Renovation of Caven Point Army Reserve Center Facility
Solicitation number
W912QR20R0018
Issued by

About this file

This solicitation requests proposals for the renovation of the Caven Point Army Reserve Center Facility in Jersey City, New Jersey. The project involves interior and exterior renovation of approximately 63,000 square feet of existing buildings, including HVAC, electrical, and communication systems replacement. Additional work includes site improvements, roof repair, and exterior window replacement. The solicitation allows for optional additions such as a new storage unit and canopy. Proposals are due by 2:00 PM Eastern Time on March 26, 2020. The contract will be awarded on a best value basis considering past performance, management approach, and small business participation. The project has an estimated construction cost between $10-25 million under NAICS code 236220. The solicitation instructs offerors to submit questions via ProjNet and attend an optional site visit.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation For Renovation of Caven Point Army Reserve Center (ARC) Jersey City, NJ

P2: 475970

Design Bid Build

Specifications Certified Final Submittal Vol.1 of 3

ARIMS: 200A

Disposition: Maintain for 15yrs after construction

25 February 2020

W912QR20R0018

W912QR20R0018-0000

Design/Bid/Build for the Renovation of Caven Point Army Reserve Center Facility to be constructed Jersey City, New Jersey.

Estimated Construction Cost is betw een $10,000,000.00 and $25,000,000.00.

NAICS Code is 236220. Size Determination is $39.5M. Please note that business size in SAM is determined by the NAICS code. If the vendor size is not listed correctly for a particular NAICS code in SAM the business w ill be considered other than a small business.

This is a full and open procurement. In accordance w ith Federal Acquisition Regulation 19.1307, this project requires the HUBZone 10% price evaluation.

Funds are not presently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available.

Central Contractor Registration and ORCA are available through the System for Aw ard Management (SAM), available at w w w .beta.sam.gov.

Offerors must comply w ith the requirements of 52.204-7, 52.204-8, 52.232-33, and any other CCR/ORCA requirements in this solicitation through SAM. PLEASE NOTE: SAM is completely free of charge for both registrants and users.

Please see Section 00 10 00, SF1442 BLOCK 10 CONTINUATION for further instructions.

LEVI R SPETH 502.315.6199

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

25-Feb-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________540 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________6 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time __2_6_ _M_a_r _2__020____ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

502.315.6195 OR 6193FAX:TEL: 502.315.6172 TEL: FAX:

W912QR20R0018 105

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

“For Official Use Only” Source Selection Information See FAR 2.101 and 3.104 Page 3

Section 00 10 00 - Solicitation

BLOCK 10 CONTINUATION PAGE

Technical inquiries and questions relating to the proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://projnet.org/projnet. Please see Section 00 21 00, ProjNet Instructions for further guidance.

Please see FAR 52.236-27 ALT 1 for Site Visit information.

The term bid and proposal are used interchangeably in industry and may be used interchangeably throughout this solicitation.

Please note, page numbering in this document may not be accurate.

All days are to be considered calendar days unless otherwise noted.

See FAR 2.101 and 3.104 Page 4

PRICE BREAKOUT SCHEDULE

Price Breakout Schedule

PROJECT: – Army Reserve Training Building LOCATION: Jersey City, New Jersey

PROPOSER’S NAME: _________________________________________________

BASE PROPOSAL

ITEM

NO. DESCRIPTION UNIT AMOUNT

0001 Primary Facility – Renovation of Training Building job $

0002 Primary Facility – Replacement of Windows job $

0003 Site Work job $

0004 Utility Fees job $

TOTAL BASE PROPOSAL $

40,000.00

See FAR 2.101 and 3.104 Page 5

OPTION PRICING

ITEM

NO. DESCRIPTION UNIT AMOUNT

0005 Elevator Addition job $

0006 Addition to Building 204 job $

0007 Front Entry Canopy job $

0008 Contractor Furnished, Contractor Installed job $ Collateral Equipment – Training Building

(CFCICE)

0009 Contractor Furnished, Contractor Installed job $ Collateral Equipment (CFCICE) Bona Fide Need

– Training Building

0010 Contractor Furnished, Contractor Installed job $ Collateral Equipment – Addition to Building 204

(CFCICE)

0011 Contractor Furnished, Contractor Installed job $ Collateral Equipment (CFCICE) Bona Fide Need

– Addition to Building 204

TOTAL ALL OPTIONS PROPOSAL $

TOTAL BASE with all OPTIONS PROPOSAL $

See FAR 2.101 and 3.104 Page 6

NOTES FOR PROPOSAL SCHEDULE

1. The company name should be indicated on the face of the proposal schedule to preclude being misplaced.

2. Proposers must insert a price on all numbered items of the Proposal Schedule. The price may be zero dollars or a deduct amount. Failure to do so will disqualify the proposal.

3. Description of Proposal Items - The general outline of the principal features of each item as listed below does not in any way limit the responsibility of the proposer for making a thorough investigation of the drawings and the specifications to determine the scope of work including each item of the proposal form.

Description of Base Proposal Items

(a) Item No. 0001 “Primary Facility – Training Building Revitalization” includes all construction work, and all applicable regulatory permitting and survey work and fees required within a line five feet outside of this building, except that work covered by Item Nos. 0002 thru 0011.

(b) Item No. 0002 “Primary Facility – Replacement of Windows” includes all construction and demolition work associated with installation of new windows in the revitalized training facility.

(c) Item No. 0003 “Site Work” includes all demolition and construction work required beyond a line five feet outside the Primary Facilities.

(d) Item No. 0004 “Utility Fees” includes all costs associated with tap fees to the local utilities.

See FAR 2.101 and 3.104 Page 7

Description of Option Proposal Items

(e) Item No. 0005 “Elevator Addition” includes all construction work, and all applicable regulatory permitting and survey work and fees required for construction of the Elevator Addition.

The Contracting Officer may exercise the option by written notice to the Contractor within 120 calendar days after Notice to Proceed is issued. The Project duration in FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK shall not be affected by the exercising of the option.

(f) Item No. 0006 “Addition to Building 204” includes all work associated with a building addition to Building 204.

The Contracting Officer may exercise the option by written notice to the Contractor within 120 calendar

(g) Item No. 0007 “Front Entry Canopy” includes all work associated with installation of a new canopy at the front door.

The Contracting Officer may exercise the option by written notice to the Contractor within 120 calendar

(h) Item No. 0008 “Contractor Furnished, Contractor Installed Collateral Equipment (CFCICE)” includes all work required to furnish and install “Collateral Funded Equipment” for the Training Building Renovation. CFCICE Equipment are items which are permanently attached to the construction. CFCICE Equipment is to be contractor provided and installed, unless otherwise noted. CFCICE Equipment for the Army Reserve Center facilities includes but is not limited to the following:

Shower room lockers Caging for unit storage and arms vault.

The Contracting Officer may exercise the option by written notice to the Contractor within 120 calendar

(i) Item No. 0009 “Contractor Furnished, Contractor Installed Collateral Equipment (CFCICE) Bona Fide Need” includes all work required to furnish and install “Collateral Funded Equipment” for the Training Building Renovation. CFCICE – Bona Fide Need equipment are items which are not permanently attached to the construction and is to be awarded before the Building Occupancy Date. CFCICE Bona Fide Need equipment is to be contractor provided and installed, unless otherwise noted. CFCICE Bona Fide Need equipment for the Army Reserve Center facilities includes the following.

Kitchen Equipment Arms Vault Dehumidifier Free standing metal shelving included in caged storage areas Shelving in Facilities Maintenance Rooms Breakroom refrigerator and microwave Fire extinguishers Window blinds

See FAR 2.101 and 3.104 Page 8

The Contracting Officer may exercise the option by written notice to the Contractor within 300 calendar

(j) Item No. 0010 “Contractor Furnished, Contractor Installed Collateral Equipment –Addition to Building 204 (CFCICE)” includes all work required to furnish and install “Collateral Funded Equipment” for the addition to Building 204. CFCICE Equipment are items which are permanently attached to the construction. CFCICE Equipment is to be contractor provided and installed, unless otherwise noted.

CFCICE Equipment for the Army Reserve Center facilities includes but is not limited to the following.

Caging for unit storage and arms vault.

The Contracting Officer may exercise the option by written notice to the Contractor within 120 calendar

(k) Item No. 0011 “Contractor Furnished, Contractor Installed Collateral Equipment (CFCICE) Bona Fide Need – Addition to Building 204” includes all work required to furnish and install “Collateral Funded Equipment” for the addition to Building 204. CFCICE – Bona Fide Need equipment are items which are not permanently attached to the construction and is to be awarded before the Building Occupancy Date.

CFCICE Bona Fide Need equipment is to be contractor provided and installed, unless otherwise noted.

CFCICE Bona Fide Need equipment for the Army Reserve Center facilities includes the following.

Free standing metal shelving included in caged storage areas

The Contracting Officer may exercise the option by written notice to the Contractor within 300 calendar

See FAR 2.101 and 3.104 Page 9

Section 00 21 00 - Instructions

PROJNET INSTRUCTIONS

OFFEROR'S QUESTIONS AND COMMENTS

Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.ProjNet.org/ProjNet. As noted below, offerors shall not submit their proposals via ProjNet. Offerors shall submit their proposals in accordance with the provisions stated in the solicitation.

To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system.

The Solicitation Number is: W912QR20R0018 The Bidder Inquiry Key is: W79Z6Y-HN4PEI Specific Instructions for ProjNet Bid Inquiry Access:

1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

2. Identify the Agency. This should be marked as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. Email. Enter the email address you would like to use for communication.

5. Select Continue. A page will then open stating a user account was not found and will ask you to create one using the provided form.

6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret

Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

7. Select Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

Specific Instructions for Future ProjNet Bid Inquiry Access:

1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

3. Identify the Agency. This should be marked as USACE.

4. Key. Enter the Bidder Inquiry Key listed above.

5. Email. Enter the email address you used to register previously in ProjNet.

6. Select Continue. A page will then open asking you to enter the answer to your

SecretQuestion.

7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

From this page you may view all bidder inquiries or add an inquiry.

Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

Offerors are requested to review the specification in its entirety and to review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

See FAR 2.101 and 3.104 Page 10

NOTES:

1. Offerors shall not submit their proposals via ProjNet, but in accordance with the provisions stated in the solicitation. Any questions regarding acceptable means of submitting offers shall be made directly to the Contract Specialist identified in the solicitation.

2. Government responses to technical inquiries and questions relating to proposal procedures or bonds that are submitted to ProjNet in accordance with the procedures above are not binding on the Government unless an amendment is issued on Standard Form 30. In the case of any conflicts, the solicitation governs. Any changes or revisions to the solicitation will be made by formal amendment. Government responses will be limited to: (a) Notice that an amendment will be issued; (b) Reference to an existing requirement contained in the solicitation; or (c) Notice that a response is not necessary.

3. The ability to enter technical inquiries and questions relating to proposal procedures or bonds will be disabled ten (10) calendar days prior to the closing date stated in the solicitation. No Government responses will be entered into the ProjNet system within five (5) calendar days prior to the closing date stated in the solicitation.

See FAR 2.101 and 3.104 Page 11

SECTION 00 22 12

PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION CRITERIA

1. Overview.

1.1 The intent of this solicitation is to select one contractor for the FFR Caven Point ARC located at Caven

Point NJ. The basis of award is the Best Value Trade-Off process. The Government will evaluate the proposals in accordance with the criteria described herein. The Contracting Officer will award a firm fixed price contract to the responsible offeror whom the Source Selection Authority (SSA) determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. The Government reserves the right to accept other than the lowest priced offer or to reject all offers.

1.2 This project is for the Renovation of Caven Point Army Reserve Center Facility to be constructed Jersey City, New Jersey. The existing Training Center includes three inter-connected buildings: 115, 115A, and

204. This work includes, but is not limited to, complete interior renovation of approximately 63,000 square feet including reconfiguration of existing interior partitions, replacement of all interior finishes including flooring, ceiling and paint, replacement of HVAC system, electrical distribution and lighting, communication infrastructure and fire suppression and alarms. The project involves general site work, roof repair, structure repairs, exterior windows replacement, code compliant stairwells, and door hardware. The project will be constructed to current Department of Army sustainable design standards and ATFP requirements. Current ADA standards will also be followed. Supporting facilities include minor clearing/grubbing, grading, paving, fencing and utility connections.

1.3 The project contains bid options such as: new construction of a 5000 sf storage unit attached to

Building 204, a new front entry canopy, and equipment options.

1.4 The target ceiling for contract award is $23,000,000.00 based on the funds made available for this project.

The Government cannot guarantee that additional funds will be available for award. Offerors are under no obligation to approach this ceiling.

2. Submittal of offers.

2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals so that a minimum of time and monies will have been expended in preparing information required herein. However, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed to clearly describe the offeror's capability for successfully completing the solicited project. Requirements stated in this Request for Proposal (RFP) are minimums. Proposals should follow in the order of sequence set forth in the RFP. Information provided out of sequence may not be evaluated and may result in the offeror’s disqualification from award.

2.2 Offerors shall submit their proposals to the US Army Corps of Engineers, 600 Dr. Martin Luther King, Jr.

Place, Room 821, Louisville, KY 40202-2267 no later than the time and date specified in Block 13 of Standard Form 1442. Mark your proposal submission to the attention of Levi Speth. NOTE: The Louisville District is in the Eastern Time Zone.

2.3 Offerors are required to submit a proposal consisting of the information identified in paragraphs 2.4 and 2.5 below. All proposal materials shall be submitted in binders with a table of contents and tabbed section dividers. The sections should parallel the submission requirements identified herein.

2.4 Volume I shall be submitted in a three-ring binder and include the following information:

Volume I – Factor I: Past Performance

See FAR 2.101 and 3.104 Page 12

Volume I – Factor II: Narrative of Management Plan Volume I – Factor III: Small Business Participation Plan

*NOTE: The complete Volume I shall be submitted in original and six (6) paper copies and one (1) electronic copy on CD/DVD. The paper version of the proposal shall be used for evaluation and will control any conflicts or discrepancies between the two media. Offeror is responsible for ensuring the paper copy is consistent with the electronic copy of the proposal. Failure to place the required submission information under the appropriate tab may result in a lower rating if the evaluators cannot readily find the appropriate information. Any specified page limits will be strictly adhered to and enforced. Information submitted that exceeds the specified limit(s) will not be evaluated.

2.5 Volume II shall be submitted in a three-ring binder (placed in a separate envelope) and shall include the following information:

Volume II – Tab A: Standard Form 1442 and Price Breakout Schedule Volume II – Tab B: Joint Venture Agreement (if any) Volume II – Tab C: Evidence of Ability to Obtain Bonding and Proof of Financial Ability Volume II – Tab D: Pre-Award Information Volume II – Tab E: Subcontracting Plan

NOTE: Volume II shall be submitted in original and one (1) electronic copy on CD/DVD. The paper version of the proposal shall be used for evaluation and will control any conflicts or discrepancies between the two media. Offeror is responsible for ensuring the paper copy is consistent with the electronic copy of the proposal. Failure to place the required submission information under the appropriate tab (factor or sub factor) may result in a lower rating if the evaluators cannot readily find the appropriate information.

3. Proposal Evaluation Process.

3.1. A Source Selection Evaluation Board (SSEB) comprised of representatives of the Corps of Engineers, User/Customer, and other required personnel will evaluate the proposals. Offerors are advised that the technical evaluation and rating of proposals will be conducted in strict confidence. Technical proposals (Volume I) will be reviewed and rated without knowledge of the price offered. The number and identities of offerors are not revealed to anyone not involved in the evaluation and award process or to other offerors.

Proposals will be evaluated based on the factors described herein, and the basis of award is a Best Value Trade-Off, as stated above.

3.2 The evaluation process essentially consists of four parts: proposal compliance review and responsibility review, technical evaluation, price evaluation, and price/technical trade-off analysis.

3.2.1 Proposal Compliance/Responsibility Review: This is an initial review to ensure that all required forms and certifications are complete, that both a technical and price proposal were received, and that the offeror is financially capable of sustaining performance under the contract and is able to obtain the required level of performance and payment bonds from an acceptable surety.

3.2.2 Technical Evaluation: The SSEB will evaluate and rate the Volume I proposals against the RFP requirements. Factor I – Past Performance will be rated using Tables 1 and 2, below. The rating will be based on overall confidence in performance, with the final confidence assessment rating based on the extent of recent, relevant past experience and the quality of the offeror’s performance. Factor II – Narrative of Management Plan will be rated using Tables 3 and 4, below. The SSEB will assign an adjectival combined technical/risk rating to the Technical Factors and corresponding Sub-factors (if any). The combined technical/risk rating includes consideration of risk, as defined in Table 4, in conjunction with the strengths, weaknesses, significant weakness, uncertainties, and deficiencies in determining technical ratings. Factor III – Small Business Participation Plan will be rated using Table 5, below, on an acceptable/unacceptable basis.

See FAR 2.101 and 3.104 Page 13

3.2.3 Price Evaluation: The SSEB and Contracting Officer/SSA will evaluate price proposals independent of the technical evaluation. The SSEB will not have access to price information until completion of the technical evaluation.

3.2.4 Price/Technical Trade-off Analysis After all above evaluations are complete, the Contracting Officer/SSA will compare the relative advantages and disadvantages of technical proposals and compare prices. The Source Selection Authority (SSA) will then consider all factors to select the proposal offering the best value to the Government.

4. Proposal Information and Related Evaluation Factors.

4.1 Proposals will be evaluated in accordance with the factors below, listed in relative order of importance. All evaluation factors, other than price, when combined are considered approximately equal to price. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

See FAR 2.101 and 3.104 Page 14

Volume Factor/Tab Description Relative Order of Importance

Volume I Factor I Past Performance 1st Factor II Narrative of Management Plan 2nd Factor III Small Business Participation Plan (ALL OFFERORS ARE

REQUIRED TO SUMBIT)

3rd

Volume II Price and Pro Forma Information (Sealed Envelope) Not Rated

Tab A Standard Form 1442 and Price Breakout Schedule Not Rated Tab B Joint Venture Agreement (if any) Not Rated Tab C Evidence of Proof to Obtain Bonding and Proof of Financial

Ability Not Rated

Tab D Pre-Award Information Not Rated Tab E Subcontracting Plan (LARGE BUSINESS OFFERORS

ONLY)

Not Rated

4.2 Ratings

Evaluators will apply the rating for the definition that most closely matches the evaluation.

TABLE 1

Past Performance Relevancy Ratings Rating Description Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

See FAR 2.101 and 3.104 Page 15

TABLE 2

Performance Confidence Assessments

Substantial Confidence Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence

Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.

Neutral Confidence

No recent/relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned. The offeror may not be evaluated favorably or unfavorably on the factor of past performance.

Limited Confidence Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will successfully perform the required effort.

TABLE 3

Technical / Risk Assessment Ratings

Adjectival Rating Description

Outstanding Proposal indicates an exceptional approach and understanding of the requirements and contains multiple strengths, and risk of unsuccessful performance is low.

Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength, and risk of unsuccessful performance is low to moderate.

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.

Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.

Unacceptable Proposal does not meet the requirements of the solicitation, and thus, contains one or more deficiencies, and/or risk of unsuccessful performance is unacceptable. Proposal is unawardable.

See FAR 2.101 and 3.104 Page 16

TABLE 4

Technical Risk Descriptions

Adjectival Rating Description

Low

Proposal may contain weakness(es) which have little potential to cause disruption of schedule, increased cost or degradation of performance.

Normal contractor efforts and normal Government monitoring will likely be able to overcome any difficulties.

Moderate

Proposal contains a significant weakness or combination of weaknesses which may potentially cause disruption of schedule, increased cost or degradation of performance. Special contractor emphasis and close Government monitoring will likely be able to overcome difficulties.

High

Proposal contains a significant weakness or combination of weaknesses which Is likely to cause significant disruption of schedule, increased cost or degradation of performance. Is unlikely to overcome any difficulties, even with special contractor emphasis and close Government monitoring.

Unacceptable Proposal contains a material failure or a combination of significant weaknesses that increases the risk of unsuccessful performance to an unacceptable level.

TABLE 5

Small Business Ratings

Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the small business objectives.

Unacceptable Proposal does not meet the small business objectives.

4.3 Definitions

1. Deficiency. A material failure of a proposal to meet a Government requirement or a combination of significant weaknesses in a proposal that increases the risk of unsuccessful contract performance to an unacceptable level. See FAR 15.001.

2. Strength. An aspect of an offeror’s proposal that has merit or exceeds specified performance or capability requirements in a way that will be advantageous to the Government during contract performance.

3. Significant Strength. An aspect of an offeror’s proposal that has appreciable merit or appreciably exceeds specified performance or capability requirements in a way that will be appreciably advantageous to the Government during contract performance.

4. Weakness. A flaw in the proposal that increases the risk of unsuccessful contract performance. See

FAR 15.001.

5. Significant Weakness. A flaw in the proposal that appreciably increases the risk of unsuccessful contract performance. See FAR 15.001.

6. Uncertainty. Any aspect of a non-cost/price factor proposal for which the intent of the offeror is unclear (e.g., more than one way to interpret the offer or inconsistencies in the proposal indicating that there may have been an error, omission, or mistake).

See FAR 2.101 and 3.104 Page 17

7. Clarification. Limited exchanges between the Government and offerors that may occur when award without discussions is contemplated. See FAR 15.306(a)(1).

8. Adverse Past Performance. Past performance information that supports a less than satisfactory rating on any evaluation.

5. Volume I – Factor I: Past Performance

5.1 Submission Requirements:

5.1.1 Provide descriptions of up to three (3) projects substantially complete or completed by the Prime

Contractor within the last five (5) years (from the solicitation issue date) that are similar to this project in size and scope. Projects completed more than five (5) years before the solicitation issue date may be considered for evaluation purposes; however, such projects will not be considered recent and therefore will be considered less relevant. Projects are considered substantially complete if enough work has been performed such that it demonstrates the ability to successfully complete all phases of the project. Projects that are not substantially complete will not be considered. An Indefinite Delivery Indefinite Quantity (IDIQ) contract may be submitted only if a single task order could be considered similar to this project.

Task orders may not be combined in order for the project to be considered similar.

5.1.2 Projects considered similar in size are renovation projects of 40,000 square feet or greater. The total square footage can be a single building, or the sum of multiple buildings as long as they were completed under one contract or one task order.

5.1.3 Projects considered similar in scope to this project are renovations of National Guard Armories, Army

Reserve Centers, Armed Forces Training Centers, office complexes, educational facilities, and vehicle maintenance shops, or multi-story facilities. Projects can also include experience in new construction;

however, projects considered similar in scope are at least 75% renovation based on the total square footage of the project.

5.1.4 The prime contractor must have self-performed at least 15% of the cost of the contract, not including the cost of materials, with its own employees to be considered similar.

5.1.5 Additional consideration may be given for projects that contain the following features:

a) Renovation Project for USACE or NAVFAC

b) LEED Silver, Gold, or Platinum certified projects

5.1.6 The following information shall be provided for each project:

a) Project Title, Location, and Contract Number/Unique Identifier

b) Current percentage of construction complete and the date it was or will be complete

a. For projects that are not yet complete, provide description of work remaining to be completed.

c) Scope of the project, to include purpose/use of facility

d) Size of the project in square feet, differentiating the square footage of new construction versus renovation if the project includes both

e) Type and percentage of work that was self-performed

f) Dollar Value of the project

g) Customer Primary Point of Contact and alternate POC (name, relationship to project, agency/firm affiliation, city, state, current and correct phone number, and current and correct email address)

h) Whether the project was for NAVFAC or USACE

See FAR 2.101 and 3.104 Page 18

i) Whether the project was LEED Silver, Gold, or Platinum certified

5.1.7 For this factor, also include any ratings, letters, awards, etc. that support past performance on these projects. Any of this information that is submitted shall clearly identify to which of the submitted projects it pertains. A sample Past Performance Questionnaire is attached for your convenience. If used, the Past Performance Questionnaire must be submitted by the offeror with the proposal submission and not sent directly to the agency from the reference. For each project, the offeror may provide information on problems encountered on the identified contracts and the offeror’s respective corrective action.

NOTE: For purposes of evaluating past performance, the Prime Contractor is defined as the contractor identified in Block 14 of the Standard Form 1442. Projects performed by contractors other than the offeror, including, but not limited to, teaming partners, subcontractors, sister or parent companies, and affiliates will not be evaluated for past performance, unless those other contractors are part of a joint venture offeror as demonstrated by a signed joint venture agreement. If more than one contractor is listed in Block 14, then a signed joint venture must be submitted with the proposal and the joint venture shall be registered as such in the System for Award Management (SAM). However, each party of the Joint Venture (JV) must submit their own Unique Entity Identifier Number (formerly known as DUNS) with the JV proposal. Projects performed by other contractors than the offeror, such as teaming partners or subcontractors, will not be evaluated for past performance, unless those other contractors are part of a JV offeror as demonstrated by a signed JV agreement. If the offeror represents the combining of two or more companies as a JV for the purpose of this RFP, each company in the JV may submit project examples, but the total submitted by the JV will not exceed three (3).

5.2 Evaluation Criteria:

5.2.1 The SSEB will first evaluate the relevancy of recent past performance identified in the proposal in response to paragraph 5.1 above. By using the criteria identified above, the SSEB will determine how relevant a past project is when compared to the recency, scope, size, and magnitude of effort and complexities of the solicited project. A relevancy rating will be assigned to each submitted project using the Past Performance Relevancy Ratings table above.

5.2.2 The SSEB will next review how well the offeror performed on those projects. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction.

The Government also reserves the right to not contact the provided references. In addition to the information submitted by the offeror, the Government reserves the right to review any other sources of relevant information for evaluating past performance, including projects other than those submitted by the offeror. The Government will, at a minimum, review past performance information retrieved through the Past Performance Information Retrieval System (PPIRS). Other sources may include, but are not limited to, past performance information retrieved from inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.

5.2.3 The SSEB will review all past performance information collected and determine the quality of the offeror’s performance, general trends, and usefulness of the information and incorporate this information into the performance confidence assessment. The SSEB will assign a final, overall Performance Confidence rating, using the ratings in the Performance Confidence Assessment table above, based on the SSEB’s assessment of (1) the degree of the offeror’s recent, relevant experience, and (2) how well the offeror performed that experience.

See FAR 2.101 and 3.104 Page 19

6. Volume I – Factor II: Narrative of Management Plan

6.1 Submission Requirements:

Provide a narrative for the project that describes how your labor, resources, subcontractors, and material suppliers will be managed, supervised, coordinated, and used to ensure successful completion of the project. Additionally, the Management Plan shall include the following information:

- Describe the duties of the key project delivery staff (e.g. PM, Superintendent, CQCSM, SSHO) and how this team will work together to deliver the project. Describe how you intend to manage the quality control requirements with personnel that have dual responsibilities.

- Describe the process for removal of asbestos and lead based paint.

- Identify the Commissioning Firm and/or Specialist(s) and their qualifications, including at least the following: years of experience in commissioning, types of projects commissioned, and certifications.

- Confirm that the commissioning firm does not have a contractual relationship with any of the other sub-contractors.

- Demonstrate understanding of the commissioning process and this solicitation/contract by providing a listing of critical milestones of the commissioning process and related construction milestones and identifying key submittals that will be provided.

- Describe the anticipated process, commissioning firm/specialist, and sub-contractor roles during the warranty period, particularly for HVAC trend log review, as specified in this solicitation/contract.

NOTE: There is a page limit of four (4) single sided, 8.5” x 11” pages, using a minimum font size of 11 and a minimum margin of one-half inch on all sides, for the narrative portion of this Factor.

6.2 Evaluation Criteria:

Narratives will be evaluated based on the level of understanding of the work and the involvement the contractor will have in the management, oversight, control, and coordination of the work performed during construction of the project. Narratives that demonstrate a clear understanding of the project requirements and provide a thorough approach for successfully managing the solicited project and/or mitigating project specific risk items, may be rated more favorably by the SSEB.

See FAR 2.101 and 3.104 Page 20

7. Volume I – Factor III: Small Business Participation Plan

7.1 Submission Requirements

ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.

The Small Business Participation Plan shall be based on the offeror’s best effort and is required to address each of the following areas individually:

The extent to which the small business programs listed in FAR 19 (small business, small disadvantaged business, woman-owned small business, HubZone, service disabled veteran owned small business, etc.) are specifically identified in the Small Business Participation Plan;

The extent of participation of such firms in terms of the value of the total acquisition in percentages (%) for the base and all optional work under this contract; the extent of commitment to use such firms (for example, enforceable commitments, i.e., teaming agreements signed, are to be considered more heavily than non-enforceable ones);

The complexity and variety of the work small firms are to perform on this acquisition;

The practicality of the Small Business Participation Plan, i.e., whether it contains aggressive goals.

7.2 The Small Business Participation Plan shall be organized as follows:

(1) Prime Contractor type of business (check all that apply):

( ) Large ( ) Small (also check type of small business) ( ) Small Non-Disadvantaged Business ( ) Small Disadvantaged Business ( ) Woman-Owned Small Business ( ) HUBZone Small Business ( ) Veteran Owned Small Business ( ) Service Disabled, Veteran Owned Small Business

(2) Percentage of your participation as a prime contractor: __________________ %

NOTE: Small Business primes’ self-performance counts as Small Business Participation, and small business primes may achieve small business participation goals through their own performance/participation as a prime and/or through subcontracting to other small businesses.

See FAR 2.101 and 3.104 Page 21

(3) Percentage of total contract value of subcontracts planned for:

% of Total Contract Value

Large % Total Small % Small Non-Disadvantaged % Small Disadvantaged % Small Woman Owned % Small HUB Zone % Small Veteran Owned % Small Service Disabled Veteran Owned %

Each percentage above shall be accompanied by detailed supporting documentation regarding individual commitments.

NOTE: The sum of the percentages of Small Non-Disadvantaged and Small Disadvantaged should equal the entries for the Total Small; however, the sum of all of the percentages need not equal 100% since the prime is not included and individual subcontractors may be counted towards more than one category.

(4) List principal supplies/services (be specific) to be subcontracted to:

Name of

Company Type of

Service/Supply Large Small Non-Disadvantaged Small Disadvantaged Small Woman Owned Small HUB Zone Small Veteran Owned Small Service Disabled Veteran Owned

NOTE: Add space as necessary in order to fully fill out this table to list all principal supplies/services.

(5) Prior Performance Information: Provide any information substantiating the offeror’s track record of utilizing small business on past contracts.

(6) For Large and Small Businesses provide descriptive information for all small business categories. Any information concerning long-term relationships with Small Business subcontractors, such as mentor-protégé relationships, should be provided.

(7) Extent of Commitment: Provide documentation regarding enforceable commitments to utilize any small business category as defined in FAR Part 19 as subcontractors.

(8) Small Business Subcontracting Plan: Each Large Business Offeror shall provide a Small Business Subcontracting Plan that contains all of the elements required by FAR Clause 52.219-9. This Plan shall be submitted separately from the Small Business Participation information required above which applies to both Large and Small Businesses. The Subcontracting Plan is not a requirement for evaluation in source selection but rather a requirement for award to a Large Business. The approved Small Business Subcontracting Plan will be incorporated into any resultant contract(s). Any subcontractors listed as a part of

See FAR 2.101 and 3.104 Page 22 this Small Business Participation Plan must also be listed in the Small Business Subcontracting Plan.

7.3 Evaluation Criteria:

ALL OFFERORS ARE REQUIRED TO SUBMIT A SMALL BUSINESS PARTICIPATION PLAN.

In order to be considered acceptable, the Small Business Participation Plan must be fully filled out in reasonable detail to demonstrate that the proposal meets the minimum total small business participation goal and to indicate an adequate approach and understanding of the small business objectives. The minimum total small business participation goal is at least twenty percent (20%) of the total contract value resulting from this solicitation. This may be demonstrated through collective small business participation for the solicited project from any type of small business or sub-category small business.

8.0 Volume II - Price and Proforma Information

8.1 Tab A - Standard Form 1442 and Proposal Price Breakout Schedule.

8.1.1 Submission Requirements:

The offeror shall complete and submit Standard Form 1442 and Section 00 10 00, Proposal Price Breakout Schedule. Both of these forms are included in Section 00 10 00 of this solicitation.

8.1.2 Evaluation Criteria:

The price will be evaluated on base proposal plus all options. The price will be evaluated for fairness and reasonableness through the use of a price analysis. Price will also be checked for unbalancing of line items.

Offerors are cautioned to distribute costs appropriately.

8.2 Tab B – Joint Venture Agreements

8.2.1 Submission Requirements:

If more than one contractor is listed in Block 14, or the offeror listed in Block 14 is a joint venture (JV), then a signed JV agreement must be submitted with the proposal and the offeror shall be registered in the System for Award Management (SAM) as a legal entity separate from the individual joint venture members. However, each member of the JV must submit its own Unique Entity Identifier (formally DUNS number) with the proposal.

Small business offerors (e.g., 8(a), HUBZone, SDVOSB) submitting a proposal as a JV or Mentor-Protégé shall submit evidence from the offeror's SBA Servicing Agency that the offeror has notified and discussed the proposed joint venture for this specific project with the appropriate SBA Representative or Business Opportunity Specialist. Joint Venture agreements and approved 8(a) Mentor-Protégé agreements must be submitted with the proposal.

8.2.2 Evaluation Criteria:

This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.

Joint Venture Agreements and Mentor-Protégé agreements must comply with the relevant regulations in Title 13 of the Code of Federal Regulations in order for an offeror to be eligible for any small business-related price preference.

See FAR 2.101 and 3.104 Page 23

8.3 Tab C – Evidence of Ability to Obtain Bonding and Proof of Financial Ability

8.3.1 Submission Requirements:

A. Financial Capability. Submit Proof of Financial Ability (Most recent financial statement covering assets and liabilities). Include the name, address, and telephone number of offeror's banking institution. If the offeror is a joint venture, submit this information for all joint venture members.

B. Bonding Capability. Submit information showing offeror's ability to be bonded for this project. Include the name, address, and telephone number of the offeror's bonding company.

8.3.2 Evaluation Criteria:

This information will be used for the purpose of completing the Pre-Award Survey and will not be rated.

See FAR Part 28 for information related to bonds.

8.4 Tab D – Pre-Award Information

8.4…