W912PA-18-R-0003
ATTACHMENT IV
PROGRESS SCHEDULE
The Contractor shall submit a Detailed Work Schedule (Ref. G-04) within 30 days as of the contract award according to the following Progress Schedule:
Item Description Completion date:
Weather’s season conditions sensitive:
G-04 Detailed Work Schedule 30 days CA No
G-06 Obtain digging permit, underground pipes and cables 30 days CA No
G-11 Access to the military installation 30 days CA No
G-14 Documentation submittals (material register submittal) 30 days CA No
NTP Issuance of Notice to Proceed (NTP) 90 days CA n/a
G-07 Obtain hot work permit 10 days NTP No
TP-1-01 Preparation and protection of work site 40 days NTP Yes
TP-1-02 Dismounting 40 days NTP Yes
TP-1-03 Removal of old watertight layer and insulation 40 days NTP Yes
TP-2-01 Substrate 150 days NTP Yes
TP-2-02 Vapor barrier 150 days NTP Yes
TP-2-03 Insulation 150 days NTP Yes
TP-2-04 Sub layer (vapor spread) 150 days NTP Yes
TP-2-05 Watertightness layer 150 days NTP Yes
TP-3-01 Wall cover 170 days NTP Yes
TP-3-02 Zinc work along the hangar wall 170 days NTP Yes
TP-3-03 Reinstallation of lightning system 170 days NTP Yes
TP-3-04 Repair weather fillets with seal around metal frame 170 days NTP Yes
TP-3-05 Provide and install rainwater inlets 170 days NTP Yes
TP-3-06 Replace water downspouts of the hangar 170 days NTP Yes
TP-3-07 Replace water downspouts of the annexes 170 days NTP Yes
TP-3-08 Replace manhole 170 days NTP Yes
TP-3-09 Replace the lighting above entrance doors 170 days NTP Yes
TP-3-10 Remove and reinstall the satellite antenna 170 days NTP Yes
G-10 Coordination in matter of safety and health Throughout contract lifetime
No
G-13 Final inspection 170 days NTP No
Legend:
CA – Contract award NTP – Notice to Proceed