This solicitation is for the construction of a Special Operations Forces human performance training facility at Fort Bragg, North Carolina. The U.S. Army Corps of Engineers, Wilmington District is seeking a contractor to construct a building with cardio, strength and nutrition training areas, physical and hydro therapy spaces, special operations cognitive enhancement and human engagement training rooms, and shower and locker facilities. The facility is required to meet LEED Silver certification standards and include sustainable features. Supporting site work will involve utilities installation, parking, lighting, landscaping and demolition of existing structures. Comprehensive security, communication and audiovisual systems are also within the scope of work. The project value is between $25-100 million. The NAICS code is 236220 and firms must be registered in SAM to be eligible for award. The solicitation was posted to beta.SAM.gov under number W912PM20R0001.

View the file

Other files for this federal contract opportunity

Other files attached to PN 81165 SOF Human Platform FORGE, newest first.
File Type Posted
Bidder Site Visit Sign In PN81165 6August2020.pdf PDF
W912PM20R0001 Amendment 0006 Conformed Copy.docx.pdf PDF
W912PM20R0001 Amendment 0006.docx.pdf PDF
W912PM20R0001 Amendment 0005.pdf PDF
W912PM20R0001 Amendment 0005 Conformed Copy.docx.pdf PDF
PN81165_RTA_SPECS_Vol IV of IV no pricing_Redacted.pdf PDF
W912PM20R0001 Amendment 0004.pdf PDF
PN81165_RTA_SPECS_Vol II of IV_0004.pdf PDF
W912PM20R0001 Amendment 0001.pdf PDF
PN81165_RTA_SPECS_Vol III of IV_0004.pdf PDF
20R0001 Amendment 0004 Conformed Copy.docx.pdf PDF
PN81165_RTA_SPECS_Vol I of IV_0004.pdf PDF
PN81165_RTA_SPECS_Vol IV of IV.pdf PDF
W912PM20R00010003_Amendment.docx.pdf PDF
W912PM20R00010003_Conformed.docx.pdf PDF
W912PM20R00010002 Amendment.pdf PDF
W912PM20R00010002 Conformed.pdf PDF
Amendment 0001 Wage Determination .pdf PDF
Summary of Changes__PN81165_Amdt0001.pdf PDF
Conformed Solicitation PN 81165.pdf PDF
FY20PN81165-C-001 C-001.pdf PDF
PN81165_READY FOR ADVERTISEMENT_VOL 1(locked).pdf PDF
W912PM20R0001 PN81165 Human Performance FORGE.pdf PDF
PN81165_READY FOR ADVERTISEMENT_VOL2.pdf PDF
PN81165_RTA_SPECS_Vol III of III.pdf PDF
PN81165_RTA_SPECS_Vol II of III.pdf PDF
Attachment 5 NAVFAC_USACE PPQ.pdf PDF
PN81165_RTA_SPECS_Vol I of III.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sol No. W912PM20R0001

PN #81165

Amendment 0004

TECHNICAL SUMMARY OF CHANGES

A. SPECIFICATIONS:

(1.) SPECIFICATION COVER SHEET

Replace Cover sheets for ALL Volumes 1-3 and Create Spec Cover Sheet for Volume 4

(2.) 01 10 00.10 38- SUPPLEMENTARY SPECIAL CONTRACT

REQUIREMENTS DREDGING / CONSTRUCTION

Replace pages 1-39 with revised enclosed pages 1-39 in their entirety.

(3.) FF & E Package- VOLUME 04 Incorporate Volume 04 to specifications pages 1-167 in its entirety.

B. DRAWINGS: NO CHANGE

Encls As stated

SOF Human Platform-Force Generation (FORGE) Facility PN81165 Fort Bragg, North Carolina

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS DREDGING / CONSTRUCTION

08/18

PART 1 GENERAL

1.1 REFERENCES

1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS

1.3 IDENTIFICATION OF EMPLOYEES - MOTSU

1.4 SUBMITTALS

1.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.6 PERFORMANCE AND PAYMENT BONDS

1.7 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING

1.8 WATER CONSERVATION

1.9 LOCAL NOTICE TO MARINERS

1.10 NAVIGATION AIDS

1.11 SEAGOING BARGE ACT

1.12 BULLETIN BOARD

1.13 FINAL EXAMINATION AND ACCEPTANCE

1.14 WORK PLAN

1.15 PROGRESS SCHEDULE

1.16 CONTRACTOR FURNISHED GOVERNMENT OFFICE

1.17 ACCOMMODATIONS AND MEALS FOR INSPECTORS

1.18 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

1.19 SHOP DRAWINGS AND MATERIALS SUBMITTAL

1.20 SAMPLING, CERTIFICATES, AND TESTING

1.21 CERTIFICATES OF COMPLIANCE

1.22 CONTRACTOR-PREPARED NETWORK ANALYSIS SYSTEM

1.23 REQUIRED CONSTRUCTION MEETINGS

1.24 SURVEY DATA

1.25 "AS-BUILT" RECORD DRAWINGS

1.26 FINISH MATERIAL SUBMITTALS

1.27 ASBESTOS PERMIT AND NOTIFICATION

1.28 IDENTIFICATION OF GOVERNMENT-FURNISHED PROPERTY

1.29 AGGREGATE SOURCES

1.30 WORK IN QUARANTINED AREA

1.31 FINAL AND CONDITIONAL ACCEPTANCE OF GRASSING

1.32 ACCEPTANCE

1.33 NCDOT SPECIFICATIONS

1.34 DEFINITIONS FOR NCDOT SPECIFICATIONS

1.35 ADDITIONAL SURVEY AND SURVEY PERSONNEL REQUIREMENTS

1.36 PLANT LOCATION

1.37 PLANT

1.38 PUBLIC CONVENIENCE AND SAFETY

1.38.1 Roads To Be Closed

1.38.2 Storage of Materials

1.39 MAINTENANCE DURING CONSTRUCTION

1.39.1 Maintenance When Work is Suspended

1.39.2 Final Mowing

1.39.3 Spilled Materials

SECTION 01 10 00.10 38 Page 1

***AMENDMENT 0004***

1.40 INSPECTION

1.41 SIGNAL LIGHTS

1.42 PARTNERING

1.43 LOAD RESTRICTIONS

1.44 BARRICADES, DANGER, WARNING, AND DETOUR SIGNS

1.44.1 Removal of Barricades And Warning Signs

1.44.2 Replacement of Signs

1.44.3 Cost of Protective Devices

1.45 PROTECTION OF EXISTING FACILITIES

1.46 PLANT LAYOUT DRAWINGS

1.47 HAUL ROADS

1.48 ASBESTOS - (Occupational Health and Environment)

1.49 RESPONSIBILITY FOR BORROW AREA ACCESS ROAD

1.50 CONTRACT AREA AND TRESPASSING

1.51 COORDINATION WITH OTHER CONTRACTORS

1.53 EQUIPMENT TESTING AND INSTRUCTION

1.54 UNDERWATER DIVING OPERATIONS

1.55 ENVIRONMENTAL SENSITIVE AREA

1.56 CONTRACT DRAWINGS AND SPECIFICATIONS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 10 00.10 38 Page 2

SECTION 01 10 00.10 38

SUPPLEMENTARY SPECIAL CONTRACT REQUIREMENTS

DREDGING / CONSTRUCTION

08/18

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO American Association of State Highway and Transportation Officials

NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)

NCDOT Standard Specifications For Roads And Structures

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

ER 1110-1-5 Plant Pest Quarantined Area and Foreign Soil Sample

ER 415-1-15 Construction Time Extensions for Weather

U.S. DEPARTMENT OF TRANSPORTATION (DOT)

DOT Barricades, Danger, Warning and Detour Signs

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910.20 Access to Employee Exposure and Medical Records

29 CFR 1910.134 Respiratory Protection

29 CFR 1910.1001 Asbestos

29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

SECTION 01 10 00.10 38 Page 3

40 CFR 61.40 General Provisions

40 CFR 61.40-61.156 Cross-reference to other Asbestos Regulations

40 CFR 61.140 40 CFR Subpart M - National Emission Standard for Asbestos

40 CFR 61.156 National Emission Standard for Asbestos

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

49 CFR 172.101 Hazardous Material Regulation-Purpose and Use of Hazardous Material Table

49 CFR 173 Shippers - General Requirements for Shipments and Packagings

1.2 DEPARTMENT OF ARMY MANDATED SECURITY REQUIREMENTS

The Contractor shall be required to comply with the following security requirements mandated by the Department of the Army:

Short-term employees (working on site less than or equal to 6 months): If a criminal history is found, the employee MAY not be allowed to work at the project site at the sole discretion of the Government.

Long-term employees (working on site more than 6 months):

ALL of the following is required WHEN REPORTING FOR WORK -

a) A completed OMB Form No. 3206-0182 (also designated as Optional Form 306).

b) A completed OMB Form No. 3206-0191 (also designated as Standard Form 85P).

c) A resume.

The Government will use all provided information to perform a National Agency Check and Inquiries (NACI) check and will pay the required fee.

The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer or his/her designated representative. All prescribed identification shall immediately be delivered to the Contracting Officer or his/her designated representative for cancellation upon the release of any employee.

(End of Clause)

1.3 IDENTIFICATION OF EMPLOYEES - MOTSU

At least 10 days before mobilizing, the Contractor shall furnish the

SECTION 01 10 00.10 38 Page 4

Contracting Officer or his/her designated representative, names, driver's license, and vehicular tag numbers of each employee that will be working on this project. The Contractor shall require employees to display identification when requested.

If there are any changes in employees who are assigned to the work at any time after the information is submitted and prior to completion of work, the Contractor shall promptly furnish updated information to the Contracting Officer or his/her designated representative.

It will be the responsibility of the Contractor to take those measures which deem necessary to protect plant and personnel prior to beginning work.

The Contracting Officer or his/her designated representative will arrange an initial coordination meeting between the Contractor and MOTSU which will be held before the Contractor begins work. When work begins, the Contractor shall coordinate all activities with the designated MOTSU personnel on a day to day basis.

(End of Clause)

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.00 37 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Subcontractors

Progress Chart; G, A

Quality Control Plan; G, A

Certificate of Insurance

Within 24 hours of conclusion of physical tests, 5 copies of test results including calibration curves and results of calibration tests.

SD-03 Product Data

WORK PLAN

PROGRESS SCHEDULE

SD-07 Certificates

U.S. Coast Guard Certification

Completion of Corps CQC Course

Letter Appointing Superintendent

SECTION 01 10 00.10 38 Page 5

Qualifications of the commercial testing laboratory or Contractor's testing laboratory/facilities G, A

1.5 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

ER 415-1-15 dtd 31 OCT 89

(a) This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be found to be satisfied in the sole discretion of the Contracting Officer:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

(b) The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER

AND/OR SEA CONDITIONS DELAYS (HOURS)

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(c) Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day.

(d) The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph (2), above, the Contracting Officer will convert any

SECTION 01 10 00.10 38 Page 6 qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "DEFAULT (FIXED-PRICE CONSTRUCTION)".

(End of Clause)

1.6 PERFORMANCE AND PAYMENT BONDS

Each bidder shall include his premiums for performance and payment bonds under the appropriate, "Performance and Payment Bonds" contract line item of the Bidding Schedule. Payment to the Contractor therefore, shall not exceed the bid price and shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.

Each bidder shall include in his bid premiums for performance and payment bonds. Payment shall be made in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount bid in excess of the actual bond premium will be included in the final pay estimate for this contract.

Each bidder shall include his premiums for performance and payment bonds in his bid. Payment to the Contractor therefore, shall be made in accordance with the Contract Clause entitled in accordance with the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS." Any additional amount included in the Contractor's bid which is in excess of the actual bond premium will be included in the final pay estimate for this contract.

(End of Clause)

1.7 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING

(1998 January HQUSACE)

(a) Where the quantity of a pay item in this contract is an estimated quantity and where the actual quantity of material within the required dredging prism, including the associated side slopes, varies more than 15 percent above or below the stated estimated quantity within the required dredging prism, an equitable adjustment in the contract unit price will be made upon demand of either party. The equitable adjustment will be based upon any increase or decrease in the costs due solely to the variations above 115 percent or below 85 percent of the estimated quantity within the required dredging prism. Any equitable adjustment in the contract unit price will also apply to that part of the actual quantity of allowable over-depth material above 115 percent or below 85 percent of the estimated allowable over-depth quantity.

(b) If the quantity variation is such as to cause an increase in the time necessary for completion, the Contracting Officer or his/her designated representative shall upon receipt of a written request for an extension of time within 10 days from the beginning of such delay, or within such further period of time which may be granted by the Contracting Officer or his/her designated representative prior to the date of final settlement of the contract, ascertain the facts and make such adjustment for extending the completion date as in their judgment the findings justify.

(End of Clause)

SECTION 01 10 00.10 38 Page 7

1.8 WATER CONSERVATION

Water is one of our valuable natural resources. Accordingly, the Contractor shall be judicious in its use in the performance of the work as specified. Water needed for compaction of roadway and/or foundation materials, and dust control shall be obtained from uncontrolled stream flow instead of potable supply sources to the extent available and suitable as determined by the Contracting Officer or his/her designated representative.

(End of Clause)

1.9 LOCAL NOTICE TO MARINERS

(a) The Contractor shall coordinate Local Notice to Mariners with the U.S. Coast Guard (USCG) by contacting USCG District Five at (757) 398-6229 or, alternately, Sector North Carolina at (910) 772-2230.

Contractor shall provide the dredging schedule and location by shoal/tangent/section.

(b) Should the Contractor, during dredging operations, encounter any objects on the channel bottom which could be a hazard to navigation, the Contractor shall notify the USCG immediately with location and other pertinent information necessary for the USCG to issue a Local Notice to Mariners. The Contractor shall provide copies of this information to the Contracting Officer or his/her designated representative.

1.10 NAVIGATION AIDS

There may be aids to navigation within the project boundaries. Some, or all, of such aids to navigation may need to be removed for the accomplishment of the contract work. Before the commencement of dredging, it is the responsibility of the Contractor to provide the U.S. Coast Guard (USCG) and any other responsible parties notification 5 weeks prior to needing a navigation aid moved. The USCG may need to bring vessels from out of state to move larger aids to navigation and the Contractor should request this service as soon as practicable, but in all cases, at least 5 weeks from the start of dredging. Any impacts to the work due to the inability of the Contractor to accomplish any needed movement of aids to navigation will not be the responsibility of the United States Government or of the Contracting Officer. Failure to notify the Coast Guard within the required timeframe may result in project delays.

The Contractor shall not remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation without express direction from the USCG. If the USCG determines they cannot respond to the Contractor's request, the USCG may request the Contractor to relocate the navigation aid(s) for dredging. The Contractor shall only relocate the navigation aid(s) and/or place the navigation aid(s) back to its charted position under the direct supervision of the

USCG.

The USCG point of contact is the USCG North Carolina Aids to Navigation Officer at (252)-247-4525, or alternately, Sector North Carolina Waterways Management at (910) 772-2230.

1.11 SEAGOING BARGE ACT

(1979 OCE)

SECTION 01 10 00.10 38 Page 8

The Seagoing Barge Act (46 U.S.C. et sq.) applies to this project. In the event the low bidder contemplates using plant that requires U.S. Coast Guard certification to comply with the Act, the low bidder shall within ten (10) calendar days after bid opening submit a copy of said certificate to the Contracting Officer or his/her designated representative. Failure to produce the certificate within the required time shall subject the bidder to a determination of nonresponsibility.

(End of Clause)

1.12 BULLETIN BOARD

Within one (1) calendar day after commencement of work under this contract, the Contractor shall provide at the job site a weatherproof, glass-covered bulletin board for displaying the Fair Employment poster, wage rates, posters and safety bulletins as noted in Section 01 35 26, paragraph DISPLAY OF SAFETY INFORMATION. The bulletin board shall be located in a conspicuous place, easily accessible to all employees, and legible copies of the aforementioned data shall be displayed until work under the contract is complete. No direct payment will be made for the bulletin board.

(End of Clause)

1.13 FINAL EXAMINATION AND ACCEPTANCE

As soon as practicable after the completion of the entire work or, if the work is divided into sections, or if any section which in the opinion of the Contracting Officer or his/her designated representative will not be subject to damage by further operations under the contract, such work will be thoroughly examined at the cost and expense of the Government by sounding or by sweeping, or both, as determined by the Contracting Officer or his/her designated representative. If any shoals, lumps, or the lack of contract depth are disclosed by this examination, the Contractor shall remove same by dredging the bottom with payment at the contract rate for (example: Unclassified Excavation, Anchorage Basin). The Contractor is only allowed to do dragging operations in lieu of dredging if approved by the Contractor Officer or his/her designated representative. The Contractor will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to be in satisfactory condition, it will be accepted. If more than two sounding or sweeping operations by the Government over an area are necessary because of work for the removal of shoals disclosed by prior sounding or sweeping, the cost of such subsequent soundings or sweeping operations will be charged against the Contractor at the rate of ($5,100.00) per day in which the Government plant is engaged in sounding or sweeping, is enroute to or from the site, or is held at or near the site for such operations.

As soon as practicable after the completion of the entire work or, if the work is divided into sections, or if any section which in the opinion of the Contracting Officer or his/her designated representative will not be subject to damage by further operations under the contract, such work will be thoroughly examined at the cost and expense of the Government by sounding or by sweeping, or both, as determined by the Contracting Officer or his/her designated representative. If any shoals, lumps, or the lack of contract depth are disclosed by this examination, the Contractor shall remove same by dredging the bottom with payment at the contract rate for

SECTION 01 10 00.10 38 Page 9 dredging. The Contractor is only allowed to do dragging operations in lieu of dredging if approved by the Contractor Officer. The Contractor will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to be in satisfactory condition, it will be accepted. If more than two sounding or sweeping operations by the Government over an area are necessary because of work for the removal of shoals disclosed by prior sounding or sweeping, the cost of such subsequent soundings or sweeping operations will be charged against the Contractor at the rate of $_________.__ per day in which the Government plant is engaged in sounding or sweeping, is enroute to or from the site, or is held at or near the site for such operations.

(End of Clause)

1.14 WORK PLAN

The Contractor shall submit a detailed work plan outlining the Contractor's proposed methods for the execution of all work under this contract. The work plan shall include a schedule that indicates the anticipated time frame to accomplish each definable feature of work within the time specified in the contract. The work plan shall provide an overall program for management of this project consisting of the following required plans:

a. The specific resources and equipment proposed for each definable feature of construction/dredging required by the contract. The Contractor shall describe and document all equipment proposed to demonstrate ability to perform the work in accordance with the proposed schedule, and shall include as a minimum the following information:

Dredges :

- Identification of the Dredge

- Total Horsepower and distribution

- Size of Suction and Discharge Lines

- Associated booster/pipeline equipment

- Estimated Pipeline Length(s) and Location(s) of booster pumps for this contract

- Scow Capacity in cubic yards

- Present location and condition

- Dredge Operation Reports for rock under comparable operating conditions. In addition, submit monthly summaries, to include daily rock production rates from these reports in cubic yards per day

- Dredge Operation Reports for non-rock under comparable operating conditions. In addition, submit monthly summaries, to include daily non-rock production rates from these reports in cubic yards per day

- Existing commitments of this equipment to other projects scheduled during the proposed contract duration

Other accompanying vessels and plant:

SECTION 01 10 00.10 38 Page 10

- Identification of the vessels

- HP/ capacity (as appropriate)

- Existing commitments of this equipment to other projects scheduled during the proposed contract duration

b. An accident prevention plan (APP) as required in Section 01 35 26 of the specifications.

The offered performance schedule will be incorporated into the contract and will become the required performance period for all contract purposes including assessment of liquidated damages.

1.15 PROGRESS SCHEDULE

Pursuant to the Contract Clause FAR 52.236-15, SCHEDULES FOR CONSTRUCTION CONTRACTS, a project schedule as described in this paragraph PROGRESS SCHEDULE shall be prepared and submitted. The Contractor shall provide the project schedule in the Precedence Diagram Method (PDM) using the Standard Data Exchange Format (SDEF). The project schedule shall be used to measure progress of the work, to evaluate potential time extensions and to provide a basis for all progress payments. It shall be in sufficient detail to properly monitor and manage the work and as a minimum shall include the following:

a. the work shall be divided into activities by acceptance section and phase of work (e.g. preconstruction structure and property condition surveys, blasting, dredging)

b. separate activities shall reflect each mobilization and demobilization of each major plant

c. activities shall be identified by associated bid item

d. all required and proposed submissions shall be included in the progress schedule

e. Government and other agency activities that could impact progress shall be shown (e.g. Government surveys, navigation aid relocations, etc.)

The schedule shall extend from NTP to the established contract completion date.

The initial progress schedule shall be included with the solicitation proposal and demonstrate that the proposed plant and resources are capable of performing the work as scheduled. Periodic schedule updates shall be provided monthly with each payment request, and whenever there is a change in logic or time extension. Each submission shall include the data disks containing the project schedule adhering to the SDEF format specified in ER 1-1-11, Appendix A; the earnings report indicating monthly and cumulative earnings; a narrative report with a description of the activities identifying the critical path(s), current or anticipated problems of delays and their impact, and proposed corrective actions; and the schedule reports containing activity number, activity description, original duration, remaining duration, early start date, early finish date, late start date, late finish date and total float. The schedule

SECTION 01 10 00.10 38 Page 11 reports shall be sorted as activity report, logic report listing preceding and succeeding activities for each activity, total float report listed in ascending order by early state date, early state sort and earning report.

A network diagram shall be submitted with the initial submission and each update. The network diagram shall depict the order, sequence and interdependence of activities, shall clearly indicate milestone dates and projected early and late earnings.

1.16 CONTRACTOR FURNISHED GOVERNMENT OFFICE

The Contractor shall furnish separate office space at the construction site to be used by the Government as a Resident Engineer Office. The location and office shall be approved by the Contracting Officer or his/her designated representative. This office shall provide a minimum of 400 square feet of working space and be divided into at least two (2) rooms plus bathroom facilities. One (1) room shall provide a minimum of 150 square feet and the other room shall provide a minimum of 250 square feet. New office furniture shall be provided to include two flat top office desks with top measurements 60 by 30-inches; two office chairs with upholstered seats and backs; two rotary desk chairs with upholstered tilting seats and backs with arms, adjustable seat height and casters; one rotary office chair with upholstered tilt seat and back without arms, adjustable seat height and casters; one plan table, plan rack, rotary drafting chair with adjustable seat from 27-inches to 30-inches high, drafting table 36-inches high, top measurements 42-inches x 72-inches with adjustable top; three legal size metal filing cabinets with four drawers;

two bookcases providing a minimum of 20 linear feet of shelf space; a water cooler and a refrigerator. Adequate office heating, air conditioning, and lighting shall be provided.

(a) All necessary utility services including water, electric, and sanitary services shall be installed and maintained by the Contractor at his expense, with the exception of telephone service, which will be installed and maintained at Government expense. The office facilities shall meet all applicable local and State codes and regulations. The office and equipment shall be fully operational and available to the Government no later than 30 days after receipt of the notice to proceed.

Upon completion of the project and after the Government has vacated the office the facilities shall be removed from project properties or otherwise suitably disposed of by the Contractor. The cost for this office shall be included in the bid price for bid item No. of the

BIDDING SCHEDULE.

(b) The Contractor shall furnish daily janitorial services for the offices, laboratory and other buildings on the project site and perform normal maintenance of facilities and grounds as deemed necessary by the Contracting Officer or his/her designated representative during the entire life of the contract. Toilet facilities shall be kept clean and sanitary at all times. Services shall be performed at such a time and in such a manner to least interfere with the operations but will be accomplished during normal working hours. Services shall be accomplished to the satisfaction of the Contracting Officer or his/her designated representative. The Contractor shall also provide daily trash collection and cleanup of the buildings and adjacent outside areas, snow removal in season, and shall dispose of all discarded debris, aggregate samples and concrete test samples in a manner approved by the Contracting Officer or his/her designated representative. No separate payment will be made for these Contractor-furnished services, and all costs thereof shall be incidental to the various bid items of the contract.

SECTION 01 10 00.10 38 Page 12

(a) The Contractor shall furnish separate office space at the construction site to be used by the Government as a Resident Engineer Office. The location and office shall be approved by the Contracting Officer or his/her representative. This office shall provide a minimum of 250 square feet of working space and bathroom facility. New office furniture shall be provided to include one flat top office desk with top measurement 60 by 30-inches; one work table with top measurement 60 by 30 inches; two office chairs with upholstered seats and backs; one rotary desk chair with upholstered tilting seats and backs with arms, adjustable seat height and casters; one legal size metal filing cabinets with four drawers; one bookcase providing a minimum of 20 linear feet of shelf space; a linear feet of shelf space; a water cooler and a refrigerator.

Adequate office heating, air conditioning, and lighting shall be provided.

(b) The Contractor shall furnish daily janitorial services for the offices, laboratory and other buildings on the project site and perform normal maintenance of facilities and grounds as deemed necessary by the Contracting Officer or his/her designated representative during the entire life of the contract. Toilet facilities shall be kept clean and sanitary at all times. Services shall be performed at such a time and in such a manner to least interfere with the operations but will be accomplished during normal working hours. Services shall be accomplished to the satisfaction of the Contracting Officer or his/her designated representative. The Contractor shall also provide daily trash collection and cleanup of the buildings and adjacent outside areas, snow removal in season, and shall dispose of all discarded debris, aggregate samples and concrete test samples in a manner approved by the Contracting Officer or his/her designated representative. No separate payment will be made for the office or these Contractor-furnished services, and all costs thereof shall be incidental to the various bid items of the contract.

(End of Clause)

1.17 ACCOMMODATIONS AND MEALS FOR INSPECTORS

(a) The Contractor shall furnish regularly to inspectors, for office purposes and sleeping purposes, when applicable, a suitable separate room onboard the dredge or other craft upon which they are employed. If no suitable office space is available thereon, the Contractor shall furnish suitable alternate accommodations ashore at a location approved by the Contracting Officer or his/her designated representative and furnish suitable transportation between the alternate accommodations and the dredge or other craft upon which they are employed.

(b) If the Contractor maintains an establishment for the subsistence of his own employees, he shall, when required, furnish to inspectors employed on the work, and to all Government agents who may visit the work on official business, meals of a quality satisfactory to the Contracting Officer or his/her designated representative. The meals furnished shall be paid for by the individual consuming the meal at a rate commensurate with the basic Government subsistence rate of: $5.00 Breakfast; $8.00 Lunch; $13.00 Dinner.

(End of Clause)

1.18 RETAINAGE FOR UNTIMELY SUBMISSION OF SUBCONTRACTING REPORTS

(a) In accordance with Contract Clause 52.219-9, Small Business

SECTION 01 10 00.10 38 Page 13

Subcontracting Plan, and 52.219-16, Liquidated Damages - Subcontracting Plan, retainage will be withheld from progress payments in an amount sufficient to protect the Government's ability to assess liquidated damages in accordance with Clause 52.219-16 for the contractor's failure to timely submit Standard Form 294, Subcontracting Report for Individual Contracts, and Standard Form 295, Summary Subcontract Report, reports.

(b) The retainage will be determined in accordance with the following formula:

Total dollar amount for subcontracting to small business multiplied by percentage of actual progress on the contract shall be withheld from the next progress payment due after the Contractor fails to submit a required report. If one or more reports have been submitted before such failure, formula for determining the amount of retainage will be adjusted by deducting any amounts reported as subcontracted to small business from the total dollar amount proposed to be subcontracted and the difference multiplied by the percentage of actual progress.

(c) Subcontracting plans are not required--

(1) For contracts or contract modifications that will be performed entirely outside of any State, territory, or possession of the United States, the District of Columbia, and the Commonwealth of Puerto Rico; or

(2) For modifications to contracts that do not contain the clause 52.219-8, Utilization of Small Business Concerns (or equivalent prior DAR, FPR, or NASA clauses); e.g., contracts awarded before Pub. L.

95-507 and which are within the scope of the contract.

(End of Clause)

1.19 SHOP DRAWINGS AND MATERIALS SUBMITTAL

(a) Five (5) days prior to the preconstruction conference (see paragraph REQUIRED CONSTRUCTION MEETINGS), the Contractor shall complete and submit to the Contracting Officer or his/her designated representative, in duplicate, Submittal Register, listing all submittals and dates. In addition to those items listed on the Submittal Register, the Contractor will furnish submittals for any deviation from the plans or specifications. The scheduled need dates must be recorded on the document for each item for control purposes. In preparing the document, adequate time (minimum of l5 days) will be allowed for review and approval and possible resubmittal. Scheduling shall be coordinated with the approved progress schedule. The Contractor's Quality Control System Manager shall review the listing at least every 30 days and take appropriate action to maintain an effective system. Copies of updated or corrected listings shall be submitted to the Contracting Officer or his/her designated representative at least every 60 days in the quantity specified. Payment will not be made for any material or equipment which does not comply with contract requirements.

(b) Contractor submittals required by the Technical Provisions are indicated in those provisions and are listed on the Submittal Register furnished in Section 01 33 00.00 37 SUBMITTAL PROCEDURES. The list does not relieve the Contractor from furnishing submittals required elsewhere in the specifications, those inadvertently omitted from the listing; or from furnishing other submittals that the Government may deem necessary as

SECTION 01 10 00.10 38 Page 14 the work progresses.

(c) Normal review levels for required approvals are indicated by letter designations as follows:

Contractor Quality Control System Manager --- (CQC) Area or Resident Engineer ------------------- (R) Engineering Branch -------------------------- (E)

The Government reserves the right to vary the review levels for (R) and

(E) to its convenience.

(d) The Contractor shall use ENG Form 4025, furnished in Section 01 33 00.00 37 SUBMITTAL PROCEDURES, to transmit Shop Drawings, Equipment Data, Material Samples or Manufacturer's Certificate of Compliance to the Government.

(End of Clause)

1.20 SAMPLING, CERTIFICATES, AND TESTING

(a) General. Within 30 days after acknowledgment of Notice to Proceed, the Contractor shall submit to the Contracting Officer or his/her designated representative five (5) copies of a list of the items for which he proposes to furnish manufacturer's certificates and/or samples for inspection and testing. The list shall include, but is not limited to the following information:

(1) Name of item

(2) Specification paragraph covering this item

(3) Date sample will be furnished

(4) Delivery date of product

(5) Items for which a certificate will be furnished

(b) Submittals. Any product or item mentioned in these specifications and required to meet Federal, ASTM, AASHTO, U. S. Army or Navy, AREMA, AWWA, and UL Specifications or Codes, specified herein with certain limiting or qualifying requirements, or any product or item which is required to be similar and equal to a specified product or item may require the submission, before delivery of the product or item to the job site, of one or more of the following:

(1) Certificate by the manufacturer that the item meets the contract requirements.

(2) Samples for inspection, comparison, and testing, including destructive tests.

(c) Sample delivery. Unless otherwise specified or authorized, all samples shall be delivered (without cost to the Government) to:

U.S. Army Engineer District, Wilmington Corps of Engineers ATTENTION: Civil Construction Section or

SECTION 01 10 00.10 38 Page 15

Military Construction Section 69 Darlington Avenue Wilmington, North Carolina 28403

U.S. Army Corps of Engineers Raleigh Area Office 11409 Falls of the Neuse Road Wake Forest, North Carolina 27587-11409

U.S. Army Corps of Engineers AIWW Bridges Resident Office Post Office Box 1269 107 Union Drive (Suite 101) Washington, North Carolina 27889-1269

U.S. Army Corps of Engineers Kerr Resident Office 5460 Buggs Island Road Boydton, Virginia 23917

If required by the Contracting Officer or his/her designated representative, duplicate samples shall be shipped to the Wilmington District Office at no expense to the Government.

(d) Testing. All tests required in the Technical Provisions shall be made by and at the expense of the Contractor except those material tests specifically excluded which will be made by and at the expense of the Government. All instruments and personnel required for the required tests shall be furnished by the Contractor. The Government reserves the right to interrupt the work to make tests on all facets of concreting and other operations. These tests will be made as necessary to insure conformance to applicable specifications and drawings and will be made by and at the expense of the Government except Contractor sampling support as required by the Technical Provisions. In those instances where testing is specified to be made at the Government's expense, the cost of the initial testing will be at the Government's expense; however, any retesting due to failure of the materials to meet the requirements in the initial test shall be performed at the Contractor's expense. The retests shall be made at laboratories approved by the Contracting Officer or his/her designated representative. The costs of retests made at Government laboratories will be deducted from the total amount due the Contractor, at actual cost to the Government, unless otherwise specified.

(End of Clause)

1.21 CERTIFICATES OF COMPLIANCE

(l969 MAY OCE)

Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in 3 copies.

Each certificate shall be signed by an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply.

Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material

SECTION 01 10 00.10 38 Page 16 is found not to meet the specific requirements.

(End of Clause)

1.22 CONTRACTOR-PREPARED NETWORK ANALYSIS SYSTEM

(APR 1968)

The progress chart to be prepared by the Contractor pursuant to the Contract Clause entitled "SCHEDULES FOR CONSTRUCTION CONTRACTS" shall consist of a network analysis system as described below. In preparing this system the scheduling of construction is the responsibility of the Contractor. The requirement for the system is included to assure adequate planning and execution of the work and to assist the Contracting Officer or his/her designated representative in appraising the reasonableness of the proposed schedule and evaluating progress of the work.

(a) An example of one of the numerous acceptable types of network and analysis systems is shown in Appendix A of the Corps of Engineers Regulation ER 1-1-11 , single copies of which are available to bona fide bidders on request. Other systems which are designed to serve the same purpose and employ the same basic principles as are illustrated in Appendix A will be accepted subject to the approval of the Contracting Officer or his/her designated representative.

(b) The system shall consist of diagrams and accompanying mathematical analyses. The diagrams shall show elements of the project in detail and the entire project in summary.

(1) Diagrams shall show the order and interdependence of activities and the sequence in which the work is to be accomplished as planned by the Contractor. The basic concept of a network analysis diagram will be followed to show how the start of a given activity is dependent on the completion of preceding activities and its completion restricts the start of following activities.

(2) Detailed network activities shown on a detailed or sub-network diagram shall include, in addition to construction activities, the submittal and approval of samples of materials and shop drawings, the procurement of critical materials and equipment, fabrication of special material and equipment and their installation and testing. All activities of the Government that affect progress, and contract required dates for completion of all or parts of the work will be shown. The detail of information shall be such that duration times of activities will range from three (3) to thirty (30) days with not over two percent (2%) of the activities exceeding these limits. The activities which comprise the following separate buildings and features shall be separately identifiable by coding or use of sub-networks or both:

Building or feature Minimum number of activities

The selection and number of activities shall be subject to the Contracting Officer or his/her designated representative's approval. Detailed networks, when summary networks are also furnished, need not be time scaled but shall be drafted to show a continuous flow from left to right with no arrows from right to left. The following information shall be shown on the diagrams for each activity: preceding and following event numbers, description of the activity, cost, and activity duration.

SECTION 01 10 00.10 38 Page 17

(3) Summary Network. If the project is of such size that the entire network cannot be readily shown on a single sheet, a summary network diagram shall be provided. The summary network diagram shall consist of a minimum of fifty activities and a maximum of one hundred and fifty activities, and shall be based on and supported by detailed diagrams. Related activities shall be grouped on the network. The critical path shall be plotted generally along the center of the sheet with channels with increasing float placed towards the top or bottom. The summary network shall be time scaled using units of approximately one-half inch equals one week or other suitable scale approved by the Contracting Officer or his/her designated representative. Weekends and holidays shall be indicated. Where slack exists, the activities shall be shown at the time when they are scheduled to be accomplished.

(4) The mathematical analysis of the network diagram shall include a tabulation of each activity shown on the detailed network diagrams. The following information will be furnished as a minimum for each activity:

(i) preceding and following event numbers (numbers shall be selected and assigned so as to permit identification of the activities with bid items);

(ii) activity description;

(iii) estimated duration of activities (the best estimate available at time of computation);

(iv) earliest start date (by calendar date);

(v) earliest finish date (by calendar date);

(vi) scheduled or actual start date (by calendar date);

(vii) scheduled or actual finish date (by calendar date);

(viii) latest start date (by calendar date);

(ix) latest finish date (by calendar date);

(x) slack or float;

(xi) monetary value of activity;

(xii) responsibility for activity (Prime Contractor, subcontractors, suppliers, Government, etc.);

(xiii) manpower required;

(xiv) percentage of activity completed;

(xv) Contractor's earnings based on portion of activity completed; and

(xvi) bid item of which activity is a part.

(5) The program or means used in making the mathematical computation shall be capable of compiling the total value of completed and partially completed activities and subtotals from separate buildings or

SECTION 01 10 00.10 38 Page 18 feature listed in paragraph (b)(2).

(6) In addition to the tabulation of activities, the computation will include the following data:

(i) identification of activities which are planned to be expedited by use of overtime or double shifts to be worked including Saturdays, Sundays and holidays;

(ii) on-site manpower loading schedule;

(iii) a description of the major items of construction equipment planned for operations of the project. (The description shall include the type, number of units and unit capacities. A schedule showing proposed time equipment will be on the job keyed to activities on which equipment will be used shall be provided); and

(iv) where portions of the work are to be paid by unit costs, the estimated number of units in an activity which was used in developing the total activity cost.

(7) The analysis shall list the activities in sorts or groups as follows:

(i) by the preceding event number from lowest to highest and then in the order of the following event number;

(ii) by the amount of slack, then in order of preceding event number;

(iii) by responsibility in order of earliest allowable start dates; and

(iv) in order of latest allowable start dates, then in order of preceding event numbers, and then in order of succeeding event numbers.

(c) Submission and approval of the system shall be as follows:

(1) A preliminary network defining the Contractor's planned operations during the first sixty (60) calendar days after receipt of Notice to Proceed will be submitted within ten (10) days. The Contractor's general approach for the balance of the project shall be indicated. Cost of activities expected to be completed or partially completed before submission and approval of the whole schedule should be included.

(2) The complete network analysis consisting of the detailed network mathematical analysis (on-site manpower loading schedule, equipment schedule) and network diagrams shall be submitted within forty

(40) calendar days after receipt of Notice to Proceed.

(d) The Contractor shall participate in a review and evaluation of the proposed network diagrams and analysis by the Contracting Officer or his/her designated representative. Any revisions necessary as a result of this review shall be resubmitted for approval of the Contracting Officer or his/her designated representative within ten (10) calendar days after the conference. The approved schedule shall then be the schedule to be used by the Contractor for planning, organizing and directing the work and

SECTION 01 10 00.10 38 Page 19 for reporting progress. If the Contractor thereafter desires to make changes in his method of operating and scheduling he shall notify the Contracting Officer or his/her designated representative in writing stating the reasons for the change. If the Contracting Officer or his/her designated representative considers these changes to be of a major nature he may require the Contractor to revise and submit for approval, without additional cost to the Government, all or the affected portion of the detailed diagrams and mathematical analysis and the summary diagram to show the effect on the entire project. A change may be considered of a major nature if the time estimated to be required or actually used for an activity or the logic of sequence of activities is varied from the original plan to a degree that there is a reasonable doubt as to the effect on the contract completion date or dates. Changes which affect activities with adequate slack time shall be considered as minor changes, except that an accumulation of minor changes may be considered a major change when their cumulative effect might affect the contract completion date.

(e) The Contractor shall submit at intervals of fifteen (15) calendar days a report of the actual construction progress by updating the mathematical analyses. Revisions causing changes in the detailed network shall be noted on the summary network, or a revised issue of affected portions of the detailed network furnished. The summary network shall be revised as necessary for the sake of clarity. However, only the initial submission or completed revisions need be time scaled. Subsequent minor revisions need not be time scaled.

(f) The report shall show the activities or portions of activities completed during the reporting period and their total value as basis for the Contractor's periodic request for payment. Payment made pursuant to the Contract Clause entitled "PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS" will be based on the total value of such activities completed or partially completed after verification by the Contracting Officer or his/her designated representative.