15-R-0005Amend1.pdf
PDF 22 KB Posted
- Attached to
- AIR MONITORING FOR ASBESTOS REMOVAL
- Solicitation number
- W912PQ15R0005
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912PQ15-C-0004_GYMO _PC.pdf | ||
| W912PQ-15-R-0005-0003.doc | DOC document | |
| Amend_2.pdf | ||
| 15-R-0005Amend1Conf.pdf | ||
| W912PQ15R0005 AIRMONITORING.pdf | ||
| SOW_Asbestos_Abatement_2_and_3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA6323 - 109 MSG/MSC STRATTON ANGB
1 AIR NATIONAL GUARD ROAD
SCOTIA NY 12302-9752
VBDZ152006
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
A. The proposal due date is extended to December 16, 2014 at 3 PM EST.
B. All CLINs w ere changed as a Not To Exceed item.
C. CLIN 0005 w as changed to an Option - and w ill be funded based on need. Clin 52.217-5 w as included in this RFP.
D. Questions and answ ers are hereby posted to this amendment.
E. Nothing follow s.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Dec-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PQ-15-R-0005
X 9B. DATED (SEE ITEM 11)
07-Nov-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Dec-2014
CODE
W912PQ - 109 MSG/MSC
1 AIR NATIONAL GUARD ROAD
SCOTIA NY 12302-9752
W912PQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W912PQ
FACILITY CODECODE
EMAIL:TEL:
W912PQ-15-R-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 11-Dec-2014 03:00 PM to 16-Dec-2014 03:00 PM.
The Issued By organization has changed from
W912PQ - USP&FO-NY
ATTN: MNPF-PC
330 OLD NISKAYUNA ROAD
LATHAM NY 12110-3514
to
W912PQ - 109 MSG/MSC
1 AIR NATIONAL GUARD ROAD
SCOTIA NY 12302-9752
Global Changes
CLIN 0001 -- CLIN 0005
The cost constraint NTE has been added.
CLIN 0001
The CLIN extended description has changed from Air Monitoring and Shielding, Asbestos Removal, Building 3 Hallway to Air Monitoring and Shielding, Asbestos Removal, Building 3 Hallway..
CLIN 0002
The CLIN extended description has changed from Air Monitoring and Shielding, Hangar 1 Pipe Removal to Air Monitoring and Shielding, Hangar 1 Pipe Removal..
CLIN 0003
The CLIN extended description has changed from Air Monitoring and Shielding, Add on #2, Buildiing 18 to Air Monitoring and Shielding, Building 18 (2 Rooms),.
CLIN 0004
The CLIN extended description has changed from Air Monitoring and Shielding, Add on #3, Building 1 to Air Monitoring, Building 1 Crawlspace.
CLIN 0005
The CLIN extended description has changed from Air Monitoring and Shielding, Add on #4, Building 2 Hallway Asbestos Abatement to Air Monitoring, Building 2 Hallway Asbestos Abatement..
The option status has changed from No Status to Option.
W912PQ-15-R-0005
SECTION 00700 - CONTRACT CLAUSES
The following have been added by reference:
52.217-5 Evaluation Of Options JUL 1990
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
The following have been added by full text:
QUESTIONS - ANSWERS
Question(s):
1. Can you provide us with the time estimate / duration to complete the abatement for each subproject? It's the only way we can accurately place a lump some bid. Also do you have an abatement plan outlining work areas and duration for each subproject?
2. Just to clarify; you are looking for a 3rd party air monitoring contractor during the abatement activities. How many total days of abatement are you anticipating?
Response: Yes; we are looking for a 3rd party air monitoring contractor during the abatement activities The following are estimated durations for the abatement of each work area:
CLIN LOCATION # Proj Days
0001 Building 3 Hallway: 7
0002 Hangar 1 (Pipe Removal): 10
0003 Building 18 (2 Rooms): 5
0004 Building 1 Crawlspace: 20
0005 Building 2 Hallways 10
3. Five (5) locations are asking for fees but the SOW lists a total of 7 locations. Please confirm the 5 locations listed in Section 0010 need air monitoring.
Response: Only the items listed above require air monitoring.
(End of Summary of Changes)