W912PA-18-R-0003

ATTACHMENT III

LIST OF DELIVERABLES

Item Ref. Deliverable Completion date Subm it To

Check Delive red 1 G-03 Hazardous products inventory list with safety data sheet 30 days CA COR

2 G-05 As-built drawings 170 days NTP COR

3 G-06 Digging Permit Request Minimum 15 days before starting the earthwork

COR

4 G-07 Hot Work Permit Request 10 days NTP COR

5 G-08 EMS briefing verification signed document 30 days CA COR

6 G-10 The Safety and Health Plan 30 days CA COR

7 G-11/A AT Level I Training for each employee Take the training within 30 days CA and provide the certificate within 60 days CA

COR

8 G-11/C iWATCH/iSALUTE Training for each employee 30 days CA and within 5 days after new employees commence contract performance

COR

9 G-11/D OPSEC Training for each employee 30 days after each report for duty COR

10 TP-2-02 Vapor Barrier - Submittal Submitted for approval 30 days

CA

COR

11 TP-2-03 Insulation - Submittal Submitted for approval 30 days

CA

COR

12 TP-2-04 Sublayer (Vapor Spread) - Submittal Submitted for approval 30 days

CA

COR

13 TP-2-05 Water Tightness Layer - Submittal Submitted for approval 30 days

CA

COR

14 TP-2-05 Raised Parts - Submittal Approved by the COR and the Fire Chief 3 weeks before starting the work

COR

15 TP-3-01 Wall Cover - Submittal Submitted for approval NLT 3 weeks prior to installation

COR

16 TP-3-02 Zinc Work Along The Hangar Wall - Submittal Submitted for approval NLT 3 weeks prior to installation

COR

17 TP-3-04 Weather Fillets With Seal Around Metal Frame - Submittal

Submitted for approval 30 days

CA

COR

18 TP-3-05 Rainwater Inlets - Submittal Submitted for approval 30 days

CA

COR

19 TP-3-06 Water Downspouts Of The Hangar - Submittal Submitted for approval 30 days

CA

COR

20 TP-3-07 Water Downspouts Of The Annexes - Submittal Submitted for approval 30 days

CA

COR

21 TP-3-08 Manhole - Submittal Submitted for approval 30 days

CA

COR

22 TP-3-09 The Lighting Above Entrance Doors - Submittal Submitted for approval NLT 3 weeks before installation

COR

Legend:

CA – Contract award NTP – Notice to Proceed