USAG BENELUX

ENGINEERING DIVISION

HANGAR # 6 - CHIEVRES AIR BASE

HAINAUT - BELGIUM

STATEMENT OF WORK

PROJECT :

R-CH-O2D-17104-17

TITLE : Repair Roof

LOCATION :

Building # 20019 – Chievres Air Base

PERFORMANCE PERIOD :

Thirty (30) calendar days after issuing of the Notice To Proceed

INDEX

CHAPTER I GENERAL

CHAPTER II TECHNICAL PROVISIONS

SECTION 1 : Preliminary work and dismounting SECTION 2 : Removal of old water tightness and insulation SECTION 3 : Repair and protect concrete SECTION 4 : New insulation SECTION 5 : New SBS membrane SECTION 6 : Upstand and special profiles SECTION 7 : Maintenance of water downspouts

CHAPTER I

GENERAL

G-01 SCOPE OF WORK

A) General work description

The project consists of the removal and replacement of the water tightness on the roof of building # 20019.

The site of work is located at: Building # 20019, Chievres Air Base, 7950 Chievres

B) Principal features

Principal items to be performed to accomplish the work consist of the following:

1 : Preliminary work and dismounting 2 : Removal of old water tightness and insulation 3 : Repair and protect concrete 4 : New insulation 5 : New SBS membrane 6 : Upstand and special profiles 7 : Maintenance of water downspouts

The above general outline of principal features does not in any way limit the responsibility of the contractor to perform all work necessary to achieve the desired end results and to supply all materials and labor required by these specifications and drawings.

G-02 DRAWINGS AND STANDARDS

A) Drawings

All work under this contract shall be carried out in strict conformity with the following drawings, which form a part of these specifications.

DRAWINGS TITLE DATE

R-CH-O2D-17104-17 Repair Roof, Bldg # 20019 – CAB May 2018

B) Specific applicable standards

All Belgian norms and regulations in force concerning the performance of this project shall be applicable, as well as a Particular safety statement as described in the USAG Benelux Memo 385-1 Para 4, in Annex A of this SOW.

G-03 GUARANTEE, WORKMANSHIP AND MATERIALS

A) Workmanship and materials

All work done by the contractor shall be in strict conformance with the best practices of the trades involved.

The contractor shall employ workmen who are skilled in their particular trades.

All materials shall be brand new.

The contractor shall in no way use asbestos containing materials for the performance of his work.

The paints shall be lead free.

B) Guarantee

The contractor shall guarantee his workmanship and materials for a minimum period of 10 years. The Chlorinated PolyEthylene (CPE) membrane will be guaranteed for a period of 15 years from the date of invoice.

G-04 SCHEDULING OF WORK

Prior to starting any work and within 30 calendar days after date of contract, the contractor shall furnish to the Contracting Officer Representative (COR) for approval, a detailed schedule showing the successive phases of the work.

G-05 AS-BUILT DRAWINGS

The initial CD-ROMs will be provided to the contractor for review. The contractor shall submit detailed as-built drawings after completion of the project and before submitting the final bill. As-built drawings will be precise and accurate.

As-built drawings will be drawn on Microstation system or any other 100% compatible software. The contractor will provide accurate details of finish parts.

G-06 UNDERGROUND PIPES AND CABLES

Before starting the earthwork, the contractor shall submit a written Digging Permit Request to the COR.

Situational drawings with the earthwork that shall be performed, when the work shall be performed, and all utilities near the earthwork site that will be effected, shall be provided to the COR a minimum of 15 days before starting the earthwork.

Drawings must be of sufficient scale to clearly show the proposed work. A drawing illustrating existing utilities shall be provided to the contractor after contract award. No digging shall occur until written approval is provided by CEPSD, TDPW or DPW.

During the replacement of the water downspouts, the contractor shall ensure that no underground pipes or cables of any kind and their accessories shall be damaged during the performance of the work. Any repair is done at the contractor’s expense and at the entire satisfaction of the COR. Additional information (drawings, etc.) about underground pipes and cables can be obtained at the Engineer Division - Hangar 6 - Chievres Air Base. However, this information is only given as an indication and does not in any way commit the responsibility of the U.S. Government. The contractor shall thus be responsible for carrying out the required soundings to verify their exactitude as part of the dismounting work as described in Par. TP-1-03.

G-07 HOT WORK PERMIT

All security measures as stated in the “Règlement Général sur la Protection du Travail” (General Regulations for Work Protection, R.G.P.T.) will be complied within seven (7) calendar days prior to starting the work, the contractor will ask a Hot Work Permit (for welding, cutting work, etc.) to the COR. This permit will be delivered by the U.S. Army Fire Officer. In addition, no open fires or burning of trash will be allowed within the confines of the USAG (United States Army Garrison) Benelux Community Benelux Community.

Contractors, concessionaires or vendors performing work or conducting business on or in facilities under the jurisdiction of the USAG Benelux Military Community Commander Area of Responsibility (AOR) shall conform to the regulation provided below.

Specific requirements and limitations are as follows:

1. Smoking is prohibited in the vicinity of hazardous operations and locations.

2. Waste material and rubbish shall not be stored or allowed to accumulate within the building or in the immediate vicinity, but shall be removed from the site at least daily. Rubbish shall not be burned on the site.

3. Contractor materials and equipment shall not be stored in a location or manner which shall create a fire exposure to facilities adjacent to the project site.

4. The contractor shall provide fire extinguishers at all locations where work is carried out.

5. In every building operation where a shed, storage, or other shanty is placed, or room or space is used for storage or workshop, the contractor shall provide at least one approved portable fire extinguisher in an accessible location. Portable fire extinguishers must be verified annually by certified companies following standards NBN S21-050 and technical notice NT117 edited by ANPI, in accordance with tem 358 of General Regulations for Work Protection (RGPT).

6. Flammable liquids and other hazardous materials such as paints, paint thinner, gasoline, asphalt, and tar shall be stored in small detached structure or out in the open and not inside main buildings. Low flash point liquid used within buildings shall be handled only in approved safety cans.

7. Adequate ventilation shall be provided for paint spraying and operations involving the application of materials using adhesives containing flammable solvents. Such operations shall be conducted remote from any potential source of ignition.

8. Asphalt and tar kettles shall be located in a safe place outside of the building. Such kettles shall not be placed on roofs or porches. Continuous supervision shall be maintained while kettles are in operation.

Metal covers shall be provided for all kettles to smother flames in case of fire.

9. Electrical wiring and equipment for lighting, heating, and power purposes shall be installed in compliance with current US and Host Nation Electrical Regulation requirements.

10. Cutting and welding shall not be permitted unless:

a. A valid Hot Work Permit (welding permit) is available; AND

b. Combustibles have been safely covered or moved away; AND

c. A fire guard with a serviceable fire extinguisher is posted for the duration of the work and 30 minutes thereafter to assure that sparks or drops of hot material do not start fires.

11. Fire hydrants shall only be used for fire fighting and training of the local fire and Emergency Services.

Water can only be taken from hydrants with the permission of the Community Fire and Emergency Services Office. Parking within 2.5 m (8 feet) of a hydrant is not permitted. Vehicles and other equipment with fuel driven motors, with mounted and filled fuel tanks shall be equipped with 2,5 kg or larger carbon dioxide or dry chemical fire extinguishers.

12. Gasoline, oil and grease shall not be disposed into drainage systems or public water systems. Oil contaminated areas shall be covered with an absorbent material and removed in accordance with the Spill Contingency plan. Any POL spillage shall be reported immediately to the DES Fire and Emergency Services Office, DSN 361-5401/5347.

13. Construction offices, huts, construction vehicles, trailers and supplies shall be located at least 10 m from all adjacent buildings.

14. Access for fire fighting vehicles shall be provided to the immediate job site at the start of construction and maintained until all construction is complete. Vehicle parking control measures shall be established.

15. Free access from the street to fire hydrants and to outside connections for standpipes or other firefighting equipment, whether permanent or temporary, shall be provided and maintained at all times. No materials or constructions shall be placed within 10 feet of such hydrants or connections, or between fire hydrants and the center line of the street.

16. Scaffolding materials or equipment shall not block fire escape routes or access routes during performance of projects in occupied buildings.

17. In all buildings over 30 feet in height, at least one stairway shall be provided in a usable condition at all times.

18. Notification and actions to be taken in case of a fire:

a. Persons who discover a fire shall immediately alarm all personnel in the area, and shall report the fire to the Community Military Police using the nearest telephone. Military telephone dial 117.

b. The fire shall be reported using the building number. If the fire is outside of a building, the nearest building number shall be given. Stay on the phone until the operator on duty has completely understood and does not have any further questions. After the notification you should immediately ensure all windows and doors are closed and that all personnel have left the area.

The responding fire department must be informed if any special dangers exists; example: If gas and pressurized containers, or paint and other flammable material are within the range of the fire.

Not only acute fires, but also fires which have been extinguished and did not cause any damage must be reported.

c. To ensure smooth notification and fire fighting procedures, it is essential to show all employees the location of the nearest telephone, make sure they are familiar with the building number in which they are employed, and inform them of the locations of the fire extinguishers.

Also, for fire safety reasons, hot work permit shall not be issued to perform cutting or welding operations before or after USAG BENELUX AOR regular duty hours (from 8:00 to 16:30).

G-08 ENVIRONMENTAL STEWARDSHIP

All measures shall be taken to prevent occurrence of spills during works. When a leak is detected (i.e. fuel leak on field works vehicles or company vans), the contractor shall coordinate immediate clean-up of the spill. Should clean-up of the spill exceed the contractors response capabilities, the contractor shall immediately contact the following:

1) The COR

2) The Chievres Air Base Fire Department (068/ 27 54 01).

3) The USAG Benelux Environmental Division (068 27 5704)

4) The Spill Response Coordinator (068 27 5906)

The contractor shall be briefed on the USAG Benelux Environmental Management System (EMS) and its significant aspects prior to commencing work on USAG Benelux. Once the contractor has been briefed, an EMS verification document should be signed and uploaded to the Brussels Regional Contracting Office website.

The USAG Benelux Environmental Management System (EMS):

USAG Benelux implemented EMS IAW EO13693, ISO 14001:2015(E), DoD, and IMCOM requirements. An EMS is an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes and resources for developing, implementing, achieving, reviewing and maintaining the environmental policy of an organization. USAG Benelux and EMS is designed to ensure that all personnel, including contract personnel, whose work activities can cause a real or potential significant environmental impact, are aware of how their work supports the EMS and are competent to perform their roles, responsibilities, and authorities while supporting the Garrison’s mission. Contractors and their personnel are required to be aware of, and comply with, the Garrison EMS policy and legal and other requirements when performing work at an installation.

The Garrison EMS is explained during the contractor pre-performance meeting and/or in the EMS manual, which may be requested from the Environmental Division through the COR.

G-09 SITE MAINTENANCE AND FINAL CLEANING

During performance of the requirement, all measures shall be taken to avoid improper temporary storage of waste generated by performance. Emphasis is placed on Petroleum, Oil and Lubricants (POL) containing equipment or soiled/ hazardous waste (scrap metal, contaminated soil). As soon as the work is finished, the contractor shall remove all equipment, excess materials, debris, etc. generated by his work and shall evacuate them outside US Government installations.

G-10 COORDINATION IN MATTER OF SAFETY AND HEALTH

In accordance with the Royal Decree of 25 January 2001 concerning temporary and mobile worksites, the Safety and Health Plan contains, but is not limited to, the following elements:

- Description of the work to be performed

- Description of the risk analysis results (stage by stage analysis of the risks, analyses which are too vague shall not be acceptable).

- Description of the prevention measures to be taken, to include the following:

1. All the mitigating measures;

2. Specific measures relating to the activities; AND

3. Instructions for the parties involved.

- Expected duration of the work to be performed simultaneously or consecutively.

- A list containing the names and addresses of all project owners and contractors.

- Name and address of the design safety coordinator.

- Name and address of the implementation safety coordinator when he is appointed.

Additionally, and in accordance with the Royal Decree of 25 January 2001, the contractor shall comply with the following:

The law of 04 August 1996 related to the welfare of workers during the execution of their work and the royal decree of 25 January 2001 concerning temporary or mobile work sites are applicable for this project.

In accordance with article 71, §3, of above mentioned royal decree, a project-coordination as foreseen in section

III, 1st sub section, of this royal decree has been set up during the elaboration of this project. Therefore, there is a safety and health plan related to this project for these specifications.

The contractor shall comply with the recommendations of this safety and health plan (available upon request to the

“Engineering Plans and Services Division”, Hangar # 6, Chievres Air Base (David Diricq, EPS Division, tel.068/27.54.46).

These recommendations are part of this project.

In application of the same article 71, §3, an execution-coordinator shall be designated by the COR for the coordination in matter of safety and health during the execution of this project.

Within 15 days after contract award, the contractor shall submit at least 3 proposals of execution-coordinator to the COR for approval, along with the necessary documents for the verification of the compliance with the conditions to exercise the coordinator function (art. 56 to 64 of R.D. dated 25.01.2001 completed by the royal decree of 19.12.2001)

No proposal may emanate from a coordinator working for the awarding firm or for an office on which the contractor has a supervisory position.

The COR has 10 calendar days to choose the execution-coordinator.

The coordinator’s fee is at the contractor’s charge.

1. The contractor has 15 days from the selection of the coordinator to make up and transmit to the COR. and to the execution-coordinator a document with all the complementary elements to his bid that could be claimed by the coordinator.

2. The execution-coordinator does not act as a substitute for the COR He plays the role of an advisor of the awarding party. His mission is the following:

3.1 General obligations from the law of 04 August 1996 and royal decree of 25 January 2001

1. Coordinate the implementation of the general prevention principles described at article 5 of the law of 04 August 1996, during the technical or planning selections, in order to schedule the various simultaneous or consecutive works or phases of work, as well as during the expectation of the duration of these various works or phases of work;

2. Coordinate the implementation of relevant provisions in order to ensure that the contractors properly implement the general prevention principles and execution principles described at articles 4, 5 and 15 of the law of 04 August 1996;

3. Draw up a coordination logbook comprising the elements described at article 33 of the royal decree of 25 January 2001, except for elements dealing with the design of the project, and to update it;

4. Write down the deficiencies of the various parties in the logbook and to notify the COR;

5. Write down contractors’ remarks in the coordination logbook and leave them for information to the parties concerned;

6. Call and be the chairman of the coordination structure when such a structure has to be set up in accordance with article 37 of the royal decree of 25 January 2001;

7. Draw up an ulterior performance file whose content conforms with article 36 of the royal decree of 25 January 2001;

8. Organize the cooperation and coordination of activities between contractors, including those who follow one another, in order to ensure the protection of workers and the prevention of accidents and professional health hazards, as well as their mutual information;

9. Coordinate the supervision of the proper application of work procedures;

10. Take all necessary precautions so that only authorized people have access to the work site.

11. At the provisional acceptance of the work, to hand over the updated logbook and the ulterior performance file to the COR, and to notify this delivery in a record attached to the ulterior performance file.

3.2 Special obligations within the scope of this project

1. Read and understand these specifications related to the work to be executed, especially the article concerning the safety and health measures to be implemented on the work site in application of the law of 4 August 1996 about the welfare of workers during the execution of their work, and of R.D.

of 25 January 2001 about temporary or mobile work sites;

2. Give advice to the COR and make proposals in due time concerning the implementation and adaptations of the document described at item 2 of above mentioned article, during the previous phase described in that item 2 as well as during the execution of the work;

3. Participate in any meeting as requested by the COR or execution-coordinator, and schedule any necessary meetings with the COR or the execution-coordinator in support of the mission;

4. Control the application of the hazards prevention measures described at item 3 of the above mentioned additional article;

5. Monitor and track contractor’s obligation deficiencies as foreseen in above mentioned item 3 in the logbook;

6. Provide a copy of the health and safety plan for this worksite which mentions the results of the risk analysis.

7. The contractor applies the hazards prevention measures foreseen in the document described at item

2, adapted if necessary. All sections of this document will also be applied to sub-contractors.

8. During the execution of the work, the contractor updates the document described at paragraph 3.1.2, either independently, when the progress of the work justifies it, the identification of unforeseen or insufficiently known hazards justifies it, at the onset of employee turnover, for any modification to the project, or at the COR’s discretion. If some update occurs as a result of contractor action, the contractor must inform the awarding party and the execution-coordinator. The contractor shall take into account any possible remark expressed by the COR.

In particular, the contractor shall also provide the following information to the COR, as well as the execution-coordinator:

- Name of the subcontractor(s), with their certificate, the nature and cost of the work they are responsible for, the expected starting date and duration;

- Traffic rules and road signs for the work site, for the public traffic area (automobiles, bicycles, handicapped people…) and for the area reserved for the work and workers, and the access rules;

- Storage procedures and evacuation of materials and debris; AND

- Work planning.

9. The contractor shall give to the execution-coordinator, spontaneously or by request, any information that is indispensable for the execution of the mission. The contractor shall invite the execution-coordinator to any meeting where the execution-coordinator’s presence is necessary for the accomplishment of the subject task. The obligations of paragraph 8 shall also be applied to all possible subcontractors.

10. The compliance with the obligations described in items 2, 5 and 6 above is an integral part of this project. The application of hazards prevention measures described at item 4 is also an integral part of the project, provided that these measures do not exceed the general obligations that the law of 4 August 1996 and the R.D. of 25 January 2001 impose to contractors, in particular articles 7 and 15 of the law, and section VI, sub section IV of the decree.

11. The full text related to the coordination in matter of safety and health concerning this project can be requested to the “Engineering Division”, Hangar # 6, Chievres Air Base (POTTIEZ Christophe, tel.068/27.56.83).

G-11 ACCESS TO THE MILITARY INSTALLATION

1. Access control/Photography. The contractor and all associated subcontractor employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor shall also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DoD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.” Contractor must receive written approval from PAO prior to taking any photos or making any sketches, and may not discuss layout of any infrastructure with anyone outside the USAG Benelux or not associated with the contract. Contractor must receive written approval from PAO prior to taking any photos or sketches. All photos, sketches, and designs must be returned to DPW upon completion of the contract.

2. Access and General Protection/Security Policy and Procedures. The contractor and all associated subcontractor employees shall comply with applicable installation, facility, and area commander installation/facility access and local security policy and procedures (provided by Government representative). The contractor shall also provide all information required for background checks to meet installation-access requirements to be accomplished by the installation provost marshal office, director of emergency services, or security office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the force protection condition at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

3. iWATCH/iSALUTE Training. The contractor and all associated subcontractors will brief all employees on the local iWATCH/iSALUTE program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days after the contract is awarded and within 5 calendar days after new employees commence contract performance, with the results reported to the COR within 30 calendar days after the contract is awarded.

G-12 SPECIAL CONSIDERATIONS (UFC 3-260-01 on 17 NOVEMBER 2008)

UFC 3-260-01: 17 NOVEMBER 2008

SECTION 14 CONSTRUCTION PHASING PLAN AND OPERATIONAL SAFETY

ON AIRFIELDS DURING CONSTRUCTION

Link: https://www.wbdg.org/FFC/DOD/UFC/ufc_3_260_01_2008.pdf

G-13 FINAL INSPECTION

The final inspection of the work shall be done in the presence of the COR, Contracting Officer/Contract Specialist and the Contractor.

G-14 SUBMITTALS

The contractor shall provide all submittals in accordance with Attachment III of the Solicitation/Contract, List of

Deliverables.

CHAPTER II

TECHNICAL PROVISIONS

SECTION 1

PRELIMINARY WORK AND DISMOUNTING

TP-1-01 INSTALLATION OF PREFABRICATED BUILDING

The contractor has to install a temporary prefabricated structure for his own needs (workers and storage of equipment) near the site. He will also be responsible for all the connections of the temporary utilities, such as electricity, water and telephone lines.

TP-1-02 APPROPRIATE EQUIPMENT

During the execution of the work, the contractor will provide scaffoldings, ladders, and all necessary equipment for a good and safe execution of the work. He will not ask or borrow equipment from the U.S. Government (ladder, scaffolding, lift machines, etc.)

TP-1-03 DISMOUNTING

Dismounted items mentioned below include the removal and evacuation out of the area of all debris resulting from the work. All debris will be evacuated to an authorized public dump at the contractor’s expense. All dismounted items become the property of the contractor, unless otherwise specified in these specifications.

Any damage caused by the contractor’s personnel during the demolition work will be repaired at his cost.

Following items are given as an indication. This list is not limitative. The contractor will carry out all required investigations to complete it if necessary.

removal of all zinc finish profiles (edge profiles, finish profiles of gutters, chimney angle fillets, masonry fillets.)

dismounting of zinc or PVC water downspouts, shoes, fasteners.

dismounting of concrete slab at ground level, sidewalk or else, at the location where the shoe connects to the existing drainage system. Manhole shall be cleaned.

The concrete slab or sidewalk will be cut properly, with minimum damage. The contractor will not damage the collector drainage. If, during the dismounting, the contractor damages the pipe, he will replace it at his own cost.

TP-1-04 CLEANING DURING THE EXECUTION OF THE WORK

During the work, the contractor will be responsible for the cleaning and cleanliness of the site.

SECTION 2

REMOVAL OF OLD ROOFING AND INSULATION

TP-2-01 OLD ROOF REMOVAL AND CLEANING

This item includes the partial removal of the water tightness (type UREFLEX from RECTICEL) and its insulation (+- 5cm thick polyurethane foam of RECTICEL RSF 60 type).

The removal of the existing overlay will be performed manually or with a machine, at the contractor’s choice. If the genuine water tightness in bitumen is still present under the insulation, the contractor has to remove it in order to achieve a perfectly clean support free of any product that could hinder the good execution of the new insulation, its adherence or the stability of the insulating material.

As the cohesion of the concrete is rather small, it is possible that some parts get loose when removing the insulating material. The contractor will remove all loose elements and will evacuate them out of the area. They will be disposed of according to environmental standards, available upon request from the COR. A disposal certificate will be provided to the COR immediately upon disposal.

This item covers the complete and careful removal of all roofing materials installed on top of the structural concrete slab composed of several layers and types of bituminous material, the insulating material and all repair materials.

TP-2-02 PRECAUTIONS

During the removal of the water tightness and insulating material, the contractor shall take appropriate measures to ensure the water downspouts do not clog the existing piping.

TP-2-03 CLEANING

Once the insulation is removed, the substrate will be cleaned properly (sweeping and vacuum cleaning), in order to provide a good surface for the application of the sloped light weight concrete. All debris shall be evacuated in 10 m3 Containers.

SECTION 3

REPAIR AND PROTECT CONCRETE

TP-3-01 SUBSTRATE

At the locations where the water tightness and/or insulation has been removed, the contractor will have to make sure that the concrete support is in good condition. If necessary, local repairs will be carried out, removing loose concrete parts, filling up holes and cracks with rich mortar mixed with Compactuna or equal material. Before applying new mortar at critical locations, a curing compound (Compactuna or equal) will be applied. Then, an adherence coat will be applied on the previously cleaned and dry substrate.

TP-3-02 CONCRETE CEMENTED ROOF WALLS

Concrete cemented roof walls/sides with a spreading of 75cm will first have a high-pressure cleaning on their entire surface. Broken or cracked surfaces will be scoured, and the reinforcements will be treated to remove all rust.

Protection of the reinforcements will be achieved with a high performance overlay with emulsion resin and cement with two-component special fillers, type FCR 841 (rust inhibitive) or equal.

Repair of concrete will be done with epoxy mortar or single-component hydraulic mortar, microsilicates, fibers and copolymere styrene acrylates, type MONOMIX or equal.

Use a formwork if necessary, followed by profiling, floating and smoothing.

Once the repairs have been executed, cornices will be protected by anti-carbonation of concrete, in order to avoid, at short term, a future damage of surfaces that have remained sane.

Operating process

Application with a brush or roller of a two-component, aqueous, epoxy, adherence primer coating (PPPU primer):

6 to 10m2/liter according to absorption factor of the substrate.

After repair of possible non-stabilized cracks, supply and application in two layers of 0.275 liters/m2 of a self-cleaning elastic covering DECADEX EVERCLEAN or equal.

N.B.: This protective coating, shall be white for concrete cemented walls.

TP-3-03 WALL SURFACES

Other concrete surfaces (such as +- 20cm high strip under the wall cover of the high part of the roof) will be treated as explained in paragraph TP-2-02 (all treatments are applicable, except that the color of the protection paint shall be grey.

SECTION 4

NEW INSULATION

TP-4-01 SLOPED INSULATION SYSTEM (PIROTHERM OR EQUAL)

On the perfectly cleaned and repaired concrete slabs, a vapor barrier made of perforated SBS (Styrene-Butadiene- Styrene) membrane, type SOPRAVIP STICK C15 or equal, shall be installed. On this layer, a sloped insulating light weight concrete will be cast on site (insulating system PIROTHERM or equal – 10cm average with slopes of min 5cm/m). The system shall be able to combine the insulating PIROTHERM or equal mortar with PVR panels to ensure a strong insulation coat. This work will be executed by firm that is certified to work with the approved materials.

R value (measure of thermal resistance): minimum 1.7m2 K/w.

Compressive strength > 0.8 N/mm2.

SECTION 5

NEW SBS MEMBRANE

TP-5-01 PRODUCT

The watertight membrane will be composed of one layer of SOPRASTICK SI (or equal) and one layer of SOPRALENE TECHNO 4 AF CLFR (or equal).

Technical characteristics

First layer

The SBS membrane is made of an elastomeric bitumen membrane reinforced with a polyester layout grid fitted on its inner side with self-adhesive elastomeric strips.

Thickness: 2.5mm Width: 1m / Length: 10m / Weight: 3.9Kg/m2 Tensile strength: min. 750N/50mm.

Breaking elongation: 30%.

Nail tear: min. 250 N.

Top layer

The SBS membrane is made of an elastomeric bitumen membrane reinforced with a polyester layout grid, and fitted on its inner side with micro perforations to adhere to the underlayer. It is UV stabilized and is technically approved by UBAtc and ATG nr. 2025 (classification B roof (t1)).

Color: black with slate finish

Thickness: 4mm

Width: 1m

Length: 10m

Weight: 4.5kg/m2

Tensile strength: min. 800N/50mm

Breaking elongation: min 45%

Incipient tear strength: min 200N

Nail tear: min 200N

Adherence between layers: min 150N/50mm

Aging: official certificate of 20000 hours in Xenotest

Fire rate minimum A1 according to norm NBN S 21-203

TP-5-02 STORAGE AND PREPARATION OF SITE

SOPREMA or equal membranes does not require any particular storage condition. Membranes must be stored flat, on a clean and smooth support, away from bad weather conditions.

Glues, putties, etc. must be stored in a dry location, well ventilated, away from bad weather, and at a temperature between 5o and 25oC.

TP-5-03 EXECUTION

The dual-layer water tightness requires more care than the multi-layer water tightness. The contractor will use a highly specialized workmanship, in order to insure by a regular and demanding inspection that, at any time and any place, the work is executed according to the manufacturer’s specifications.

The work will be executed only by firms approved to work with the approved materials (SOPREMA or equal).

The SBS membrane will be laid without tension on a dry substrate free of unevenness. This membrane is welded with bitumen.

TP-5-04 OVERLAPPING OF THE EDGES

The longitudinal overlapping of the edges is at least 100mm. Crosswise, strips are laid edge to edge. They are covered with a separating strip on a width of 5cm, followed by the welding of a 200mm wide bridging strip.

Assembling the edges will be executed by hot welding. Welding will be performed by manual or automatic welding machines. The welding must be at least 30mm wide from the outer edge of the upper edge. The welding area will then be hard pressed if manual welding is used.

SECTION 6

UPSTANDS AND SPECIAL PROFILES

TP-6-01 UPSTANDS

Upstands are made of a 1.5mm thick homogeneous (non-reinforced) membrane used for the execution of details, at locations where the membrane must be distorted. The membrane will be of the type SOPREMA or equal. All finish details are shown on the drawing.

TP-6-02 SPECIAL PROFILES

Special profiles will be made of co-laminated steel sheet, type SOPREMA or equal. They are used for the execution of edges, fillets, etc.

The co-laminated steel sheet shall be made of a 0.63mm thick galvanized steel sheet on which a 0.5mm thick SBS sheet shall be co-laminated.

Characteristics thickness: 1.13 +- 0.06mm width: 1m length: 2m mass per unit area: 5.6kg/m2 color: grey

For the fillets, the contractor shall use a zinc apron flashing fixed in the masonry, and overlapping the SBS membrane.

SECTION 7

MAINTENANCE OF WATER DOWNSPOUTS

TP-7-01 PREPARATION

The straight parts crossing the concrete cemented roof walls as connection for rainwater shall be replaced with rigid PVC-P basis for a quick and aesthetic finish of the water downspouts, the inlet filters included. Connection membrane shall consist of PVC and inlet filter.

Characteristics formulation: rigid PVC color: light grey size: 110mm for 120mm downspouts (exact dimensions will be verified on site by the contractor)

TP-7-02 CONNECTIONS

The PVC pipe will be directly inserted in the 100/120mm welded zinc pipes.

TP-7-03 WATER DOWNSPOUTS (REINSTALLATION)

Water downspouts and appurtenances (funnels, elbows, etc) shall be made of zinc and welded. Color: natural zinc.

Characteristics color: natural zinc shape: rounded thickness: 0.7mm length: 2m sections: 113cm2 reference: t2r 1207 from MOPAC or equal

Water downspouts shall be supported every meter by an appropriate hinged collar (ref. ccr 12 from MOPAC or equal). Before reinstallation, manholes shall be cleaned and eventual repairs done.

TP-7-04 RAINWATER SHOE (REINSTALLATION)

The existing rainwater shoes are in good condition. They shall be reinstalled. Straight or bent shoe according to the location. The tail shall be made of hot galvanized steel (450gr of zinc/m2). Fastening by means of two hinged collars. The shoe is 1.00m high, 120mm. The shoe shall be inserted into the downspout and the sewage system by means of a flexible joint. Various repairs (concrete, masonry, etc.) at ground level, at the location where the shoe fits into the sewage pipe, will be carefully executed by the contractor.

Finish color: black Reference: DDR 12-10N from MOPAC or equal.

Headquarters USAG Benelux Memo 385-1

USA Garrison Benelux

Unit 21419

APO AE 09708-1419

1 July 2010

Safety

Safety & Occupational Health Involvement in New Construction, Demolition and Renovation Projects Contracts, and Service/

Supply Contracts in Belgium

For the Commander:

Official: VON JOSE ROBERTS

Deputy to the Garrison Commander

Summary. This publication prescribes applicable administrative procedures and responsibilities to ensure that all Safety & Occupational Heath aspects are evaluated during the planning, decision and execution process of contracts.

Applicability. This publication applies to contracts in the geographical area of responsibility of USAG

Benelux/Chièvres Garrison and USAG Brussels, in Belgium.

Supplementation. Organizations will not supplement this memorandum.

Records Management. Records created as a result of processes prescribed by this regulation must be identified, maintained, and disposed of according to AR 25-400-2. Record titles and descriptions are available on the Army Records Information Management System website at https://www.arims.army.mil.

Proponent. The proponent of this publication is the US Army Garrison Benelux, Installation Safety

Office (ISO), Unit 21419, APO AE 09708-1419, DSN 361-5561.

Suggested Improvement. Users may send suggestions to improve this pamphlet on a DA Form 2028, Recommended Changes to Publications and Blank Forms, to the US Army Garrison Benelux, DHR, Admin Services Division, Unit 21419, APO AE 09708-1419, DSN 361-5617.

Distribution. Distribution of the publication is made IAW USAG Benelux Reg 25-51; block D, plus 5 copies to ASD. This publication is available in electronic media https://portal.eur.army.mil/sites/imcom-e/usag/benelux/dhr/Lists/USAG%20Benelux%20Publications/AllItems.aspx

Annex A https://www.arims.army.mil/

USAG Benelux Memo 385-1 1 July 2010

1. References.

a. DoDI 6055.1, DoD Safety & Occupational Health (SOH) Program.

b. AR 385-10, The Army Safety Program.

c. EM (Engineer Manual) 385-1-1, Safety & Health Requirements.

d. Code of Federal Regulation (CFR) 48, Accident Prevention.

e. Code of Federal Regulation (CFR) 29 1926, Safety & Health for Construction.

f. Belgian Code of Well-Being at Work, 04 Aug 96.

g. Belgian Royal Decree, Temporary or Mobile Construction Sites, 25 Jan 01.

2. Purpose. To implement a Safety & Occupational Health involvement process for new construction, demolition, renovation project contracts/service and supply contracts for the United States Army Garrison

Benelux in Belgium.

3. Objectives. To evaluate all Safety & Occupational Heath aspects during the planning, decision and execution process of contracts.

4. Responsibilities.

a. The Requiring Activity (RA) will:

(1) Ensure that a Safety & Occupational Health review is incorporated into all contracts.

(2) The following statements must be included in the Specification/Performance Work Statement of all contracts:

(a) The project will respect the principles established by the law of 04 August 1996 related to the welfare of workers during the execution of their work and the Royal Decree of 25 January 2001 concerning temporary or mobile work sites.

(b) The Contractor will take all necessary measures to respect the safety principles established in the Belgian Law of 04 August 1996 and Belgian Royal Decree, 25 Jan 01.

(c) Upon notification of non-compliance with Safety & Occupational Health aspects, the

Contracting Officer Representative (COR) and the Contractor will initiate immediate measures of corrective action to restore Safety & Occupational Health within the perimeter of the work site.

(d) Upon oral notification of imminent life threatening danger by the COR and/or the Installation

Safety Officer (ISO), the Contractor will immediately stop activities until situation has been corrected.

The COR will immediately report any incident/accident to the ISO and the Contracting Office (CO).

USAG Benelux Memo 385-1, dtd 1 Ju110

1 July 2010 USAG Benelux Memo 385-1

(e) For Service and Supply Contracts, the Contractor will complete a USAG Benelux Form 385-

1A-E, USAG Benelux Safety Hazard Analysis, and forward it to the ISO no later than 7 working days prior to the anticipated start of the work.

(f) For military construction (MILCON) and Sustainment Renovation and Modernization (SRM) projects with only one contractor involved, the Contractor Safety Representative (CSR) will meet with the

ISO and COR to review and evaluate all Safety & Occupational Health aspects of the contract. This meeting is primarily to exchange information pertaining to potential hazards generated by the nature of the work to be performed. The meeting should take place no later than 1 week prior to the anticipated start of the work. The CSR will brief the ISO on equipment, machinery, work processes, hazardous products used during the accomplishment of the contract, and all safety measures taken or anticipated to minimize hazards, such as the use of personal protective equipments (PPE’S).

(g) For MILCON and SRM projects with more than one contractor/sub-contractor involved, the

COR will appoint a qualified on-site Safety and Health Pre-Execution Coordinator (SHPEC) in the pre-execution phase of the project. During that phase, the appointed SHPEC will generate a thorough Safety and Health Plan (SHP) that will include the appropriate safety and health precautions related to the project. The SHP will be provided to the contractor, COR, and ISO 7 days prior to the anticipated start of the work. The SHPEC wage and expenses will be paid by the contractor. A copy of the SHP will be retained at the USAG Benelux Directorate of Public Work, Hangar # 6, Chièvres Air Base, at

+3268275446.

(h) Prior to the execution phase of the project, the COR will appoint a qualified on-site Safety and Health Execution Coordinator (SHEC). The SHEC shall coordinate all safety and health preventive measures as per the SHP. The SHEC does not act as a substitute for the COR but rather plays the role of an advisor of the contractor. The SHEC will brief the ISO on equipment, machinery, work processes, hazardous products used during the accomplishment of the contract, and all safety measures taken or anticipated to minimize hazards, such as the use of personal protective equipments (PPE’S).

b. The Installation Safety Officer (ISO) will:

(1) Meet with the contractor and the COR 7 days prior to the anticipated start of the work to exchange information as far as hazards present on the installation (in the area where the contractor will operate).

(2) For MILCON and SRM projects with more than one contractor/sub-contractor, where an on-site

SHEC is mandated, meet and address same issues as in Para b.1 above.

(3) During the accomplishment of the contracts, periodically meet with the COR and/or the qualified SHEC to address any upcoming safety issue.

(4) Notify the COR and the Contracting Office (CO) of any non compliance with the Safety &

Occupational Health aspects.

USAG Benelux Memo 385-1 1 July 2010

(5) In case of imminent life threatening danger, issue an order stopping all or part of the work until satisfactory corrective action has been taken with immediate notification to the COR and the CO.

(6) Determine additional needs for environment, industrial hygiene, occupational health, and fire prevention review of the project, if it was not coordinated in the early phase of the project.

c. The Contracting Officer Representative (COR) will:

(1) Attend all of the above described meetings (see para. a & b above).

(2) For contracts without an SHEC, follow-up on all aspects of safety & occupational health. Report any safety deficiencies and incident/accident to the ISO and the CO.

(3) Notify the CO and the contractor orally, with a written confirmation, of any non compliance with the safety & occupational health aspects. Additionally, the COR will request immediate initiation of corrective action.

(4) In case of imminent life threatening danger, will issue an order stopping all or part of the work until satisfactory corrective action has been taken with immediate notification to the ISO.

Appendix A - USAG Form 385-1A-E, USAG Benelux Safety Hazard Analysis

1 July 2010 USAG Benelux Memo 385-1

Appendix A

USAG Benelux Form 385-1A-E, USAG Benelux Safety Hazard Analysis (this form can be downloaded from our USAG Benelux Portal -https://portal.eur.army.mil/sites/imcom-e/usag/benelux/dhr/Lists/USAG%20Benelux%20Forms/AllItems.aspx)

USAG Benelux Memo 385-1 1 July 2010

1 July 2010 USAG Benelux Memo 385-1

USAG Benelux Memo 385-1 1 July 2010

File details come from the government source that posted it.