STATEMENT OF WORK
Projects.
ES 00346-8 Replace PV and Trafo MV switchgears in substation bldg 5882, Depot
ES 00177-8 Upgrade POD Bldg 5180, Depot
Basic Project and Options. The project consists of one basic project only. No optional work is included.
Phase 1 (Design) Description:
I. Scope of the work.
Introduction
Depot Electrical MV system is currently a closed 15kV loop with logic selectivity managed by a
SCADA system connected to the national grid by two (alternative) points of delivery.
Medium Voltage panels inside substation bldg 5882 have been partially renovated in 2015 with the exception of the MV panel connecting the 1.4MWpeak Photovoltaic System and the MV panel feeding the 15/0.4kV transformer inside the substation.
The renovated panels are:
- 1 switchgear type 8DJH by Siemens with disconnector for the incoming line from Point of delivery bldg 5078
- 1 switchgear type 8DJH by Siemens for the voltage transformers
- 1 switchgear type 8DJH by Siemens with circuit breaker and relay model S7J80 by Siemens for the protection of the MV cable loop
- 1 switchgear type 8DJH by Siemens with circuit breaker and relay model S7J80 by Siemens for the protection of the MV cable loop
- 1 switchgear type 8DJH by Siemens with disconnector feeding the MV panel connecting the
PV system and the MV panel feeding the 15/0.4kV transformer (ABB brand complete with
Thytronic relays).
The Siemens relays are connected to a communication switch located in a cabinet inside the substation and are part of a SCADA system that allows the remote monitoring and control of the
MV system of the Depot area; the existing supervisory control and data acquisition is SIMATIC
WinCC by Siemens: the system is composed by 2 redundant PLC and a server located in bldg
5012, plus a workstation located in bldg 5155 and a workstation located in bldg 5140.
The existing MV switchgear connecting the PV system is complete with 2 relays, 1 relay
Thytronic PRO-N NA60 for the line protection and 1 relay Thytronic PRON-N NV10P acting as
“Dispositivo di Interfaccia” (DDI).
The existing MV switchgear feeding the 15/0.4kV transformer is complete with 1 relay Thytronic.
Over the ABB MV switchgear there is a cabinet with MV voltage transformers (TV), providing the voltage measure to the Power Factor Unit located between the transformer and the LV panel.
The existing MV cables are routed under the concrete floor in a big accessible atrium.
The existing “Dispositivo di Interfaccia” (DDI) in bldg 5882 is connected to the “Dispositivo
Generale” (DG) of the Depot South Point of Delivery (POD) bldg 5078, acting also as
“Dispositivo di Rincalzo” (DDR).
Another POD, bldg 5180, is existing in the North Depot area; this POD is actually not connected to the DDI of the photovoltaic system and is not authorized to be used to feed the Depot without disconnecting the PV system.
An existing “regolamento di esercizio” is currently available, corresponding to the situation above explained.
Works to be done
The general scope of the project is to:
- replace the existing MV panels feeding the existing Photovoltaic system and the 15/0.4kV transformer, installing new panels and relays to be connected to the existing SCADA system.
- connect the North POD bldg 5180 to the PV system DDI in order to be allowed to feed the
MV loop from this POD keeping the PV system connected.
In this phase the work consists of designing details and providing calculations and everything necessary to define all the works required to fulfill the scope of work, consisting of:
a. Remove the two existing MV switchgears connecting the PV system and feeding the transformer.
b. Remove the existing Siemens MV switchgear feeding the two ABB MV switchgears indicated in point a. including the MV cable and the current transformer providing current measure to the power factor unit.
c. Remove the cabinet with the voltage transformers and the relative cables.
d. Install two new MV switchgears type 8DJH by Siemens with motorized vacuum circuit breaker and relay model S7J80 by Siemens (same type and model of the existing MV panels feeding the MV loop) connecting them to the existing Siemens switchgears in order to have all the panels in line.
The new relay connecting the PV system shall be set to perform at least the following
ANSI functions: 50, 51, 67N, 81, 27, 59.
The new relay feeding the existing transformer 15/0.4kV shall be set to perform at least the following ANSI functions: 50, 51, 50N, 51N.
Install new current transformers and homopolar current transformers.
Provide auxiliary circuits feeding as necessary.
Connect the new relays to the existing communication switch.
Provide new holes in the floor in correspondence with the new panels to re-route and reconnect the existing MV cables.
Provide new MV cables connectors elbow plug-in type for the connection of the existing
MV cables to the new panels.
Perform grounding of the new switchgears as necessary, connecting to the main grounding bar of the substation; install labels on grounding conductors.
Perform the setting of the new MV relays complying with the Energy distributor requirements and providing the proper selectivity of the protections.
e. Relocate the cabinet with the switch to allow the installation of the new MV panels;
modify conduits and cables as necessary.
f. Repair the floor with concrete covering the holes in correspondence with the removed panels.
g. Update the existing SCADA system incorporating the new MV panels into the supervision and control system; perform all the necessary hardware and software upgrade/update, including in the 2 workstations. The SCADA system shall allow the monitoring of all the electrical measures and the electrical status and shall allow the remote control of the motorized breaker.
h. Modify the setting of the existing Power Factor Unit after the removal of the cabinet with the voltage transformer and the removal of the current transformers. Voltage input shall be the LV voltage. Install new current transformers on the LV cables downstream the transformer 15/0.4kV to provide the measurement to the Power Factor Unit.
i. Install the new Electrical diagram of the substation to be affixed inside the substation;
minimum diagram dimensions: 841x594 mm (ISO A1); the diagram shall be plastic type or plasticized paper.
j. Connect the new “Dispositivo di Interfaccia” (DDI) of the photovoltaic system to the existing “Dispositivo Generale” (DG) located in the Point of Delivery building 5180, making it acting also as “Dispositivo di Rincalzo” (DDR). Install a new armored cable
FG16R16NR16 connecting the new DDI to the auxiliary terminals of the existing relay
(Siemens S7J80) in bldg 5180 in order to allow the trip of the DG in case of improper operation of the DDI. New cable shall be routed inside the existing cable ducts. The cable shall be preferably without any splices; if strictly necessary, maximum 2 splices will be allowed to be done; in this case the splices shall be performed outside a manhole and then located inside the manhole leaving 2 meters at least of spare cable. Splices shall be straight heat-shrinkable type for extruded insulation cables up to a 1 kV.
Contractor shall pay particular attention to pull the cable in the most proper way in order to avoid any damage to the conductors.
Inside the substations the new cable shall be routed inside galvanized steel rigid conduits and boxes with minimum ingress protection IP55.
k. Verify the relay setting of the DG in bldg 5180 in accordance with the requirements of the National Grid Energy provider and modify the settings if necessary.
l. Provide a new “Regolamento di Esercizio” incorporating the works done. The new
“Regolamento di Esercizio” shall be complete with all the required attachments according to the Italian standard CEI 0-16; the document shall be delivered to the Government complete in all its parts, including all the payments (stamps, taxes or anything else) that could be necessary, ready for the Government Representative signature. Once the
Government Representative will sign the document, this will be delivered to the Electricity provider by the Government, not by the Contractor.
Additional Codes Compliance
In addition to the above listed works, all other requirements to make the work totally in compliance with Italian and U.S. standards shall be identified, summarized in a report and included in the design.
II. Documentation required Documents required to accomplish this phase prior to building construction are as follows:
- As-built drawings of the existing utilities to be used for design will be prepared based on the documents which will be provided by the Government and on site investigations and measurements taken in order to ascertain local conditions and extent of required work.
- Complete design analysis of the mechanical, electrical, fire protection systems (as applicable), including utilities rerouting with minimal service interruption specified.
- Verify and prepare documentation for special and/or hazardous material handling and disposal per current Italian regulation, to include ASL approval if applicable. The designer shall identify all to be disposed off in landfill or to be delivered to recycling plant.
- The requirements of Italian Law 81 of 2008 are deemed applicable to this project. The
Government will award separate contracts for Design and Construction Safety Coordination.
During the Design Phase maximum cooperation will be granted to the nominated Safety
Coordinator to allow preparation of Safety and Coordination Plan and other documents required by Law.
- Sets of construction drawings on ISO A1 sheets. As a minimum the drawings must contain as minimum the following information:
Architectural layout: plans (existing and new condition)
Electrical system: plans (existing and new condition)
Electrical system: panels wiring diagrams including auxiliary circuits diagram
(existing and new condition);
Electrical system: details.
All drawings shall be to scale, with graphic scale indicated. Dimensions and material identifications shall be clearly indicated. Drawings shall include all necessary notes and legends. All wording shall be in both English and Italian.
- Detailed technical report (in English and Italian) to include the following:
Detailed description of all works to be accomplished;
Method of accomplishment;
Materials and finishing;
Reference to norms and laws (both US and Italian) in force;
- For any excavations deeper than 6" (15 cm.), the Contractor must request the digging permit to the COR. This form will be provided to the Contractor at the pre-construction conference.
- Construction drawings, design analysis, technical report and the new “Regolamento di esercizio” must be prepared and signed by professional engineers, within their respective expertise, registered in Italy, who will accept responsibility in accordance with Italian laws in force.
- All documents shall be submitted in paper and electronic format Autocad compatible for drawings, MS Office compatible for documents and in TIFF/PDF format for raster and pictures.
- The final submission shall include Certification of Compliance with Italian Norms. It will consist of the following statement, to be signed and stamped by a professional engineer:
“Having reviewed the definitive and detailed project No. ES 00346-8, pertaining to
“Replace PV and Trafo MV switchgears in substation bldg 5882, Depot, Livorno, Italy” and project No ES 00177-8, pertaining to “Upgrade POD Bldg 5180, Depot, Livorno, Italy”, I declare that I have ascertained that the technological system included therein comply with the applicable Italian norms.
DATE SIGNATURE
Esaminato il progetto definitivo e dettagliato No. ES 00346-8 “Sostituzione dei quadri di media tensione fotovoltaico e trasformatore nella cabina edificio 5882, Depot, Livorno, Italia” e No. ES 00177-8 “Miglioria del Punto di Consegna edificio 5180, Depot, Livorno, Italia”, dichiaro di aver accertato che strutture ed impianti tecnologici in esso contenuti rispondono alla vigente normativa italiana.
DATA FIRMA
- The final design submittal shall also be accompanied by the following statement, signed by a technically qualified representative of the construction contractor:
“I, undersigned __________, in the vest of __________, have reviewed the final design submittal of project _____________, prepared by __________, with particular reference to the drawings and technical specifications, and I have found it:
- complete;
- constructible;
- fully compliant with the Scope of Work;
- feasible within the terms of the contract.
I understand that the above mentioned design documents, once reviewed and accepted by the Government, will become contract documents. I also understand that if anything of the
Scope of Work is missing in the design, my Company will still be obliged to perform.”
III. Drawings and documents provided to Contractor The following drawings are provided to the contractor with the purpose of showing the consistency of the facility where the work is planned. There is, however, no guarantee that the situation shown in the drawings exactly reflects the existing conditions. The drawings are provided in tiff or pdf format and will not be available in CAD format (unless otherwise indicated):
- Depot plan (available also in CAD format)
- Plan Bldg 5180 (available also in CAD format)
- Plan Bldg 5882 (available also in CAD format)
- MV one line diagram bldg 5882 (available also in CAD format)
- Wiring diagram MV panel 5180
IV. Technical Specification Technical Specification, are furnished to the Contractor to be used as the basis for design. The
TS will be able to be modified/expanded/integrated as applicable only upon authorization of the Design COR. However integrations will be mandatory for sections which are not covered in what provided by the Government.
V. Applicable Codes All applicable Italian Laws, Italian Codes and American Codes, in particular:
- Italian D.M. 37/08
- CEI 0-16
- All applicable Italian CEI and European CEI EN norms
- NFPA 70 “National Electric Code”
- All applicable NFPA codes
- UFC 3-501-01, Unified Facilities Criteria, Electrical Engineering
- UFC 3-520-01, Unified Facilities Criteria, Interior Electrical Systems
- UFC 4-010-01, Unified Facilities Criteria, Design: DOD Minimum Antiterrorism
Standards for Buildings
- All other applicable Unified Facilities Criteria
VI. Submission Requirements.
(1) PREFINAL DESIGN SUBMISSION (90% DESIGN COMPLETION).
The prefinal design will be delivered as per enclosed Progress Plan and will consist of the following elements in the quantities specified for the project:
ELEMENT QUANTITY
a. Print copies of drawings 2 sets (English and Italian)
b. Print copies of technical specifications 2 sets (English only)
c. Print copies of final design analysis 2 sets (English and Italian)
d. Compact disk, rewritable, containing:
1. The entire technical specifications (English and Italian) in a data format compatible with Adobe Acrobat Reader.
2. All project drawings in a data format compatible with
Adobe Acrobat Reader.
1 set
(2) FINAL DESIGN SUBMISSION (100% DESIGN COMPLETION).
The final design will be delivered as per enclosed Progress Plan and will consist of the following elements in the quantities specified for the project:
ELEMENT QUANTITY
a. Print copies of drawings signed and stamped 2 sets (English and Italian)
b. Print copies of technical specifications signed and stamped 2 sets (English only)
c. Print copies of final design analysis signed and stamped 2 sets (English and Italian)
d. Final version of the new “Regolamento di Esercizio”, signed and stamped
1 original (Italian only)
e. Certification of Compliance with Italian norms, signed and stamped
2 originals
f. Compact disk, rewritable, containing:
1. The entire technical specifications (English) in a data format compatible with Word for Windows Software.
2. All project drawings (English and Italian) in a data format compatible with Autocad Software
1 set
g. Compact disk, rewritable, containing:
1. The entire technical specifications (English) in a data format compatible with Adobe Acrobat Reader.
2. All project drawings (English and Italian) in a data format compatible with Adobe Acrobat Reader.
3. Final design analysis (English and Italian) in a data format compatible with Adobe Acrobat Reader.
4. Pdf Scan of the final version of the new “Regolamento di
Esercizio”, signed and stamped
1 set
Documents at point a., b., c. above will be delivered after the other documents have been checked and approved, and will incorporate any further comment or discovered deficiency.
VII. Design Review Meetings.
The Contractor is expected to attend a pre-design meeting and a review meeting after the pre-final submittal. The meeting will take place at the COR’s office, Bldg 5155, Supply and
Maintenance Area, Livorno.
VIII. Design Review Comments.
In general, design review comments will be returned to designers within 15 calendar days from the date of receipt of design. Every submittal after the preliminary shall be accompanied by an annotated copy of the review comments.
Phase 2 (Construction) Description:
Provide construction of all features of the project as designed in phase 1 and approved, in accordance with proposed and approved design and progress plan. Construction will start upon final approval of design, and will last as per the enclosed progress plan (enclosure 1).
General notes:
a. At the completion of the work, the following documents will be provided to the COR:
- Copy of the certification of each utility system, according to Italian D.M. 37/08 requirements; in addition to paper copy, provide a .pdf file of each certification, created by scanning the original document, stamped and signed, attachments included.
- Copy of the instruction manuals of the systems, if applicable.
- Copy of the As built drawings stamped and signed, in reproducible format; in addition to the reproducible copy provide electronic copies in CAD format (.dwg files) and in
ADOBE ACROBAT format (.pdf files)
- All the other documents required in the Scope of Work.
b. Compliance with laws, regulations, criteria. All design and construction work shall be performed in full accordance with applicable Italian and United States laws, regulations, codes, whichever is more restrictive at contract award date. Main criteria are listed under
2.e. This includes any required certification by engineers licensed in Italy.
c. The project is subject to D. Lgs. 81/08. The Safety & Coordination Plan will be prepared during the design phase. The contractor shall provide his/her Piano Operativo di Sicurezza
(safety plan, complementary final plan) and comply with the requirements of above mentioned laws as well as with those all other applicable Italian safety laws.
d. Emergency Situations. Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:
- A copy of the Camp Darby Emergency Plan, to which contractor will refer in the case of the emergency conditions indicated in the plan itself.
- Base Grid Coordinates layout, with the work site highlighted.
- List of emergency telephone numbers.
e. Project Identification Sign. The contractor shall supply and install a sign identifying the project. The sign shall be of high-resistant plywood for outdoor installation, white painted.
The dimensions shall be 1200x2400x12 mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be 10 cm. The sign shall be fixed to a structure made of any material provided it is lasting and in compliance with all safety requirements. The sign shall be well visible, with the lower side at 1.2 m from ground level.
f. The annexed Technical Specifications general sections Ia, Ib, are ruling, for what attains construction management and quality control, and are not allowed to be modified by
Contractor.
IX. AT/OPSEC/Environmental requirements:
AT Level I Training. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas will complete AT Level I awareness training within 30 calendar days after the contract start-date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor will submit certificates of completion for each affected contractor employee and subcontractor employee to the COR or to the contracting officer, if a COR is not assigned, prior to issuance of Installation Access Passes. AT Level I awareness training is available online at https://atlevel1.dtic.mil/at.
According to AR 530-1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.
Access and General Protection/Security Policy and Procedures: The Contractor shall obtain entry passes for each employee from the COR. The Contractor shall inform his personnel that they may be subjected to search when entering or leaving the installation at the discretion of the Installation Commander. Upon completion of the contract work or upon employee termination the Contractor shall return all passes to the Contracting Officer or the COR.
Contractor and all associated sub-contractors' employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshall Office, Director of Emergency Services, or
Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection
Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
iWATCH Training: The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the
COR. This training shall be completed within 15 calendar days of contract award and within
10 calendar days of new employees commencing performance with the results reported to the
COR NLT 10 calendar days after contract award.
ENVIRONMENTAL MANAGEMENT SYSTEM: The USAG Italy implements an EMS in accordance with EO13693, ISO 14001:2004(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. The USAG
Italy EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities and authorities while supporting the USAG Italy mission. Contractors and their personnel are required to be aware of, and comply with, the USAG Italy Environmental policy and legal and other requirements when performing work at an installation.
The contractor will provide the following information semi-annually to be used by the
Government to address environmental performance relative to the goals of the USAG Italy
Environmental Management System. Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July-
December will be submitted by 15 January each year.
Media Report Element #1 Report Element #2
Non-Hazardous Solid
Waste
Total Waste
Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Construction
Debris/Demolition
Materials
Total Waste
Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Compostable/Organic
Material
Total Waste
Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Hazardous Materials Total Used (Kg)
Hazardous Waste Total Generated
(Kg)
Total Recycled (Kg)
Energy Consumption -
Electricity
Total Energy
Consumed (MBtu)
Energy Consumption -
Fuel
Total Fuel
Consumed (L)
Renewable/Alternative
Energy
Total Consumed
(MW)
Facility
Construction/Renovation
Number of Buildings
LEED Certified
Silver or Higher
SqFt of buildings LEED
Certified
SECTION END
IMVI-LPW-F 16 November 2018
PERFORMANCE WORK SCHEDULE
1. Project:
ES 00346-8 Replace PV and Trafo MV switchgears in substation bldg 5882, Depot
ES 00177-8 Upgrade POD Bldg 5180, Depot
2. This project is made of one (1) Basic Project Item and no (0) Project Option Items.
3. This project shall be performed in two phases. The contract performance period for the entire contract (Phase 1 plus Phase 2) is as follows:
- Design Phase: 75 calendar days;
- Construction Phase: 75 calendar days.
Individual Notice to Proceeds will be released for each of the two phases.
a. Phase 1 (Design): This phase is managed by a Contracting Officer Representative, from the Directorate of Public Works (DPW), Engineering Services Branch. The US
Government should not take longer than 15 days to provide review comments to the contractor for each planned submittal.
b. Phase 2 (Construction): This phase will be controlled by the COR from the DPW
Construction Management Branch, in accordance with documents approved in Phase
1. Normally, construction can begin after the contractor has made all changes identified during the Government design review. However, the contractor may be allowed to proceed with construction while clarification and Hall/Services comments are being incorporated into the design. The revisions can be approved by partial re-submittals.
c. The Notice to Proceed (NTP) date for the Design Phase will be established at the Pre-
Performance Conference. After the final design submittal has been approved and it is time to start construction, the first phase is closed and a new Notice to Proceed is issued by the Contracting Officer to the contractor.
d. Phasing: Project phasing will be in accordance with the Milestones Plan at Enclosure
1, which is a Contract document.
Overall number of Calendar Days allowed will be in accordance with paragraph 3. This will include Government times as listed in the Milestone Plan at Enclosure 1.
e. General Installation Access Information: Once the contractor has been awarded the contract, he must apply for installation passes for each contract personnel requiring access for more than 60 calendar days to perform work. It takes a minimum of 30 working days from the date of application to the Security Office to be issued an installation pass. This strict access requirement will require more attention for scheduling and handling pass applications and shall be considered prior to submission of contractor’s proposal.
f. General Submittal Requirements:
(1) Government approval is required for extensions of design, critical materials, deviations, O&M manuals or those involving equipment whose compatibility with the entire system must be checked, and other items as designated by the
Contracting Officer. Within the terms of the Contract Clause entitled
“Specifications and Drawings for Construction,” they are considered to be “shop drawings.” The Contracting Officer’s approval of submittals shall not be construed as a complete check, but will indicate that the general method of construction, materials, detailing and other information are satisfactory.
Approval will not relieve the Contractor of the responsibility for any error, which may exist, as the contractor is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.
(2) Shop drawing submittals for Government approval are required for electrical, mechanical and LAN equipment to be installed and shall be made concurrently, and shall include layout drawings showing the equipment proposed to be furnished, including special foundations, duct work, piping and electrical conduit, superimposed on the building plans and elevation. Elevation views of the layout shall be included. The layouts shall be true to scale in both plan and elevation.
The equipment shall be shown in its final position as recommended by the manufacturer and shall contain adequate dimensions to determine the location of all equipment proposed and areas required for maintenance indicated.
(3) Definitions and Examples: The examples provided below are not all-inclusive and are used only for illustration purposes.
(4) Extensions of design examples are fire alarm and sprinkler protection systems, prefabricated buildings, structural steel drawings, standing seam metal roof drawings, coordination studies such as short circuit analysis of contractor selected electrical equipment, etc.
(5) Critical materials are defined as materials, which must meet specific quality performance standards required by design parameters, the failure of which will have a major impact on the operation, maintenance, quality of life or life safety of the system. Examples of critical materials are coatings for cathodic protection of storage tanks, high-pressure piping and controls, acid and hazardous waste systems, or architectural finishes for customer approval.
(6) Deviations are any submittal by the construction contractor that varies from or are omitted from the construction contract specifications.
(7) Examples of equipment which must be checked for compatibility with existing systems or the entire new system are equipment for sewage treatment and water purification plants, energy management control systems, intrusion detection systems, power generation and distribution systems, etc.
SECTION END
Milestones Date Phase duration Progressive
Design Phase
NTP/Start Design 1-Feb-19 0 Submittal Prefinal Design 3-Mar-19 30 30 Comments 18-Mar-19 15 45 Submittal Final Design and Approval Requests 2-Apr-19 15 60 Comments 17-Apr-19 15 75
Pause
Construction Phase NTP/Start Construction 15-Apr-18 Completion of construction 29-Jun-18 75 75
TOTAL = 150
Feb 19 is hypothetycal Design NTP date.
In case this date changes, the plan will vary.
Notes
Passes for construction shall be otnained during design phase
Project ES 00346-8 Replace PV and Trafo MV switchgears in substation bldg 5882
MILESTONES PLAN