14 MAY 2018 VOLUME 02
© 2018 DIVISIONS 21-33
PROJECT MANUAL
REPAIR AND ADD TO FIRE STATION
MCENTIRE JOINT NATIONAL GUARD BASE
SOUTH CAROLINA AIR NATIONAL GUARD
169TH FIGHTER WING
EASTOVER, SC
CONTRACT NO: W912QG-11-D-0001
PROJECT NO. PSTE 122002 & 139022
LS3P COMMISSION NUMBER: 1301-154910
B-3 FINAL SUBMITTAL
ARCHITECT
205 ½ KING STREET
CHARLESTON, SC 29401
THIS PAGE INTENTIONALLY LEFT BLANK
SEALS
for
REPAIR AND ADD TO FIRE STATION
MCENTIRE JOINT NATIONAL GUARD BASE
SOTH CAROLINA AIR NATIONAL GUARD
169TH FIGHTER WING
EASTOVER, SC
CONTRACT NO: W912QG-11-D-0001
PROJECT NO. PSTE 122002 & 139022
LS3P COMMISSION NUMBER: 1301-154910
B-3 FINAL SUBMITTAL – 14 MAY 2018
ARCHITECT
LS3P ASSO CIATES LTD
205-1/2 King Street
Charleston, SC 29401
Phone: 843-577-4444
Fax: 843-722-4789
CIVIL ENGINEER
ADC ENGINEERING, INC.
1226 Yeamans Hall Road
Hanahan, SC 29410
Phone: 843-566-0161
Fax: 843-566-0162
Chris Cook, P.E.
LANDSCAPE ARCHITECT
ADC ENGINEERING, INC.
1226 Yeamans Hall Road
Hanahan, SC 29410
Phone: 843-566-0161
Fax: 843-566-0162
Bryant Stowe, R.L.A.
STRUCTURAL ENGINEER
MICHAEL M. SIMPSON &
ASSOCIATES, INC.(MMSA)
30 Patewood Drive
Building 1, Suite 100
Greenville, SC 29615
Phone: 864-331-1201
Fax: 864-331-1070
Michael M. Simpson, P.E.
MECHANICAL/PLUMBING ENGINEER
DWG CONSULTING ENGINEERS
1009 Anna Knapp Blvd.
Mt. Pleasant, SC 29464 Phone: 843-849-1141 Fax: 843-849-6756
Engineer’s Name, P.E.
FIRE PROTECTION ENGINEER
1009 Ann Knapp Blvd.
Mt. Pleasant, SC 29464 Phone: 843-849-1141
ELECTRICAL ENGINEER
1009 Ann Knapp Blvd.
Mt. Pleasant, SC 29464 Phone: 843-849-1141
TELECOMMUNICATIONS/
SECURITY ENGINEER
DWG CONSULTING ENGINEERS
1009 Ann Knapp Blvd.
Mt. Pleasant, SC 29464 Phone: 843-849-1141
REPAIR AND ADD TO FIRE STATION W912QG-11-D-0001
McENTIRE JNGB, SC AIR NATIONAL GUARD, EASTOVER, SC PSTE 122002 & 139022
PROJECT TABLE OF CONTENTS - 1
B-3 FINAL SUBMITTAL 14 MAY 2018
PROJECT TABLE OF CONTENTS
VOLUME 01
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 33 00 SUBMITTAL PROCEDURES
ATTACHMENT: SUBMITTAL REGISTER
01 33 29 SUSTAINABILITY REPORTING
ATTACHMENT: LEED CHECKLIST
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 58 00 PROJECT IDENTIFICATION
01 60 00 PRODUCT REQUIREMENTS
01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 75 00.00 40 STARTING AND ADJUSTING
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
DIVISION 03 – CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 01 00.91 UNIT MASONRY CLEANING
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23.16 STRUCTURAL WELDING
05 12 00 STRUCTURAL STEEL
05 21 00 STRUCTURAL JOIST FRAMIING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
05 52 00 METAL RAILINGS
PROJECT TABLE OF CONTENTS - 2
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 21 19 SPRAY INSULATION
07 41 13 METAL ROOF PANELS
07 42 13 METAL WALL PANELS
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 81 00 SPRAY-APPLIED FIREPROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 33 23 OVERHEAD COILING DOORS
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 44 00 CURTAIN WALL AND GLZED ASSEMBLIES
08 60 45 SKYLIGHTS AND TRANSLUCENT PANELS
08 71 00 DOOR HARDWARE
ATTACHMENT: HARDWARE SCHEDULE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 06 90 EXTERIOR COLOR SCHEDULE
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 67 23.13 STANDARD RESINOUS FLOORING
09 68 00 CARPET
09 72 00 WALLCOVERINGS
09 84 20 ACOUSTICAL WALL PANELS
09 90 00 PAINTS AND COATINGS
09 94 13 ACRYLIC COATINGS BID OPTION A07
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
PROJECT TABLE OF CONTENTS - 3
10 21 13 TOILET COMPARTMENTS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
10 73 26 MANUFACTUED WALKWAY COVERINGS
DIVISION 11 – EQUIPMENT
11 05 40 COMMON WORK RESULTS FOR FOODSERVICE EQUIPMENT
11 06 40.13 FOODSERVICE EQUIPMENT SCHEDULE
11 52 00 AUDIO-VISUAL EQUIPMENT
DIVISION 12 - FURNISHINGS
12 24 13 ROLLER WINDOW SHADES
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 – SPECIAL CONSTRUCTION
13 34 19 METAL BUILDING SYSTEMS
DIVISION 14 - Not Used
VOLUME 02
DIVISION 21 - FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL
22 07 19.00 40 PLUMBING PIPING INSULATION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING
AND EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 23 00 REFRIGERANT PIPING
23 31 13.00 40 METAL DUCTS
23 34 23.00 40 HVAC POWER VENTILATORS
23 35 00.00 10 OVREHEAD VEHICLE TAILPIPE EXHAUST REMOVAL SYSTEM(S)
23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS
23 54 16.00 10 HEATING SYSTEM; GAS-FIRED HEATERS
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
PROJECT TABLE OF CONTENTS - 4
23 82 19.00 40 FAN COIL UNITS
23 82 46.00 40 ELECTRIC UNIT HEATERS
DIVISION 25 - Not Used
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT
26 08 00 APPARATUS INSPECTION AND TESTING
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 12 19.00 40 PAD-MOUNTED, LIQUID-FILLED, MEDIUM –VOLTAGE TRANSFORMERS
26 18 23.00 40 MEDIUM-VOLTAGE SURGE ARRESTERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 PANELBOARDS
26 27 13.10 30 ELECTRIC METERS
26 32 15.00 10 DIESEL-GENERATOR SET STAIONARY 100-2500 KW, WITH AUXILIARIES
26 36 00.00 10 AUTOMATIC TRANSFER SWITCH AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 – COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 11 DIGITAL, ADDRESSABLE FIRE-ALARM AND MASS NOTIFICATION SYSTEM
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
31 31 16 SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL
31 32 11 SOIL SURFACE EROSION CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23 PAVEMENT MARKINGS
32 31 19 METAL GATES
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERS
33 40 00 STORM DRAINAGE UTILITIES
PROJECT TABLE OF CONTENTS - 5
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 77 36.00 40 MEDIUM-VOLTAGE UTILITY FUSES
APPENDIX A
SEISMIC SITE CLASSIFICATION REPORT, DATED JANUARY 5, 2016, PROVIDED BY
TERRACON CONSULTANTS, INC.
APPENDIX B
GEOTECHNICAL ENGINEERING REPORT, DATED JANUARY 5, 2016, PROVIDED BY TERRACON
CONSULTANTS, INC.
APPENDIX C
SUPPLEMENTAL ASBESTOS SAMPLING, DATED DECEMBER 11, 2015, PROVIDED BY TERRACON
CONSULTANTS, INC.
-- End of Project Table of Contents --
01 00 00.00 – Page 1
SECTION 01 00 00.00
GENERAL REQUIREMENTS
07/16
1. INSURANCE - MINIMUM AMOUNTS
1.1. Reference Contract Clause titled, “Insurance -Work on a Government
Installation (FAR 52.228-5). Kinds and minimum amounts are as follows:
KIND AMOUNTS (FAR 28.307-2)
Workmen’s Compensation $100,000 (see paragraph 1.2, below)
Comprehensive General Liability $500,000 per occurrence for bodily injury
Comprehensive Automobile Liability $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage
(If applicable) $200,000 per person and $500,000 per occurrence
Aircraft Public and Passenger for bodily injury, other than passenger
Liability liability and $200,000 per occurrence for property damage; coverage for passenger liability bodily injury shall be at least
$200,000 multiplied by the number of seats
$200,000 multiplied by the number of seats or passengers, whichever is greater
1.2. Except in states with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.
1.3. NOTE: Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the
Government’s interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The
Contractor shall maintain a copy of proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance, and shall make copies available to the Contracting
Officer upon request.
2. ORDER OF PRECEDENCE (REFERENCE FAR 52.236-21)
2.1. Any inconsistency in this solicitation or contract will be resolved by giving precedence in the following order:
1) Representations and other instructions,
2) Contract clauses,
3) Other documents, to include special contract requirements Section
00800, exhibits, and attachments, 01 00 00.00 – Page 2
4) The specifications
5) The drawings
3. SCHEDULING
3.1. Normal base work hours for the Contractor will be between the hours of
7:30 AM through 5:00 PM, excluding Saturdays, Sundays, and Federal
Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer’s Representative (COR) five (5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces. When the
COR determines that they are reasonably available, he may authorize the
Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the
Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.
3.2. The following Federal legal Holidays are observed by this base:
New Year’s Day 1 January
Martin Luther King’s Birthday Third Monday of January
President’s Day Third Monday of February
Memorial Day Last Monday of May
Independence Day 4 July
Labor Day First Monday in September
Columbus Day Second Monday in October
Veteran’s Day 11 November
Thanksgiving Day Fourth Thursday in November
Christmas Day 25 December
3.3. NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday; holidays falling on a Sunday will be observed on the following Monday.
3.4. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the contractor must notify the Contracting Officer (or the Contracting Officer’s
Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting
Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The purpose of the above precautions is to ensure construction inspection and recording of work proceedings.
3.5. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the
Contractor in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.
4. INVOICING AND PAYMENT
01 00 00.00 – Page 3
4.1. Properly prepared invoices, bearing the contract number, shall be submitted in quadruplicate to the Contracting Office, USPFO For South
Carolina, 9 National Guard Rd, Columbia, SC 29201, on designated invoice forms provided at the pre-construction meeting PRIOR to uploading in Wide Area Workflow (WAWF) the DFAS paying system. This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow (WAWF). See end of this Section for important information and codes needed.). Payment will be made by in accordance with FAR Clause 52.232-5 Fixed-Price Construction Contracts and FAR Clause 52.232-27, Prompt Payment for Construction Contracts, All payments will be made by electronic transfer of funds (EFT).
4.2. To meet compliance with DFARS 252.232-7003, Electronic Submission of
Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://wawf.eb.mil. Payment will be made by paying office specified in the contract award in accordance with the clauses
Payments under Fixed-Price Construction Contracts, FAR 52.232-5, and
Prompt Payment for Construction Contracts, FAR 52.232-27.
4.3. The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment.
Do not input invoice into WAWF until the pre-approval of invoice is received from the contracting officer. This will lessen the need for rejections in WAWF Payment may be withheld unless all contractual requirements including but not limited to: RECEIPT OF PROPER WEEKLY
PAYROLLS IAW DAVIS BACON REQUIREMENTS, Small Business Subcontracting
Reports, have been timely received.
4.4. All requests for payments through WAWF must include a Subcontractor
Payment Register pursuant to FAR Clause 52.232-5 and a contractor’s certification that reads as follows:
I hereby certify, to the best of my knowledge and belief that –
The amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract; All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and requirements of Chapter 39 of Title 31, United States Code; This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from subcontractor or supplier in accordance with the terms and conditions of the subcontract; and This certification is not to be construed as final acceptance of a subcontractor’s performance.
4.5. The Government will make payment upon satisfactory completion of work
AND receipt of a proper certification for payment. Payment may be withheld unless all contractual requirements, including but not limited to: RECEIPT OF PROPER WEEKLY PAYROLLS IAW DAVIS BACON REQUIREMENTS, and Small Business Subcontracting Reports, have been timely received.
Payrolls shall indicate CLIN to which they are applicable.
01 00 00.00 – Page 4
A release of claims is required for all final payment requests and shall be submitted by the contractor with the final invoice.
5. CONTRACT ADMINISTRATION
5.1. The contracting office of the USPFO for South Carolina, 9 National
Guard Rd, Columbia, SC 29201, is the office having administrative jurisdiction over this contract for all matters. A list of the names and telephone numbers of the Government team comprising the contract administrator, Contracting Officer’s Representative (COR), consultant, and point of contact at the project site will be provided at the post-award/pre-construction conference.
5.2. All correspondence shall be addressed to the Contracting Officer. A copy of all correspondence shall be furnished to the contracting officer’s representative. Enclosures attached to or transmitted with the correspondence shall also be furnished with an original and one copy. Each letter shall make reference to the contract name, contract number, project number, and project title, and shall have only one subject. For tracking purposes, a sequential numbering system should be used for all correspondence.
6. PAPERLESS CONTRACTING
6.1. The National Guard is fully committed to the Federal Government’s electronic commerce and paperless contracting initiatives. As such, it is anticipated that to the maximum extent possible to include but not limited to correspondence, modification distribution, etc., to include specifications and drawings, will be issued using electronic methods, i.e., electronic mail (e-mail). Contractors shall have and maintain capability to receive documents in this manner.
6.2. Additionally, it is anticipated that within the life of this contract, other electronic processes will be enacted. These include, but are not limited to, electronic bidding/offers, change order proposals, and electronic invoicing. When implemented by the Contracting Officer, contractors shall participate fully in any of these new requirements at no additional cost to the Government.
7. TELEPHONE COMMUNICATIONS SECURITY MONITORING
7.1. All communications with DOD organizations are subject to communications security (COMSEC) review. Contractor personnel must be aware that telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations.
Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The contractor shall assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.
8. UTILITY SERVICES
01 00 00.00 – Page 5
8.1. The Contracting Officer has determined that Government-operated utilities are adequate and will be furnished to the contractor without charge where existing outlets are available. The contractor is responsible for installing temporary service outlets, as necessary, at its expense in accordance with the clause entitled “Availability and
Use of Utility Services” (FAR Clause 52.236-14). The following utilities will be available: Power, Water, and Sewer.
9. PREPARATION OF MATERIAL APPROVAL SUBMITTALS
9.1. The contractor shall submit all materials and articles requiring approval, as required by the Material and Workmanship Clause, FAR
52.236-5. Submittals shall be made using AF Form 3000, or approved equal. Submittals shall be processed in accordance with the procedures in Section 01 33 00, Submittals. Submittals shall be given a distinct identification system by CLIN if multiple CLINS are applicable.
Individual submittal documents shall not be comprised of items for more than one CLIN. Address for delivery of submittals will be provided at the post award/pre-construction conference. The contractor is reminded that an individual within the company who has authority to make the certification must sign the certification on the AF Form 3000.
10. WORK PROGRESS AND PREPARATION OF PROGRESS SCHEDULES AND REPORTS
10.1. A weekly meeting may be held with the Contractor, COR and Contracting Officer (KO), if necessary, to discuss work progress, problems and potential change orders. The Contractor shall attend these meetings at no additional cost to the Government. Prior to beginning work on specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premises and buildings; space for storage of materials and equipment;
delivery of materials; and use of approaches, use of corridors, stairways and similar means of passage.
10.2. In accordance with FAR Clause 52.236-15, “Schedules for Construction
Contracts”, the contractor shall within five days after work commences on the contract, or another period of time determined by the KO, prepare and submit to the KO for approval three copies of a practicable schedule showing the order in which the contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing features of work. A composite schedule for the overall contract shall also be provided. The schedule shall be on an AF Form
3064, Contract Progress Schedule, or an approved computer generated format similar to the AF Form 3064. The work shall be scheduled so that, upon the start of construction, work progresses in a continuous and diligent manner. A schedule which does not reflect steady and reasonable progress throughout the construction period will be rejected. Both the Contractor and the COR are required to provide monthly progress reports covering the period from notice to proceed through final inspection. Unless agreement cannot be made on the applicable percentage of progress a joint report will be submitted to the Contracting Officer. This reports shall be submitted on the NGB
Contract Progress Report form (similar to an AF Form 3065), or an
01 00 00.00 – Page 6 approved computer generated similar format. These reports shall track progress by CLIN, if contract contains multiple CLINs, multiple AF Form
3064 and NG Contract Progress Reports will also be required for payment purposes.
10.3. Additionally, for projects exceeding $1M, the contractor shall provide a project plan in a commercially available network scheduling software that meets requirements of the specification to define work tasks and track progress. At least five days prior to work initiation, the contractor shall provide the Contracting Officer a hardcopy CPM and a formatted diskette or CD copy, or e-mail file copy, of the plan that shall include definition of rescues. No work may start until the
Contracting Officer approves the plan in writing.
10.4. The Contractor shall prepare a work progress schedule required for completion of each of the various divisions of work. Updated plans and
Form 3064 showing work progress (hardcopy and formatted diskette or CD, or e-mail file copy), unless otherwise directed by the Contracting
Officer, shall be provided monthly If there are possible deviations from the original plan, those must be noted and approved by the
Contracting Officer before work changes are implemented. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed. Reference Contract Clause FAR 52.236-15, “Schedules for
Construction Contracts”. The reports contemplated by the clause herein titled “Schedules for Construction Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule” and a National Guard Contract Progress
Report”.
11. NOTICE OF COMPLETION OF CONSTRUCTION/PRE-FINAL AND FINAL INSPECTION
11.1. The contractor shall conduct a pre-final inspection in the presence of the Contracting Officer’s Representative (COR) prior to the date scheduled for Final Inspection. Any discrepancies noted shall be corrected prior to Final Inspection.
11.2. The contractor shall request scheduling of a final inspection in writing to the Contracting Officer at least five (5) working days prior to the desired date or as otherwise negotiated with the Contracting
Officer.
11.3. Civil Engineering personnel and the Contracting Officer will perform the Final Inspection in the presence of the contractor, and any discrepancies noted shall be corrected within the time specified by the
Contracting Officer.
11.4. Final Inspection shall not constitute acceptance of a project unless so stipulated by issuance of a separate acceptance notice.
11.5. The contractor is cautioned to ensure they have completed adequate
Quality Control reviews prior to scheduling pre-final or final inspections. In the event the Contracting Officer finds that the project is not ready for the applicable inspection, (too many discrepancies) the contractor may be held liable for the costs of a
01 00 00.00 – Page 7 repeat inspection. If the inspection involves A/E personnel these costs may include additional labor, travel and miscellaneous expenses.
12. DESIGNATION OF TECHNICAL REPRESENTATIVE
12.1. The Contracting Officer will appoint a qualified Contracting Officer’s Representative (COR) for the purposes of technically administering the contract; however, all matters concerning this contract or any work ordered placed against this contract must first be approved by the
Contracting Officer. This in no way authorizes anyone other than the
Contracting Officer to commit the Government to changes in terms of the contract.
13. CONTRACTOR STAFF AND EMPLOYEES
13.1. Prior to commencing on-site construction, the contractor shall provide the Contracting Officer with a telephone number and FAX number at which the contractor or his representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.
13.2. Supervision. The Government shall not exercise any supervision or control over the contractor employees performing services under this contract; such employees shall be accountable not to the Government, but solely to the contractor, who in turn is responsible to the
Government.
13.3. Contractor’s Employees. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting
Officer may, in writing, require the contractor to remove from the job site, any employee the Contracting Officer deems incompetent, careless or otherwise objectionable.
14. CONTRACTOR OFFICE AND STORAGE
14.1. Parking of contractor vehicles shall be restricted to the contractor’s designed on-site area or the work area. The company name shall be prominently displayed on all construction vehicles parked on the job site.
14.2. Security of material storage areas on the job site shall be the responsibility of the contractor. The area shall be kept neat and orderly and free of debris.
15. RECORD DRAWINGS
15.1. During construction of a project and on the job site, the contractor shall maintain a completed record of all changes and corrections from the layout shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly, and submit the “red line” drawings to the Contracting Officer upon completion of the project. The record drawings shall indicate all changes and corrections concerning the actual locations of all sub-surface utility lines. In order for the location of these lines and
01 00 00.00 – Page 8 appurtenances to be determined in the event the surface opening or indictors become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of the each run including each change in direction. Valves splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded. The Government does not guarantee the accuracy of existing record drawings; it is the contractor’s responsibility to verify all as-built conditions.
16. VERIFICATION OF DIMENSIONS
16.1. The contractor shall be responsible for the coordination and proper relation of all aspects of the work. He/she shall field verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with any phase of the work. Where exact locations are not given for the positioning of equipment and devices, they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts.
17. SECURITY REQUIREMENTS
17.1. The contractor shall comply with all security regulations imposed by the base/post commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.
17.2. It is expected that new security requirements to satisfy contractor personal identification requirements in Homeland Security Presidential
Directive (HSPD-12), ''Policy for a Common Identification Standard for
Federal Employees and Contractors,'' and Federal Information Processing
Standards Publication (FIPS PUB) Number 201, ''Personal Identity
Verification (PIV) of Federal Employees and Contractors” are incorporated in the life of this contract. Contractor shall comply with all requirements, at no additional cost to the Government.
17.3. The contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.
17.4. Contractors shall follow instructions provided by the Security Forces for access to the McEntire Joint National Guard Base, Eastover, South
Carolina. If a gate pass is not granted to a contractor allowing the delivery of goods, execution of warranty support, or performance of services please contact the contracting officer. Be sure that all of your employees have the proper ID (drivers license, state ID, immigration card, U.S. Passport, etc.). If they do not have the proper
ID, they will be turned away.
17.5. The Prime Contractor and all of its subcontractors will be required to wear orange or lime colored safety vests while performing work on the installation.
17.6. U.S. Government will not be held liable for any delays or breach of contract caused by refusal of the Security Forces to allow entry.
01 00 00.00 – Page 9
17.7. All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S., and are authorized by the US government to work in the United States (i.e.
Green card, worker authorization, etc.). All prospective contractors
MUST have at least one form of U.S. government issued photo identification (drivers license, U.S. passport, U.S. work visa, etc.)
for entry to the installation. Security Forces will review any questionable identification documents for determination as to whether or not said identification is authorized for access to the installation.
17.8. All prospective contractors/contractor employees, once it has been established that they maintain the appropriate credential as described in one above, are subject to a Criminal History Check.
17.9. Note: For the purposes of Contracting services, it is implied that, that any and all parties agree to a Criminal History Background Check once entered into any contract. Any documents that are provided and found fraudulent to include, but not limited to driver’s licenses, contracting licenses, etc., will result in an arrest and potential termination for default from the contract. All contractors are subject to search in order to obtain entry onto the installation and while working on the installation. Any refusal to submit to a search of their person or vehicle will be deemed as a violent act of aggression against the installation and will be cause for dismissal from the installation and revocation of future privileges and installation access.
17.10. AT Level I Training. This provision/contract text is for contractor employees with an area of performance within a National
Guard controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to
National Guard installations, facilities and controlled access shall complete AT Level I awareness training. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the Contracting Officer’s Representative
(COR).
17.11. AT Level 1 awareness training is available at the following website: https://atlevel1.dtic.mil/at
18. REGULATIONS
18.1. The contractor shall comply with all applicable Federal, State, Local, DOD, National Guard Bureau, Army and Air Force regulations pertaining to safety, traffic control and fire prevention.
18.2. The contractor may use the Civil Engineering library, which contains most applicable Army and Air Force publications as well as some commercial project data information, or the Defense Procurement and
Acquisition Policy website, http://www.acq.osd.mil/dpap/, which has links for several other sites with available publications, forms and project data information. These may also be acquired from the
Government Printing Office website, http://www.gpoaccess.gov/index.html https://atlevel1.dtic.mil/at http://www.acq.osd.mil/dpap/ http://www.gpoaccess.gov/index.html
01 00 00.00 – Page 10
19. TRANSPORTATION, HANDLING AND STORAGE
19.1. The contractor shall coordinate with suppliers and shippers to ensure that incoming materials are properly identified with the contractor’s name, contract number and project title. The contractor shall designate an authorized individual to be available to receive shipment.
The Government will not provide storage other than that available at the project site.
19.2. Storage of supplies, materials and equipment on the project site shall be accomplished in such a manner so as to prevent mechanical and climatic damage and loss due to vandalism or theft. Equipment temporarily removed in the performance of work and stored on the job site shall be stored and protected in accordance with previous paragraphs, and shall be replaced in a condition compatible with its original state. Security for equipment and material removed from the job site for temporary storage until reuse shall be the responsibility of the contractor.
20. CLEANUP AND DISPOSAL OF DEBRIS AND FILL MATERIALS
20.1. At the end of each workday, the contractor shall clean up the work and storage areas and stack all materials in a manner approved by the
Contracting Officer or his designated representative. Upon completion of a project, the contractor shall ensure that all dirt, trash, and debris resulting from the construction operations are removed from the work area. Unless directed otherwise in the contract or by the
Contracting Officer, disposal of debris shall be made at the contractor’s expense and shall be delivered to a state approved disposal site located off base. Debris shall not be left in such a manner that wind or other weather conditions can cause the debris to be scattered outside the work area (i.e., on nearby runways, ramps or taxiways).
20.2. The hauling and disposal of excess fill material including rock, gravel, sod, broken concrete or asphalt, plaster, etc., shall be the responsibility of the contractor. Disposal shall be in accordance with applicable state and local regulations.
21. ENVIRONMENTAL IMPACT
21.1. All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law. Should the United States
Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
22. HAZARDOUS MATERIALS
01 00 00.00 – Page 11
22.1. Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the
Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract.
22.2. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos-containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating. Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
23. POLLUTION ABATEMENT
23.1. All work shall be performed in a manner minimizing pollution of air, water and land as required.
23.2. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected. Gravel, sand and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the contractor.
23.3. Burning of any material is strictly prohibited.
23.4. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials. Grading shall be accomplished to prevent surface drainage from the construction site containing harmful amounts of sediment from draining onto adjacent areas.
23.5. Flushing of concrete trucks is restricted to the location specifically designed for this purpose by the Contracting Officer’s Representative.
23.6. Excess mortar, plaster or drywall materials shall not be disposed of on Government property. Water utilized for plastering or drywall equipment shall be disposed of in accordance with the instructions of the COR, and under no circumstances shall water be disposed of in areas which are planted or scheduled to be planted.
01 00 00.00 – Page 12
24. COORDINATION WITH GOVERNMENT ACTIVITIES
24.1. If it becomes necessary to interrupt work activities in buildings and/or areas for construction purposes, permission to do so must be requested in writing to the Contracting Officer 5 working days prior to commencing work on the planned interruption and shall be subject to
Civil Engineering approval. Written requests for street closing shall be submitted for approval of the Civil Engineer 5 working days prior to closing the street.
24.2. Work in connection with this contract which requires utility outages, including electrical, water, gas, steam, etc., which will close down or limit (as determined by the Contracting Officer) normal activities in the building, construction area or other affected areas, shall be performed by the contractor at a time other than the regular work period of the organization occupying the facility. Work required by the contractor on a non-standard basis or at premium pay shall be done at no additional cost to the Government. Request for utility outages shall be submitted to the Civil Engineer, in writing 5 working days prior to commencing work and shall be subject to his/her approval.
24.3. Any temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utility services shall be subject to Contracting Officer’s approval.
25. UNAUTHORIZED PERSONNEL
25.1. The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices, and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
26. PERFORMANCE EVALUATION OF CONTRACTOR
26.1. As a minimum, the contractor’s performance will be evaluated upon final inspection. Any specific requirements for contract quality control and quality assurance by the Government personnel will be defined in the specifications. The contractor will be rated as outstanding, satisfactory or unsatisfactory in the areas of contract quality control, timely performance, effectiveness of management, compliance with labor standards, and compliance with safety standards. The contractor will be notified of any unsatisfactory rating, either in an individual element or in the overall rating, prior to completing the evaluation, and all contractor comments will be made a part of the official record. Performance evaluation reports will be available to all DoD Contracting Officers for their future use.
26.2. Past Performance evaluations will be posted via https://www.cpars.gov.
It is the responsibility of the contractor to request access to this site.
https://www.cpars.gov/
01 00 00.00 – Page 13
27. CONTRACTOR QUALITY CONTROL
27.1. The contractor shall comply with the quality control provisions as specified herein. The Contractor shall perform all quality control inspection and/or testing required by this contract unless specifically designated to be performed by the Government. The quality control system consists of plans, workmanship, fabrication, construction, and operations that comply with contract requirements. The system shall cover construction operations, including fabrication both on-site and off-site, and shall be keyed to the proposed construction sequence. If the contractor fails to submit an acceptable quality control plan within the time herein prescribed, the Contracting Officer may refuse to allow construction to start if an acceptable interim plan is not furnished or may withhold funds from progress payments in accordance with the contract clause titled, “Payments under Fixed Price
Construction Contracts”, until such time as the contractor submits an acceptable final plan.
27.2. Quality Control Plan
27.3. General. Upon receipt of the Notice of Contract Award, the contractor’s quality control plan (2 copies) shall be submitted for acceptance in accordance with division 014000-1 of the specifications.
27.4. Acceptance. The Contracting Officer’s Representative will review the quality control plan. The contractor shall make such changes and additions as necessary for clarity and completeness as requested by the
Contracting Officer’s Representative through the Contracting Officer.
Acceptance of the contractor’s plan is predicated on satisfactory performance during construction. Acceptance is conditional and the
Government reserves the right to require the contractor to make changes in quality control plans, personnel and operations to correct deficiencies and to assure contract compliance.
27.5. Changes. When the contractor proposes changes in the quality control plan or implementation during construction, the Contracting Officer shall be notified in writing. The contractor shall implement no changes prior to acceptance in writing by the Contracting Officer.
28. SAFETY ASSURANCE
28.1. Compliance with Regulations. All work including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1910/1926. Work involving the disturbance or dismantling of asbestos or asbestos-containing materials; the demolition of structures containing asbestos; and/or disposal and removal of asbestos, shall also comply with the requirements of 40 CFR, Part 61, Subpart A. All work shall comply with applicable state and municipal safety and health requirements. Where there is a conflict between applicable regulations, the most stringent shall apply. The
Safety Manual is available at the following web site:
http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRe quirementsManual.aspx http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx
01 00 00.00 – Page 14
28.2. Contractor Responsibility. The contractor shall assume full responsibility and liability for compliance with all applicable regulations pertaining to the health and safety of personnel during the execution of work. The Government shall not be held liable for any actions on the part of the contractor, his employees or subcontractors, which result in illness, injury or death.
28.3. Inspections, Tests and Reports. The required inspections, tests and reports made by the contractor, subcontractors, specially trained technicians, equipment manufacturers and others as required, shall be at the contractor’s expense.
28.4. Materials and Equipment. Special facilities, devices, equipment, clothing and similar items used by the contractor in the execution of work shall comply with applicable regulations.
28.5. Traffic Control Devices. The contractor shall comply with the recommendations contained in Part 6 of the U. S. Department of
Transportation, Federal Highway Administration’s “Manual on Uniform
Traffic Control Devices”, 2003 edition with Revision 2 available at http://mutcd.fhwa.dot.gov/)to ensure proper warnings to motorists and adequate traffic control. The contractor shall provide all warning lights, barricades and other traffic control devices and signs.
29. WORK BY THE GOVERNMENT
29.1. The Government reserves the right to undertake performance by
Government forces, for the same type or similar work as contracted herein, as the Government deems necessary or desirable, and to do so will not breach or otherwise violate this contract.
30. VALUE ENGINEERING CHANGE PROPOSALS
30.1. All value engineering change proposals (VECP’s) shall be submitted in accordance with the requirements of FAR Clause 52.248-3, Value
Engineering – Construction. All VECP’s shall be submitted in 3 copies.
31. PRE-CONSTRUCTION CONFERENCE
31.1. Before work commences on this contract, the Contracting Officer will conduct a conference to acquaint the contractor with Government policies and procedures that are to be observed during the execution of the work and to develop mutual understanding relative to the administration of the contract. Contractors and/or major subcontractors shall attend this meeting at no additional cost to the
Government.
32. RESERVED
33. MILITARY REAL PROPERTY DATA – DD FORM 1354
33.1. Contractors shall furnish real property data to the Government for each new construction and/or renovation project awarded, unless otherwise notified. The real property data shall be furnished via DD Form 1354, 01 00 00.00 – Page 15
Transfer and Acceptance of Military Real Property, or in a format prescribed on the DD Form 1354. The Contractor is responsible for accuracy of data current up to the time of submission.
33.2. For major renovation and/or complex projects, or those expected to exceed 12 months, the Contractor shall furnish real property data no less than on a quarterly basis. Frequency of submission shall be standard throughout the duration of the project. Contractors are advised to record information on the DD Form 1354 (or approved facsimile) as the project progresses, due to the volume of data required to be furnished. Upon completion of the project, the
Contractor shall furnish a final, comprehensive DD Form 1354.
33.3. DD Form 1354 accounts for five percent (5%) of the total contract amount and therefore, 5% must be shown on the AF Form 3065 or similar breakdown of costs submitted for payment purposes. Upon acceptance of data by the real property specialist, the contractor may invoice for submission of real property data.
33.4. Contractors should contact Maj Gareth Fleischer (803) 647-8647 with questions pertaining to the DD Form 1354. For construction data assistance, Contractors may consult the COR assigned to the project.
34. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
34.1. This Paragraph specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting
Officer to award a time extension under this clause, the following conditions must be satisfied:
34.2. The weather experienced at the project site during the contract period must be found to…