W912QR20B0021Plans-0000.pdf
PDF 41 MB Posted
- Attached to
- HPW Bldg. 441 at WPAFB, OH
- Solicitation number
- W912QR20B0021
About this file
This federal contract opportunity solicitation is for the design/build renovation of HPW Building 441 at Wright-Patterson Air Force Base in Ohio. The estimated construction cost is between $10-25 million, with a NAICS code of 236220 and size standard of $39.5 million. This is a 100% total small business set-aside solicitation issued by the Department of the Army Corps of Engineers Louisville District. Interested vendors must register at beta.SAM.gov to download the solicitation, as faxed, telephoned or mailed requests will not be accepted. The solicitation details the required design/build renovation services and provides response and award date information.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LOUISVILLE DISTRICT
US Army Corps of Engineers ®
WRIGHT PATTERSON AIR FORCE BASE
REPAIR FSD-1 INTERIOR, EXTERIOR, AND HVAC
FACILITY 20441
CONTRACT NO.:
ISSUE DATE.:
FA8601-13-D0003
JULY 2020
PROJECT #ZHTV 160073
A DVANCED
E NGINEERING
C ONSULTANTS
Mechanical | Electrical | Plumbing | Fire Protection 1405 Dublin Road Tel: (614) 486-4778 Columbus, Ohio 43215 Fax: (614) 486-4082
P2 #476238
W912QR20B0021SOLICITATION NO.:
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D
V A
N C
E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CERTIFIED FINAL
07/17/2020
G E
N E
R A
L C
O V
E R
P A
G E
G-001
G .L
E
IT
C H
K .F
IE
LD
S
K .F
IE
LD
S
CERTIFIED FINAL
ARIMS: 200A Disposition: Maintain for 15yrs after construction
31 July 2020
W912QR20B0021
W
2Q R
B0
1-
1. COORDINATE ALL WORK THROUGH THE GOVERNMENT CONTRACTING
OFFICER.
2. ANY NEW TYPES OF HAZARDOUS MATERIALS TO BE USED, AND THE
WASTES THAT MAY BE GENERATED AS A RESULT OF THAT USE NEED
TO BE CONSIDERED IN CONSTRUCTION. IF APPROPRIATE, DEDICATED
SPACE FOR STORAGE OF HAZARDOUS MATERIALS AND WASTE NEED
TO BE PROVIDED. IN ADDITION PROPER COORDINATION IS NEEDED
WITH 88 CEG/CEIEC. QUESTIONS CONCERNING THE REQUIREMENTS
FOR STORAGE AND DISPOSAL OF ANY HAZARDOUS MATERIALS CAN
BE ADDRESSED BY THE 88 CEG/CEIEC HAZARDOUS MATERIALS PM,
MIKE VAUGHN, (937-257-8028 OR MICHAEL.VAUGHN.3@US.AF.MIL) OR
88 CEG/CEIEC HAZARDOUS WASTE PM, GARY SELBY (937-257-3349 OR
GARY.SELBY@US.AF.MIL).
3. BECAUSE IT IS NOT POSSIBLE TO DEFINITELY KNOW THE LOCATION OF
ALL POTENTIAL ASBESTOS CONTAINING MATERIALS (ACM) WITHIN A
FACILITY, FOR INSTANCE ACM FIRE WALLS OR ACM FLOOR TILE, THE
CONTRACTOR PERFORMING THIS WORK SHALL COMPLY WITH ALL
RELEVANT PARTS OF 29 CFR 1910.1001 AND/OR 29 CFR 1926.1101 AS
MAY BE APPLICABLE. A LIMITED ASBESTOS AND LEAD-BASED PAINT
SURVEY WAS PERFORMED ON 12 JUN 2017. THIS REPORT CAN BE
FOUND IN THE PROJECT SPECIFICATIONS. IDENTIFIED AREAS ARE
NOTED ON THE DRAWINGS. IF ADDITIONAL SUSPECT
ASBESTOS-CONTAINING MATERIAL IS FOUND THE CONTRACTOR SHALL
STOP WORK IMMEDIATELY AND NOTIFY THE CONTRACTING OFFICER.
4. CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE HIS OWN
TELEPHONE AND COMPUTER CONNECTIONS FOR HIS CONSTRUCTION
TRAILER ON SITE.
5. THE MAJORITY OF THE BUILDING WILL BE VACANT BUT SMALL
PORTIONS WILL REMAIN PARTIALLY OCCUPIED. CONTRACTOR SHALL
COORDINATE ALL ACTIVITIES REQUIRED IN BASE OCCUPIED AREAS
WITH THE GOVERNMENT PROJECT MANAGER, CONTRACTING OFFICER,
AND BUILDING SECURITY OPERATIONS OFFICER.
6. CONTRACTOR SHALL REQUEST AND RECEIVE PERMISSION PRIOR TO
ANY UTILITY OUTAGE A MINIMUM OF 2 WEEKS PRIOR TO OUTAGE.
7. CONTRACTOR SHALL KEEP CONSTRUCTION SITE CLEAN AT ALL TIMES.
8. SOIL DISTURBANCE DURING THIS PROJECT, INCLUDING EQUIPMENT
STAGING AREAS, WILL REQUIRE EROSION CONTROL MEASURES. FOR
PROJECTS THAT DISTURB LESS THAN AN ACRE OF SOIL, AN EROSION
CONTROL PLAN IS REQUIRED PRIOR TO DISTURBANCE. FOR
PROJECTS THAT DISTURB MORE THAN AN ACRE, A NOTICE OF INTENT
(NOI) MUST BE APPROVED BY THE OHIO EPA PRIOR TO ANY SOIL BEING
DISTURBED AS WELL AS A STORM WATER POLLUTION PREVENTION
PLAN (SWPPP) APPROVED BY 88 CEG/CEIEA. THE CONSTRUCTION
CONTRACTOR SHALL PREPARE AND SUBMIT THE SWPPP AND DRAFT
NOI TO THE CONTRACTING OFFICER'S REPRESENTATIVE TO BE
FORWARDED TO ENVIRONMENTAL MANAGEMENT, 88 CEG/CEIEA, FOR
REVIEW. ONCE THE SWPPP AND DRAFT NOI HAVE BEEN APPROVED BY
THE COR AND ENVIRONMENTAL MANAGEMENT, THE CONTRACTOR
SHALL PREPARE AND FORWARD THE FINAL NOI TO THE OHIO EPA.
PLEASE CONTACT AND 88 CEG/CEIEA WATER PM, KAREN BEASON, BY
EMAIL AT KAREN.BEASON@US.AF.MIL OR BY PHONE AT (937) 257-5899
FOR ADDITIONAL INFORMATION.
9. ANY FIRE SUPPRESSION EQUIPMENT CONTAINING IONIZING
RADIOACTIVE MATERIAL (SMOKE DETECTORS) AND ANY EMERGENCY
EXIT SIGNS CONTAINING IONIZING RADIOACTIVE MATERIAL SHALL BE
TURNED INTO 88 AMDS/SGPB. COORDINATE THIS TURN-IN WITH
WPAFB 88 AMDS/SGPB RADIATION SAFETY OFFICER AT 937-255-6815.
10. ALL METAL AND WIRING SHALL BE RECYCLED AT THE WPAFB BASE
RECYCLING CENTER. THE WPAFB RECYCLING CENTER IS AVAILABLE
FOR CONTRACTOR USE TO REDUCE WASTE DISPOSAL. ALL
RECYCLABLE METAL IS TO BE RECYCLED THROUGH THE BASE
RECYCLING CENTER. ALL RECYCLING MUST BE ACCOMPLISHED IN
ACCORDANCE WITH WPAFB SPECIFICATION SECTION 01 02 20.
CONTACT WPAFB RECYCLING PROGRAM MANAGER AT 937-257-5060 TO
CONFIRM WHAT MATERIALS ARE RECYCLABLE AND TO COORDINATE
TURN-IN. THE CONTRACTOR SHALL SUBMIT A QUARTERLY SUMMARY
REPORT TO THE GOVERNMENT CONTRACT REPRESENTATIVE IAW
WPAFB SPECIFICATION SECTION 01 02 20 STATING (1) THE COST TO
RECYCLE AND THE TONNAGE OF CONSTRUCTION AND DEMOLITION
MATERIALS RECYCLED, (2) THE COST TO DIVERT/REUSE THE TONNAGE
OF CONSTRUCTION AND DEMOLITION MATERIALS DIVERTED/REUSE, (3)
THE COST TO MULCH AND THE TONNAGE AND COST OF
CONSTRUCTION AND DEMOLITION MATERIALS MULCHED, (4) THE COST
FOR WASTE-TO-ENERGY AND THE TONNAGE OF CONSTRUCTION AND
DEMOLITION MATERIALS CONVERTED FROM WASTE-TO-ENERGY, (5)
THE COST TO LANDFILL AND THE TONNAGE OF CONSTRUCTION AND
DEMOLITION MATERIALS LAND-FILLED, (6) THE COST TO INCINERATE
AND THE TONNAGE OF CONSTRUCTION AND DEMOLITION MATERIALS
INCINERATED, AND (7) EXPLANATION OF THE DIVERSION RATE IF LESS
THAN 60%. THE QUARTERLY SUMMARY REPORTS SHALL BE RECEIVED
ON APRIL 7, JULY 7, OCTOBER 7, AND JANUARY 7 COVERING THE
THREE MONTHS PRIOR. THE QUARTERLY SUMMARY REPORTS SHALL
BE ON THE WPAFB DIVERSION FORM. FOR ADDITIONAL INFORMATION
CONTACT THE RECYCLING PM, DAVE DALTON, AT 937-257-5060 OR
DAVID.DALTON.2@US.AF.MIL.
11. TURN-IN ALL MERCURY CONTAINING DEVICES, SWITCHES AND
THERMOSTATS TO 88 CEG/CEIE IN ACCORDANCE WITH WPAFB
SPECIFICATION SECTION 01 02 20 FOR RECYCLING.
12. TURN-IN ALL MERCURY CONTAINING LAMPS TO 88 CEG/CEIE IN
ACCORDANCE WITH WPAFB SPECIFICATION SECTION 01 02 20.
13. TURN-IN ALL PCB CONTAINING LIGHT BALLAST TO 88 CEG/CEIE IN
ACCORDANCE WITH WPAFB SPECIFICATION SECTION 01 02 20.
14. REMOVE AND DISPOSE OF ANY ASBESTOS CONTAINING MATERIAL IN
ACCORDANCE WITH WPAFB SPECIFICATION SECTION 01 02 20.
15. ANY LEAD CONTAINING PAINT CONTROL MEASURES SHALL BE
PERFORMED IN ACCORDANCE WITH WPAFB SPECIFICATION 01 02 20.
16. RECOVER AND RECLAIM ANY REFRIGERANT IN ACCORDANCE WITH
WPAFB SPECIFICATION SECTION 02 09 10.
17. NO ASBESTOS-CONTAINING MATERIAL SHALL BE INSTALLED DURING
THIS PROJECT.
18. ALL WINDOW AND DOOR FRAME CAULKING AND GLAZING WILL BE
TREATED AS CONTAINING ASBESTOS UNLESS TESTING PROVES IT TO
BE ASBESTOS FREE.
19. THE GENERATION OF FUGITIVE EMISSIONS MUST BE KEPT TO A
MINIMUM USING APPROVED DUST SUPPRESSION METHODS SUCH AS
WATER SPRAYS ON AREAS OF HIGH DUST GENERATION. FOR
ADDITIONAL INFORMATION PLEASE CONTACT 88 CEG/CEIE AIR PM
CHRIS TUMBUSCH (937-257-2455 OR
CHRISTOPHER.TUMBUSCH@US.AF.MIL).
20. 30 DAYS PRIOR TO THE START OF WORK, THE CONTRACTOR SHALL
TAKE A REPRESENTATIVE SAMPLE OF THE HVAC SYSTEM WATER TO
DETERMINE WHETHER IT CAN BE DRAINED DIRECTLY INTO THE
SANITARY SEWER. ANALYZE THE WATER TO DETERMINE THE TOTAL
LEVEL OF EACH OF THE FOLLOWING: CADMIUM, CHROMIUM, COPPER,
CYANIDE, LEAD, MERCURY, MOLYBDENUM, NICKEL, SILVER, ZINC AND
SULFIDE. THE LAB PERFORMING THE ANALYSIS MUST BE CERTIFIED
BY OHIO EPA TO ANALYZE FOR THESE PARAMETERS. PROVIDE A
COPY OF THE LAB'S REPORT TO THE CONTRACTING OFFICER, WHO
WILL IN TURN FORWARD IT TO 88 CEG/CEIEA FOR A DETERMINATION
ON THE WASTEWATER DISPOSAL METHOD.
21. UTILITIES HAVE BEEN PRIVATIZED AT WRIGHT PATTERSON AIR FORCE
BASE. CONNECTION TO WATER, SANITARY, AND NATURAL GAS
INFRASTRUCTURE MUST BE COORDINATED WITH THE APPROPRIATE
UTILITY OWNER.
22. THERE WILL BE NO WORK ACCOMPLISHED ON ALL FEDERAL HOLIDAYS.
(NEW YEAR'S DAY, MLK DAY, PRESIDENT'S DAY, MEMORIAL DAY,
INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,
THANKSGIVING, AND CHRISTMAS DAY).
23. DEMOLITION OF LOAD-BEARING WALLS OR STRUCTURAL
COMPONENTS REQUIRE NOTIFICATION OF DEMOLITION AND
RENOVATION TO THE REGIONAL AIR POLLUTION AND CONTROL
AGENCY (RAPCA) A MINIMUM OF 10 WORK DAYS PRIOR TO BEGINNING
CONSTRUCTION.
24. IF ANY DRINKING WATER MAINS ARE BEING EXTENDED, UPSIZED, OR
NEW MAINS ARE BEING INSTALLED, A PLANS APPROVAL MAY BE
REQUIRED FROM THE OHIO EPA PRIOR TO BEGINNING MAIN
INSTALLATION. THE CONSTRUCTION CONTRACTOR SHALL PREPARE
AND SUBMIT A DRAFT PLANS APPROVAL PACKAGE TO THE
CONTRACTING OFFICER'S REPRESENTATIVE, INCLUDING A CHECK FOR
ANY APPLICABLE OHIO EPA FEES, FOR REVIEW AND PROCESSING BY
ENVIRONMENTAL MANAGEMENT, 88 CEG/CEIEA. ENVIRONMENTAL
MANAGEMENT SHALL ENDORSE THE PACKAGE AS THE UTILITY OWNER
AND SHALL SUBMIT IT TO OHIO EPA. PLEASE CONTACT THE 88
CEG/CEIEA WATER PM, KAREN BEASON, BY EMAIL AT
KAREN.BEASON@US.AF.MIL OR BY PHONE AT 937-257-5899 FOR
ADDITIONAL INFORMATION.
25. IF ANY SANITARY SEWER MAINS ARE BEING EXTENDED, UPSIZED OR
NEW MAINS ARE BEING INSTALLED A PERMIT TO INSTALL (PTI) MAY BE
REQUIRED FROM THE OHIO EPA PRIOR TO BEGINNING MAIN
INSTALLATION. THE CONSTRUCTION CONTRACTOR SHALL PREPARE
AND SUBMIT A DRAFT PTI PACKAGE TO THE CONTRACTING OFFICER'S
REPRESENTATIVE, INCLUDING A CHECK FOR ANY APPLICABLE OHIO
EPA FEES, FOR REVIEW AND PROCESSING BY ENVIRONMENTAL
MANAGEMENT, 88 CEG/CEIEA. ENVIRONMENTAL MANAGEMENT SHALL
ENDORSE THE PACKAGE AS THE UTILITY OWNER AND SHALL SUBMIT IT
TO OHIO EPA. PLEASE CONTACT THE 88 CEG/CEIEA WATER PM, KAREN
BEASON, BY EMAIL AT KAREN.BEASON@US.AF.MIL OR BY PHONE AT
937-257-5899 FOR ADDITIONAL INFORMATION.
26. IF ANY REFRIGERANT-CONTAINING EQUIPMENT SCHEDULED FOR NEW
INSTALLATION, INCLUDING WATER COOLERS, THEY MUST UTILIZE AN
HFC REFRIGERANT. CFC AND HCFC REFRIGERANTS ARE NOT
AUTHORIZED FOR NEW EQUIPMENT INSTALLATIONS. FOR ADDITIONAL
INFORMATION PLEASE CONTACT THE 88 CEG/CEIEA AIR PM CHRIS
TUMBUSCH. CHRIS CAN BE REACHED AT 937-257-2455 OR BY EMAIL AT
CHRISTOPHER.TUMBUSCH@US.AF.MIL.
27. IF AN EMERGENCY GENERATOR OR BOILER WILL BE INSTALLED, AN
AIR SOURCE PERMIT MAY BE REQUIRED FOR THE GENERATOR AND
POSSIBLY THE FUEL TANK. FOR ADDITIONAL INFORMATION PLEASE
CONTACT THE 88 CEG/CEIEA AIR PM CHRIS TUMBUSCH. CHRIS CAN BE
REACHED AT 937-257-2455 OR BY EMAIL AT
CHRISTOPHER.TUMBUSCH@US.AF.MIL.
28. ANY TRANSFORMERS, SWITCH GEAR, OR ELECTRICAL PANELS
CONTAINING OIL SCHEDULED FOR REMOVAL MUST HAVE THE
EQUIPMENT OIL VERIFIED TO BE NON PCB-CONTAINING PRIOR TO
TURN-IN. 88 CEG/CEIE MAINTAINS A BASE-WIDE PCB DATA-BASE FOR
OIL CONTAINING EQUIPMENT. IF THE EQUIPMENT CANNOT BE
LOCATED IN THE DATA-BASE THE OIL FROM EACH INDIVIDUAL PIECE
OF EQUIPMENT MUST BE SAMPLED FOR PCB. PLEASE CONTACT THE
88 CEG/CEIEC USED OIL TECHNICIAN BOB JARUSIEWIC BY EMAIL AT
ROBERT.JARUSIEWIC@US.AF.MIL OR BY PHONE AT 937-257-2889 FOR
ADDITIONAL INFORMATION.
29. STORM WATER INNOVATIVE DESIGN MEASURES MUST BE
INCORPORATED INTO THE DESIGN IAW SECTION 438 OF THE ENERGY
INDEPENDENCE AND SECURITY ACT (EISA) IF THE PROJECT HAS A
FOOTPRINT THAT EXCEEDS 5000 SQ FT. PLEASE CONTACT THE 88
CEG/CEIEA WATER PM KAREN BEASON BY EMAIL AT
KAREN.BEASON@US.AF.MIL OR BY PHONE AT 937-257-5899 FOR
ADDITIONAL INFORMATION.
30. A CRANE PLAN SUBMITTAL IS REQUIRED FOR GOVERNMENT
APPROVAL. THE CRANE PLAN SHALL INCLUDE THE CRANE LOCATION,
HEIGHT, DATES OF USE AND POINT OF CONTACT. PLEASE NOTE THAT
AN FAA FORM 7460-1 WILL BE REQUIRED IF CRANE IS OVER 200FT AND
THESE DOCUMENTS MAY TAKE 60 DAYS OR MORE TO PROCESS.
31. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH WPAFB
SPECIFICATION SECTION 01 02 20.
32. CONTRACTORS ARE FREE TO USE ANY PRODUCT WHICH MEETS THE
GOVERNMENT'S MINIMUM REQUIREMENTS AND NOT IN CONFLICT WITH
OTHER CONTRACT PROVISIONS. UNLESS INDICATED OTHERWISE ON
THE PLANS OR SPECIFICATIONS (E.G. SOLE-SOURCE), ALL LISTED
MANUFACTURERS ARE THE BASIS OF DESIGN. FOR THESE BASIS OF
DESIGN PRODUCTS, OTHER MANUFACTURERS MAY BE SUBSTITUTED
AS LONG AS THE STANDARD OF QUALITY AND CHARACTERISTICS OF
THE SUBSTITUTED MANUFACTURER MEET OR EXCEED THE STANDARD
OF QUALITY AND CHARACTERISTICS OF THE BASIS OF DESIGN.
G-001 COVER PAGE
G-002 GENERAL NOTES AND SHEET INDEX
G-003 SEQUENCING GENERAL NOTES
G-101 BASEMENT FLOOR PLAN - SEQUENCE 1
G-102 FIRST FLOOR PLAN - SEQUENCE 1
G-103 SECOND FLOOR PLAN - SEQUENCE 1
G-104 ROOF/PENTHOUSE PLAN - SEQUENCE 1
G-105 BASEMENT FLOOR PLAN - SEQUENCE 2
G-106 FIRST FLOOR PLAN - SEQUENCE 2
G-107 BASEMENT FLOOR PLAN - SEQUENCE 3
G-108 FIRST FLOOR PLAN - SEQUENCE 3
G-109 SECOND FLOOR PLAN - SEQUENCE 3
G-110 ROOF/PENTHOUSE PLAN - SEQUENCE 3
G-111 FIRST FLOOR PLAN - SEQUENCE 4
G-112 FIRST FLOOR PLAN - SEQUENCE 5
G-113 SECOND FLOOR PLAN - SEQUENCE 5
G-114 SECOND FLOOR PLAN - SEQUENCE 6
G-115 BASEMENT FLOOR PLAN - UTILITY COORDINATION
G-116 FIRST FLOOR PLAN - UTILITY COORDINATION
G-117 SECOND FLOOR PLAN - UTILITY COORDINATION
G-301 SECTIONS - UTILITY COORDINATION
GI101 BASEMENT FLOOR PLAN - LIFE SAFETY
GI102 FIRST FLOOR PLAN - LIFE SAFETY
GI103 SECOND FLOOR PLAN - LIFE SAFETY
H-101 BASEMENT PLAN - HAZARDOUS MATERIAL ABATEMENT PLAN
H-102 BASEMENT PLAN - HAZARDOUS MATERIAL ABATEMENT PLAN
H-103 PARTIAL FIRST FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN
H-104 PARTIAL FIRST FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN
H-105 SECOND FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN
H-106 SECOND FLOOR HAZARDOUS MATERIAL ABATEMENT PLAN
H-107 ROOF HAZARDOUS MATERIAL ABATEMENT PLAN
C-001 GENERAL NOTES AND LEGEND
GC101 LOCATION MAP AND HAUL ROUTE
V-101 EXISTING CONDITIONS & DEMOLITION PLAN
C-101 CIVIL SITE PLAN
C-102 CIVIL SITE PLAN
C-501 CIVIL DETAILS
C-502 CIVIL DETAILS
S-001 GENERAL STRUCTURAL NOTES
S-002 GENERAL STRUCTURAL NOTES
S-401 NEW ADDITION FOUNDATION PLAN & EQUIPMENT PAD PLAN
S-402 NEW ADDITION ROOF FRAMING PLAN
S-411 NEW CANOPY FOUNDATION PLAN
S-412 NEW CANOPY FRAMING PLAN
S-501 FOUNDATION DETAILS
S-502 FRAMING DETAILS
S-511 CANOPY FOUNDATION DETAILS
S-512 CANOPY FRAMING DETAILS
S-601 STRUCTURAL TYPICAL DETAILS
S-602 STRUCTURAL TYPICAL DETAILS
A-001 GENERAL NOTES, ABBREVIATIONS, & SYMBOLS
AD101 BASEMENT DEMOLITION PLAN
AD102 FIRST FLOOR DEMOLITION PLAN
AD103 SECOND FLOOR DEMOLITION PLAN
AD104 ROOF/PENTHOUSE DEMOLITION PLAN
AD111 BASEMENT CEILING DEMOLITION PLAN
AD112 FIRST FLOOR CEILING DEMOLITION PLAN
AD113 SECOND FLOOR CEILING DEMOLITION PLAN
A-101 BASEMENT FLOOR PLAN
A-102 FIRST FLOOR PLAN
A-103 SECOND FLOOR PLAN
A-104 ROOF/PENTHOUSE PLAN
A-111 BASEMENT CEILING PLAN
A-112 FIRST FLOOR CEILING PLAN
A-113 SECOND FLOOR CEILING PLAN
A-201 ELEVATIONS
A-202 ELEVATIONS
A-301 WALL SECTIONS
A-302 SECTION DETAILS
A-303 SECTION DETAILS
A-401 ENLARGED PLANS & ELEVATIONS - MECHANICAL ROOM
A-402 ENLARGED PLANS - COURTYARDS
A-403 ENLARGED PLANS & ELEVATIONS - RESTROOMS
A-404 ENLARGED PLANS & ELEVATIONS - RESTROOMS
A-405 ENLARGED PLANS & ELEVATIONS - RESTROOMS
A-501 CANOPY SECTIONS
A-502 CANOPY SECTIONS
A-503 CANOPY SECTIONS
A-601 DOOR SCHEDULES AND DETAILS
A-602 WINDOW SCHEDULES AND DETAILS
A-603 PARTITION TYPES
A-701 STAIR PLANS & SECTIONS
A-702 STAIR PLANS & SECTIONS
A-703 STAIR PLANS & SECTIONS
A-704 STAIR PLANS & SECTIONS
A-709 STAIR SECTIONS & DETAILS
A-901 ELEVATIONS & PERSPECTIVES
I-101 BASEMENT EXISTING FURNITURE PLAN
I-102 FIRST FLOOR EXISTING FURNITURE PLAN
I-103 SECOND FLOOR NEW AND EXISTING FURNITURE PLAN
I-111 BASEMENT FINISH PLAN
I-112 FIRST FLOOR FINISH PLAN
I-113 SECOND FLOOR FINISH PLAN
I-201 BASEMENT SIGNAGE PLAN
I-202 FIRST FLOOR SIGNAGE PLAN
I-203 SECOND FLOOR SIGNAGE PLAN
I-204 SIGNAGE TYPICALS & SCHEDULE
I-401 ENLARGED FURNITURE PLANS
I-402 ENLARGED PANEL PLAN
I-403 ENLARGED FINISH PLAN AND DETAILS
I-601 FINISH SCHEDULE
F-001 GENERAL INFORMATION - FIRE PROTECTION
FD101 BASEMENT FLOOR PLAN - FIRE PROTECTION - DEMOLITION
FD102 FIRST FLOOR PLAN - FIRE PROTECTION - DEMOLITION
FD103 SECOND FLOOR PLAN - FIRE PROTECTION - DEMOLITION
FD104 ROOF/PENTHOUSE PLAN - FIRE PROTECTION - DEMOLITION
F-101 BASEMENT FLOOR PLAN - FIRE PROTECTION
F-102 FIRST FLOOR PLAN - FIRE PROTECTION
F-103 SECOND FLOOR PLAN - FIRE PROTECTION
F-104 ROOF/PENTHOUSE PLAN - FIRE PROTECTION
F-501 DETAILS - FIRE PROTECTION
FA001 GENERAL INFORMATION - FIRE ALARM
FA101 BASEMENT FLOOR PLAN WEST - FIRE ALARM
FA102 BASEMENT FLOOR PLAN EAST - FIRE ALARM
FA111 FIRST FLOOR PLAN WEST - FIRE ALARM
FA112 FIRST FLOOR PLAN EAST - FIRE ALARM
FA121 SECOND FLOOR PLAN WEST - FIRE ALARM
FA122 SECOND FLOOR PLAN EAST - FIRE ALARM
FA131 ROOF/PENTHOUSE PLAN WEST - FIRE ALARM
FA132 ROOF/PENTHOUSE PLAN EAST - FIRE ALARM
FA431 ENLARGED PENTHOUSE PLAN - FIRE ALARM
FA501 DETAILS - FIRE ALARM
FA502 DETAILS - FIRE ALARM
P-001 GENERAL INFORMATION - PLUMBING
P-101 BASEMENT PLAN - PLUMBING
P-102 FIRST FLOOR PLAN - PLUMBING
P-103 SECOND FLOOR PLAN - PLUMBING
P-104 ROOF/PENTHOUSE PLAN - PLUMBING
P-301 DIAGRAMS - PLUMBING
P-601 DETAILS AND SCHEDULES - PLUMBING
M-001 GENERAL INFORMATION - MECHANICAL
MD101 BASEMENT FLOOR PLAN WEST - HVAC - DEMOLITION
MD102 BASEMENT FLOOR PLAN EAST - HVAC - DEMOLITION
MD103 BASEMENT FLOOR PLAN WEST - HVAC PIPING - DEMOLITION
MD104 BASEMENT FLOOR PLAN EAST - HVAC PIPING - DEMOLITION
MD111 FIRST FLOOR PLAN WEST - HVAC - DEMOLITION
MD112 FIRST FLOOR PLAN EAST - HVAC - DEMOLITION
MD113 FIRST FLOOR PLAN WEST - HVAC PIPING - DEMOLITION
MD114 FIRST FLOOR PLAN EAST - HVAC PIPING - DEMOLITION
MD121 SECOND FLOOR PLAN WEST - HVAC - DEMOLITION
MD122 SECOND FLOOR PLAN EAST - HVAC - DEMOLITION
MD123 SECOND FLOOR PLAN WEST - HVAC PIPING - DEMOLITION
MD133 ROOF/PENTHOUSE PLAN WEST - HVAC PIPING - DEMOLITION
MD134 ROOF/PENTHOUSE PLAN EAST - HVAC PIPING - DEMOLITION
MD411 ENLARGED FIRST FLOOR PLANS - MECHANICAL - DEMOLITION
MD421 ENLARGED SECOND FLOOR PLANS - MECHANICAL - DEMOLITION
MD431 ENLARGED PENTHOUSE PLAN - HVAC - DEMOLITION
MD432 ENLARGED PENTHOUSE PLAN - HVAC PIPING - DEMOLITION
MH101 BASEMENT FLOOR PLAN WEST - HVAC
MH102 BASEMENT FLOOR PLAN EAST - HVAC
MH111 FIRST FLOOR PLAN WEST - HVAC
MH112 FIRST FLOOR PLAN EAST - HVAC
MH121 SECOND FLOOR PLAN WEST - HVAC
MH122 SECOND FLOOR PLAN EAST - HVAC
MP101 BASEMENT FLOOR PLAN WEST - HVAC PIPING
MP102 BASEMENT FLOOR PLAN EAST - HVAC PIPING
MP111 FIRST FLOOR PLAN WEST - HVAC PIPING
MP112 FIRST FLOOR PLAN EAST - HVAC PIPING
MP121 SECOND FLOOR PLAN WEST - HVAC PIPING
MP122 SECOND FLOOR PLAN EAST - HVAC PIPING
MP131 ROOF/PENTHOUSE PLAN WEST - HVAC PIPING
MP132 ROOF/PENTHOUSE PLAN EAST - HVAC PIPING
M-301 SECTIONS - MECHANICAL
M-411 ENLARGED FIRST FLOOR PLANS - MECHANICAL
M-421 ENLARGED SECOND FLOOR PLANS - MECHANICAL
M-431 ENLARGED PENTHOUSE PLAN - HVAC
M-432 ENLARGED PENTHOUSE PLAN - HVAC PIPING
M-501 DETAILS - MECHANICAL
M-502 DETAILS - MECHANICAL
M-503 DETAILS - MECHANICAL
M-504 DETAILS - MECHANICAL
M-601 SCHEDULES - MECHANICAL
M-602 SCHEDULES - MECHANICAL
M-603 SCHEDULES - MECHANICAL
M-604 SCHEDULES - MECHANICAL
M-701 CONTROLS - MECHANICAL
M-702 CONTROLS - MECHANICAL
M-703 CONTROLS - MECHANICAL
M-704 CONTROLS - MECHANICAL
M-705 CONTROLS - MECHANICAL
M-706 CONTROLS - MECHANICAL
M-707 CONTROLS - MECHANICAL
M-708 CONTROLS - MECHANICAL
M-709 CONTROLS - MECHANICAL
M-710 CONTROLS - MECHANICAL
M-711 CONTROLS - MECHANICAL
M-712 CONTROLS - MECHANICAL
M-713 CONTROLS - MECHANICAL
M-714 CONTROLS - MECHANICAL
M-715 CONTROLS - MECHANICAL
M-716 CONTROLS - MECHANICAL
M-717 CONTROLS - MECHANICAL
M-718 CONTROLS - MECHANICAL
M-719 CONTROLS - MECHANICAL
M-720 CONTROLS - MECHANICAL
M-721 CONTROLS - MECHANICAL
M-722 CONTROLS - MECHANICAL
M-723 CONTROLS - MECHANICAL
M-724 CONTROLS - MECHANICAL
M-725 CONTROLS - MECHANICAL
M-726 CONTROLS - MECHANICAL
M-727 CONTROLS - MECHANICAL
M-728 CONTROLS - MECHANICAL
M-729 CONTROLS - MECHANICAL
M-730 CONTROLS - MECHANICAL
M-731 CONTROLS - MECHANICAL
M-732 CONTROLS - MECHANICAL
M-801 DIAGRAMS - MECHANICAL
M-802 DIAGRAMS - MECHANICAL
M-803 DIAGRAMS - MECHANICAL
M-804 DIAGRAMS - MECHANICAL
M-805 DIAGRAMS - MECHANICAL
M-806 DIAGRAMS - MECHANICAL
E-001 GENERAL INFORMATION - ELECTRICAL
ED101 BASEMENT FLOOR PLAN WEST - ELECTRICAL - DEMOLITION
ED102 BASEMENT FLOOR PLAN EAST - ELECTRICAL - DEMOLITION
ED111 FIRST FLOOR PLAN WEST - ELECTRICAL - DEMOLITION
ED112 FIRST FLOOR PLAN EAST - ELECTRICAL - DEMOLITION
ED121 SECOND FLOOR PLAN WEST - ELECTRICAL - DEMOLITION
ED122 SECOND FLOOR PLAN EAST - ELECTRICAL - DEMOLITION
ED411 ENLARGED FIRST FLOOR PLAN - ELECTRICAL - DEMOLITION
ED431 ENLARGED PENTHOUSE PLAN - ELECTRICAL - DEMOLITION
ED501 DETAILS - ELECTRICAL - DEMOLITION
ED701 DIAGRAMS - DEMOLITION
ED702 DIAGRAMS - DEMOLITION
EG131 ROOF/PENTHOUSE PLAN - LIGHTNING PROTECTION
EL101 BASEMENT FLOOR PLAN WEST - LIGHTING
EL102 BASEMENT FLOOR PLAN EAST - LIGHTING
EL111 FIRST FLOOR PLAN WEST - LIGHTING
EL112 FIRST FLOOR PLAN EAST - LIGHTING
EL121 SECOND FLOOR PLAN WEST - LIGHTING
EL122 SECOND FLOOR PLAN EAST - LIGHTING
EP101 BASEMENT FLOOR PLAN WEST - POWER
EP102 BASEMENT FLOOR PLAN EAST - POWER
EP111 FIRST FLOOR PLAN WEST - POWER
EP112 FIRST FLOOR PLAN EAST - POWER
EP121 SECOND FLOOR PLAN WEST - POWER
EP122 SECOND FLOOR PLAN EAST - POWER
E-401 ENLARGED PLANS - ELECTRICAL
E-411 ENLARGED FIRST FLOOR PLANS - ELECTRICAL
E-431 ENLARGED PENTHOUSE PLAN - ELECTRICAL
E-501 DETAILS - ELECTRICAL
E-502 DETAILS - ELECTRICAL
E-601 SCHEDULES - ELECTRICAL
E-602 SCHEDULES - ELECTRICAL
E-603 SCHEDULES - ELECTRICAL
E-604 SCHEDULES - ELECTRICAL
E-605 SCHEDULES - ELECTRICAL
E-606 SCHEDULES - ELECTRICAL
E-607 SCHEDULES - ELECTRICAL
E-701 DIAGRAMS - ELECTRICAL
E-702 DIAGRAMS - ELECTRICAL
E-703 DIAGRAMS - ELECTRICAL
E-704 DIAGRAMS - ELECTRICAL
T-001 GENERAL INFORMATION - TELECOMMUNICATIONS
TS101 SITE PLAN - TELECOMMUNICATIONS
TD101 BASEMENT FLOOR PLAN WEST - TELECOMMUNICATIONS - DEMOLITION
TD102 BASEMENT FLOOR PLAN EAST - TELECOMMUNICATIONS - DEMOLITION
TD111 FIRST FLOOR PLAN WEST - TELECOMMUNICATIONS - DEMOLITION
TD112 FIRST FLOOR PLAN EAST - TELECOMMUNICATIONS - DEMOLITION
TD121 SECOND FLOOR PLAN WEST - TELECOMMUNICATIONS - DEMOLITION
TD122 SECOND FLOOR PLAN EAST - TELECOMMUNICATIONS - DEMOLITION
TD701 DIAGRAMS - TELECOMMUNICATIONS - DEMOLITION
T-101 BASEMENT FLOOR PLAN WEST - TELECOMMUNICATIONS
T-102 BASEMENT FLOOR PLAN EAST - TELECOMMUNICATIONS
T-111 FIRST FLOOR PLAN WEST - TELECOMMUNICATIONS
T-112 FIRST FLOOR PLAN EAST - TELECOMMUNICATIONS
T-121 SECOND FLOOR PLAN WEST - TELECOMMUNICATIONS
T-122 SECOND FLOOR PLAN EAST - TELECOMMUNICATIONS
T-401 ENLARGED PLANS - TELECOMMUNICATIONS
T-501 DETAILS - TELECOMMUNICATIONS
T-502 DETAILS - TELECOMMUNICATIONS
T-701 DIAGRAMS - TELECOMMUNICATIONS
GENERAL NOTESSHEET INDEX
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D
V A
N C
E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
G E
N E
R A
L G
E N
E R
A L
N O
TE
S
A N
D S
H E
E T
IN
D
E X
G-002
G . L
E
IT
C H
K . F
IE
LD
S
K . F
IE
LD
S
CERTIFIED FINAL
ARIMS: 200A Disposition: Maintain for 15yrs after construction
W
2Q R
B0
1-
1. THESE NOTES APPLY TO ALL PROPOSED SEQUENCING SHEETS
2. THE UPGRADE AND REPLACEMENT HVAC SYSTEMS SHALL OCCUR IN
SEVERAL SEQUENCES SO THAT SELECT LABS CAN REMAIN
OPERATIONAL DURING CONSTRUCTION. ONLY LIMITED NUMBERS OF
AIR HANDLING UNITS (AHU'S) AND SUBSYSTEMS WILL BE PERMITTED
TO BE SHUTDOWN AT ANY GIVEN TIME FOR SHORT DURATIONS
DURING THE CONSTRUCTION TO MAINTAIN BUILDING FUNCTIONALITY.
3. THIS PROPOSED SEQUENCE OUTLINES A PLAN OF CONSTRUCTION
STAGING AND IS INTENDED FOR THE USE OF THE SUCCESSFUL
CONTRACTOR AS A STARTING POINT FOR THE DETAILED PLANNING
AND COORDINATION OF THE WORK SCHEDULE AND PROCESS
REQUIRED WITH THE CONTRACTING OFFICER'S REPRESENTATIVE.
4. STAGING SHALL ALLOW THE BUILDING TO BE MAXIMALLY FUNCTIONAL
THROUGHOUT CONSTRUCTION.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR DETAILING AND
COORDINATING THE STAGING, WORK PROCESS AND SCHEDULING
WITH THE CONTRACTING OFFICER'S REPRESENTATIVE. A DETAILED
METHOD OF PROCEDURE WILL BE REQUIRED FOR EACH PART OF THE
DEMOLITION AND CONSTRUCTION.
6. CONTRACTOR MAY EXECUTE TASKS CONCURRENTLY AS THE
DETAILED PLANNING, SCHEDULING AND COORDINATION OF ALL
DISCIPLINES ALLOWS.
7. THE GOVERNMENT HAS IDENTIFIED NINE LAB FACILITIES THAT WILL
NEED TO REMAIN OPERATIONAL DURING CONSTRUCTION. THESE LAB
FACILITIES WILL BE THE DRIVING FACTOR BEHIND THE SEQUENCING
PLAN TO MINIMIZE DISRUPTION TO THE USER'S MISSION. THE NINE
LAB FACILITIES THAT WERE IDENTIFIED ARE:
7.1. SHARC
7.2. BAMLAB
7.3. VERITAS
7.4. VOCRES
7.5. ALF
7.6. MIRE
7.7. AAC
7.8. BATMAN
7.9. REAT
8. ALL OFFICE PERSONNEL WILL BE DISPLACED FROM BUILDING 441 TO A
TEMPORARY SWING SPACE. ONLY A FEW LAB STAFF WILL REMAIN IN
THE BUILDING DURING THE CONSTRUCTION.
9. THE ALF AND VERITAS LABS WILL REQUIRE TEMPORARY COOLING
DURING CONSTRUCTION TO MAINTAIN A SPACE RELATIVE HUMIDITY
OF NO MORE THAT 55%.
10. OUTAGES TO THE LAB FACILITIES MUST BE COORDINATED WITH THE
COR A MINIMUM OF FOUR WEEKS IN ADVANCE.
11. CONTRACTOR SHALL MAINTAIN A MINIMUM OF TWO PATHS OF EGRESS
DURING CONSTRUCTION.
12. CONTRACTOR SHALL COORDINATE WITH COR FOR LAB MOBILE DATA
CART REQUIREMENTS.
GENERAL NOTES
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
G E
N E
R A
L G
E N
E R
A L
N O
TE
S
G-003
G . L
E
IT
C H
K . F
IE
LD
S
K . F
IE
LD
S
CERTIFIED FINAL
a3 a2a1b6 b7 b8 b9b5.1b5b4b2b1 aF aE aD aC aB aA bB bA.2 bA.1 bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0
UP
UP
UP
BAMLAB
0-111
VERITAS
0-114A
FABRICATION
SHOP
0-117
MECH
0-118
STORAGE
0-117A
OFFICE
0-124
LAB
0-120
LAB
0-120B
LAB
0-120A
ELEVATOR
0E1
MENS
0-012
OFFICE
0-119A
OFFICE
0-119B
OFFICE
0-119
LAB
0-126B
LAB
0-126C
LAB
0-126A
STAIR C
0S2
VOCRES
0-116A
MECH
0-902
STORAGE
0-112
SHARC
0-108
0-113
BREAK ROOM
0-103
JAN.
0-904
CORRIDOR
0-906
STORAGE
0-107
LAB
0-102
COMM
0-115A
OFFICE
0-106
LAB
0-110
WOMENS
0-011
VERITAS
CONTROL
0-114
LISTENING LAB
0-101
CONFERENCE
ROOM
0-104
STORAGE
0-104ASHARC CONTROL
0-109
LAB
0-110A
VESTIBULE
0-903
STAIR A
0S4
OFFICE
0-105
VOCRES
CONTROL
0-116
OFFICE
0-125
CORRIDOR
0-905
SOFTWARE
DEVELOPMENT
LAB
0-123
STAIR B
0S1CORRIDOR
0-901
OFFICE
0-119C
LISTENING LAB
0-126
EEG LAB
0-122
VIRTUAL AUDIO
LAB
0-121
LAB
0-121A
ELEC
0-115
4' 8' 16'03/32"=1'-0"A1
BASEMENT FLOOR PLAN - SEQUENCE 1
SEQUENCE OF CONSTRUCTION
A. SEQUENCE ONE:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 270 DAYS.
A.A. LABS:
A.A.A. CONTRACTOR WILL NOT HAVE ACCESS TO ALL LAB FACILITIES DURING
THIS CONSTRUCTION SEQUENCE.
A.B. HVAC:
A.B.A. CHILLED WATER PIPING:
A.B.A.A. ROUTE NEW CHW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE CHW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.B.B. HOT WATER PIPING:
A.B.B.A. ROUTE NEW HW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE HW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.B.C. AC-5 AND AC-10:
A.B.C.A. REPLACE AC-5 IN FAB SHOP 0-117 WITH NEW CHW/HW AIR
HANDLING UNIT. REPLACE ASSOCIATED CHW PIPING WITH NEW
PIPING FROM SEQUENCE ONE SYSTEM. ROUTE NEW HW FROM
SEQUENCE ONE SYSTEM. DEMOLISH ALL ASSOCIATED STEAM AND
CONDENSATE PIPING.
A.B.C.B. REPLACE DUCT SYSTEM WITH NEW DUCT SYSTEM.
A.B.C.C. REPLACE AC-10 IN BASEMENT MECHANICAL ROOM 0-118.
COORDINATE REPLACEMENT WITH ELECTRICAL (MECHANICAL
ROOM HOUSES THE 400 HZ AND 28 VOLT DC GENERATORS).
A.D. FIRE ALARM:
A.D.A. PROVIDE TEMPORARY WALL MOUNTED SMOKE DETECTORS IN LABS
AND LAB CONTROL ROOMS, DETECTORS MUST BE BETWEEN 4" AND 12"
FROM THE CEILING AFTER THE EXISTING CEILING GRID HAS BEEN
REMOVED.
A.D.B. PROVIDE FIXED TEMPERATURE HEAT DETECTORS ONLY AND NOT RATE
OF RISE DETECTORS.
A.D.C. HEAT DETECTORS SHALL BE LOCATED IN CORRIDORS AND OTHER
AREAS OF THE BUILDING. ON THE SECOND FLOOR LOCATE HEAT
DETECTORS IN CORRIDORS AND REMOVE ALL DOORS FROM THEIR
HINGES TO COMMUNICATE AREAS.
A.D.D. CONTRACTOR SHALL PROVIDE A PLAN FOR PROTECTION TO THE FIRE
DEPARTMENT FOR REVIEW AND COORDINATION OF SMOKE AND HEAT
DETECTOR LOCATIONS.
A.D.E. NOTIFICATION SHALL BE REQUIRED IN THE LABS DURING
CONSTRUCTION (TEMPORARY SYSTEM).
A.D.F. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE ALF LAB,
LOCATE DETECTOR OUTSIDE OF THE LAB DOOR.
A.D.C. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE REAT LAB,
LOCATE DETECTOR OUTSIDE OF THE LAB DOOR.
A.E. EGRESS:
A.E.A. PROVIDE TEMPORARY EXIT AND EMERGENCY EGRESS LIGHTING WITH
90 MINUTE BATTERY BACKUP FOR BUILDING EGRESS, COORDINATE
LOCATIONS WITH THE AHJ.
SEQUENCE 1
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
B
A S
E M
E N
T
FL
O O
R P
LA
N
G-101
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A
N a2a1b6 b7 b8 b9b5b4 aE aD aC aB aA bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0 a3b1
DN
UP
DN
UP
DN
DN UP
ALF
1-010
MIRE
1-008A
STAGING
1-009
CORRIDOR
1-904
AAC
1-008D
REAT
1-008E
LAB
1-008B
MECH
1-006
CONTROL
1-008
WOMENS
1-007
STAIR B
1S1
STAIR C
1S2
CONFERENCE
1-004
STORAGE
1-004AOFFICE
1-003C
OFFICE
1-003B
OFFICE
1-003A
OFFICE
1-003
OFFICE
1-005
OFFICE
1-005A
STORAGE
1-012
STORAGE
1-011
OFFICE
1-017
OFFICE
1-013
OFFICE
1-015
COMM
1-014A
STORAGE
1-019A
KITCHENETTE
1-106
MECH
1-901
STORAGE
1-020A
OFFICE
1-018C
STORAGE
1-018B
LOBBY
1-902
CONFERENCE
ROOM
1-019
WOMENS
1-R02
STAIR A
1S4
STAIR D
1S3
MENS
1-R01
OFFICE
1-018A
OFFICE
1-018
ENTRY
1-900
CONFERENCE
1-020
ELEC
1-014
CORRIDOR
1-903
CONTROL
1-008C
1-016
MENS
1-016A
SHOWER
4' 8' 16'03/32"=1'-0"A1
FIRST FLOOR PLAN - SEQUENCE 1
SEQUENCE OF CONSTRUCTION
A. SEQUENCE ONE:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 270 DAYS.
A.A. EXTERIOR:
A.A.A. NEW RAMPS TO BE INSTALLED.
A.B. LABS:
A.B.A. CONTRACTOR WILL NOT HAVE ACCESS TO ALL LAB FACILITIES DURING
THIS CONSTRUCTION SEQUENCE.
A.C. HVAC:
A.C.A. COOLING PLANT:
A.C.A.A. PROVIDE NEW CHILLERS AND ASSOCIATED EQUIPMENT IN NEW
MECHANICAL ROOM.
A.C.A.B. ROUTE NEW CHW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE CHW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.C.B. HEATING PLANT:
A.C.B.A. PROVIDE NEW BOILERS AND ASSOCIATED EQUIPMENT IN NEW
MECHANICAL ROOM.
A.C.B.B. ROUTE NEW HW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE HW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.D. ELECTRICAL:
A.D.A. AC-5 AND AC-10:
A.D.A.A. DISCONNECT FEEDS FROM THE PP-1C TO AC-5 AND SOURCE TO
AC10.
A.D.A.B. PROVIDE ELECTRICAL FEEDS FROM PANEL PP-1C TO NEW AC-5
AND SOURCE TO AC-10.
A.D.B. SWITCHBOARDS:
A.D.B.A. ADD FUSING AND A POWER FEED FROM SPARE SWITCH IN SPACE
10 OF SWITCHBOARD PDC-A IN THE SECOND FLOOR
A.E. FIRE ALARM:
A.E.A. PROVIDE TEMPORARY WALL MOUNTED DETECTORS IN ENTRY LOBBY,
DETECTORS MUST BE BETWEEN 4" AND 12" FROM THE CEILING AFTER
THE EXISTING CEILING GRID HAS BEEN REMOVED.
A.E.B. PROVIDE FIXED TEMPERATURE HEAT DETECTORS ONLY AND NOT RATE
OR RISE DETECTORS.
A.E.C. HEAT DETECTORS SHALL BE LOCATED IN CORRIDORS AND OTHER
AREAS OF THE BUILDING. ON THE SECOND FLOOR LOCATE HEAT
DETECTORS IN CORRIDORS AND REMOVE ALL DOORS FROM THIER
HINGES TO COMMUNICATE AREAS.
A.E.D. CONTRACTOR SHALL PROVIDE A PLAN FOR PROTECTION TO THE FIRE
DEPARTMENT FOR REVIEW AND COORDINATION OF SMOKE AND HEAT
DETECTOR LOCATIONS.
A.E.E. NOTIFICATION SHALL BE REQUIRED IN THE LABS DURING
CONSTRUCTION (TEMPORARY SYSTEM).
A.E.F. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE ALF LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.E.G. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE REAT LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.F. ARCHITECTURAL:
A.F.A. CONSTRUCT MECHANICAL ROOM ADDITION.
A.F.B. REWORK FRONT ENTRY RAMP.
A.G. EGRESS:
A.G.A. PROVIDE TEMPORARY EXIT AND EMERGENCY EGRESS LIGHTING WITH
90 MINUTE BATTERY BACKUP FOR BUILDING EGRESS, COORDINATE
LOCATIONS WITH THE AHJ.
SEQUENCE 1
SEQUENCE 1
SEQUENCE 1
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
FI
R S
T
FL
O O
R P
LA
N
G-102
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A a2a1b6 b7 b8 b9b5.1b5b4b2 aE aD aC aB aA bB bA.2 bA.1 bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0 a3b1
DN
DN
DN
MENS
2-020B
STORAGE
2-903
STAIR B
2S1
MECH
2-904
STAIR D
2S3
STAIR C
2S2
COMM
2-116C
STORAGE
2-116
JANITOR
2-118
OFFICE
2-115B
STAIR A
2S4
KITCHENETTE
2-107B
STORAGE
2-107A
OFFICE
2-008
OFFICE
2-007
OFFICE
2-006
OFFICE
2-004
OFFICE
2-001
OFFICE
2-002
OFFICE
2-003
OFFICE
2-016
OFFICE
2-100
OFFICE
2-117B
CORRIDOR
2-117G
OFFICE
2-117
CLOSET
2-117H
CORRIDOR
2-901
OFFICE
2-115C
OFFICE
2-115D
OFFICE
2-117E STORAGE
2-117F
CONFERENCE
ROOM
2-107
OFFICE
2-115
OFFICE
2-101
OFFICE
2-102
OFFICE
2-103
OFFICE
2-117D STORAGE
2-104
OFFICE
2-117C
WOMENS
2-020A
OFFICE
2-117A
ELEC
2-116B
ALF
1-010
CORRIDOR
2-905
OFFICE
2-023B
OFFICE
2-023 OFFICE
2-023C
OFFICE
2-023D
OFFICE
2-023E
CORRIDOR
2-902
4' 8' 16'03/32"=1'-0"A1
SECOND FLOOR PLAN - SEQUENCE 1
SEQUENCE 1
SEQUENCE OF CONSTRUCTION
A. SEQUENCE ONE:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 270 DAYS.
A.A. LABS:
A.A.A. CONTRACTOR WILL NOT HAVE ACCESS TO ALL LAB FACILITIES DURING
THIS CONSTRUCTION SEQUENCE.
A.B. HVAC:
A.B.A. CHILLED WATER PIPING:
A.B.A.A. ROUTE NEW CHW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE CHW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.B.B. HOT WATER PIPING:
A.B.B.A. ROUTE NEW HW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE HW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.B.C. PROVIDE DDC FRONT END COMMUNICATIONS IN MECHANICAL ROOM
2-904 TO COMMUNICATE WITH THE WPAFB SYSTEM.
A.C. FIRE ALARM:
A.C.A. PROVIDE TEMPORARY WALL MOUNTED DETECTORS IN ENTRY LOBBY,
DETECTORS MUST BE BETWEEN 4" AND 12" FROM THE CEILING AFTER
THE EXISTING CEILING GRID HAS BEEN REMOVED.
A.C.B. PROVIDE FIXED TEMPERATURE HEAT DETECTORS ONLY AND NOT RATE
OR RISE DETECTORS.
A.C.C. HEAT DETECTORS SHALL BE LOCATED IN CORRIDORS AND OTHER
AREAS OF THE BUILDING. ON THE SECOND FLOOR LOCATE HEAT
DETECTORS IN CORRIDORS AND REMOVE ALL DOORS FROM THIER
HINGES TO COMMUNICATE AREAS.
A.C.D. CONTRACTOR SHALL PROVIDE A PLAN FOR PROTECTION TO THE FIRE
DEPARTMENT FOR REVIEW AND COORDINATION OF SMOKE AND HEAT
DETECTOR LOCATIONS.
A.C.E. NOTIFICATION SHALL BE REQUIRED IN THE LABS DURING
CONSTRUCTION (TEMPORARY SYSTEM).
A.D. EGRESS:
A.D.A. PROVIDE TEMPORARY EXIT AND EMERGENCY EGRESS LIGHTING WITH
90 MINUTE BATTERY BACKUP FOR BUILDING EGRESS, COORDINATE
LOCATIONS WITH THE AHJ.
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
S
E C
O N
D F
LO
O
R P
LA
N
G-103
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A aE aD aC aB aA bB bA.2 bA.1 bA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0 a3b1
PENTHOUSE
3-100
PENTHOUSE
3-101
4' 8' 16'03/32"=1'-0"A1
ROOF/PENTHOUSE PLAN - SEQUENCE 1
SEQUENCE 1
SEQUENCE 1
SEQUENCE OF CONSTRUCTION
A. SEQUENCE ONE:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 270 DAYS.
A.A. LABS:
A.A.A. CONTRACTOR WILL NOT HAVE ACCESS TO ALL LAB FACILITIES DURING
THIS CONSTRUCTION SEQUENCE.
A.B. HVAC:
A.B.A. CHILLED WATER PIPING:
A.B.A.A. ROUTE NEW CHW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE CHW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
A.B.B. HOT WATER PIPING:
A.B.B.A. ROUTE NEW HW PIPING FROM MECHANICAL ROOM ADDITION TO
PENTHOUSE MECHANICAL ROOMS. TERMINATE HW PIPING MAINS
IN INTERIOR OF PENTHOUSE MECHANICAL ROOMS WITH VALVED
TAPS FOR FUTURE CONNECTION DURING OTHER SEQUENCES.
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
R
O O
F/ P
E N
TH
O
U S
E P
LA
N
G-104
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A aE aD aC aB aA bB bA.2 bA.1 bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0
UP
UP
UP
BAMLAB
0-111
VERITAS
0-114A
FABRICATION
SHOP
0-117
MECH
0-118
STORAGE
0-117A
OFFICE
0-124
LAB
0-120
LAB
0-120B
LAB
0-120A
ELEVATOR
0E1
MENS
0-012
OFFICE
0-119A
OFFICE
0-119B
OFFICE
0-119
LAB
0-126B
LAB
0-126C
LAB
0-126A
STAIR C
0S2
VOCRES
0-116A
MECH
0-902
STORAGE
0-112
SHARC
0-108
0-113
BREAK ROOM
0-103
JAN.
0-904
CORRIDOR
0-906
STORAGE
0-107
LAB
0-102
COMM
0-115A
OFFICE
0-106
LAB
0-110
WOMENS
0-011
VERITAS
CONTROL
0-114
LISTENING LAB
0-101
CONFERENCE
ROOM
0-104
STORAGE
0-104ASHARC CONTROL
0-109
LAB
0-110A
VESTIBULE
0-903
STAIR A
0S4
OFFICE
0-105
VOCRES
CONTROL
0-116
OFFICE
0-125
CORRIDOR
0-905
SOFTWARE
DEVELOPMENT
LAB
0-123
STAIR B
0S1CORRIDOR
0-901
OFFICE
0-119C
LISTENING LAB
0-126
EEG LAB
0-122
VIRTUAL AUDIO
LAB
0-121
LAB
0-121A
ELEC
0-115
4' 8' 16'03/32"=1'-0"A1
BASEMENT FLOOR PLAN - SEQUENCE 2
SEQUENCE 2
S W
SEQUENCE OF CONSTRUCTION
A. SEQUENCE TWO:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 120 DAYS.
A.A. CORRIDOR:
A.A.A. TEMPORARY BARRIER SHALL BE CONSTRUCTED ALONG COLUMN LINE
b6 IN THE SOUTH CORRIDOR 0-901.
A.A.B. CORRIDOR SHALL BE KEPT CLEAR OF DEBRIS DURING CONSTRUCTION.
A.A.C. REFER TO SECTIONS FOR SEQUENCE OF WORK IN CORRIDORS.
A.B. LABS:
A.B.A. CONTRACTOR WILL HAVE ACCESS TO LAB FACILITIES VOCRES AND
BATMAN (0-120) DURING THIS CONSTRUCTION SEQUENCE.
A.C. HVAC:
A.C.C. AC-3:
A.C.C.A. REPLACE DUCT SYSTEM WITH DISTRIBUTED VARIABLE AIR VOLUME
(VAV) DUCT SYSTEM.
A.C.C.B. ROUTE NEW HW PIPING FROM SEQUENCE ONE PIPING MAINS TO
VAV REHEAT COILS.
A.C.C.C. PIPING WORK IN CORRIDOR 0-901 SHALL REMAIN AT A MINIMUM TO
AVOID DISTURBANCE OF ADJACENT SPACES.
A.D. ELECTRICAL:
A.D.A. PANELS:
A.D.A.A. DISCONNECT THE FEED FROM SWITCHBOARD MCC-A TO PANELS
LL-1B, 3C (LPA), LPB, LPC, LPD, PP-5 AND THE SIREN COMPRESSOR.
REPLACE THE INTERNAL BUS-WORK FOR PANELS PP-10, PP-11 AND
PP-12.
A.D.B. SWITCHBOARDS:
A.D.B.A. PROVIDE FEEDS FROM SWITCHBOARD PDC-A TO NEW HVAC
DEVICES AC-3, AND RF-3. PROVIDE FEEDS FROM SWITCHBOARDS
PDC-C AND PDC-E TO LOADS INDICATED ON THE ONE-LINE
DIAGRAM. PROVIDE A TEMPORARY FEED FROM PDC-E TO PANEL
LPC ON THE SECOND FLOOR.
A.D.C. LIGHTING:
A.D.C.A. THE EAST BASEMENT WILL BE A CONSTRUCTION ZONE. PROVIDE
LED TYPE TEMPORARY CONSTRUCTION LIGHT STRINGS IN THE
BASEMENT CORRIDOR. PROVIDE FEEDER FROM 277VAC PANEL
LPE, CIRCUIT 9 TO THIS STRING. PROVIDE BATTERY BACKED
EMERGENCY LIGHT/EXIT SIGN COMBINATIONS ON THE STRING TO
INDICATE THE EGRESS PATH PER THE LIFE SAFETY DIAGRAMS.
THE CORRIDOR LIGHTING LEVEL SHALL BE AT LEAST 5
FOOT-CANDLES.
A.D.C.B. PROVIDE BATTERY BACKED LIGHTING IN THE VOCRES CONTROL
ROOM. PROVIDE FEEDER FROM 277VAC PANEL LPE, CIRCUIT 9 TO
THIS LIGHTING. THE CORRIDOR LIGHTING LEVEL SHALL BE AT
LEAST 5 FOOT-CANDLES.
A.E. FIRE ALARM:
A.E.A. PROVIDE FIXED TEMPERATURE HEAT DETECTORS ONLY AND NOT RATE
OR RISE DETECTORS.
A.E.B. HEAT DETECTORS SHALL BE LOCATED IN CORRIDORS AND OTHER
AREAS OF THE BUILDING. ON THE SECOND FLOOR LOCATE HEAT
DETECTORS IN CORRIDORS AND REMOVE ALL DOORS FROM THIER
HINGES TO COMMUNICATE AREAS.
A.E.C. CONTRACTOR SHALL PROVIDE A PLAN FOR PROTECTION TO THE FIRE
DEPARTMENT FOR REVIEW AND COORDINATION OF SMOKE AND HEAT
DETECTOR LOCATIONS.
A.E.D. NOTIFICATION SHALL BE REQUIRED IN THE LABS DURING
CONSTRUCTION (TEMPORARY SYSTEM).
A.E.E. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE ALF LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.E.F. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE REAT LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.F. EGRESS:
A.F.A. PROVIDE TEMPORARY EXIT AND EMERGENCY EGRESS LIGHTING WITH
90 MINUTE BATTERY BACKUP FOR BUILDING EGRESS, COORDINATE
LOCATIONS WITH THE AHJ.
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
B
A S
E M
E N
T
FL
O O
R P
LA
N
G-105
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A aE aD aC aB aA bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0 a3b1
DN
UP
DN
UP
DN
DN UP
ALF
1-010
MIRE
1-008A
STAGING
1-009
CORRIDOR
1-904
AAC
1-008D
REAT
1-008E
LAB
1-008B
MECH
1-006
CONTROL
1-008
WOMENS
1-007
STAIR B
1S1
STAIR C
1S2
CONFERENCE
1-004
STORAGE
1-004AOFFICE
1-003C
OFFICE
1-003B
OFFICE
1-003A
OFFICE
1-003
OFFICE
1-005
OFFICE
1-005A
STORAGE
1-012
STORAGE
1-011
OFFICE
1-017
OFFICE
1-013
OFFICE
1-015
COMM
1-014A
STORAGE
1-019A
KITCHENETTE
1-106
MECH
1-901
STORAGE
1-020A
OFFICE
1-018C
STORAGE
1-018B
LOBBY
1-902
CONFERENCE
ROOM
1-019
WOMENS
1-R02
STAIR A
1S4
STAIR D
1S3
MENS
1-R01
OFFICE
1-018A
OFFICE
1-018
ENTRY
1-900
CONFERENCE
1-020
ELEC
1-014
CORRIDOR
1-903
CONTROL
1-008C
1-016
MENS
1-016A
SHOWER
4' 8' 16'03/32"=1'-0"A1
FIRST FLOOR PLAN - SEQUENCE 2
SEQUENCE 2
SEQUENCE OF CONSTRUCTION
A. SEQUENCE TWO:
ALL WORK ASSOCIATED WITH THIS SEQUENCE SHALL BE COMPLETED IN NO MORE
THAN 120 DAYS.
A.A. CORRIDOR:
A.A.A. TEMPORARY BARRIER SHALL BE CONSTRUCTED ALONG COLUMN LINE
b6 IN THE SOUTH CORRIDOR 0-901.
A.A.B. CORRIDOR SHALL BE KEPT CLEAR OF DEBRIS DURING CONSTRUCTION.
A.A.C. REFER TO SECTIONS FOR SEQUENCE OF WORK IN CORRIDORS.
A.B. LABS:
A.B.A. CONTRACTOR WILL HAVE ACCESS TO LAB FACILITIES VOCRES AND
BATMAN (0-120) DURING THIS CONSTRUCTION SEQUENCE.
A.C. HVAC:
A.C.A. AC-3:
A.C.A.A. REPLACE AC-3 IN MECHANICAL ROOM 1-006 WITH NEW CHW/HW AIR
HANDLING UNIT. REPLACE ASSOCIATED CHW PIPING WITH NEW
PIPING FROM SEQUENCE ONE SYSTEM. ROUTE NEW HW FROM
SEQUENCE ONE SYSTEM. DEMOLISH ALL ASSOCIATED STEAM
PIPING.
A.D. ELECTRICAL:
A.D.A. PANELS:
A.D.A.A. OPEN THE SWITCH AND DISCONNECT THE FEED FROM
SWITCHBOARD MCC-A TO PANEL PPJ. REPLACE THE INTERNAL
BUS-WORK FOR THIS PANEL. RE-FEED THIS PANEL FROM SPARE
FUSED SWITCH 5 IN SWITCHBOARD PDP-A.
A.D.A.B. OPEN THE SWITCH AND DISCONNECT THE FEED FROM
SWITCHBOARD MCC-A TO PANELS PP2, PP-4 AND ROOM 211 AH.
THIS EQUIPMENT IS NO LONGER USED.
A.D.A.C. OPEN THE SWITCH AND DISCONNECT THE FEED FROM
SWITCHBOARD MCC-A TO PANEL PP-1C. REPLACE THE INTERNAL
BUS-WORK FOR PANELS PP-1C, 1-400 AND THE BASEMENT DC
PANEL.
A.D.A.D. DISCONNECT FEEDS FROM SWITCHBOARD PDC-A TO EXISTING AIR
HANDLING UNIT AC-4, FAN RF-4 AND CONDENSER #4.
A.D.A.E. OPEN THE SWITCHES AND DISCONNECT THE FEEDS FROM
SWITCHBOARD MCC-A TO THE 45KVA TRANSFORMER AND
DISCONNECT SWITCH FOR PANEL CP-1B. DISCONNECT THE FEED
FROM SWITCHBOARD MCC-A TO THE DISCONNECT AND 75KVA
TRANSFORMER FOR PANEL PP-100. TEMPORARILY RELOCATE THE
TRANSFORMERS AND DISCONNECT SWITCHES WHILE THE AIR
HANDLER AH-4 DUCT WORK IS REMOVED.
A.D.A.F. DISCONNECT THE FEEDS FROM PANEL PDP-1 TO THE
TRANSFORMER T-24, THE SIREN COMPRESSOR AND PANELS PP-10,
PP-11, PP-12 AND HP-1. DISCONNECT THE FEED WIRING FROM
MCC-A TO PANEL PDP-1. SINCE THE PDP-1 FEED IS TIED DIRECTLY
TO THE BUS-WORK FOR MCC-A (AND NOT THROUGH AN ISOLATING
BREAKER), THE MCC-A SWITCHBOARD WILL NEED TO BE SHUT
DOWN FOR THIS WORK. REMOVE PANEL PDP-1 ON THE STAIRWAY.
A.D.A.G. DISCONNECT FEEDS FROM PANEL PP-1 TO AIR CONDITIONER #3,
CHILLERS AND CONDENSER LOADS. DISCONNECT THE FEED FROM
SWITCHBOARD MCC-A TO PANEL PP-1. REMOVE PANEL PP-1.
A.D.B. SWITCHBOARDS:
A.D.B.A. AFTER AC-4 IS REMOVED, THE LOUVER OPENING ON THE WALL IS
AVAILABLE FOR REMOVING ELECTRICAL EQUIPMENT. DISCONNECT
THE ELECTRICAL FEED FROM SWITCHBOARD PDC-A TO
SWITCHBOARD MCC-A. REMOVE SWITCHBOARD MCC-A.
A.D.B.B. PROVIDE NEW SWITCHBOARD PDC-C IN THE FIRST FLOOR
ELECTRICAL ROOM. PROVIDE A FEED FROM SWITCHBOARD PDC-A
TO SWITCHBOARD PDC-C. USE THE SAME SWITCH THAT MCC-A
WAS CONNECTED TO. REPLACE FUSES AS REQUIRED.
A.D.B.C. PROVIDE NEW SWITCHBOARD PDC-E IN THE FIRST FLOOR
ELECTRICAL ROOM. PROVIDE A FEED FROM A SPARE FUSED
SWITCH ON SWITCHBOARD PDP-A TO SWITCHBOARD PDC-E.
A.D.B.D. RE-INSTALL THE TRANSFORMERS AND DISCONNECT SWITCHES
FOR PANELS PP-100 AND CP1-1B. PROVIDE FEEDS TO THESE
CIRCUITS. UPON COMPLETION OF THESE STEPS, THE LABS CAN BE
OPERATIONAL.
A.E. FIRE ALARM:
A.E.A. PROVIDE TEMPORARY WALL MOUNTED DETECTORS IN ENTRY LOBBY,
DETECTORS MUST BE BETWEEN 4" AND 12" FROM THE CEILING AFTER
THE EXISTING CEILING GRID HAS BEEN REMOVED.
A.E.B. PROVIDE FIXED TEMPERATURE HEAT DETECTORS ONLY AND NOT RATE
OR RISE DETECTORS.
A.E.C. HEAT DETECTORS SHALL BE LOCATED IN CORRIDORS AND OTHER
AREAS OF THE BUILDING. ON THE SECOND FLOOR LOCATE HEAT
DETECTORS IN CORRIDORS AND REMOVE ALL DOORS FROM THIER
HINGES TO COMMUNICATE AREAS.
A.E.D. CONTRACTOR SHALL PROVIDE A PLAN FOR PROTECTION TO THE FIRE
DEPARTMENT FOR REVIEW AND COORDINATION OF SMOKE AND HEAT
DETECTOR LOCATIONS.
A.E.E. NOTIFICATION SHALL BE REQUIRED IN THE LABS DURING
CONSTRUCTION (TEMPORARY SYSTEM).
A.E.F. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE ALF LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.E.G. PROVIDE TEMPORARY SMOKE DETECTOR SERVING THE REAT LAB,
LOCATE DETECTOR OUTSIDE THE LAB DOOR.
A.F. EGRESS:
A.F.A. PROVIDE TEMPORARY EXIT AND EMERGENCY EGRESS LIGHTING WITH
90 MINUTE BATTERY BACKUP FOR BUILDING EGRESS, COORDINATE
LOCATIONS WITH THE AHJ.
S O
LI
C
IT
A
TI
O
N N
O
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
TI
O
N
1 3 5
C
7 9
A
M A
R K
IS
S
U E
D A
TE
S
IZ
E
S U
B M
IT
TE
D B
Y
C O
N
TR
A C
T N
O
SHEET ID
D A
TE
US Army Corps of Engineers
U .S
. A R
M Y
C O
R P
S O
F E
N G
IN
E
E R
S
LO
U
IS
V
IL
LE
, K Y
LO
U
IS
V
IL
LE
D
IS
TR
IC
T
W R
IG
H
T P
A
TT
E R
S O
N A
FB
R
E P
A
IR
F S
D -1
IN
TE
R
IO
R , E
X
TE
R
IO
R , A
N D
H V
A C
FA
C
IL
IT
Y
(Z H
TV
B
D
E
F
G
2 4 6 8 10
JU
LY
W
2Q R
B
FA
-1
3- D
A D V A N C E D
E N
G
IN
E E
R
IN
G C
O N
S U
LT
A
N
TS
M ec ha ni ca l |
E le ct ric al
Pl um bi ng
Fi re P ro te ct io n
D ub lin
R oa d Te l:
(6
) 4
-4
C ol um bu s, O hi o
Fa x:
(6
) 4
-4
NORTH
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
UNCLASSIFIED//FOR OFFICIAL USE ONLY - PROPERTY OF THE US GOVERNMENT, LIMITED REPRODUCTION AND DISSEMINATION TO MINIMUM REQUIRED TO BID AND CONSTRUCT THE PROJECT
H
P
N O
CORRECTED FINAL
07/17/2020
S E
Q U
E N
C E
FI
R S
T
FL
O O
R P
LA
N
G-106
J.
L
E E
K . F
IE
LD
S
E . L
E H
M A aE aD aC aB aA bB bA.2 bA.1 bAbA bC bD bE bF bG bH bJ bK bL bM bN bA.3
E.9
E.1
EX1 1.0 2.0
UP
UP
UP
BAMLAB
0-111
VERITAS
0-114A
FABRICATION
SHOP
0-117
MECH
0-118
STORAGE
0-117A
OFFICE
0-124
LAB
0-120
LAB
0-120B
LAB
0-120A
ELEVATOR
0E1
MENS
0-012
OFFICE
0-119A
OFFICE
0-119B
OFFICE
0-119
LAB
0-126B
LAB
0-126C
LAB
0-126A
STAIR C
0S2
VOCRES
0-116A
MECH
0-902
STORAGE
0-112
SHARC
0-108
0-113
BREAK ROOM
0-103
JAN.
0-904
CORRIDOR
0-906
STORAGE
0-107
LAB
0-102
COMM
0-115A
OFFICE
0-106
LAB
0-110
WOMENS
0-011
VERITAS
CONTROL
0-114
LISTENING…