Attachment 2 - Specification Clarifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Hydrant_Loop_Q&A__1.DOCX | DOCX document | |
| Site_Visit_Attendance.pdf | ||
| EXHIBIT_B_Information_and_Consent_Form.doc | DOC document | |
| EXHIBIT_A_Performance_Relevancy.doc | DOC document | |
| Drawing_Clarifications.pdf | ||
| W912PQ18R7003_UPGRADE_HYDRANT_LOOP.pdf | ||
| 60341187_Final_Specs_6-6-16.pdf | ||
| EXHIBIT_C_Package_Information_and_Forms.doc | DOC document | |
| Drawings_Reduced.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION CLARIFICATIONS
Disregard all U.S. ARMY CORPS OF ENGINEERS (USACE) references. USACE is not involved in any way with this project. Specifications provided from USACE documents are to be followed but only if they are in these specific project specifications.
01 11 00 - 1.8 LOCATION OF UNDERGORUND UTILITIES - Dig permits must be worked with Dig Safe and the 109th Civil Engineer Squadron. 7 days' notice is required.
01 11 00 - 1.9 SALVAGE MATERIAL AND EQUIPMENT - The 109th is not looking to salvage any materials or equipment.
01 14 00 - 1.4.1.2 Identification Badges and installation Access - all contractors outside of deliveries will be required to submit a badge application no less than 3 work days prior to arrival. If cleared to come on the installation, they will have to be escorted to Security Forces. This process takes approx. 30 min per person. Once badged they will have access to the work site without having to check in and out.
01 14 00 - 1.4.3 Working Hours - Base hours of operation are 7:00 am to 4 pm.
01 30 00 - 1.3 PROGRESS AND COMPLETION PICTURES - This is not a requirement
01 30 00 - 1.8 PARTNERING - This is not a requirement
01 32 0.00 10 PROJECT SCHEDULE - This section is not a requirement. A project schedule will be required prior to beginning construction operations but Primavera P6 is not a requirement. Other schedule options are to be approved by Contracting.
01 33 29 - SUSTAINABILITY REPORTING - This is not a requirement (no buildings are part of this project)
01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS - All applicable OSHA requirements are to be followed. Safety is the responsibility of the Contractor but the 109th has the right to stop any actions they deem as unsafe.
01 50 00 - 3.3 - AVAILABILITY AND USE OF UTILITY SERVICES - This is not a requirement except for 3.3.6 and 3.3.7. If the contractor is required to tie into the 109th's power source there will not be a need for the amount of power to be metered. Bathrooms, temporary facilities and phones will not be provided by the 109th.
01 58 00 - PROJECT IDENTIFICATION - This is not a requirement
01 74 19 - CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT - This is not a requirement. Contractor is responsible for removing all waste from the site.
All contractors on site should recycle as much material as they are able to.
Some recyclable material can be removed by the base if approved by Contracting office.