Corps of Engineers GOVERNMENT ESTIMATE P.O. Box 532711 Los Angeles, CA 90053-2325
1.1 Bid Items
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0001 Diversion and Control of Water 1 LS 267,345.00 267,345.00 0001A Mobilization and Demobilization 1 LS 2,614,039.00 2,614,039.00 0002 Clear Site and Remove Obstructions, All Areas 41 Acre 11,882.00 487,162.00 0003 Foundation Preparation, Soil Cement Levee 1 LS 543,007.00 543,007.00 0004 Removal and Disposal of Levee Signs, 1 LS 772,330.00 772,330.00
Gates, Fences, and Bikeway Rails 0005 Installation of Levee:
A. Signs 15 Ea 1,188.00 17,820.00 B. Gates **11 Ea 1,426.00 15,686.00
C. Chainlink Fences 200 LF 45.00 9,000.00 D. Bikeway Rail 17,240 LF 166.00 2,861,840.00
0006 Removal of Soil Cement and Rock Groins 17,600 CY 66.00 1,161,600.00 and Rocks in Areas Indicated
0007 Excavation, Toe ***640,000 CY 15.00 9,600,000.00 0008 Compacted Fill, Soil Cement Levee ***183,600 CY 6.00 1,101,600.00 0009 Compacted Fill, Access Ramps 2,500 CY 18.00 45,000.00 0010 Miscellaneous Fill 521,000 CY 7.00 3,647,000.00 0011 Borrow Material, Soil Cement Levee 54,500 CY 8.00 436,000.00 0012 15'' Riprap Slope Protection, Access Ramps 600 CY 87.00 52,200.00 0013 18'' Riprap Slope Protection, U.S. HWY 101 1,725 CY 101.00 174,225.00
Undercrossing Upper Slopes and Levee Toedown 0014 Grout Protection, HWY 101 Under 150 CY 208.00 31,200.00
Crossing Slopes and Levee Toedown 0015 Removal of the Existing ABC, Levee Road 1 LS 321,408.00 321,408.00 0016 Installation of 4'' ABC, Levee Road 3,600 CY 108.00 388,800.00 0017 Seal an Existing 12'' DIA. PVC PIPE 1 LS 11,882.00 11,882.00
With Controlled Low Strength Material (CLSM) 0018 Survey Marker Installation 1 LS 11,882.00 11,882.00 0019 As-Built Drawings 1 LS 17,823.00 17,823.00
0020 RCB and RCP Culverts 1 LS 1,544,659.00 1,544,659.00
Total Estimated Amount:
$26,133,508.00
W912PL-09-B-0007 - Santa Maria Valley Levees - South Levee Improvement Project - Reaches 1 & 2 - Bids of Sept 8, 2009
R. WILLIAMS CONSTRUCTION, INC
1306 A-NORTH "H" ST, PMB-307
LOMPOC, CA 93436
1.1 Bid Items
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0001 Diversion and Control of Water 1 LS 758,000.00 758,000.00 0001A Mobilization and Demobilization 1 LS 800,000.00 800,000.00 0002 Clear Site and Remove Obstructions, All Areas 41 Acre 3,840.00 157,440.00 0003 Foundation Preparation, Soil Cement Levee 1 LS 682,500.00 682,500.00 0004 Removal and Disposal of Levee Signs, 1 LS 14,700.00 14,700.00
Gates, Fences, and Bikeway Rails 0005 Installation of Levee:
A. Signs 15 Ea 226.00 3,390.00 B. Gates **11 Ea 1,900.00 20,900.00
C. Chainlink Fences 200 LF 26.25 5,250.00 D. Bikeway Rail 17,240 LF 16.33 281,529.20
0006 Removal of Soil Cement and Rock Groins 17,600 CY 5.60 98,560.00 and Rocks in Areas Indicated
0007 Excavation, Toe ***640,000 CY 1.46 934,400.00 0008 Compacted Fill, Soil Cement Levee ***183,600 CY 29.97 5,502,492.00 0009 Compacted Fill, Access Ramps 2,500 CY 2.85 7,125.00 0010 Miscellaneous Fill 521,000 CY 0.44 229,240.00 0011 Borrow Material, Soil Cement Levee 54,500 CY 1.46 79,570.00 0012 15'' Riprap Slope Protection, Access Ramps 600 CY 22.85 13,710.00 0013 18'' Riprap Slope Protection, U.S. HWY 101 1,725 CY 23.85 41,141.25
Undercrossing Upper Slopes and Levee Toedown 0014 Grout Protection, HWY 101 Under 150 CY 139.35 20,902.50
Crossing Slopes and Levee Toedown 0015 Removal of the Existing ABC, Levee Road 1 LS 52,835.00 52,835.00 0016 Installation of 4'' ABC, Levee Road 3,600 CY 41.00 147,600.00 0017 Seal an Existing 12'' DIA. PVC PIPE 1 LS 2,790.00 2,790.00
With Controlled Low Strength Material (CLSM) 0018 Survey Marker Installation 1 LS 5,250.00 5,250.00 0019 As-Built Drawings 1 LS 1,575.00 1,575.00 0020 RCB and RCP Culverts 1 LS 171,000.00 171,000.00
Total Estimated Amount:
$10,031,899.95
W912PL-09-B-0007 - Santa Maria Valley Levees - South Levee Improvement Project - Reaches 1 & 2 - Bids of Sept 8, 2009
Wood Bros, Inc.
14147 18th Ave, (P.O. Box 216) Lemoore, CA 93245
1.1 Bid Items
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0001 Diversion and Control of Water 1 LS 119,200.00 119,200.00 0001A Mobilization and Demobilization 1 LS 500,000.00 500,000.00 0002 Clear Site and Remove Obstructions, All Areas 41 Acre 14,120.00 578,920.00 0003 Foundation Preparation, Soil Cement Levee 1 LS 99,380.00 99,380.00 0004 Removal and Disposal of Levee Signs, 1 LS 49,760.00 49,760.00
Gates, Fences, and Bikeway Rails 0005 Installation of Levee:
A. Signs 15 Ea 360.00 5,400.00 B. Gates **11 Ea 2,901.00 31,911.00
C. Chainlink Fences 200 LF 33.35 6,670.00 D. Bikeway Rail 17,240 LF 16.30 281,012.00
0006 Removal of Soil Cement and Rock Groins 17,600 CY 3.48 61,248.00 and Rocks in Areas Indicated
0007 Excavation, Toe ***640,000 CY 2.00 1,280,000.00 0008 Compacted Fill, Soil Cement Levee ***183,600 CY 33.80 6,205,680.00 0009 Compacted Fill, Access Ramps 2,500 CY 7.97 19,925.00 0010 Miscellaneous Fill 521,000 CY 1.00 521,000.00 0011 Borrow Material, Soil Cement Levee 54,500 CY 1.59 86,655.00 0012 15'' Riprap Slope Protection, Access Ramps 600 CY 102.00 61,200.00 0013 18'' Riprap Slope Protection, U.S. HWY 101 1,725 CY 103.00 177,675.00
Undercrossing Upper Slopes and Levee Toedown 0014 Grout Protection, HWY 101 Under 150 CY 148.00 22,200.00
Crossing Slopes and Levee Toedown 0015 Removal of the Existing ABC, Levee Road 1 LS 37,920.00 37,920.00 0016 Installation of 4'' ABC, Levee Road 3,600 CY 46.73 168,228.00 0017 Seal an Existing 12'' DIA. PVC PIPE 1 LS 3,145.00 3,145.00
With Controlled Low Strength Material (CLSM) 0018 Survey Marker Installation 1 LS 3,510.00 3,510.00 0019 As-Built Drawings 1 LS 41,712.00 41,712.00 0020 RCB and RCP Culverts 1 LS 164,446.00 164,446.00
Total Estimated Amount:
$10,526,797.00
W912PL-09-B-0007 - Santa Maria Valley Levees - South Levee Improvement Project - Reaches 1 & 2 - Bids of Sept 8, 2009
Sukut Construction, Inc.
5805 Sepulveda Blvd. Suite 690 Van Nuys, CA 91411
1.1 Bid Items
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
0001 Diversion and Control of Water 1 LS 50,000.00 50,000.00 0001A Mobilization and Demobilization 1 LS 1,045,000.00 1,045,000.00 0002 Clear Site and Remove Obstructions, All Areas 41 Acre 900.00 36,900.00 0003 Foundation Preparation, Soil Cement Levee 1 LS 105,000.00 105,000.00 0004 Removal and Disposal of Levee Signs, 1 LS 80,000.00 80,000.00
Gates, Fences, and Bikeway Rails 0005 Installation of Levee:
A. Signs 15 Ea 425.00 6,375.00 B. Gates **11 Ea 2,000.00 22,000.00
C. Chainlink Fences 200 LF 30.00 6,000.00 D. Bikeway Rail 17,240 LF 15.00 258,600.00
0006 Removal of Soil Cement and Rock Groins 17,600 CY 5.50 96,800.00 and Rocks in Areas Indicated
0007 Excavation, Toe ***640,000 CY 1.95 1,248,000.00 0008 Compacted Fill, Soil Cement Levee ***183,600 CY 38.00 6,976,800.00 0009 Compacted Fill, Access Ramps 2,500 CY 3.00 7,500.00 0010 Miscellaneous Fill 521,000 CY 0.20 104,200.00 0011 Borrow Material, Soil Cement Levee 54,500 CY 2.00 109,000.00 0012 15'' Riprap Slope Protection, Access Ramps 600 CY 25.00 15,000.00 0013 18'' Riprap Slope Protection, U.S. HWY 101 1,725 CY 25.00 43,125.00
Undercrossing Upper Slopes and Levee Toedown 0014 Grout Protection, HWY 101 Under 150 CY 275.00 41,250.00
Crossing Slopes and Levee Toedown 0015 Removal of the Existing ABC, Levee Road 1 LS 17,000.00 17,000.00 0016 Installation of 4'' ABC, Levee Road 3,600 CY 44.00 158,400.00 0017 Seal an Existing 12'' DIA. PVC PIPE 1 LS 3,000.00 3,000.00
With Controlled Low Strength Material (CLSM) 0018 Survey Marker Installation 1 LS 2,500.00 2,500.00 0019 As-Built Drawings 1 LS 8,500.00 8,500.00 0020 RCB and RCP Culverts 1 LS 160,000.00 160,000.00
Total Estimated Amount:
$10,600,950.00
W912PL-09-B-0007 - Santa Maria Valley Levees - South Levee Improvement Project - Reaches 1 & 2 - Bids of Sept 8, 2009
Bidders Total Estimated Amount ALT Fillisch Contractors Inc. $11,069,209.00
13300 Citrus St.
Corona, CA 92880
Earth Construction & Mining $12,355,770.00 11542 Knott St., #10
Garden Grove, CA 92841
C.A. Rasmussen Inc. $12,446,735.00 28548 Livingston Avenue
Valencia, CA 91355
John Madonna Construction CO., Inc. $12,605,440.00 P.O. Box 5310
San Luis Obispo, CA 93403-5310
Granite Construction Company $12,977,400.00 585 W. Beach Street
Watsonville, CA 95076
CJW Construction, Inc. $13,438,745.00 841 East Washington Avenue, Suite B
Santa Ana, CA 92701
Ace Engineering, Inc. $14,380,481.00 1880 Wright Ave.
La Verne, CA 91750
Whitaker Construction Group, Inc. $14,644,730.00 2752 Concrete Court
Paso Robles, CA 93446
Miller Environmental Inc. $14,896,860.00 2210 South Dupont Drive
Anaheim, CA 92806
B.C. Schmidt Construction, Inc. $16,547,675.00 P.O. Box 1557
Williams, CA 95987-5148
CalPortland Construction $16,937,021.00 P.O. Box 1280
Santa Maria, CA 93456
W912PL-09-B-0007 - Santa Maria Valley Levees - South Levee Improvement Project - Reaches 1 & 2 - Bids of Sept 8, 2009
U.S Army Corps of Engineers Los Angeles District W912PL-09-B-0007
SANTA MARIA VALLEY LEVEES
SOUTH LEVEE IMPROVEMENT PROJECT
CONSTRUCTION SPECIFICATIONS
FOR
SOUTH LEVEE
REACH 1
(Blosser Road to U.S. Hwy 101 Bridge) and
REACH 2
(U.S. Hwy 101 Bridge to Suey Crossing Road Bridge)
SANTA BARBARA, CALIFORNIA
Construction Solicitation And Specifications
Unrestricted
Prepared By:
USACE Los Angeles District
P.O. Box 2711 Los Angeles, California 90053
July 2009
| Sheet1 |
| Sheet2 |
| Sheet3 |
| Sheet4 |
| Sheet5 |
| SpecCoverSht_W912PL-09-B-0007.pdf |
| Los Angeles District W912PL-09-B-0007 |
| SANTA MARIA VALLEY LEVEES |
| SOUTH LEVEE IMPROVEMENT PROJECT |
| CONSTRUCTION SPECIFICATIONS |
| FOR |
| SOUTH LEVEE |
| REACH 1 |
| (Blosser Road to U.S. Hwy 101 Bridge) |
| and |
| REACH 2 |
| (U.S. Hwy 101 Bridge to Suey Crossing Road Bridge) |
| SANTA BARBARA, CALIFORNIA |
| Los Angeles, California 90053 |