This document provides details on a forthcoming Request for Proposal for cafeteria and conference center renovations at a military base in Ohio. The U.S. Army Corps of Engineers Louisville District will issue the RFP to renovate approximately 8,000 square feet, including replacing ceilings, floors, exhaust hoods, furniture and audiovisual equipment at the cafeteria and improving the entryway, conference room, and restrooms at the conference center. The contract duration is 360 calendar days with a firm-fixed price. Offerors must be registered in the Joint Certification Program and certified as U.S. owned with U.S. citizen personnel to be considered responsive. The RFP will be available on beta.sam.gov and awarded without discussions to the lowest priced bid. The North American Industry Classification System code is 236220 and it is set aside for small businesses. The project value is estimated between $1-5 million.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY/RESERVE BRANCH
ATTN: KELSIE HALL
600 DR M L KING JR PL RM 821
LOUISVILLE KY 40202-2239
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR20B0018 for SRM Lima Abrams Center and Cafeteria Renovations is hereby amended as follow s:
SEE CONTINUATION
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912QR20B0018
X 9B. DATED (SEE ITEM 11)
15-Jul-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
U0003
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Aug-2020
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE 964859
FACILITY CODECODE
EMAIL:TEL:
W912QR20B0018-0003
W912QR20B0018
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF CHANGES AMDT 0003
The due date for bids is hereby changed from 02:00 PM ET on 3 September 2020 to 02:00 PM ET on 17 September 2020.
Abrams Center
1. The following Drawings have been revised and replaced in their entirety:
a. G-001 COVER SHEET
b. LP101 LAYOUT PLAN
c. AD110 DEMOLITION FLOOR PLAN
d. A-110 NEW WORK PLAN
e. A-400 ENLARGED RESTROOM PLANS
f. A-420 CASEWORK ELEVATIONS
g. A-483 INTERIOR ELEVATIONS
h. A-610 FINISH SCHEDLE AND KEYS
i. F-110 LIFE SAFETY PLAN
2. The following Drawings have been added new in their entirety:
a. CS101 LAYOUT PLAN
3. The following Specification Sections have been revised and replaced in their entirety:
a. 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
b. 02 41 00 DEMOLITION
c. 08 14 00 WOOD DOORS
d. 11 46 01.00 48 FOOD SERVICE EQUIPMENT
e. 12 24 13 ROLLER SHADES
4. All other conditions and terms remain unchanged.
CAFETERIA RENOVATION
1. The following Drawings have been revised and replaced in their entirety:
a. AD111 EXISTING EQUIPMENT SCHEDULE
b. A-140 REFLECTED CEILING PLAN
c. A-200 BUILDING ELEVATIONS
d. A-402 NEW WORK EQUIPMENT SCHEDULE
e. A-500 DOOR TYPES, FRAMES TYPES & SCHEDULES
f. A-540 WALL TYPES & DETAILS
g. A-610 FINISH SCHEDULE & KEYS
h. PD111 PLUMBING DEMOLITION PLAN
i. PP111 PLUMBING PLAN
j. MD110 FLOOR PLAN – MECHANICAL DEMOLITION
k. MH110 FLOOR PLAN – MECHANICAL NEW WORK
l. M-601 MECHANICAL CONTROLS
m. ED111 PARTIAL FLOOR PLAN – EXISTING ELECTRICAL
W912QR20B0018
n. EP410 ENLARGED FLOOR PLANS – POWER
o. EP701 ELECTRICAL PANEL SCHEDULES
p. EY601 AUDIO/VISUAL DETAILS AND DIAGRAMS
2. The following Specification Sections have been revised and replaced in their entirety:
a. 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
b. 02 41 00 DEMOLITION
c. 08 14 00 WOOD DOORS
d. 09 90 00 PAINTS AND COATINGS
e. 11 46 01.01 LISTAPPENDIX TO FOOD SERVICE EQUIPMENT
3. All other conditions and terms remain unchanged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 03-Sep-2020 02:00 PM to 17-Sep-2020 02:00 PM.
(End of Summary of Changes)
1 - P2 #466520, CAFETERIA RENOVATION Solicitation No. W912QR20B0018
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
05/18
AMENDMENT 0003
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. FEDERAL AVIATION ADMINISTRATION (FAA)
FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and Lighting
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2015) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL PROCEDURES:
1.3 DOD CONDITION OF READINESS (COR)
DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots (60mph or 95 km/hr) or greater.
Contact the Contracting Officer for the current COR setting.
SECTION 01 50 00 Page 1 0164101CAFETERIA
Monitor weather conditions a minimum of twice a day and take appropriate actions according to the aproved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.
Unless otherwise directed by the Contracting Officer, comply with:
a. Condition FOUR (Sustained winds of 50 knots or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 4 feet high. Remove all debris, trash, or objects that could become missile hazards.
b. Condition THREE (Sustained winds of 50 knots or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.
c. Condition TWO (Sustained winds of 50 knots or greater expected within 24 hours): Curtail or cease routine activities until securing operation is complete. Reinforce or remove form work and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite. Expend every effort to clear all missile hazards and loose equipment from general base areas.
d. Condition ONE. (Sustained winds of 50 knots or greater expected within 12 hours): Secure the jobsite, and leave Government premises.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Within one calendar day of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with
01 35 26.00 06 GOVERNMENTAL SAFETY REQUIREMENTS.
2.1.2 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of contruction hazards. Signs must require unauthorized persons to keep out of the construction site.
Correct the data required by safety signs daily.
SECTION 01 50 00 Page 2 0164101CAFETERIA
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this contract in accordance with EM 385-1-1 Section 04.
Construct with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic are be avoided. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
Amendment 0003*************************************************************
2.3 FENCING
Provide temporary chain link fencing around the contractor staging area.
At the Contractor's option, the construction site may also be enclosed.
Provide safety fencing at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic. Specific fencing requirements are as described herein. All fencing will meet the requirements of EM 385-1-1 .
**************************************************************Amendment 0003
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches. Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Chain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases toform long spens as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any
SECTION 01 50 00 Page 3 0164101CAFETERIA direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various sufaces such as sand, soil, ashpalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Fencing and posts must be completely removed at the completion of construction and any surfaces disturbed or damaged must be restored to its original condition. Underground utilities must be located and identified prior to setting fence posts. Fence must be equipped with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.
PART 3 EXECUTION
3.1 EMPLOYEE PARKING
Construction contract employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will be within reasonable walking distance of the construction site. Employee parking must not interfere with existing and established parking requirements of the government installation.
3.2 TEMPORARY BULLETIN BOARD
Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.
3.3 AVAILABILITY AND USE OF UTILITY SERVICES
3.3.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
3.3.2 Payment for Utility Services
Reasonable amounts of the following utilities will be made available without charge.
3.3.3 Telephone
Make arrangements and pay all costs for telephone facilities desired.
SECTION 01 50 00 Page 4 0164101CAFETERIA
3.3.4 Obstruction Lighting of Cranes
Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. Light construction and installation must comply with FAA AC 70/7460-1 . Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.
3.3.5 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials weekly to minimize potential hazards.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close any thoroughfare or interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. . Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.
3.4.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the Contracting Officer.
SECTION 01 50 00 Page 5 0164101CAFETERIA
3.4.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19.00 06 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.5 CONTRACTOR'S TEMPORARY FACILITIES
3.5.1 Quality Control Manager Records and Field Office
Provide on the jobsite an office with approximately 100 square feet of useful floor area for the exclusive use of the QC Manager. Provide a weathertight structure with adequate heating and cooling, toilet facilities, lighting, ventilation, a 4 by 8 foot plan table, a standard size office desk and chair, computer station, and working communications facilities. Provide either a 1,500 watt radiant heater and a window-mounted air conditioner rated at 9,000 Btus minimum or a window-mounted heat pump of the same minimum heating and cooling ratings.
Provide a door with a cylinder lock and windows with locking hardware.
Make utility connections. Locate as directed. File quality control records in the office and make available at all times to the Government.
After completion of the work, remove the entire structure from the site.
3.5.2 Safety Systems
Protect the integrity of any installed safety systems or personnel safety devices. Obtain prior approval from Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.5.3 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.5.4 Storage Area
Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored brown, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.
3.5.5 Supplemental Storage Area
Upon request, and pending availability, the Contracting Officer will
SECTION 01 50 00 Page 6 0164101CAFETERIA designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. The area will be maintained in an clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.
3.5.6 Appearance of Trailers
a. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Paint in accordance with facility standards and maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.
3.5.7 Maintenance of Storage Area
a. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, and will be traversed with construction equipment or other vehicles, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.
b. Cut grass (or annual weeds) within the construction and storage sites to a maximum 4 inch height at least once a week during the growing season, whether or not area is visible to the public to assist in rodent control. Trim the grass around fences at time of grass cutting. Maintain grass or weeds on stockpiled earth as descried above.
3.5.8 Security Provisions
Provide adequate outside security lighting at the temporary facilities.
The Contractor will be responsible for the security of its own equipment.
3.5.9 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.5.9.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings
SECTION 01 50 00 Page 7 0164101CAFETERIA in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
Amendment 0003***************************************************************
3.6 SECTION NOT USED
***************************************************************Amendment 0003
3.7 PLANT COMMUNICATIONS
Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.
3.8 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, removefrom the work site.
3.9 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.10 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
SECTION 01 50 00 Page 8 0164101CAFETERIA
SECTION 02 41 00
DEMOLITION
05/10
AMENDMENT 0003
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 145 (1991; R 2012) Standard Specification for Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes
AASHTO T 180 (2017) Standard Method of Test for Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
SECTION 02 41 00 Page 1 0164101CAFETERIA
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations.
Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.
1.2.3 General Requirements
Do not begin demolition until authorization is received from the Contracting Officer. Remove rubbish and debris from the project site; do not allow accumulations outside. The work includes demolition,, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer.
Coordinate the work of this section with all other work indicated.
Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload pavements to remain. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, and debris from work areas daily.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted. Where burning is permitted, adhere to federal, state, and local regulations.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
SECTION 02 41 00 Page 2 0164101CAFETERIA submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan; G, AE Existing Conditions
SD-07 Certificates
Notification; G, AE
1.6 QUALITY ASSURANCE
Submit timely notification of demolition projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61 , Subpart M.
Notify the the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution. Vacuum and dust the work area daily weed. Sweep pavements as often as necessary to control the spread of debris.
1.7 PROTECTION
1.7.1 Traffic Control Signs
Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.
1.7.2 Protection of Personnel
Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site.
1.8 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the possible conflicting electrical conduits, plumbing lines, the location and extent of existing cracks and other damage and description of surface
SECTION 02 41 00 Page 3 0164101CAFETERIA conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.
b. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.
c. Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:
Soil classification AASHTO M 145
Moisture-density relations AASHTO T 180, Method B or D
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled.
Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified.
Materials shall be designated for reuse onsite whenever possible.
3.1.1 Structures
a. Remove existing structures indicated to be removed entirely.
b. Demolish structures in a systematic manner from the top of the structure to the ground. Demolish concrete walls in small sections.
Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.
c. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, SECTION 02 41 00 Page 4 0164101CAFETERIA except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.3 Paving and Slabs
Remove sawcut concrete and asphaltic concrete paving and slabs including aggregate base as indicated to a depth of 12 inches below existing adjacent grade. Provide neat sawcuts at limits of pavement removal as indicated.
Pavement and slabs designated to be recycled and utilized in this project shall be moved, ground and stored as directed by the Contracting Officer.
Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense.
3.2 DISPOSITION OF MATERIAL
3.2.1 Title to Materials
Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, and removal procedures, and authorization by the Contracting Officer to begin demolition. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.2.2 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable material.
3.3 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.4 DISPOSAL OF REMOVED MATERIALS
3.4.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified in the Waste Management Plan.
Storage of removed materials on the project site is prohibited.
3.4.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
Amendment 0003*************************************************************
SECTION 02 41 00 Page 5 0164101CAFETERIA
3.4.3 Removal to Spoil Areas on Government Property
No spoil areas or waste areas exist on the Government Property.
Contractor to remove all waste and spoil material at Contractor's expense and in accordance with all local ordinances and regulations.
**************************************************************Amendment 0003
3.4.4 Removal from Government Property
Transport waste materials removed from demolished and from Government property for legal disposal. Dispose of waste soil as directed.
-- End of Section --
SECTION 02 41 00 Page 6 0164101CAFETERIA
SECTION 08 14 00
WOOD DOORS
08/16
AMENDMENT 0003
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN FOREST FOUNDATION (AFF)
ATFS STANDARDS (2015) American Tree Farm System Standards of Sustainability 2015-2020
ARCHITECTURAL WOODWORK INSTITUTE (AWI)
AWI AWS (2nd Edition) Architectural Woodwork Standards
CALIFORNIA AIR RESOURCES BOARD (CARB)
CARB 93120 (2007) Airborne Toxic Control Measure (ATCM) to Reduce Formaldehyde Emissions from Composite Wood Products
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH SECTION 01350 (2004; Add 2004-01) Standard Practice for the Testing Of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers
CSA GROUP (CSA)
CSA Z809-08 (R2013) Sustainable Forest Management
FOREST STEWARDSHIP COUNCIL (FSC)
FSC STD 01 001 (2000) Principles and Criteria for Forest Stewardship
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 80 (2016) Standard for Fire Doors and Other Opening Protectives
PROGRAMME FOR ENDORSEMENT OF FOREST CERTIFICATION (PEFC)
PEFC ST 2002:2013 (2015) PEFC International Standard Chain of Custody of Forest Based Products Requirements
SECTION 08 14 00 Page 1 0164101CAFETERIA
SUSTAINABLE FOREST INITIATIVE (SFI)
SFI 2015-2019 (2015) Standards, Rules for Label Use, Procedures and Guidance
WINDOW AND DOOR MANUFACTURERS ASSOCIATION (WDMA)
ANSI/WDMA I.S.1A (2013) Interior Architectural Wood Flush Doors
ANSI/WDMA I.S.6A (2013) Interior Architectural Stile and Rail Doors
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 06 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Doors; G, RO
Submit drawings or catalog data showing each type of door unit.
Indicate within drawings and data the door types and construction, sizes, thickness, methods of assembly and glazing,.
SD-03 Product Data
Doors; G, RO
Accessories
Water-resistant Sealer
Sample Warranty
SD-04 Samples
Doors
Prior to the delivery of wood doors, submit a sample section of each type of door which shows the stile, rail, veneer, finish, and core construction.
Door Finish Colors; G
Submit a minimum of three color selection samples , minimum 3 by 5 inches in size representing wood stain for selection by the Contracting Officer.
SD-06 Test Reports
Cycle-Slam
Hinge Loading Resistance
SECTION 08 14 00 Page 2 0164101CAFETERIA
Submit cycle-slam test report for doors tested in accordance with ANSI/WDMA I.S.1A , and hinge loading resistance test report for doors tested in accordance with ANSI/WDMA I.S.6A .
SD-07 Certificates
Certificates of Grade
Certified Sustainably Harvested Wood; G
Indoor Air Quality: G, RO
SD-11 Closeout Submittals
Certified Sustainably Harvested Flush Wood Doors
Recycled Content for Door Cores
Indoor Air Quality for Particleboard and Agrifiber Door Cores
Warranty
1.3 CERTIFICATIONS
1.3.1 Certified Wood Grades
Provide certificates of grade from the grading agency.
1.3.2 Certified Sustainably Harvested Wood
Provide wood certified as sustainably harvested by FSC STD 01 001 , ATFS STANDARDS, CSA Z809-08 , SFI 2015-2019 , or other third party program certified by PEFC ST 2002:2013 . Provide a letter of Certification of Sustainably Harvested Wood signed by the wood supplier. Identify certifying organization and their third party program name and indicate compliance with chain-of-custody program requirements. Submit sustainable wood certification data; identify each certified product on a line item basis. Submit copies of invoices bearing certification numbers.
1.3.3 Indoor Air Quality Certification
1.3.3.1 Composite Wood, Wood Structural Panel and Agrifiber Products
For purposes of this specification, composite wood and agrifiber products include particleboard, medium density fiberboard (MDF), wheatboard, strawboard, panel substrates, and door cores. Products must contain no added urea-formaldehyde resins. Provide products certified to meet emissions requirements of either CARB 93120 or CDPH SECTION 01350 (limit requirements for either office or classroom spaces regardless of space type). Provide current product certification documentation from certification body.
1.4 DELIVERY, STORAGE, AND HANDLING
Deliver doors to the site in an undamaged condition and protect against damage and dampness. Stack doors flat under cover. Support on blocking, a minimum of 4 inch thick, located at each end and at the midpoint of the door. Store doors in a well-ventilated building so that they will not be
SECTION 08 14 00 Page 3 0164101CAFETERIA exposed to excessive moisture, heat, dryness, direct sunlight, or extreme changes of temperature and humidity. Do not store in a building under construction until concrete, masonry work, and plaster are dry. Replace defective or damaged doors with new ones.
1.5 WARRANTY
Warrant doors free of defects as set forth in the door manufacturer's standard door warranty.
PART 2 PRODUCTS
2.1 PRODUCT SUSTAINABILITY CRITERIA
For products in this section, where applicable and to extent allowed by performance criteria, provide and document the following:
2.1.1 Certified Sustainably Harvested Wood
Certified sustainably harvested wood is identified for some products in this section. Other products listed in this section may be available as certified sustainably harvested wood; identify those products that meet project requirements for certified sustainably harvested wood.
2.1.2 Recycled Content for Wood Doors
Recycled content is identified for some products in this section. Other products listed in this section may be available with recycled content;
identify those products that meet project requirements for recycled content.
2.1.3 Reduce Volatile Organic Compounds (VOC) (Low-Emitting Materials) for Products
Reduced VOC content is identified for some products in this section. Other products listed in this section may be available with reduced VOC content.
2.2 DOORS
Provide doors of the types, sizes, and designs indicated on drawings free of urea-formaldehyde resins.
Amendment 0003*************************************************************
2.2.1 Flush Doors
Conform to ANSI/WDMA I.S.1A for flush doors. Provide solid core doors with lock blocks and 1 inch minimum thickness hinge stile. Hardwood stile edge bands of doors shall receive a natural finish to be stained, compatible with face veneer. When used, locate finger-joints under hardware. Provide certified sustainably harvested flush wood doors.
2.2.1.1 Interior Flush Doors
Provide staved lumber particleboard or agrifiber core, Type II flush doors conforming to ANSI/WDMA I.S.1A with faces of premium grade natural birch for stained finish. Hardwood veneers must be rotary cut slip matched.
Door cores must have a minimum recycled content of 45 percent. Provide data identifying percentage of recycled content for door cores. Provide certification of indoor air quality for particleboard and agrifiber door
SECTION 08 14 00 Page 4 0164101CAFETERIA cores.
**************************************************************Amendment 0003
2.3 ACCESSORIES
2.3.1 Door Light Openings
Provide glazed openings with the manufacturer's standard wood moldings.
Provide moldings for doors to receive natural finish of the same wood species and color as the wood face veneers. Provide moldings on the exterior doors with sloped surfaces. Lip type moldings for flush doors.
2.3.2 Additional Hardware Reinforcement
Provide the minimum lock blocks to secure the specified hardware. The measurement of top, bottom, and intermediate rail blocks are a minimum 5 inch by full core width. Comply with the manufacturer's labeling requirements for reinforcement blocking, but not mineral material similar to the core.
2.4 FABRICATION
2.4.1 Marking
Stamp each door with a brand, stamp, or other identifying mark indicating quality and construction of the door.
2.4.2 Quality and Construction
Identify the standard on which the construction of the door was based , identify the standard under which preservative treatment was made, and identify doors having a Type I glue bond.
2.4.3 Preservative Treatment
Treat doors scheduled for restrooms, janitor closets and other possible wet locations including exterior doors with a water-repellent preservative treatment and so marketed at the manufacturer's plant.
2.4.4 Adhesives and Bonds
ANSI/WDMA I.S.1A . Use Type I bond for exterior doors and Type II bond for interior doors. Provide a nonstaining adhesive on doors with a natural finish.
2.4.5 Prefitting
Provide factory finished and factory prefitted doors for the specified hardware, door frame and door-swing indicated. Machine and size doors at the factory by the door manufacturer in accordance with the standards under which the doors are produced and manufactured. The work includes sizing, beveling edges, mortising, and drilling for hardware and providing necessary beaded openings for glass and louvers. Provide the door manufacturer with the necessary hardware samples, and frame and hardware schedules to coordinate the work.
SECTION 08 14 00 Page 5 0164101CAFETERIA
2.4.6 Finishes
2.4.6.1 Factory Finish
Provide doors finished at the factory by the door manufacturer as follows:
WDMA System TR-8 (UV cured acrylated polyester/urethane) or TR-2 (catalyzed lacquer) or TR-4 (conversion varnish) factory finish systems that utilize water-based stains and finishes with ultraviolet UV protection. The coating is AWI AWS premium, medium rubbed sheen, open grain effect. Use stain when required to produce the finish specified for color. Seal edges, cutouts, trim, and wood accessories, and apply two coats of finish compatible with the door face finish. Touch-up finishes that are scratched or marred, or where exposed fastener holes are filled, in accordance with the door manufacturer's instructions. Match color and sheen of factory finish using materials compatible for field application.
2.4.6.2 Color
Provide door finish colors in accordance with the drawings.
2.4.7 Water-Resistant Sealer
Provide manufacturer's standard water-resistant sealer compatible with the specified finishes.
2.5 SOURCE QUALITY CONTROL
Meet or exceed the following minimum performance criteria of stiles of "B" and "C" label fire doors utilizing standard mortise leaf hinges:
a. Cycle-slam: Standard Duty Doors: 250,000 cycles with no loose hinge screws or other visible signs of failure when tested in accordance with the requirements of ANSI/WDMA I.S.1A Heavy Duty Doors: 500,000 cycles with no loose hinge screws or other visible signs of failure when tested in accordance with the requirements of ANSI/WDMA I.S.1A .
b. Hinge loading resistance: Averages of ten test samples not less than Standard Duty doors: 400 pounds force Heavy Duty doors: 475 pounds force when tested for direct screw withdrawal in accordance with ANSI/WDMA I.S.6A using a No. 12, 1-1/4 inch long, steel, fully threaded wood screw. Drill 5/32 inch pilot hole, use 1-1/2 inch opening around screw for bearing surface, and engage screw full, except for last 1/8 inch. Do not use a steel plate to reinforce screw area.
PART 3 EXECUTION
3.1 INSTALLATION
Do not install building construction materials that show visual evidence of biological growth.
Before installation, seal top and bottom edges of doors with the approved water-resistant sealer. Seal cuts made on the job immediately after cutting using approved water-resistant sealer. Fit, trim, and hang doors with a 1/16 inch minimum, 1/8 inch maximum clearance at sides and top, and a 3/16 inch minimum, 1/4 inch maximum clearance over thresholds. Provide 3/8 inch minimum, 7/16 inch maximum clearance at bottom where no threshold occurs. Bevel edges of doors at the rate of 1/8 inch in 2 inch. Door
SECTION 08 14 00 Page 6 0164101CAFETERIA warp must not exceed 1/4 inch when measured in accordance with
ANSI/WDMA I.S.1A .
3.1.1 Fire Doors
Install fire doors in accordance with NFPA 80 . Do not paint over labels.
-- End of Section --
SECTION 08 14 00 Page 7 0164101CAFETERIA
SECTION 09 90 00
PAINTS AND COATINGS
05/11
AMENDMENT 0003
PART…