This document is a Design-Build Solicitation for the Army Reserve National Roofing Program (NRP) FY25 Task Order 07, covering roof replacement projects at two Army Reserve locations in Minnesota. The solicitation includes two volumes: Volume A for MN001 in Arden Hills (37,619 sq ft, involving architectural shingles and PVC single-ply membrane replacement) and Volume B for MN005 in Buffalo (23,896 sq ft, involving EPDM single-ply membrane replacement). The project requires a Registered Roof Consultant (RRC) with at least 10 years of experience to design and oversee the roof replacements, which will involve removing existing roof systems, repairing decking, and installing new roof systems compliant with UFC 3-110-03 Roofing standards.
The contract is part of a Multiple Award Task Order Contract (MATOC) with contract numbers W912QR24D0054 through W912QR24D0063, specifically for Building Envelope, Roof Repair, and Replacement Construction supporting U.S. Army Reserves. The base bid period of performance is 300 days from Notice to Proceed, with an optional additional 175 calendar days for Option 1. The project involves comprehensive design and construction services, including site investigations, surveys, design analysis, and construction, with a focus on creating an energy-efficient, durable, and maintainable roofing solution. The solicitation is issued by the Department of the Army Corps of Engineers Engineering District Louisville.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation For Army Reserve National Roofing Program FY25 Task Order 07
P2: 565479
Design-Build
Volume A – MN001 - Arden Hills, MN
Volume B – MN005- Buffalo, MN (Option 1)
Certified Final
22 July 2025
W912QR-50297502
MATOC W912QR24D0054 thru 24D0063 All requirements of the base MATOC Volume 1 of 2 shall apply to this Task Order unless noted otherwise.
ARIMS: 200A
Disposition: Maintain for 15yrs after construction
W912QR-50297502_NRP07-0000
SECTION 00010 - SOLICITATION CONTRACT FORM
SECTION 00010 – PRICE BREAKOUT SCHEDULE
PROJECT: The Scope of Work (SOW) is for the design and construction services required to repair failed or failing roofs in the United States Army Reserve Command (USARC) roofing inventory under the NRP FY25 Project 7
LOCATIONS: USARC
PROPOSER’S NAME:
ITEM
NUMBER Description UNIT AMOUNT
BASE Work For MN001
0001 Construction: All work, materials, and labor JOB $___________ required to replace the roof at MN001 Building USARC
0002 Design: All work and labor required to JOB $___________ design the roof at MN001 Building USARC
0003 Construction: All work, materials, and labor JOB $___________ required to repair the roof at MN001 Building STORAGE
0004 Design: All work and labor required to design the roof at MN001 Building STORAGE JOB $___________
TOTAL PROJECT BASE PROPOSAL $
FACILITY LOCATION
MN001 Arden Hills, MN MN005 Buffalo, MN
OPTIONS: Options may be exercised up to 120 days from Notice to Proceed
OPTION 1 Work For MN005 0005 Construction: All work, materials, and labor JOB $___________ required to replace the roof at MN005 Building USARC
0006 Design: All work and labor required to JOB $___________ design the roof at MN005 Building USARC
0007 Construction: All work, materials, and labor JOB $___________ required to replace the roof at MN005 Building OMS
0008 Design: All work and labor required to JOB $___________ design the roof at MN005 Building OMS
Total Option 1 $___________
TOTAL ALL OPTIONS PROPOSAL $
TOTAL PROJECT BASE PLUS OPTIONS PROPOSAL $
Provide the binding contract rates and hours included in job prices above for all base and option tasks.
Project Manager _______ hours x _______ = $___________
Superintendent _______ hours x _______ = $___________
CQC Manager _______ hours x _______ = $___________
Site Safety Health Officer _______ hours x _______ = $___________
NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE
NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.
NOTE NO. 2. Offerors must insert a price on all numbered items including options of the CLIN Schedule.
Failure to do so may result in the offer being unacceptable.
NOTE NO. 3.
The Offeror’s Base Bid and all Options will be evaluated for best value to the Government. The basis for award is the trade-off process. In accordance with 52.217-5, Evaluation of Options, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the options.
NOTE NO. 4.
The Base Bid Period of Performance (PoP) is three hundred (300) days from Notice to Proceed.
Option 1 – If and when exercised, the Period of Performance for Option 1 will add an additional one hundred and seventy-five (175) calendar days to the Period of Performance.
--END OF CLIN SCHEDULE—
August 2025 Solicitation
ARIMS: 200A
Disposition: Maintain for 15 yrs after construction
Army Reserve National Roofing Program
FY25 Task Order 7
Volume A
MN001 Arden Hills, MN
National Roofing Program (NRP) FY25 Project 07 P2 565479 MN001, Arden Hills MN, US
TABLE OF CONTENTS
VOLUME A: MN001, Arden Hills, MN
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 50.00 06 SPECIAL PROVISIONS FOR TASK ORDERS
00 80 50.00 06 Submittal Register
DIVISION 01 – GENERAL REQUIREMENTS
01 11 50.00 06 Task Order SCOPE OF WORK
ATTACHMENTS
ATTACHMENT A: Site Location
ATTACHMENT B: Building Layout
ATTACHMENT C: Site Inspection Report, 24 April 2025(For Information Only)
--End of Table of Contents--
NRP FY25 Project 7
P2 565479 17-Jun-25
SECTION 00 80 50.00 06
Version CERTIFIED FINAL
SECTION
00 80 50.00 06
SPECIAL PROVISIONS FOR TASK ORDERS
Updated 17 June 2025
1. PART 1 GENERAL
1.1. SUBMITTALS
Government approval/acceptance is required for submittals with a "GOVT” designation; submittals not having a "GOVT" designation are for information only. When used, a designation following the "GOVT" designation identifies the office that will review the submittal for the Government. The submittals listed in the Submittal Register at the end of this specification section shall be submitted in accordance with Section 01 33 00.
SD-01 Preconstruction Submittals
SD-02 Shop Drawings
SD-05 Design Data
SD-07 Certificates
SD-11 Closeout Submittals
1.2. NOT USED
1.3. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK - Paragraph 1.3 of Section 00 80 00.00 06 is replaced with the following:
1.3.1 Notice to Proceed (NTP) will be issued to the contractor upon receipt and approval of the bonds. Under this NTP, the contractor shall be required to commence work within 10 calendar days from the NTP and complete the work within 420 days from NTP.
1.3.2 Refer to FAR 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 50 for the amount of Liquidated Damages for the Task order project.
1.3.3 Refer to FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 50 for a notification of significant contract dates.
1.3.4 Additional Requirements/Clarifications of Work Included Within the Contract
The time stated in FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 50 for completion shall include as-built drawings, O&M manuals, operational tests/reports/training/instructions, and equipment lists.
1.4. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. ER 415-1-15
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the "Default (Fixed-Price Construction)" as discussed in Section 00 70 00 of the base contract and Section 00 70 50 of this task order. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON (5) DAY WORK
WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MN001 22 21 22 21 19 6 4 4 7 19 19 20
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair-weather workdays, and issue a modification in accordance with the "Default (Fixed-Price Construction)" in section 00 70 00 of the base contract, Volume 1.
1.5. WAGE RATES
The decision of the Secretary of Labor, covering rates of wages, including fringe benefits to be paid laborers and mechanics performing work under this contract, is attached to this solicitation. The payment for all classes of laborers and mechanics actually employed to perform work under the contract will be specified in the following contract provisions: "Contract Work Hours and Safety Standards -- Overtime Compensation"; "Construction Wage Rate Requirements"; and "Compliance with Copeland Act Requirements" in Section 00 70 00 of the base contract.
Wage decision included: MN20250195
The work to be performed is located in Arden Hills, MN, Ramsey County.
4655 LEXINGTON AVENUE NORTH
ARDEN HILLS, MN 55112
1.6. NOT USED
1.7. Antiterrorism (AT) and Operations Security (OPSEC)- Paragraph 1.7
1.7.1 AT Level I training. This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil.
1.7.2 Access and general protection/security policy and procedures.
This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area.
Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access http://jko.jten.mil/ requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.7.3 AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language requires U.S.-based contractor employees and associated subcontractor employees to make available and to receive Government-provided area of responsibility (AOR)–specific AT awareness training as directed by AR 525-13. Specific AOR training content is directed by the combatant commander, with the unit ATO being the local point of contact.
1.7.4 Army Training Certification Tracking System (ATCTS) registration for contractor employees who require access to Government information systems. All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services and must successfully complete the DoD Information Assurance Awareness prior to access to the information system and annually thereafter.
1.7.5 For contracts that require a formal OPSEC program. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it, and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.
1.7.6 Controlled Unclassified Information (CUI). Include DFARS clause 252.204-7012, which requires the contractor to comply with NIST 800-
171. Also include DFARS provision 252.204-2019 into solicitations.
Acquisition officials should follow procedures outlined in DFARS 204.73 and verify vendors have an adequate NIST SP 800-171 summary assessment score within the Supplier Performance Risk System (within PIEE). If the score doesn’t show a medium- or high-level assessment with a score of 110 or better (as described in the “NIST SP 800-171 DoD Assessment Methodology”), include clause252.204-7020 and obtain the vendor’s “system security plan” and “plan of action” for NIST SP 800-171 verification and assurance by Army security officials.
1.8. NOT USED
1.9. NOT USED
1.10. NOT USED
1.11. NOT USED
1.12. NOT USED
1.13. NOT USED
1.14. NOT USED
1.15. NOT USED
1.16. NOT USED
1.17. NOT USED
1.18. NOT USED
1.19. NOT USED
1.20. NOT USED
1.21. NOT USED
1.22. NOT USED
1.23. NOT USED
1.24. NOT USED
1.25. NOT USED
1.26. NOT USED
2. PART 2 PRODUCTS NOT USED
3. PART 3 EXECUTION NOT USED
Line
Act-ivity
Trans-mittal # Specification Section SD # SD Description Item Submitted
Paragraph
Classi-fication:
GA for
GOVT or A/E Revwr Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR /
Auth - Date RCD
From
CONTR
Date FWD To
Other Revwr
Date
RCD
From Other Revwr
Action Code
Date Of Action
Mailed To
CONTR/
Date RCD From
APPR
Authority Remarks
01 32 01.00 06 SD-01 Preconstruction Submittal Project Schedule 3.4 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Accident Prevention Plan (APP) 1.7 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Activity Hazard Analysis (AHA) 1.8 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Design Quality Control Plan 3.2 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Construction Quality Control Plan 3.3 GA
01 50 00 SD-01 Preconstruction Submittal Construction Site Plan 1.3 GA
01 57 19.00 06 SD-01 Preconstruction Submittal Environmental Protection Plan 1.7 GA
01 74 19 SD-01 Preconstruction Submittal Construction Waste Management Plan 1.7 GA
00 80 00.00 06 SD-07 Certificates No Asbestos - Containing Material (ACM) Certification 1.14 GA
00 80 00.00 06 SD-07 Certificates Insurance 1.31 GA
00 80 00.00 06 SD-07 Certificates Warranties 1.15 GA
00 80 00.00 06 SD-11 Closeout Submittals Preliminary (Working) As-Built Drawings 3.4 GA
00 80 00.00 06 SD-11 Closeout Submittals Final As-Built Drawings 3.4 GA
SB MATOC CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION APPROVING AUTHORITY
TITLE: NRP FY25 Project 7
SUBMITTAL REGISTER
JOB NAME: MN001
LOCATION: Arden Hills, MN
CONTRACT NO:
CONTRACTOR:
FY25 NRP Project 7
MN001, ARDEN HILLS, MN
SECTION 01 11 50.00 06
01 11 50.00 06
Task Order SCOPE OF WORK
1. PROJECT INFORMATION
1.1. GENERAL
Design/Build: The Contractor shall provide all labor, equipment, supplies, and consultant services and all site investigations, surveys, analysis, sampling, testing and verification of existing field conditions as required for design and construction of the Roof Replacement Project at MN001 to result in a complete and useable Facility. Contractor shall provide complete design analysis incorporating all engineering computations, analysis, test, and survey results, building code (including fire protection, life safety, environmental and accessibility) review as it pertains/affects/relates to this project, equipment and material data and documentation of existing conditions.
1.2. SCOPE OF WORK
Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order. The work includes design and construction to replace the following roof systems located at MN001:
Building RFID (SF) Section(s) Existing Roof System USARC (37,619) 1 Architectural Shingles USARC (421) 2 PVC Single Ply Membrane USARC (860) 3 PVC Single Ply Membrane
Design/Build: Design and construction shall comply with the requirements contained in this Task Order Request for Proposal (RFP). The design and technical criteria contained and cited in this RFP and the Unified Facilities Guide Specifications (UFGS) establish minimum standards for design and construction quality. The Designers of Record shall use the Unified Facilities Guide Specifications (UFGS) and the requirements contained in this RFP to fully develop the technical specifications and construction drawings. The objective of this solicitation is to obtain an energy efficient, durable, maintainable, and sustainable space.
Design/Build: The illustrations and exhibits included in this RFP illustrate the conceptual design of the project and are provided to define the scope of work and budget. The concepts provided shall be further developed by the Design/Build Contractor to comply with the customer’s functional needs.
All demolition required to construct the project is included as part of the work of this Contract.
1.3. SITE LOCATION
This project is located at ARDEN HILLS, MN. 4655 LEXINGTON AVENUE NORTH
ARDEN HILLS, MN 55112
1.4. EXISTING SITE UTILITIES
1.4.1. The contractor shall verify the location of all utilities serving the building. Upgrading the existing utilities, (unless noted otherwise) outside the limits of construction, is not a part of this project.
1.5. BID OPTIONS
1.7. ATTACHMENTS
Design/Build: Information provided in the Attachments is intended to guide the completion of the design by establishing existing conditions, and the desired character, appearance, and function of the new construction. The following Attachments are included and shall be used and strictly adhered-to in completing the design and construction of the project.
a. ATTACHMENT A: Site Location
b. ATTACHMENT B: Building Layout Plans
c. ATTACHMENT C: Site Inspection Report, 24-Apr-25
1.14. PERSONNEL REQUIREMENTS AND QUALIFICATIONS
1.15. Registered Roof Consultant (RRC) (Designer of Record) shall have a degree in Architecture or Engineering and have at least ten (10) years of experience in roof repairs. The RRC must be currently licensed by the International Institute of Building Envelope Enclosures (IIBEC).
2. DESIGN REQUIREMENTS
2.1. GENERAL
The Contractor shall prepare complete construction documents for all work designed as required by the RFP. The construction documents to be prepared shall include, but are not limited to, construction drawings, specifications, submittals, and design analysis as required in Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD), Volume 1. Materials and equipment shall be limited to those specified except that where no specific material and equipment is specified or no basis of design is identified, the Contractor shall use materials and equipment accepted within the construction industry and in compliance with Design Criteria.
2.2. DESIGN
2.2.1. The Contractor shall prepare a 100% design for the project in accordance with the RFP using industry standard materials and efficient practices. The design of the materials selected shall be high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy, and coordination of all designs, drawings, specifications, and other documents or publications upon which the design and construction are based. It shall be the responsibility of the Design/ Build Contractor to verify the accuracy of the documents provided.
2.2.2 CAD/BIM Requirement
The contractor will not be required to produce advanced modeling and design drawings will be limited to CAD files.
2.2.3 Design Submittal Requirements
The contractor will not be required to produce charette or interim design submittals. The contractor will submit a final design, a corrected final design, and a certified final design. The independent Registered Roof Observer (RRO) identified under Section 01 11 00.00 06 Paragraph 3.3.2.3 shall review the final design as part of the contractor design QC review team. The RRO shall attend the final design plan-in-hand review meeting.
2.1.4 Design Professionals
General Scope of work for most task orders will be for roof replacement and exterior water proofing with associated work. Roof replacement design will be certified by a RRC and have a professional engineer or architectural stamp. Structural analysis will only be required if there is a change in the dead load for the structural system or if called out in the task order scope of work. Electrical and mechanical design will be limited to relocating existing systems.
2.2.2. Design Milestone Schedule
The sample schedule and sequence of work shown below was prepared for the Contractor’s use in its schedule preparation. This schedule is not intended to be the actual awarded design-build schedule. Upon receipt of the Notice to Proceed, the selected Contractor will be required to submit its proposed design and construction schedule for Government review and acceptance.
Notice to Proceed (NTP) Day 0 Design Quality Control Plan (DQCP) NTP + 14 Days Charette Report (FIO no review) NTP + 40 Days Interim Submittal (FIO no review) NTP + 60 Days Final Submittal NTP + 120 Days Final Plan in Hand Meeting (on-site) NTP + 138 Days Corrected Final Submittal NTP + 152 Days Certified Final Submittal NTP + 160 Days
2.3. REQUEST FOR PROPOSAL (RFP) INTENT
The intent of this RFP section is to describe the requirements for appearance, function, materials, and types of construction in sufficient detail to enable engineering and design to be completed by the Contractor.
2.4. Design Milestone Meetings
2.4.1. Charette / Kickoff Meeting
2.4.1.1. Shall be in person and on-site.
2.4.2. Final Design / Plan-in-hand Review Meeting
2.4.2.1. Shall be in person and on-site.
2.5. NOT USED
2.6. NOT USED
2.7. NOT USED
2.8. NOT USED
2.9. NOT USED
2.10. NOT USED
2.11. NOT USED
2.12. GOVERNMENT FURNISHED MATERIALS
2.12.1. GFM Handover
The GFM has been provided as part of the Solicitation package.
2.12.2. GFM File Formats
GFM are provided only in PDF format.
2.13. (See Paragraph 2.1 Section 01 11 00.00 06) DESIGN SUBMITTAL
DISTRIBUTION MATRIX
Submittal Reviewers & Mailing Addresses
U.S. Army Corps of Engineers Isaias Enriquez, P.E.
Isaias.Enriquez@usace.army.mil LRL-ED-MR Room 414 600 Doctor Martin Luther King Junior Place Louisville, KY 40202
Timothy M. McClellan, P.E., RRC Timothy.m.mcclellan@usace.army.mil LRL-ED-MR Room 414 600 Doctor Martin Luther King Junior Place Louisville, KY 40202
U.S. Army Corps of Engineers John P. Hearn John.P.Hearn@usace.army.mil
LRL-CD
2475 K Street Bldg 52
WPAFB OH 45433
Michael Brooks Michael.s.brooks@usace.army.mil
LRL-CDR
Jeffrey E. Bayers, P.E., P.M.P.
Jeffrey.e.bayers@usace.army.mil
LRL-PM-R
Steve Coffey, P.E.
USARC G 3/5/7 Engineers - Desk 4N-4001-62
W912QR-50297502_NRP07-0000
mailto:Timothy.m.mcclellan@usace.army.mil mailto:John.P.Hearn@usace.army.mil mailto:Michael.s.brooks@usace.army.mil mailto:Jeffrey.e.bayers@usace.army.mil
4700 Knox Street, Bldg 8-8108 Ft. Bragg, NC 28310 Phone: 910-570-8961 Email: steven.w.coffey3.civ@army.mil
Justin Reeder, P.E., RRC, RRO, CDT USARC-ARIMD Engineering Branch / SAIN Engineering USAR National Roofing Program REM Phone: 843.813.2423 Email: justin.reeder@saineng.com
88th RD Dan Breitsprecher 60 South O Street Fort McCoy, WI 54656 Phone: 608-343-0766 Email: Daniel.l.breitsprecher.ctr@army.mil
3. GENERAL CONSTRUCTION REQUIREMENTS
3.1. SUMMARY
3.1.1. The requirements include:
a. Construction considerations and use of the premises.
b. Protection of personnel and Government property.
c. Construction facilities and job site standards.
d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.
3.2. GENERAL INFORMATION
3.2.1. NOT USED
3.2.2. NOT USED
3.2.3. Coordinate all construction activities with:
a. Contracting Officer’s Representative
b. Base Fire Department
c. Base Security/Police
d. Base Civil Engineer
e. Building Occupants
3.2.4. NOT USED
3.2.5. NOT USED
3.2.6. NOT USED
mailto:steven.w.coffey3.civ@army.mil mailto:justin.reeder@saineng.com mailto:Daniel.l.breitsprecher.ctr@army.mil
3.2.7. NOT USED
3.2.8. NOT USED
3.2.9. Project and Safety Signs. See 01 50 00, Paragraph 2.1.3.
3.3. DOCUMENTATION
3.3.1. NOT USED
3.3.2. NOT USED
3.4. NOT USED
3.5. Work Schedule under Section 01 11 00.00 06 Paragraph 3.9.1.2 is changed to “Work S WORK SCHEDULE: The Contractor shall schedule the work between the hours of 7:00 a.m. and 4:30 p.m. Monday through Friday.
3.5.1. No work shall occur on Federal Holidays.
3.5.2. No work shall occur on drill weekends.
3.5.3. Permission to perform any work outside of these hours must be in writing and submitted five (5) calendar days in advance for approval by the Contracting Officer.
3.5.4. The Government may or may not grant such permission at its discretion.
3.6. Contractor Personal Vehicle Parking under Section 01 11 00.00 06 Paragraph 3.9.1.7 is changed to Contractor Personal Vehicle Parking:
The contractor may use a limited number of parking spaces in the existing lots for the contractor’s employee parking of personal vehicles. The Contractor shall coordinate with the Government on the exact number of available spaces, and shall make provisions to transport employees to the site should inadequate parking spaces be available on site. Parking in these areas is available on a first-come first served basis.
4. NOT USED
5. NOT USED
6. EXTERIOR EQUIPMENT
6.1. NOT USED
7. ARCHITECTURAL / BUILDING ENVELOPE
7.1. Approximately 1100 LF of exterior sealant to be replaced at USARC (Section 1). Approximately 130 LF of seam to be completed on roof of STORAGE building.
7.2. Remove skylights to below deck (19 EA) at USARC. Secure skylight tube below deck and repair deck per UFC. Paint bottom portion of skylight secured to deck to match deck.
8. NOT USED
9. NOT USED
10. NOT USED
11. NOT USED
12. NOT USED
13. NOT USED
14. Roof System
Roof system installed shall comply with UFC 3-110-03 Roofing, with Change 5, or the latest version available. Where they do not existing contractor shall install roof access ladders from the ground to roof and between roof sections to allow access to all sections.
Contractor bids shall include removal of 2-8 inches of insulation to low slope roof areas (PVC). Existing roof systems may be multi-layered with differing roof system types below the surface membrane. Contractor is responsible for identifying all equipment mounted directly below the deck and to utilize a connection method that either avoids the deck or relocates equipment in a way that complies with current building codes.
Hand nail all shingles. No pneumatic, battery and/or power actuated tools shall be used for shingle installation.
Replace roof with the following:
Building RFID (SF) Section(s) New Roof System USARC (37,619) 1 Architectural Shingles USARC (421) 2 2-Ply Modified Bitumen USARC (860) 3 2-Ply Modified Bitumen
14.1. NOT USED
14.2 ROOF DECK REPAIR
Note: Existing condition are as follows per Attachment C pg 14, architectural shingles over underlayment on sheathing, which is attached to wood blocking, creating an air space over insulation, with a vapor barrier on metal decking. DOR will confirm existing conditions for the design effort.
Remove and replace all wood blocking, wood decking, and underlayment at USARC, Section 1.
Design and install ventilation per IBC standards. This may include additional ventilation means as needed.
Remove and replace insulation.
Remove existing vapor barrier and replace with new.
Install ice and water shield adhered to the plywood sheathing across entire roof structure.
--End of Section --
Attachment A
Site Location
Attachment B
Building Layout Plans
Attachment C
Site Inspection Report 24 April 2025
Note: This attachment is for documentation of existing conditions. The requirements of the 01 11 50.00 06 and the base MATOC take precedence over any recommended repairs included in this inspection report.
SC Engineers COA #1906
ROOF ASSESSMENT REPORT
FOR
NATIONAL ROOFING PROGRAM (NRP)
FY23 1-N, MN001
4655 LEXINGTON AVENUE NORTH
ARDEN HILLS, MN 48317
April 24, 2025
REI PROJECT NO. 23CHS-020
MN001
TABLE OF CONTENTS
I. OVERALL MAP
II. USARC BUILDING SITE OVERVIEW
III. USARC BUILDING SECTION 1
A. SECTION 1 COMPOSITION
B. SECTION 1 OBSERVATION
C. SECTION 1 DEFICIENCIES
D. SECTION 1 SUMMARY
IV. USARC BUILDING SECTION 2
A. SECTION 2 COMPOSITION
B. SECTION 2 OBSERVATION
C. SECTION 2 SUMMARY
V. USARC BUILDING SECTION 3
A. SECTION 3 COMPOSITION
B. SECTION 3 OBSERVATION
C. SECTION 3 DEFICIENCIES
D. SECTION 3 SUMMARY
several substrate R Onsite review of d revealed that the
The r The d further indicated
Based on what REI observed while onsite, . Additionally, on s that s that
1079 LF
37,619 Sq Ft Total the
55 Sq Ft
2 EA
1 EA
Total se
129LF
August 2025 Solicitation
ARIMS: 200A
Disposition: Maintain for 15 yrs after construction
Army Reserve National Roofing Program FY25 Task Order 7
Volume B
MN005 Buffalo, MN (Option 1)
National Roofing Program (NRP) FY25 Project 7 P2 565479 MN005, Buffalo MN, US
TABLE OF CONTENTS
VOLUME B: MN005, Buffalo, MN
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
00 80 50.00 06 SPECIAL PROVISIONS FOR TASK ORDERS
00 80 50.00 06 Submittal Register
DIVISION 01 – GENERAL REQUIREMENTS
01 11 50.00 06 Task Order SCOPE OF WORK
ATTACHMENTS
ATTACHMENT A: Site Location
ATTACHMENT B: Building Layout
ATTACHMENT C: Site Inspection Report, 24 April 2025(For Information Only)
--End of Table of Contents--
00 80 50.00 06
SPECIAL PROVISIONS FOR TASK ORDERS
17 June 2025
1. PART 1 GENERAL
1.1. SUBMITTALS
Government approval/acceptance is required for submittals with a "GOVT” designation; submittals not having a "GOVT" designation are for information only. When used, a designation following the "GOVT" designation identifies the office that will review the submittal for the Government. The submittals listed in the Submittal Register at the end of this specification section shall be submitted in accordance with Section 01 33 00.
SD-01 Preconstruction Submittals
SD-02 Shop Drawings
SD-05 Design Data
SD-07 Certificates
SD-11 Closeout Submittals
1.2. NOT USED
1.3. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK - Paragraph 1.3
1.3.1 Notice to Proceed (NTP) will be issued to the contractor upon receipt and approval of the bonds. Under this NTP, the contractor shall be required to commence work within 10 calendar days from the NTP and complete the work within 420 days from NTP.
1.3.2 Refer to FAR 52.211-12 "LIQUIDATED DAMAGES" in Section 00 70 50 for the amount of Liquidated Damages for the Task order project.
1.3.3 Refer to FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 50 for a notification of significant contract dates.
1.3.4 Additional Requirements/Clarifications of Work Included Within the Contract
The time stated in FAR 52.211-10 "Commencement, Prosecution, and Completion of Work" in Section 00 70 50 for completion shall include as-built drawings, O&M manuals, operational tests/reports/training/instructions, and equipment lists.
1.4. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. ER 415-1-15
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the "Default (Fixed-Price Construction)" as discussed in Section 00 70 00 of the base contract and Section 00 70 50 of this task order. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORKDAYS BASED ON (5) DAY WORK
WEEK
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
MN005 22 21 22 21 19 6 4 4 7 19 19 20
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated listed above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair-weather workdays, and issue a modification in accordance with the "Default (Fixed-Price Construction)" in section 00 70 00 of the base contract, Volume 1 .
1.5. WAGE RATES
The decision of the Secretary of Labor, covering rates of wages, including fringe benefits to be paid laborers and mechanics performing work under this contract, is attached to this solicitation. The payment for all classes of laborers and mechanics actually employed to perform work under the contract will be specified in the following contract provisions: "Contract Work Hours and Safety Standards -- Overtime Compensation"; "Construction Wage Rate Requirements"; and "Compliance with Copeland Act Requirements" in Section 00 70 00 of the base contract.
Wage decision included: MN20250219
The work to be performed is located in Buffalo, MN, Wright County.
1101 3rd St. South Buffalo, MN 55313
1.7. Antiterrorism (AT) and Operations Security (OPSEC)- Paragraph 1.7
1.7.1 AT Level I training. This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil.
1.7.2 Access and general protection/security policy and procedures.
This standard language is for contractor employees with an area of performance within an Army-controlled installation, facility, or area.
Contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access http://jko.jten.mil/ requirements to be accomplished by the installation Provost Marshal Office, Director of Emergency Services, or Security Office. Contractor workforce must comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
1.7.3 AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language requires U.S.-based contractor employees and associated subcontractor employees to make available and to receive Government-provided area of responsibility (AOR)–specific AT awareness training as directed by AR 525-13. Specific AOR training content is directed by the combatant commander, with the unit ATO being the local point of contact.
1.7.4 Army Training Certification Tracking System (ATCTS) registration for contractor employees who require access to Government information systems. All contractor employees with access to a Government info system must be registered in the ATCTS at commencement of services and must successfully complete the DoD Information Assurance Awareness prior to access to the information system and annually thereafter.
1.7.5 For contracts that require a formal OPSEC program. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it, and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.
1.7.6 Controlled Unclassified Information (CUI). Include DFARS clause 252.204-7012, which requires the contractor to comply with NIST 800-
171. Also include DFARS provision 252.204-2019 into solicitations.
Acquisition officials should follow procedures outlined in DFARS 204.73 and verify vendors have an adequate NIST SP 800-171 summary assessment score within the Supplier Performance Risk System (within PIEE). If the score doesn’t show a medium- or high-level assessment with a score of 110 or better (as described in the “NIST SP 800-171 DoD Assessment Methodology”), include clause252.204-7020 and obtain the vendor’s “system security plan” and “plan of action” for NIST SP 800-171 verification and assurance by Army security officials.
1.14. NOT USED
1.15. NOT USED
1.20. NOT USED
1.21. NOT USED
1.22. NOT USED
1.23. NOT USED
1.24. NOT USED
1.25. NOT USED
1.26. NOT USED
2. PART 2 PRODUCTS NOT USED
3. PART 3 EXECUTION NOT USED
Line
Act-ivity
Trans-mittal # Specification Section SD # SD Description Item Submitted
Paragraph
Classi-fication:
GA for
GOVT or A/E Revwr Submit
Approval Needed
By
Material Needed
By Action Code
Date Of Action
Date FWD to APPR /
Auth - Date RCD
From
CONTR
Date FWD To
Other Revwr
Date
RCD
From Other Revwr
Action Code
Date Of Action
Mailed To
CONTR/
Date RCD From
APPR
Authority Remarks
01 32 01.00 06 SD-01 Preconstruction Submittal Project Schedule 3.4 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Accident Prevention Plan (APP) 1.7 GA
01 35 26.00 06 SD-01 Preconstruction Submittal Activity Hazard Analysis (AHA) 1.8 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Design Quality Control Plan 3.2 GA
01 45 04.10 06 SD-01 Preconstruction Submittal Construction Quality Control Plan 3.3 GA
01 50 00 SD-01 Preconstruction Submittal Construction Site Plan 1.3 GA
01 57 19.00 06 SD-01 Preconstruction Submittal Environmental Protection Plan 1.7 GA
01 74 19 SD-01 Preconstruction Submittal Construction Waste Management Plan 1.7 GA
00 80 00.00 06 SD-07 Certificates No Asbestos - Containing Material (ACM) Certification 1.14 GA
00 80 00.00 06 SD-07 Certificates Insurance 1.31 GA
00 80 00.00 06 SD-07 Certificates Warranties 1.15 GA
00 80 00.00 06 SD-11 Closeout Submittals Preliminary (Working) As-Built Drawings 3.4 GA
00 80 00.00 06 SD-11 Closeout Submittals Final As-Built Drawings 3.4 GA
SB MATOC CONTRACTOR SCHEDULE
DATES
CONTRACTOR
ACTION APPROVING AUTHORITY
TITLE: NRP FY25 Project 7
SUBMITTAL REGISTER
JOB NAME: MN005
LOCATION: Buffalo, MN
CONTRACT NO:
CONTRACTOR:
MN005, Buffalo, MN
01 11 50.00 06
Task Order SCOPE OF WORK
1. PROJECT INFORMATION
1.1. GENERAL
Design/Build: The Contractor shall provide all labor, equipment, supplies, and consultant services and all site investigations, surveys, analysis, sampling, testing and verification of existing field conditions as required for design and construction of the Roof Replacement Project at MN005 to result in a complete and useable Facility. Contractor shall provide complete design analysis incorporating all engineering computations, analysis, test, and survey results, building code (including fire protection, life safety, environmental and accessibility) review as it pertains/affects/relates to this project, equipment and material data and documentation of existing conditions.
1.2. SCOPE OF WORK
Unless specifically noted otherwise in this Specification Section or in the base MATOC contract Volume 1 of 2 itself, all requirements of the base MATOC contract Volume 1 of 2 shall apply to this Task Order. The work includes design and construction to replace the following roof systems located at MN005:
Building RFID (SF) Section(s) Existing Roof System USARC (2,761) 1 EPDM Single Ply Membrane USARC (1,112) 2 EPDM Single Ply Membrane USARC (12,047) 3 EPDM Single Ply Membrane OMS (7,976) 1 EPDM Single Ply Membrane
Design/Build: Design and construction shall comply with the requirements contained in this Task Order Request for Proposal (RFP). The design and technical criteria contained and cited in this RFP and the Unified Facilities Guide Specifications (UFGS) establish minimum standards for design and construction quality. The Designers of Record shall use the Unified Facilities Guide Specifications (UFGS) and the requirements contained in this RFP to fully develop the technical specifications and construction drawings. The objective of this solicitation is to obtain an energy efficient, durable, maintainable, and sustainable space.
Design/Build: The illustrations and exhibits included in this RFP illustrate the conceptual design of the project and are provided to define the scope of work and budget. The concepts provided shall be further developed by the Design/Build Contractor to comply with the customer’s functional needs.
All demolition required to construct the project is included as part of the work of this Contract.
1.3. SITE LOCATION
This project is located at Buffalo, MN. 1101 3rd St. South Buffalo, MN 55313
1.4. EXISTING SITE UTILITIES
1.4.1. The contractor shall verify the location of all utilities serving the building. Upgrading the existing utilities, (unless noted otherwise) outside the limits of construction, is not a part of this project.
1.5. BID OPTIONS
1.7. ATTACHMENTS
Design/Build: Information provided in the Attachments is intended to guide the completion of the design by establishing existing conditions, and the desired character, appearance, and function of the new construction. The following Attachments are included and shall be used and strictly adhered-to in completing the design and construction of the project.
a. ATTACHMENT A: Site Location
b. ATTACHMENT B: Building Layout Plans
c. ATTACHMENT C: Site Inspection Report, 24-Apr-25
1.14. PERSONNEL REQUIREMENTS AND QUALIFICATIONS
1.15. Registered Roof Consultant (RRC) (Designer of Record) shall have a degree in Architecture or Engineering and have at least ten (10) years of experience in roof repairs. The RRC must be currently licensed by the International Institute of Building Envelope Enclosures (IIBEC).
2. DESIGN REQUIREMENTS
2.1. GENERAL
The Contractor shall prepare complete construction documents for all work designed as required by the RFP. The construction documents to be prepared shall include, but are not limited to, construction drawings, specifications, submittals, and design analysis as required in Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD), Volume 1. Materials and equipment shall be limited to those specified except that where no specific material and equipment is specified or no basis of design is identified, the Contractor shall use materials and equipment accepted within the construction industry and in compliance with Design Criteria.
2.2. DESIGN
2.2.1. The Contractor shall prepare a 100% design for the project in accordance with the RFP using industry standard materials and efficient practices. The design of the materials selected shall be high quality, durable and easily maintained. The Contractor shall be responsible for the professional quality, code compliance, technical accuracy, and coordination of all designs, drawings, specifications, and other documents or publications upon which the design and construction are based. It shall be the responsibility of the Design/ Build Contractor to verify the accuracy of the documents provided.
2.2.2 CAD/BIM Requirement
The contractor will not be required to produce advanced modeling and design drawings will be limited to CAD files.
2.2.3 Design Submittal Requirements
The contractor will not be required to produce charette or interim design submittals. The contractor will submit a final design, a corrected final design, and a certified final design. The independent Registered Roof Observer (RRO) identified under Section 01 11 00.00 06 Paragraph 3.3..2.3 shall review the final design as part of the contractor design QC review team. The RRO shall attend the final design plan-in-hand review meeting.
2.1.4 Design Professionals
General Scope of work for most task orders will be for roof replacement and exterior water proofing with associated work. Roof replacement design will be certified by a RRC and have a professional engineer or architectural stamp. Structural analysis will only be required if there is a change in the dead load for the structural system or if called out in the task order scope of work. Electrical and mechanical design will be limited to relocating existing systems.
2.2.2. Design Milestone Schedule
The sample schedule and sequence of work shown below was prepared for the Contractor’s use in its schedule preparation. This schedule is not intended to be the actual awarded design-build schedule. Upon receipt of the Notice to Proceed, the selected Contractor will be required to submit its proposed design and construction schedule for Government review and acceptance.
Notice to Proceed (NTP) Day 0 Design Quality Control Plan (DQCP) NTP + 14 Days Charette Report (FIO no review) NTP + 40 Days Interim Submittal (FIO no review) NTP + 90 Days Final Submittal NTP + 120 Days Final Plan in Hand Meeting (on-site) NTP + 138 Days Corrected Final Submittal NTP + 152 Days Certified Final Submittal NTP + 160 Days
2.3. REQUEST FOR PROPOSAL (RFP) INTENT
The intent of this RFP section is to describe the requirements for appearance, function, materials, and types of construction in sufficient detail to enable engineering and design to be completed by the Contractor.
2.4. Design Milestone Meetings
2.4.1. Charette / Kickoff Meeting
2.4.1.1. Shall be in person and on-site.
2.4.2. Final Design / Plan-in-hand Review Meeting
2.4.2.1. Shall be in person and on-site.
2.5. NOT USED
2.6. NOT USED
2.7. NOT USED
2.8. NOT USED
2.9. NOT USED
2.10. NOT USED
2.11. NOT USED
2.12. GOVERNMENT FURNISHED MATERIALS
2.12.1. GFM Handover
The GFM has been provided as part of the Solicitation package.
2.12.2. GFM File Formats
GFM are provided only in PDF format.
2.13. (See Paragraph 2.1 Section 01 11 00.00 06) DESIGN SUBMITTAL
DISTRIBUTION MATRIX
Submittal Reviewers & Mailing Addresses
Isaias Enriquez Isaias.Enriquez@usace.army.mil LRL-ED-MR Room 414
Timothy M. McClellan, P.E., RRC Timothy.m.mcclellan@usace.army.mil LRL-ED-MR Room 414 600 Doctor Martin Luther King Junior Place Louisville, KY 40202
U.S. Army Corps of Engineers John P. Hearn John.P.Hearn@usace.army.mil
LRL-CD
2475 K Street Bldg 52
WPAFB OH 45433
Michael Brooks Michael.s.brooks@usace.army.mil
LRL-CDR
Jeffrey E. Bayers, P.E., P.M.P.
Jeffrey.e.bayers@usace.army.mil
LRL-PM-R
600 Doctor Martin Luther King Junior Place Louisville, KY 40202
W912QR-50297502_NRP07-0000
mailto:Timothy.m.mcclellan@usace.army.mil mailto:John.P.Hearn@usace.army.mil mailto:Michael.s.brooks@usace.army.mil mailto:Jeffrey.e.bayers@usace.army.mil
Steve Coffey, PE USARC G 3/5/7 Engineers - Desk 4N-4001-62 4700 Knox Street, Bldg 8-8108 Ft. Bragg, NC 28310 Phone: 910-570-8961 Email: steven.w.coffey3.civ@army.mil
Justin Reeder, PE, RRC, RRO, CDT USARC-ARIMD Engineering Branch / SAIN Engineering USAR National Roofing Program REM Phone: 843.813.2423 Email: justin.reeder@saineng.com
88th RD Dan Breitsprecher 60 South O Street Fort McCoy, WI 54656 Phone: 608-343-0766 Email: Daniel.l.breitsprecher.ctr@army.mil
3. GENERAL CONSTRUCTION REQUIREMENTS
3.1. SUMMARY
3.1.1. The requirements include:
a. Construction considerations and use of the premises.
b. Protection of personnel and Government property.
c. Construction facilities and job site standards.
d. The requirements of this section apply to the entire project including all amendments or modifications that may be issued to modify the contract documents.
3.2. GENERAL INFORMATION
3.2.1. NOT USED
3.2.2. NOT USED
3.2.3. Coordinate all construction activities with:
a. Contracting Officer’s Representative
b. Base Fire Department
c. Base Security/Police
d. Base Civil Engineer
e. Building Occupants
3.2.4. NOT USED
3.2.5. NOT USED
mailto:steven.w.coffey3.civ@army.mil mailto:justin.reeder@saineng.com mailto:Daniel.l.breitsprecher.ctr@army.mil
3.2.6. NOT USED
3.2.7. NOT USED
3.2.8. NOT USED
3.2.9. Project and Safety Signs. See 01 50 00, Paragraph 2.1.3.
3.3. DOCUMENTATION
3.3.1. NOT USED
3.3.2. NOT USED
3.4. NOT USED
3.5. Work Schedule under Section 01 11 00.00 06 Paragraph 3.9.1.2 is changed to “Work S WORK SCHEDULE: The Contractor shall schedule the work between the hours of 7:00 a.m. and 4:30 p.m.