The Government cannot guarantee that additional funds will be available for award. Offerors are under no obligation to approach this ceiling.
2. Submittal of offers.
2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein. However, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed to clearly describe the offeror's capability for successfully completing the solicited project. Requirements stated in this Request for Proposal (RFP) are minimums. Proposals should follow in the order of sequence set forth in the RFP. Information provided out of sequence may not be evaluated and may result in the offeror’s disqualification from award.
2.2 Offerors shall submit their proposals electronically in accordance with the Proposal Submission
Instructions in Section 00 21 00 of the solicitation. Please follow the instructions precisely as proposals must complete the upload no later than the time and date specified in Block 13 of Standard Form 1442.
NOTE: The Louisville District is in the Eastern Time Zone.
See FAR 2.101 and 3.104 Page 2
2.3 Offerors are required to submit a proposal consisting of the information identified in paragraphs 2.4 and 2.5 below. All proposal materials shall be submitted in binders with a table of contents and tabbed section dividers. The sections should parallel the submission requirements identified herein.
2.4 The Complete Volume I shall be submitted electronically in accordance with the Proposal Submission
Instructions in Section 00 22 12 of the solicitation and include the following information:
Volume I – Factor I: Past Performance
Volume I – Factor II: Narrative of Management Plan
Volume I – Factor III: Small Business Participation Plan
*NOTE: Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information. Any specified page limits will be strictly adhered to and enforced. Information submitted that exceeds the specified limit(s) will not be evaluated.
2.5 Volume II shall be submitted electronically in accordance with the Proposal Submission Instructions in
Section 00 22 12 of the solicitation and shall include the following information:
Volume II – Tab A: Standard Form 1442 and Price Breakout Schedule
Volume II – Tab B: Joint Venture Agreement (if any)
Volume II – Tab C: Evidence of Ability to Obtain Bonding and Proof of Financial Ability
Volume II – Tab D: Pre-Award Information
Volume II – Tab E: Subcontracting Plan
NOTE: Failure to place the required submission information under the appropriate tab (factor or sub factor) may result in a lower rating if the evaluators cannot readily find the appropriate information.
3. Proposal Evaluation Process.
3.1. A Source Selection Evaluation Board (SSEB) comprised of representatives of the Corps of Engineers, User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. Technical proposals
(Volume I) will be reviewed and rated without knowledge of the price offered. The number and identities of offerors are not revealed to anyone not involved in the evaluation and award process or to other offerors.
Proposals will be evaluated based on the factors described herein, and the basis of award is a Best Value
Trade-Off, as stated above.
3.2 The evaluation process essentially consists of four parts: proposal compliance review and responsibility review, technical evaluation, price evaluation, and price/technical trade-off analysis.
3.2.1 Proposal Compliance/Responsibility Review: This is an initial review to ensure that all required forms and certifications are complete, that both a technical and price proposal were received, and that the offeror is financially capable of sustaining performance under the contract and is able to obtain the required level of performance and payment bonds from an acceptable surety.
See FAR 2.101 and 3.104 Page 3
3.2.2 Technical Evaluation: The SSEB will evaluate and rate the Volume I proposals against the RFP requirements. Factor I – Past Performance will be rated using Tables 1 and 2, below. The rating will be based on overall confidence in performance, with the final confidence assessment rating based on the extent of recent, relevant past experience and the quality of the offeror’s performance. Factor II – Narrative of Management Plan will be rated using Tables 3 and 4, below. The SSEB will assign an adjectival combined technical/risk rating to the Technical Factors and corresponding Sub-factors (if any). The combined technical/risk rating includes consideration of risk, as defined in Table 4, in conjunction with the strengths, weaknesses, significant weakness, uncertainties, and deficiencies in determining technical ratings. Factor III – Small Business Participation Plan will be rated using Table 5, below, on an acceptable/unacceptable basis.
3.2.3 Price Evaluation: The SSEB and Contracting Officer/SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation.
3.2.4 Price/Technical Trade-off Analysis After all above evaluations are complete, the Contracting Officer/SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The
Source Selection Authority (SSA) will then consider all factors to select the proposal offering the best value to the Government.
4. Proposal Information and Related Evaluation Factors.
4.1 Proposals will be evaluated in accordance with the factors below, listed in relative order of importance. All evaluation factors, other than price, when combined are considered approximately equal to price. The
Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
See FAR 2.101 and 3.104 Page 4
Volume Factor/Tab Description Relative Order of
Importance
Volume I Factor I Past Performance 1st
Factor II Narrative of Management Plan 2nd
Factor III Small Business Participation Plan (ALL OFFERORS
ARE REQUIRED TO SUMBIT)
3rd
Volume II Price and Pro Forma Information (Sealed Envelope) Not Rated
Tab A Standard Form 1442 and Price Breakout Schedule Not Rated
Tab B Joint Venture Agreement (if any) Not Rated
Tab C Evidence of Proof to Obtain Bonding and Proof of
Financial Ability
Not Rated
Tab D Pre-Award Information Not Rated
Tab E Subcontracting Plan (LARGE BUSINESS OFFERORS
ONLY)
Not Rated
4.2 Ratings
Evaluators will apply the rating for the definition that most closely matches the evaluation.
TABLE 1
Past Performance Relevancy Ratings
Rating Description
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
See FAR 2.101 and 3.104 Page 5
TABLE 2
Performance Confidence Assessments
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Neutral Confidence
No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.
TABLE 3
Technical / Risk Assessment Ratings
Adjectival Rating Description
Outstanding
Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.
Good
Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.
Acceptable
Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Unacceptable
Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.
See FAR 2.101 and 3.104 Page 6
TABLE 4
Technical Risk Descriptions
Adjectival Rating Description
Low
Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor efforts and normal Government monitoring will likely be able to overcome any difficulties.
Moderate
Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance. Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.
High
Proposal contains a significant weakness or combination of weaknesses which Is likely to cause significant disruption of schedule, increased cost or degradation of performance. Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.
Unacceptable
Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.
TABLE 5
Small Business Ratings
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the small business objectives.
Unacceptable Proposal does not meet the small business objectives.
4.3 Definitions
1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.
2. Strength. An aspect of an offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.
3. Significant Strength. An aspect of an offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.
4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See
FAR 15.001.
See FAR 2.101 and 3.104 Page 7
5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.
6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear
(e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).
7. Clarification. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated. See FAR 15.306(a)(1).
8. Adverse Past Performance. Past performance information that supports a less than satisfactory rating on any evaluation.
5. Volume I – Factor I: Past Performance
5.1 Submission Requirements:
5.1.1 Provide descriptions of up to three (3) projects substantially complete or completed by the Prime
Contractor within the last seven (7) years (from the solicitation issue date) that are similar to this project in size and scope. Projects completed more than seven (7) years before the solicitation issue date may be considered for evaluation purposes; however, such projects will not be considered recent and therefore will be considered less relevant. Projects are considered substantially complete if enough work has been performed such that it demonstrates the ability to successfully complete all phases of the project. An
Indefinite Delivery Indefinite Quantity (IDIQ) contract may be submitted only if a single task order could be considered similar to this project. Task orders may not be combined in order for the project to be considered similar.
5.1.2 Projects considered similar in size are new construction projects of 50,000 square feet or greater of vertical construction.
5.1.3 Projects considered similar in scope to this project are new construction of military barracks, dormitories, or senior living facilities, which consist of three or more stories.
5.1.4 The prime contractor must have self-performed at least 15% of the cost of the contract, not including the cost of materials, with its own employees to be considered similar.
5.1.5 Additional consideration may be given for projects that contain the following features:
a) New Construction Project for USACE or NAVFAC
5.1.6 The following information shall be provided for each project:
a) Project Title, Location, and Contract Number/Unique Identifier
b) Current percentage of construction complete and the date it was or will be complete
a. For projects that are not yet complete, provide description of work remaining to be completed.
c) Scope of the project, to include purpose/use of facility
See FAR 2.101 and 3.104 Page 8
d) Size of the project in square feet, differentiating the square footage of new construction versus renovation if the project includes both
e) Type and percentage of work that was self-performed
f) Dollar Value of the project
g) Customer Primary Point of Contact and alternate POC (name, relationship to project, agency/firm affiliation, city, state, current and correct phone number, and current and correct email address)
h) Whether the project was for NAVFAC or USACE
i) Whether the project demonstrated progressive collapse safety features
5.1.7 For this factor, also include any ratings, letters, awards, etc. that support past performance on these projects. Any of this information that is submitted shall clearly identify to which of the submitted projects it pertains. A sample Past Performance Questionnaire is attached for your convenience. If used, the Past
Performance Questionnaire must be submitted by the offeror with the proposal submission and not sent directly to the agency from the reference. For each project, the offeror may provide information on problems encountered on the identified contracts and the offeror’s respective corrective action.
NOTE: For purposes of evaluating past performance, the Prime Contractor is defined as the contractor identified in Block 14 of the Standard Form 1442. Projects performed by contractors other than the offeror, including, but not limited to, teaming partners, subcontractors, sister or parent companies, and affiliates will not be evaluated for past performance, unless those other contractors are part of a joint venture offeror as demonstrated by a signed joint venture agreement. If more than one contractor is listed in Block 14, then a signed joint venture must be submitted with the proposal and the joint venture shall be registered as such in the System for Award Management (SAM). However, each party of the Joint Venture (JV) must submit their own Unique Entity Identifier Number (formerly known as DUNS) with the JV proposal. If the offeror represents the combining of two or more companies as a JV for the purpose of this RFP, each company in the JV may submit project examples, but the total submitted by the JV will not exceed three (3).
5.2 Evaluation Criteria:
5.2.1 The SSEB will first evaluate the relevancy of recent past performance identified in the proposal in response to paragraph 5.1 above. By using the criteria identified above, the SSEB will determine how relevant a past project is when compared to the recency, scope, size, and magnitude of effort and complexities of the solicited project. A relevancy rating will be assigned to each submitted project using the Past Performance
Relevancy Ratings table above.
5.2.2 The SSEB will next review how well the offeror performed on those projects. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction.
The Government also reserves the right to not contact the provided references. In addition to the information submitted by the offeror, the Government reserves the right to review any other sources of relevant information for evaluating past performance, including projects other than those submitted by the offeror. The Government will, at a minimum, review past performance information retrieved through the
Past Performance Information Retrieval System (PPIRS). Other sources may include, but are not limited to, past performance information retrieved from inquiries of owner representative(s), Federal Awardee
Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
See FAR 2.101 and 3.104 Page 9
5.2.3 The SSEB will review all past performance information collected and determine the quality of the offeror’s performance, general trends, and usefulness of the information and incorporate this information into the performance confidence assessment. The SSEB will assign a final, overall Performance Confidence rating, using the ratings in the Performance Confidence Assessment table above, based on the SSEB’s assessment of (1) the degree of the offeror’s recent, relevant experience, and (2) how well the offeror performed that experience.
6. Volume I – Factor II: Narrative of Management Plan
6.1 Submission Requirements:
Provide a narrative for the project that describes how your labor, resources, subcontractors, and material suppliers will be managed, supervised, coordinated, and used to ensure successful completion of the project. Additionally, the Management Plan shall include the following information:
- Describe the duties of the key project delivery staff (PM, Superintendent, CQCSM, SSHO) and how this team will work together to deliver the project. Describe how you intend to manage the quality control requirements with personnel that have dual responsibilities.
- Identify the Commissioning Firm and/or Specialist(s) and their qualifications, including at least the following: years of experience in commissioning, types of projects commissioned, and certifications. Offerors are advised that any subcontractor submitted for review shall be utilized on the contract for the work required by the evaluation. Evaluation and acceptance of a subcontractor does not relieve any of the conditions required by the plans and specification. If a subcontractor is unable to perform the work or a replacement is needed it shall be submitted to the Contracting
Officer for their approval prior to any work being completed.
- Describe, in a narrative format, the commissioning process and critical milestones of the commissioning process and how they relate to critical construction milestones. Describe, in narrative format, the key submittals for commissioning process. Describe, by role and qualifications, who will be in lead authority for the contractor (in-house or first tier sub) during the commissioning process. Lay out their roles and authority over all involved subcontractors.
- Describe the anticipated process, commissioning firm/specialist, and sub-contractor roles during the warranty period, particularly for HVAC trend log review, as specified in Spec 01 91 00 15
Total Building Commissioning Spec.
NOTE: There is a page limit of four (4) single sided, 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides, for the narrative portion of this Factor.
6.2 Evaluation Criteria:
Narratives will be evaluated based on the level of understanding of the work and the involvement the contractor will have in the management, oversight, control, and coordination of the work performed during construction of the project. Narratives that demonstrate a clear understanding of the project requirements and provide a thorough approach for successfully managing the solicited project and/or mitigating project specific risk items, may be rated more favorably by the SSEB.
See FAR 2.101 and 3.104 Page 10
7. Volume I – Factor III: Small Business Participation Plan
7.1 Submission Requirements
ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.
The Small Business Participation Plan shall be based on the offeror’s best effort and is required to address each of the following areas individually:
The extent to which the small business programs listed in FAR 19 (small business, small disadvantaged business, woman-owned small business, HubZone, service disabled veteran owned small business, etc.) are specifically identified in the Small Business Participation Plan;
The extent of participation of such firms in terms of the value of the total acquisition in percentages (%) for the base and all optional work under this contract; the extent of commitment to use such firms (for example, enforceable commitments, i.e., teaming agreements signed, are to be considered more heavily than non-enforceable ones);
The complexity and variety of the work small firms are to perform on this acquisition;
The practicality of the Small Business Participation Plan, i.e., whether it contains aggressive goals.
7.2 The Small Business Participation Plan shall be organized as follows:
(1) Prime Contractor type of business (check all that apply):
( ) Large
( ) Small (also check type of small business)
( ) Small Non-Disadvantaged Business
( ) Small Disadvantaged Business
( ) Woman-Owned Small Business
( ) HUBZone Small Business
( ) Veteran Owned Small Business
( ) Service Disabled, Veteran Owned Small Business
(2) Percentage of your participation as a prime contractor: __________________ %
NOTE: Small Business primes’ self-performance counts as Small Business Participation, and small business primes may achieve small business participation goals through their own performance/participation as a prime and/or through subcontracting to other small businesses.
See FAR 2.101 and 3.104 Page 11
(3) Percentage of total contract value of subcontracts planned for:
% of Total
Contract Value
Large %
Total Small %
Small Non-Disadvantaged %
Small Disadvantaged %
Small Woman Owned %
Small HUB Zone %
Small Veteran Owned %
Small Service Disabled Veteran
Owned
Each percentage above shall be accompanied by detailed supporting documentation regarding individual commitments.
NOTE: The sum of the percentages of Small Non-Disadvantaged and Small Disadvantaged should equal the entries for the Total Small; however, the sum of all of the percentages need not equal 100% since the prime is not included and individual subcontractors may be counted towards more than one category.
(4) List principal supplies/services (be specific) to be subcontracted to:
Name of
Company
Type of
Service/Supply
Large
Small Non-Disadvantaged
Small Disadvantaged
Small Woman Owned
Small HUB Zone
Small Veteran Owned
Small Service Disabled Veteran
Owned
NOTE: Add space as necessary in order to fully fill out this table to list all principal supplies/services.
(5) Prior Performance Information: Provide any information substantiating the offeror’s track record of utilizing small business on past contracts.
(6) For Large and Small Businesses provide descriptive information for all small business categories. Any information concerning long-term relationships with Small Business subcontractors, such as mentor-protégé relationships, should be provided.
See FAR 2.101 and 3.104 Page 12
(7) Extent of Commitment: Provide documentation regarding enforceable commitments to utilize any small business category as defined in FAR Part 19 as subcontractors.
(8) Small Business Subcontracting Plan: Each Large Business Offeror shall provide a Small
Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-
9. This Plan shall be submitted separately from the Small Business Participation information required above which applies to both Large and Small Businesses. The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a
Large Business. The approved Small Business Subcontracting Plan will be incorporated into any resultant contract(s). Any subcontractors listed as a part of this Small Business
Participation Plan must also be listed in the Small Business Subcontracting Plan.
7.3 Evaluation Criteria:
ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.
In order to be considered acceptable, the Small Business Participation Plan must be fully filled out in reasonable detail to demonstrate that the proposal meets the minimum total small business participation goal and to indicate an adequate approach and understanding of the small business objectives. The minimum total small business participation goal is at least twenty percent (20%) of the total contract value resulting from this solicitation. This may be demonstrated through collective small business participation for the solicited project from any type of small business or sub-category small business.
8.0 Volume II - Price and Proforma Information
8.1 Tab A - Standard Form 1442 and Proposal Price Breakout Schedule.
8.1.1 Submission Requirements:
The offeror shall complete and submit Standard Form 1442 and Section 00 10 00, Proposal Price Breakout
Schedule. Both of these forms are included in Section 00 10 00 of this solicitation.
8.1.2 Evaluation Criteria:
The price will be evaluated on base proposal plus all options. The price will be evaluated for fairness and reasonableness through the use of a price analysis. Price will also be checked for unbalancing of line items.
Offerors are cautioned to distribute costs appropriately.
8.2 Tab B – Joint Venture Agreements
8.2.1 Submission Requirements:
If more than one contractor is listed in Block 14, or the offeror listed in Block 14 is a joint venture (JV), then a signed JV agreement must be submitted with the proposal and the offeror shall be registered in the
System for Award Management (SAM) as a legal entity separate from the individual joint venture
See FAR 2.101 and 3.104 Page 13 members. However, each member of the JV must submit its own Unique Entity Identifier (formally DUNS number) with the proposal.
Small business offerors (e.g., 8(a), HUBZone, SDVOSB) submitting a proposal as a JV or Mentor-Protégé shall submit evidence from the offeror's SBA Servicing Agency that the offeror has notified and discussed the proposed joint venture for this specific project with the appropriate SBA Representative or Business
Opportunity Specialist. Joint Venture agreements and approved 8(a) Mentor-Protégé agreements must be submitted with the proposal.
8.2.2 Evaluation Criteria:
This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.
Joint Venture Agreements and Mentor-Protégé agreements must comply with the relevant regulations in
Title 13 of the Code of Federal Regulations in order for an offeror to be eligible for any small business-related price preference.
8.3 Tab C – Evidence of Ability to Obtain Bonding and Proof of Financial Ability
8.3.1 Submission Requirements:
A. Financial Capability. Submit Proof of Financial Ability (Most recent financial statement covering assets and liabilities). Include the name, address, and telephone number of offeror's banking institution.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .