W912QR20B0021Specs-0001.pdf
PDF 2 MB Posted
- Attached to
- HPW Bldg. 441 at WPAFB, OH
- Solicitation number
- W912QR20B0021
About this file
This is a solicitation for the renovation of HPW Building 441 at Wright-Patterson Air Force Base in Ohio. The estimated construction cost is between $10 million and $25 million. The project involves design/build services. It is a 100% total small business set-aside with a NAICS code of 236220. The solicitation will be available electronically only through the Federal Contract Opportunities website at beta.SAM.gov. The agency is the Department of the Army Corps of Engineers Engineering District Louisville.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912QR20B0021 for the Renovation of HPW Bldg. 441 at WPAFB, OH is hereby modif ied as follow s:
SEE CONTINUATION
1. CONTRACT ID CODE PAGE OF PAGES
1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR20B0021
X 9B. DATED (SEE ITEM 11)
31-Jul-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3.EFFECTIVE DATE
20-Aug-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912QR20B0021Specs-0001
W912QR20B0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMDT 0001 SUMMARY OF CHANGES
Solicitation W912QR20B0021 for the Renovation of HPW Bldg. 441 at WPAFB, OH is hereby modified as follows:
a. The follwing Specification Sections have been revised and replaced in their entirety:
a. 23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE
b. 28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
b. The following Drawings have been revised and replaced in their entirety:
a. FA001
b. FA111
c. FA501
d. M-603
c. The bid acceptance period is hereby changed from 90 calendar days to 120 calendar days.
d. FAR Clause 52.204-24 is hereby added to Section 00 45 00.
e. FAR Clause 52.204-25 is hereby added to Section 00 70 00.
f. The bid due date is hereby changed from 1:00pm ET on 01 September 2020 to 1:00pm ET on 03
September 2020.
g. All other terms and conditions remain unchnaged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 01-Sep-2020 01:00 PM to 03-Sep-2020 01:00 PM.
The offeror acceptance period has increased by 30 from 90 to 120.
SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS
The following have been added by full text:
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (AUG 2020)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in the provision at 52.204-26, Covered Telecommunications Equipment or Services--Representation, or in paragraph (v) of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Items.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [ ] will, [ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--
It [ ] does, [ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures.
(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(End of provision)
The following have been deleted:
52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment.
DEC 2019
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been added by reference:
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2020
The following have been deleted:
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2019
(End of Summary of Changes)
Repair FSD-1 Interior Exterior and HVAC F441 1705011
P2# 476238 Repair FSD-1 Interior, Exterior and HVAC W912QR20B0021 Facility 20441 Wright Patterson AFB Ohio
SECTION 23 64 10
WATER CHILLERS, VAPOR COMPRESSION TYPE
11/16
AMENDMENT 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI 550/590 I-P (2015; ERTA 2016) Performance Rating Of Water-Chilling and Heat Pump Water-Heating Packages Using the Vapor Compression Cycle
AHRI 575 (2008) Method of Measuring Machinery Sound Within an Equipment Space
ANSI/AHRI 460 (2005) Performance Rating of Remote Mechanical-Draft Air-Cooled Refrigerant Condensers
AMERICAN BEARING MANUFACTURERS ASSOCIATION (ABMA)
ABMA 11 (2014) Load Ratings and Fatigue Life for Roller Bearings
ABMA 9 (2015) Load Ratings and Fatigue Life for Ball Bearings
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ANSI/ASHRAE 15 & 34 (2016) ANSI/ASHRAE Standard 15-Safety Standard for Refrigeration Systems and ANSI/ASHRAE Standard 34-Designation and Safety Classification of Refrigerants
ASHRAE 90.1 - IP (2016; ERTA 1-8 2017; INT 1-5 2017) Energy Standard for Buildings Except Low-Rise Residential Buildings
AMERICAN WELDING SOCIETY (AWS)
AWS Z49.1 (2012) Safety in Welding and Cutting and Allied Processes
SECTION 23 64 10 Page 1
ASME INTERNATIONAL (ASME)
ASME BPVC SEC VIII D1 (2017) BPVC Section VIII-Rules for Construction of Pressure Vessels Division 1
ASTM INTERNATIONAL (ASTM)
ASTM A307 (2014; E 2017) Standard Specification for Carbon Steel Bolts, Studs, and Threaded Rod 60 000 PSI Tensile Strength
ASTM B117 (2016) Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM D520 (2000; R 2011) Zinc Dust Pigment
ASTM E84 (2018) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM F104 (2011) Standard Classification System for Nonmetallic Gasket Materials
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA MG 1 (2018) Motors and Generators
NEMA MG 11 (1977; R 2012) Energy Management Guide for Selection and Use of Single Phase Motors
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 .00 06
SUBMITTAL PROCEDURES:
SD-03 Product Data
Water Chiller ; G
Verification of Dimensions
Factory Tests
System Performance Tests
Demonstrations
Water Chiller - Field Acceptance Test Plan
SD-06 Test Reports
Field Acceptance Testing
Water Chiller - Field Acceptance Test Report
Factory Tests
SECTION 23 64 10 Page 2
System Performance Tests
SD-07 Certificates
Refrigeration System ; G
SD-08 Manufacturer's Instructions
Water Chiller - Installation Instructions ; G
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals ; G
SD-11 Closeout Submittals
Energy Efficient Equipment for Chillers ; S
Indoor Air Quality During Construction ; S
Ozone Depleting Substances ; S
1.3 SAFETY REQUIREMENTS
Exposed moving parts, parts that produce high operating temperature, parts which may be electrically energized, and parts that may be a hazard to operating personnel must be insulated, fully enclosed, guarded, or fitted with other types of safety devices. Safety devices must be installed so that proper operation of equipment is not impaired. Welding and cutting safety requirements must be in accordance with AWS Z49.1 .
1.4 DELIVERY, STORAGE, AND HANDLING
Stored items must be protected from the weather, humidity and temperature variations, dirt and dust, or other contaminants. Proper protection and care of all material both before and during installation will be the Contractor's responsibility. Any materials found to be damaged must be replaced at the Contractor's expense. During installation, piping and similar openings must be capped to keep out dirt and other foreign matter.
1.5 PROJECT REQUIREMENTS
1.5.1 Verification of Dimensions
The Contractor must become familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.
PART 2 PRODUCTS
2.1 PRODUCT SUSTAINABILITY CRITERIA
For products in this section, where applicable and to extent allowed by performance criteria, provide and document the following:
2.1.1 Energy Efficient Equipment for Chillers
Provide chillers meeting the efficiency requirements as stated within this section.
SECTION 23 64 10 Page 3
2.1.2 Ozone Depleting Substances
Chillers must not use CFC-based refrigerants, and must have an Ozone Depletion Potential (ODP) no greater than 0.0, with exception to R-123, in conformance with this section.
2.2 STANDARD COMMERCIAL PRODUCTS
AMDT 0001***********************************************************
Materials and equipment will be standard Commercial cataloged products from Trane Technologies.
******************************************************************AMDT 0001
These products must have a two year record of satisfactory field service prior to bid opening. The two year record of service must include applications of equipment and materials under similar circumstances and of similar size. Products having less than a two year record of satisfactory field service will be acceptable if a certified record of satisfactory field service for not less than 6000 hours can be shown. The 6000 hour service record must not include any manufacturer's prototype or factory testing. Satisfactory field service must have been completed by a product that has been, and presently is being sold or offered for sale on the commercial market through the following copyrighted means:
advertisements, manufacturer's catalogs, or brochures.
2.3 MANUFACTURER'S STANDARD NAMEPLATES
Major equipment including chillers, compressors, compressor drivers, condensers, water coolers, receivers, refrigerant leak detectors, heat exchanges, fans, and motors must have the manufacturer's name, address, type or style, model or serial number, and catalog number on a plate secured to the item of equipment. Plates must be durable and legible throughout equipment life. Plates must be fixed in prominent locations with nonferrous screws or bolts.
2.4 ELECTRICAL WORK
a. Provide motors, controllers, integral disconnects, contactors, and controls with their respective pieces of equipment, except controllers indicated as part of motor control centers. Provide electrical equipment, including motors and wiring, as specified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. Manual or automatic control and protective or signal devices required for the operation specified and control wiring required for controls and devices specified, but not shown, must be provided. For packaged equipment, the manufacturer must provide controllers including the required monitors and timed restart.
b. For single-phase motors, provide high-efficiency type, fractional-horsepower alternating-current motors, including motors that are part of a system, in accordance with NEMA MG 11.
c. For polyphase motors, provide squirrel-cage medium induction motors, including motors that are part of a system, and that meet the efficiency ratings for premium efficiency motors in accordance with
NEMA MG 1.
d. Provide motors in accordance with NEMA MG 1 and of sufficient size to drive the load at the specified capacity without exceeding the
SECTION 23 64 10 Page 4 nameplate rating of the motor. Motors must be rated for continuous duty with the enclosure specified. Motor duty requirements must allow for maximum frequency start-stop operation and minimum encountered interval between start and stop. Motor torque must be capable of accelerating the connected load within 20 seconds with 80 percent of the rated voltage maintained at motor terminals during one starting period. Provide motor starters complete with thermal overload protection and other necessary appurtenances. Motor enclosure type may be either TEAO or TEFC.
e. Use adjustable frequency drives for all variable-speed motor applications. Provide variable frequency drives for motors as specified in Section 26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER
600 VOLTS.
f. Provide inverter duty premium efficiency motors for use with variable frequency drives.
2.5 SPLIT-SYSTEM WATER CHILLER, VAPOR COMPRESSION TYPE
Total chiller system must be certified for performance per AHRI 550/590 I-P .
If chiller is not in scope of AHRI 550/590 I-P then chiller must be rated in accordance with AHRI 550/590 I-P. Individual chiller components must be constructed and rated in accordance with the applicable AHRI standards. Chiller system must conform to ANSI/ASHRAE 15 & 34 . The chiller must be ASHRAE 90.1 - IP compliant and meet 10 CFR Part 433, 434 and 435 efficiency performance standards for federal construction. The manufacturer must provide certification of compliance. Chiller must be assembled, leak-tested, charged (refrigerant and oil), and adjusted at the job site in strict accordance with manufacturer's recommendations. Unit components delivered separately must be sealed and charged with a nitrogen holding charge. Unit assembly must be completed in strict accordance with manufacturer's recommendations. Chiller must operate within capacity range and speed recommended by the manufacturer. Parts weighing 50 pounds or more which must be removed for inspection, cleaning, or repair, must have lifting eyes or lugs. Chiller must include all customary auxiliaries deemed necessary by the manufacturer for safe, controlled, automatic operation of the equipment. Chiller's water cooler must be provided with standard water boxes with grooved mechanical or flanged connections.
Chillers must operate at partial load conditions without increased vibration over normal vibration at full load, and must be capable of continuous operation down to minimum capacity. As a minimum, chiller must include the following components as defined in paragraph CHILLER
COMPONENTS.
a. Refrigerant and oil
b. Structural base
c. Chiller refrigerant circuit
d. Controls package
f. Tools
2.5.1 Compressor-Chiller Unit
As a minimum, the compressor-chiller unit must include the following
SECTION 23 64 10 Page 5 components as defined in paragraph CHILLER COMPONENTS.
a. Scroll or rotary screw compressor
b. Compressor driver, electric motor
c. Compressor driver connection
d. Water cooler (evaporator)
2.5.2 Condensing Unit
As a minimum, the condensing unit must include the following components as defined in paragraph CHILLER COMPONENTS.
a. Scroll, reciprocating, or rotary screw compressor
b. Compressor driver, electric motor
c. Compressor driver connection
d. Air or water cooled condenser
2.5.3 Remote Air-Cooled Condenser
Condenser must be a factory-fabricated and assembled unit, consisting of coils, fans, and condenser fan motors. Condenser must be rated in accordance with ANSI/AHRI 460 . Unless the condenser coil is completely protected through inherent design, louvered panel coil guards must be provided by the manufacturer to prevent physical damage to the coil.
Manufacturer must certify that the condenser and associated equipment are designed for the submitted condensing temperature. For design conditions, if matched combination catalog ratings matching remote condensers to compressors are not available, the Contractor must furnish a crossplotting of the gross heat rejection of the condenser against the gross heat rejection of the compressor, for the design conditions to show the compatibility of the equipment furnished.
2.5.3.1 Condenser Casing
Condenser casing must be aluminum not less than 0.040 inch or hot-dip galvanized steel not lighter than 18 gauge 0.0516 inch . Condensers having horizontal air discharge must be provided with discharge baffle to direct air upward, constructed of the same material and thickness as the casing.
2.5.3.2 Coil
Condenser coil may be of the extended-surface fin-and-tube type and must be constructed of seamless copper tubes with compatible aluminum fins.
Fins must be soldered or mechanically bonded to the tubes and installed in a metal casing. Coils must be circuited and sized for a minimum of 5 degrees F subcooling and full pumpdown capacity. Coil must be factory leak and pressure tested after assembly in accordance with ANSI/ASHRAE 15 & 34 . As an option, t he condenser coil may be of the microchannel heat exchanger technology (MCHX) type consisting of a series of flat tubes containing a series of multiple, parallel flow microchannels layered between the refrigerant manifolds in a two-pass arrangement.
Provide coils constructed of aluminum alloys for fins, tubes, and manifolds. Coil must be factory leak and pressure tested after assembly
SECTION 23 64 10 Page 6 in accordance with ANSI/ASHRAE 15 & 34 .
2.5.3.3 Fans
Provide centrifugal or propeller type fans as best suited for the application. Fans must be direct driven. Fans must be statically and dynamically balanced.
2.5.3.4 Condenser Sizing
Size condensers for full capacity at 30 degrees F temperature difference between entering outside air and condensing refrigerant. Subcooling must not be considered in determining compressor and condenser capacities. For design conditions, submit a cross-plot of net refrigeration effect of compressor to establish net refrigeration effect and compatibility of equipment furnished.
2.5.3.5 Low Ambient Control
Provide factory mounted head pressure control for operation during low ambient conditions. Head pressure must be controlled by fan cycling or fan speed control. Low ambient control must permit compressor operation below 40 degrees F .
2.5.3.6 High Ambient Unloading
Provide unloading capability to allow operation in high ambient conditions 20 degrees F above design conditions.
2.6 CHILLER COMPONENTS
2.6.1 Refrigerant and Oil
Refrigerants must be one of the fluorocarbon gases. Refrigerants must have number designations and safety classifications in accordance with ANSI/ASHRAE 15 & 34 . Refrigerants classified by the EPA as Class 2 must not be allowed with the exception of R-123. The ODP must be in accordance with the "Montreal Protocol On Substances That Deplete The Ozone Layer," September 1987, as amended through 2000, sponsored by the United Nations Environment Programme.
2.6.2 Structural Base
Chiller and individual chiller components must be provided with a factory-mounted structural steel base (welded or bolted) or support legs. Chiller and individual chiller components must be isolated from the building structure by means of vibration isolators with published load ratings. Vibration isolators must have isolation characteristics as recommended by the manufacturer for the unit supplied and the service intended.
2.6.3 Chiller Refrigerant Circuit
Chiller refrigerant circuit must be completely piped and factory leak tested in accordance with ANSI/ASHRAE 15 & 34 . For multicompressor units, not less than 2 independent refrigerant circuits must be provided.
Circuit must include as a minimum a combination filter and drier, combination sight glass and moisture indicator, an electronic or thermostatic expansion valve with external equalizer or float valve, SECTION 23 64 10 Page 7 charging ports, compressor service valves for field-serviceable compressors, and superheat adjustment.
2.6.4 Controls Package
Provide chillers with a complete factory-mounted, microprocessor based operating and safety control system. Controls package must contain as a minimum a digital display, an on-auto-off switch, motor starters, variable frequency motor controller, disconnect switches, power wiring, and control wiring. Controls package must provide operating controls, monitoring capabilities, programmable setpoints, safety controls, and interfaces as defined below.
2.6.4.1 Operating Controls
Chiller must be provided with the following adjustable operating controls as a minimum.
a. Leaving chilled water temperature control
b. Adjustable timer or automated controls to prevent a compressor from short cycling
c. Automatic lead/lag controls (adjustable) for multi-compressor units
d. Load limiting
e. System capacity control to adjust the unit capacity in accordance with the system load and the programmable setpoints. Controls must automatically re-cycle the chiller on power interruption.
f. Startup and head pressure controls to allow system operation at all ambient temperatures down to 35 degrees F .
g. Fan sequencing for air-cooled condenser
2.6.4.2 Monitoring Capabilities
During normal operations, the control system must be capable of monitoring and displaying the following operating parameters. Access and operation of display must not require opening or removing any panels or doors.
a. Entering and leaving chilled water temperatures
b. Chilled water flow
d. Self diagnostic
e. Operation status
f. Operating hours
g. Number of starts
h. Compressor status (on or off)
i. Compressor load (percent)
j. Refrigerant discharge and suction pressures
SECTION 23 64 10 Page 8
m. Oil pressure
2.6.4.3 Configurable Setpoints
The control system must be capable of being configured directly at the unit's interface panel. No parameters may be capable of being changed without first entering a security access code. The programmable setpoints must include the following as a minimum:
a. Leaving Chilled Water Temperature
c. Time Clock/Calendar Date
2.6.4.4 Safety Controls with Manual Reset
Chiller must be provided with the following safety controls which automatically shutdown the chiller and which require manual reset.
a. Low chilled water temperature protection
b. High condenser refrigerant discharge pressure protection
c. Low evaporator pressure protection
d. Chilled water flow detection
e. High motor winding temperature protection
f. Low oil flow protection if applicable
k. Motor current overload and phase loss protection
2.6.4.5 Safety Controls with Automatic Reset
Chiller must be provided with the following safety controls which automatically shutdown the chiller and which provide automatic reset.
a. Over/under voltage protection
b. Chilled water flow interlock
e. Phase reversal protection
2.6.4.6 Remote Alarm
During the initiation of a safety shutdown, a chiller's control system must be capable of activating a remote alarm bell. In coordination with the chiller, the Contractor must provide an alarm circuit (including transformer if applicable) and a minimum 4 inch diameter alarm bell.
Alarm circuit must activate bell in the event of machine shutdown due to the chiller's monitoring of safety controls. The alarm bell must not sound for a chiller that uses low-pressure cutout as an operating control.
2.6.4.7 Utility Monitoring and Control System Interface
Provide a Utility Monitoring and Control System (UMCS) interface meeting the requirements of Section Section 23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL SYSTEMS. The interface must
SECTION 23 64 10 Page 9 provide all system operating conditions, capacity controls, and safety shutdown conditions as network points. In addition, the following points must be overridable via the network interface:
a. Unit Start/Stop
b. Leaving Chilled Water Temperature Setpoint
2.6.5 Compressor(s)
2.6.5.1 Rotary Screw Compressor(s)
Compressors must operate stably for indefinite time periods to at least 25 percent capacity reduction without gas bypass external to the compressor.
Provision must be made to insure proper lubrication of bearings and shaft seals on shutdown with or without electric power supply. Rotary screw compressors must include:
a. An open or hermetic, positive displacement, oil-injected design directly driven by the compressor driver. Allow access to internal compressor components for repairs, inspection, and replacement of parts.
b. Rotors must be solid steel, possessing sufficient rigidity for proper operation.
c. A maximum rotor operating speed no greater than 3600 RPM. Provide cast iron rotor housing.
d. Casings of cast iron, precision machined for minimal clearance about periphery of rotors with minimal clearance at rotor tops and rotor ends.
e. A lubrication system of the forced-feed type that provides oil at the proper pressure to all parts requiring lubrication.
f. Bearing housing must be conservatively loaded and rated for an L(10) life of not less than 200,000 hours. Shaft main bearings of the sleeve type with heavy duty bushings or rolling element type in accordance with ABMA 9 or ABMA 11.
g. A differential oil pressure or flow cutout to allow the compressor to operate only when the required oil pressure or flow is provided to the bearings.
h. A temperature- or pressure-initiated, hydraulically actuated, single-slide-valve, capacity-control system to provide minimum automatic capacity modulation from 100 percent to 15 percent.
i. An oil separator and oil return system to remove oil entrained in the refrigerant gas and automatically return the oil to the compressor.
j. Crankcase oil heaters must be provided.
2.6.6 Compressor Driver, Electric Motor
Components such as motors, starters, and wiring must be in accordance with paragraph ELECTRICAL WORK. Motor starter S must be unit mounted as indicated with starter type, wiring, and accessories coordinated with the
SECTION 23 64 10 Page 10 chiller manufacturer.
2.6.7 Air-Cooled Condenser Coil
Condenser coil must be of the extended-surface fin-and-tube type and may be constructed of seamless copper tubes with compatible aluminum fins.
Fins must be soldered or mechanically bonded to the tubes and installed in a metal casing. Coils must be circuited and sized for a minimum of 5 degrees F subcooling and full pumpdown capacity. Coil must be factory leak and pressure tested after assembly in accordance with ANSI/ASHRAE 15 & 34 . As an option, t he condenser coil may be of the microchannel heat exchanger technology (MCHX) type consisting of a series of flat tubes containing a series of multiple, parallel flow microchannels layered between the refrigerant manifolds in a two-pass arrangement.
Provide coils constructed of aluminum alloys for fins, tubes, and manifolds. Coil must be factory leak and pressure tested after assembly in accordance with ANSI/ASHRAE 15 & 34 .
2.6.8 Receivers
Receiver must bear a stamp certifying compliance with ASME BPVC SEC VIII D1 and must meet the requirements of ANSI/ASHRAE 15 & 34 . Inner surfaces must be thoroughly cleaned by sandblasting or other approved means. Each receiver must have a storage capacity not less than 20 percent in excess of that required for the fully-charged system. Each receiver must be equipped with inlet, outlet drop pipe, drain plug, purging valve, relief valves of capacity and setting required by ANSI/ASHRAE 15 & 34 , and two bull's eye liquid-level sight glasses. Sight glasses must be in the same vertical plane, 90 degrees apart, perpendicular to the axis of the receiver, and not over 3 inches horizontally from the drop pipe measured along the axis of the receiver. In lieu of bull's eye sight glass, external gauge glass with metal glass guard and automatic closing stop valves may be provided.
2.6.9 Tools
One complete set of special tools, as recommended by the manufacturer for field maintenance of the system, must be provided. Tools must be mounted on a tool board in the equipment room or contained in a toolbox as directed by the Contracting Officer.
2.7 ACCESSORIES
2.7.1 Refrigerant Leak Detector
Detector must be the continuously-operating, halogen-specific type.
Detector must be appropriate for the refrigerant in use. Detector must be specifically designed for area monitoring and must include two sampling points installed where indicated. Detector design and construction must be compatible with the temperature, humidity, barometric pressure and voltage fluctuations of the operating area. Detector must have an adjustable sensitivity such that it can detect refrigerant at or above 3 parts per million (ppm). Detector must be supplied factory-calibrated for the appropriate refrigerant(s). Detector must be provided with an alarm relay output which energizes when the detector detects a refrigerant level at or above the TLV-TWA (or toxicity measurement consistent therewith) for the refrigerant(s) in use. The detector's relay must be capable of initiating corresponding alarms and ventilation systems as indicated on the drawings. Detector must be provided with a failure relay output that
SECTION 23 64 10 Page 11 energizes when the monitor detects a fault in its operation.
2.7.2 Refrigerant Relief Valve/Rupture Disc Assembly
The assembly must be a combination pressure relief valve and rupture disc designed for refrigerant usage. The assembly must be in accordance with ASME BPVC SEC VIII D1 and ANSI/ASHRAE 15 & 34 . The assembly must be provided with a pressure gauge assembly which will provide local indication if a rupture disc is broken. Rupture disc must be the non-fragmenting type.
2.7.3 Refrigerant Signs
Refrigerant signs must be a medium-weight aluminum type with a baked enamel finish. Signs must be suitable for indoor or outdoor service.
Signs must have a white background with red letters not less than 0.5 inches in height.
2.7.3.1 Installation Identification
Each new refrigerating system must be provided with a refrigerant sign which indicates the following as a minimum:
a. Contractor's name.
b. Refrigerant number and amount of refrigerant.
c. The lubricant identity and amount.
d. Field test pressure applied.
2.7.3.2 Controls and Piping Identification
Refrigerant systems containing more than 110 lb of refrigerant must be provided with refrigerant signs which designate the following as a minimum:
a. Valves or switches for controlling the refrigerant flow , the ventilation system, and the refrigerant compressor(s).
b. Pressure limiting device(s).
2.7.4 Gaskets
Gaskets must conform to ASTM F104 - classification for compressed sheet with nitrile binder and acrylic fibers for maximum 700 degrees F service.
2.7.5 Bolts and Nuts
Bolts and nuts, except as required for piping applications, must be in accordance with ASTM A307. The bolt head must be marked to identify the manufacturer and the standard with which the bolt complies in accordance with ASTM A307.
2.8 FABRICATION
2.8.1 Factory Coating
Unless otherwise specified, equipment and component items, when fabricated from ferrous metal, must be factory finished with the manufacturer's
SECTION 23 64 10 Page 12 standard finish, except that items located outside of buildings must have weather resistant finishes that will withstand 125 hours exposure to the salt spray test specified in ASTM B117 using a 5 percent sodium chloride solution. Immediately after completion of the test, the specimen must show no signs of blistering, wrinkling, cracking, or loss of adhesion and no sign of rust creepage beyond 1/8 inch on either side of the scratch mark. Cut edges of galvanized surfaces where hot-dip galvanized sheet steel is used must be coated with a zinc-rich coating conforming to ASTM D520, Type I.
2.8.2 Factory Applied Insulation
Chiller must be provided with factory installed insulation on surfaces subject to sweating including the water cooler, suction line piping, economizer, and cooling lines. Insulation on heads of coolers may be field applied, however it must be installed to provide easy removal and replacement of heads without damage to the insulation. Where motors are the gas-cooled type, factory installed insulation must be provided on the cold-gas inlet connection to the motor per manufacturer's standard practice. Factory insulated items installed outdoors are not required to be fire-rated. As a minimum, factory insulated items installed indoors must have a flame spread index no higher than 75 and a smoke developed index no higher than 150. Factory insulated items (no jacket) installed indoors and which are located in air plenums, in ceiling spaces, and in attic spaces must have a flame spread index no higher than 25 and a smoke developed index no higher than 50. Flame spread and smoke developed indexes must be determined by ASTM E84. Insulation must be tested in the same density and installed thickness as the material to be used in the actual construction. Material supplied by a manufacturer with a jacket must be tested as a composite material. Jackets, facings, and adhesives must have a flame spread index no higher than 25 and a smoke developed index no higher than 50 when tested in accordance with ASTM E84.
2.9 FACTORY TESTS
2.9.1 Chiller Performance Test
The Contractor and proposed chiller manufacturer shall be responsible for performing the chiller factory test to validate the specified full load capacity, full load EER, and NPLV in accordance with AHRI 550/590 I-P except as indicated. The Contractor and chiller manufacturer must provide to the Government a certified chiller factory test report in accordance with AHRI 550/590 I-P to confirm that the chiller performs as specified.
Tests must be conducted in an AHRI certified test facility in conformance with AHRI 550/590 I-P procedures and tolerances, except as indicated. At a minimum, chiller capacity must be validated to meet the scheduled requirements indicated on the drawings. Tolerance or deviation must be in strict accordance with AHRI 550/590 I-P . Stable operation at minimum load of 10 percent of total capacity must be demonstrated during the factory test.
2.9.1.1 Temperature Adjustments
Temperature adjustments must adhere to AHRI 550/590 I-P to adjust from the design fouling factor to the clean tube condition. Test temperature adjustments must be verified prior to testing by the manufacturer. There must be no exceptions to conducting the test with clean tubes with the temperature adjustments per AHRI 550/590 I-P . The manufacturer must clean the tubes prior to testing to obtain a test fouling factor of 0.0000.
SECTION 23 64 10 Page 13
2.9.1.2 Test Instrumentation
The factory test instrumentation must be per AHRI 550/590 I-P and the calibration must be traceable to the National Institute of Standards and Technology.
2.9.1.3 Equipment Adjustments
If the equipment fails to perform within allowable tolerances, the manufacturer must be allowed to make necessary revisions to his equipment and retest as required. The manufacturer shall assume all expenses incurred by the Government to witness the retest.
2.9.2 Chiller Sound Test
Chillers must be sound tested at the factory prior to shipment to confirm the sound pressure level specified herein. Tests and data must be conducted and measured in strict accordance with AHRI 575 at the full load system operating conditions. The chiller sound pressure level, in decibels (dB), with a reference pressure of 20 micropascals, must not exceed 85 dB, A weighted. Ratings must be in accordance with AHRI 575 .
No reduction of entering condenser water temperature or raising of leaving chilled water temperature will be allowed. A minimum of 75 percent of the sound data points must be taken along the length of the machine, and established as the minimum percentage of total possible points used to determine sound levels. In the event that the chiller does not meet the dBA sound pressure level, the manufacturer shall, at his expense, provide sufficient attenuation to the machine to meet the specified value. This attenuation must be applied in such a manner that it does not hinder the operation or routine maintenance procedures of the chiller. The attenuation material, adhesives, coatings, and other accessories must have surface burning characteristics as determined by ASTM E84.
2.10 SUPPLEMENTAL COMPONENTS/SERVICES
2.10.1 Chilled Water Piping and Accessories
Chilled and condenser water piping and accessories must be provided and installed in accordance with Section 23 64 26 CHILLED, CHILLED-HOT, AND
CONDENSER WATER PIPING SYSTEMS.
2.10.2 Refrigerant Piping
Refrigerant piping for split-system water chillers must be provided and installed in accordance with Section 23 23 00 REFRIGERANT PIPING.
2.10.3 Temperature Controls
Chiller control packages must be fully coordinated with and integrated into the temperature control system indicated in Section 23 09 23.02
BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL SYSTEMS.
PART 3 EXECUTION
3.1 CONSTRUCTION-RELATED SUSTAINABILITY CRITERIA
For construction activities in this section, provide and document the following:
SECTION 23 64 10 Page 14
3.1.1 Indoor Air Quality During Construction
Provide documentation showing that after construction ends, and prior to occupancy, new filters were installed.
3.2 INSTALLATION
Installation of water chiller systems including materials, installation, workmanship, fabrication, assembly, erection, examination, inspection, and testing must be in accordance with the manufacturer's written installation instructions, including the following:
(1) Water chiller - installation instructions
3.2.1 Installation Instructions
Provide manufacturer's standard catalog data, at least 5 weeks prior to the purchase or installation of a particular component, highlighted to show features such as materials, dimensions, options, performance and efficiency. Data must include manufacturer's recommended installation instructions and procedures. Data must be adequate to demonstrate compliance with contract requirements.
3.2.2 Vibration Isolation
If vibration isolation is specified for a unit, vibration isolator literature must be included containing catalog cuts and certification that the isolation characteristics of the isolators provided meet the manufacturer's recommendations.
3.2.3 Verification of Dimensions
Provide a letter including the date the site was visited, conformation of existing conditions, and any discrepancies found.
3.2.4 System Performance Test Schedules
Provide a schedule, at least 2 weeks prior to the start of related testing, for the system performance tests. The schedules must identify the proposed date, time, and location for each test.
3.2.5 Certificates
Where the system, components, or equipment are specified to comply with requirements of AGA, NFPA, ARI, ASHRAE, ASME, or UL, proof of such compliance must be provided. The label or listing of the specified agency must be acceptable evidence. In lieu of the label or listing, a written certificate from an approved, nationally recognized testing organization equipped to perform such services, stating that the items have been tested and conform to the requirements and testing methods of the specified agency may be submitted. When performance requirements of this project's drawings and specifications vary from standard ARI rating conditions, computer printouts, catalog, or other application data certified by ARI or a nationally recognized laboratory as described above must be included.
If ARI does not have a current certification program that encompasses such application data, the manufacturer may self certify that his application data complies with project performance requirements in accordance with the specified test standards.
SECTION 23 64 10 Page 15
3.2.6 Operation and Maintenance Manuals
Provide Six complete copies of an operation manual in bound 8 1/2 by 11 inch booklets listing step-by-step procedures required for system startup, operation, abnormal shutdown, emergency shutdown, and normal shutdown at least 4 weeks prior to the first training course. The booklets must include the manufacturer's name, model number, and parts list. The manuals must include the manufacturer's name, model number, service manual, and a brief description of all equipment and their basic operating features. Six complete copies of maintenance manual in bound 8 1/2 by 11 inch booklets listing routine maintenance procedures, possible breakdowns and repairs, and a trouble shooting guide. The manuals must include piping and equipment layouts and simplified wiring and control diagrams of the system as installed.
3.2.7 Connections to Existing Systems
Notify the Contracting Officer in writing at least 15 calendar days prior to the date the connections are required. Obtain approval before interrupting service. Furnish materials required to make connections into existing systems and perform excavating, backfilling, compacting, and other incidental labor as required. Furnish labor and tools for making actual connections to existing systems.
3.2.8 Refrigeration System
3.2.8.1 Equipment
Refrigeration equipment and the installation thereof must conform to ANSI/ASHRAE 15 & 34 . Necessary supports must be provided for all equipment, appurtenances, and pipe as required, including frames or supports for compressors, pumps, cooling towers, condensers, water coolers, and similar items. Compressors must be isolated from the building structure. If mechanical vibration isolators are not provided, vibration absorbing foundations must be provided. Each foundation must include isolation units consisting of machine and floor or foundation fastenings, together with intermediate isolation material. Other floor-mounted equipment must be set on not less than a 6 inch concrete pad doweled in place. Concrete foundations for floor mounted pumps must have a mass equivalent to three times the weight of the components, pump, base plate, and motor to be supported. In lieu of concrete pad foundation, concrete pedestal block with isolators placed between the pedestal block and the floor may be provided. Concrete pedestal block must be of mass not less than three times the combined pump, motor, and base weights.
Isolators must be selected and sized based on load-bearing requirements and the lowest frequency of vibration to be isolated. Lines connected to pumps mounted on pedestal blocks must be provided with flexible connectors.