About this file

Attachment 1

View the file

Other files

File Type Posted
W912PF-17-R-0015-0001.pdf PDF
ATTACHMENT__3.pdf PDF
ATTACHMENT_1_EXCEL.xlsx XLSX spreadsheet
Self_Certification_for_Antimafia_-_Enclosure__1.pdf PDF
List_of_work_Features_-_Attachment__1.pdf PDF
Statement_of_Work__Attachment___2.pdf PDF
W912PF-17-R-0015.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. HB-41026-7J

IGE-DD-LGZ UXO SURV-FINAL

HARDSCAPE- LEGACY ZONE

DEL DIN - VICENZA - ITALY

28 FEB 2017

FOUO Page 1 of 11

Quantity/Quantità Material Cost/Costo MaterialeLabor Cost/Costo Manodo Total Cost/Costo T Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro

BASIC

G ZONE G BLDG 43-139 m² 3,770.69 E ZONE E BLDG 43-139 m² 2,979.93 F ZONE F BLDG 43-139 m² 797.46

I SUB TOTAL 7,548.08

OPTION

C ZONE C BLDG -139 m² 3,420.48 H ZONE H BLDG -139 m² 1,651.67

II SUB TOTAL m² 5,072.15

GRAND TOTAL WORK m² 12,620.23

RATE FY 17 € 1.0000 = $0.8990

1464736227.ln Typewritten Text

ATTACHMENT #1

Project No.HB-41026-7J

IGE-DD-LGZ-UXO SURVEY C

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 2 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

B LEGACY AREA UXO SURVEY FIELD OP

Safety IAW LAW 81/2088 1.00%

GRAND TOTAL WORK

RATE FY 17 € 1.0000 = $0.8990

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

ZONE C BLDG -139

1.0 Italian 5th Command Authorization LS 1.00

2.0 Final statement and related area release LS 1.00

total

B LEGACY AREA UXO SURVEY FIELD OP

1.0 Site Preparation LS 1.00

2.0

Existing facility and utilities topographic survey with GPS method including elevation. Exposure of underground utility line will be m² 3,420.48

3.0 Mechanical UXO monitoring down to max. allowed (7.00 m from ground m² 3,420.48

4.0 BCM Excavation including material filtering with archaeology assistance m³ 3,420.48

5.0 Excavated material disposal IAW italian rules. m³ 342.05

6.0 Existing Underground metal tank removal and disposal including related concrete structure LS

7.0 Filling back material filtered on site (gravel, soil) and compaction m³ 273.64

7.0 Filling back with new material (gravel, soil) including transpotation and compaction m³ 68.41

1464736227.ln

IGE-DD-LGZ-UXO SURVEY C

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 3 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

8.0 Assitance to Construction Excavation including archaeology monitoring. Hrs 40.00

9.0

CMR: Contractor Manpower Reporting (CMR) data must be accurate and complete and entered into CMR during the data gathering period of 1 October through October 31 for every year, or part of the year for which the contract is in force. LS 1.00 total

1464736227.ln

IGE-DD-LGZ-UXO SURVEY E

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 4 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

B LEGACY AREA UXO SURVEY FIELD OP

Safety IAW LAW 81/2088 1.00%

GRAND TOTAL WORK

RATE FY 17 € 1.0000 = $0.8990

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

ZONE E BLDG 43-139

1.0 Italian 5th Command Authorization LS 1.00

2.0 Final statement and related area release LS 1.00

total

B LEGACY AREA UXO SURVEY FIELD OP

1.0 Site Preparation LS 1.00

2.0

Existing facility and utilities topographic survey with GPS method including elevation. Exposure of underground utility line will be m² 2,979.93

3.0 Mechanical UXO monitoring down to max. allowed (7.00 m from ground m² 2,979.93

4.0 BCM Excavation including material filtering with archaeology assistance m³ 2,979.93

5.0 Excavated material disposal IAW italian rules. m³ 595.99

6.0 Existing Underground metal tank removal and disposal including related concrete structure LS

7.0 Filling back material filtered on site (gravel, soil) and compaction m³ 2,383.94

7.0 Filling back with new material (gravel, soil) including transpotation and compaction m³ 595.99

1464736227.ln

IGE-DD-LGZ-UXO SURVEY E

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 5 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

8.0 Assitance to Construction Excavation including archaeology monitoring. Hrs

9.0

CMR: Contractor Manpower Reporting (CMR) data must be accurate and complete and entered into CMR during the data gathering period of 1 October through October 31 for every year, or part of the year for which the contract is in force. LS 1.00 total

1464736227.ln

IGE-DD-LGZ-UXO SURVEY F

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 6 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

B LEGACY AREA UXO SURVEY FIELD OP

Safety IAW LAW 81/2088 1.00%

GRAND TOTAL WORK

RATE FY 17 € 1.0000 = $0.8990

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

ZONE F BLDG 43-139

1.0 Italian 5th Command Authorization LS 1.00

2.0 Final statement and related area release LS 1.00

total

B LEGACY AREA UXO SURVEY FIELD OP

1.0 Site Preparation LS 1.00

2.0

Existing facility and utilities topographic survey with GPS method including elevation. Exposure of underground utility line will be m² 797.46

3.0 Mechanical UXO monitoring down to max. allowed (7.00 m from ground m²

4.0 BCM Excavation including material filtering with archaeology assistance m³ 797.46

5.0 Excavated material disposal IAW italian rules. m³ 159.49

6.0 Existing Underground metal tank removal and disposal including related concrete structure LS

7.0 Filling back material filtered on site (gravel, soil) and compaction m³ 127.59

7.0 Filling back with new material (gravel, soil) including transpotation and compaction m³ 31.90

1464736227.ln

IGE-DD-LGZ-UXO SURVEY F

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 7 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

8.0 Assitance to Construction Excavation including archaeology monitoring. Hrs

9.0

CMR: Contractor Manpower Reporting (CMR) data must be accurate and complete and entered into CMR during the data gathering period of 1 October through October 31 for every year, or part of the year for which the contract is in force. LS 1.00 total

1464736227.ln

IGE-DD-LGZ-UXO SURVEY G

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 8 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

B LEGACY AREA UXO SURVEY FIELD OP

Safety IAW LAW 81/2088 1.00%

GRAND TOTAL WORK

RATE FY 17 € 1.0000 = $0.8990

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

ZONE G BLDG 43-139

1.0 Italian 5th Command Authorization LS 1.00

2.0 Final statement and related area release LS 1.00

total

B LEGACY AREA UXO SURVEY FIELD OP

1.0 Site Preparation LS 1.00

2.0

Existing facility and utilities topographic survey with GPS method including elevation. Exposure of underground utility line will be m² 3,770.69

3.0 Mechanical UXO monitoring down to max. allowed (7.00 m from ground m²

4.0 BCM Excavation including material filtering with archaeology assistance m³ 3,770.69

5.0 Excavated material disposal IAW italian rules. m³ 754.14

6.0 Existing Underground metal tank removal and disposal including related concrete structure LS

7.0 Filling back material filtered on site (gravel, soil) and compaction m³ 3,016.55

7.0 Filling back with new material (gravel, soil) including transpotation and compaction m³ 754.14

1464736227.ln

IGE-DD-LGZ-UXO SURVEY G

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 9 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

8.0 Assitance to Construction Excavation including archaeology monitoring. Hrs

9.0

CMR: Contractor Manpower Reporting (CMR) data must be accurate and complete and entered into CMR during the data gathering period of 1 October through October 31 for every year, or part of the year for which the contract is in force. LS 1.00 total

1464736227.ln Typewritten Text

1464736227.ln

IGE-DD-LGZ-UXO SURVEY H

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 10 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

B LEGACY AREA UXO SURVEY FIELD OP

Safety IAW LAW 81/2088 1.00%

GRAND TOTAL WORK

RATE FY 17 € 1.0000 = $0.8990

A LEGACY AREA UXO SURVEY 5TH COMM ADMIN

ZONE H BLDG -139

1.0 Italian 5th Command Authorization LS 1.00

2.0 Final statement and related area release LS 1.00

total

B LEGACY AREA UXO SURVEY FIELD OP

1.0 Site Preparation LS 1.00

2.0

Existing facility and utilities topographic survey with GPS method including elevation. Exposure of underground utility line will be m² 1,651.67

3.0 Mechanical UXO monitoring down to max. allowed (7.00 m from ground m² 1,651.67

4.0 BCM Excavation including material filtering with archaeology assistance m³ 1,982.00

5.0 Excavated material disposal IAW italian rules. m³ 396.40

6.0 Existing Underground metal tank removal and disposal including related concrete structure LS

7.0 Filling back material filtered on site (gravel, soil) and compaction m³ 1,585.60

7.0 Filling back with new material (gravel, soil) including transpotation and m³ 396.40

8.0 Assitance to Construction Excavation including archaeology monitoring. Hrs

1464736227.ln

IGE-DD-LGZ-UXO SURVEY H

HARDSCAPE - LEGACY ZONE

DEL DIN - VICENZA - ITALY

30 JAN 2017

FOUO Page 11 of 11

Quantity/Quantità Material Cost/Costo Materiale Labor Cost/Costo Manodopera Total Cost/Costo Totale Item DESCRIPTION Unit "K" "L" Unit "K" "L" Unit "K" "L" "K" "L" "K+L"

Unità Unità Euro Euro Unità Euro Euro Euro Euro Euro

9.0

CMR: Contractor Manpower Reporting (CMR) data must be accurate and complete and entered into CMR during the data gathering period of 1 October through October 31 for every year, or part of the year for which the contract is in force. LS 1.00 total

1464736227.ln

IGE-DD-LGZ UXO SURV-FINAL
IGE-DD-LGZ-UXO SURVEY C
IGE-DD-LGZ-UXO SURVEY E
IGE-DD-LGZ-UXO SURVEY F
IGE-DD-LGZ-UXO SURVEY G
IGE-DD-LGZ-UXO SURVEY H