Hydrant_Loop_Q&A__1.DOCX

DOCX document 13 KB Posted

Attached to
Upgrade Hydrant Loop Federal contract opportunity
Solicitation number
W912PQ18R7003
Issued by
Department of the Army New York Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Upgrade Hydrant Loop, newest first.
File Type Posted
Site_Visit_Attendance.pdf PDF
Specification_Clarifications.pdf PDF
EXHIBIT_B_Information_and_Consent_Form.doc DOC document
EXHIBIT_A_Performance_Relevancy.doc DOC document
Drawing_Clarifications.pdf PDF
W912PQ18R7003_UPGRADE_HYDRANT_LOOP.pdf PDF
60341187_Final_Specs_6-6-16.pdf PDF
EXHIBIT_C_Package_Information_and_Forms.doc DOC document
Drawings_Reduced.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION 1: Looking at the Bid Forms, Item No. 0001 – Repair – Includes Site Prep, Repair Hydrants, Repair Water Vault UG Water Meter?

There is no repair work shown on the plans. Everything shown is new construction. Under this item do we only include the New Hydrants on the Existing Water mains?

ANSWER 1: Item 0001 only includes the new hydrants and vault; all the plumbing in the vault will be in Item 0002.

QUESTION 2: For Item No 0002 – Do we include all of the new 8” Water Main Costs, the Back Flow Preventer and the New Water Meter & Vault in this Item?

ANSWER 2: Yes on everything except for the vault itself which should be included in Item 0001.

QUESTION 3: What Item No. Do we place the Removal of the Existing Water meter Vault?

ANSWER 3: CLIN 0001

QUESTION 4: What Item No. do we place the 8” Insertion Valve Cost?

ANSWER 4: CLIN 0002

QUESTION 5: Clarify Item No. 0003 “Contract Manpower Report” (CMRA) what is this?

ANSWER 5: Contract Manpower Reporting is a Congressional Requirement placed on Department of Defense Agencies to account for all contracted labor hours (to include subcontractor labor hours) required for the performance of services to include construction.

For this item (Item 0003) the successful contractor shall report the total of all contractor labor hours (including subcontractor labor hours) required for the performance of this project to the secure data collection site at http://www.ecmra.mil/ Again, reporting is accomplished based on TOTAL hours (not broken down by trade, person, company, etc.) For example, if a project took 10 people, one 40 hour week to accomplish, the report would be 400 hours (10 x 40 = 400).

Contractors may charge a reasonable fee for this reporting requirement. If you choose to charge for this reporting, the charge must be annotated on Item 0003. If there is no charge, this should be annotated as well.

According to the Army CMRA Website (https://cmra.army.mil/notices/Disclosure.aspx) “The public reporting burden for this collection of information is estimated to average 5 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.” If you choose to charge for this requirement, please do so accordingly.

QUESTION 6: Since we will be in rock for some of the new water main will Trench Blasting me permitted?

ANSWER 6: No blasting will be permitted. Stone typically exists of shale and can be removed by excavator or jackhammer attachment.