Hydrant_Loop_Q&A__1.DOCX
DOCX document 13 KB Posted
- Attached to
- Upgrade Hydrant Loop Federal contract opportunity
- Solicitation number
- W912PQ18R7003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Attendance.pdf | ||
| Specification_Clarifications.pdf | ||
| EXHIBIT_B_Information_and_Consent_Form.doc | DOC document | |
| EXHIBIT_A_Performance_Relevancy.doc | DOC document | |
| Drawing_Clarifications.pdf | ||
| W912PQ18R7003_UPGRADE_HYDRANT_LOOP.pdf | ||
| 60341187_Final_Specs_6-6-16.pdf | ||
| EXHIBIT_C_Package_Information_and_Forms.doc | DOC document | |
| Drawings_Reduced.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTION 1: Looking at the Bid Forms, Item No. 0001 – Repair – Includes Site Prep, Repair Hydrants, Repair Water Vault UG Water Meter?
There is no repair work shown on the plans. Everything shown is new construction. Under this item do we only include the New Hydrants on the Existing Water mains?
ANSWER 1: Item 0001 only includes the new hydrants and vault; all the plumbing in the vault will be in Item 0002.
QUESTION 2: For Item No 0002 – Do we include all of the new 8” Water Main Costs, the Back Flow Preventer and the New Water Meter & Vault in this Item?
ANSWER 2: Yes on everything except for the vault itself which should be included in Item 0001.
QUESTION 3: What Item No. Do we place the Removal of the Existing Water meter Vault?
ANSWER 3: CLIN 0001
QUESTION 4: What Item No. do we place the 8” Insertion Valve Cost?
ANSWER 4: CLIN 0002
QUESTION 5: Clarify Item No. 0003 “Contract Manpower Report” (CMRA) what is this?
ANSWER 5: Contract Manpower Reporting is a Congressional Requirement placed on Department of Defense Agencies to account for all contracted labor hours (to include subcontractor labor hours) required for the performance of services to include construction.
For this item (Item 0003) the successful contractor shall report the total of all contractor labor hours (including subcontractor labor hours) required for the performance of this project to the secure data collection site at http://www.ecmra.mil/ Again, reporting is accomplished based on TOTAL hours (not broken down by trade, person, company, etc.) For example, if a project took 10 people, one 40 hour week to accomplish, the report would be 400 hours (10 x 40 = 400).
Contractors may charge a reasonable fee for this reporting requirement. If you choose to charge for this reporting, the charge must be annotated on Item 0003. If there is no charge, this should be annotated as well.
According to the Army CMRA Website (https://cmra.army.mil/notices/Disclosure.aspx) “The public reporting burden for this collection of information is estimated to average 5 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.” If you choose to charge for this requirement, please do so accordingly.
QUESTION 6: Since we will be in rock for some of the new water main will Trench Blasting me permitted?
ANSWER 6: No blasting will be permitted. Stone typically exists of shale and can be removed by excavator or jackhammer attachment.