Questions and Answers for W912PA18Q0032, Roof Repair Bldg 20019 - Chievres Air Base
| 1 |
| When the contract will be awarded, when to start the works and how many days are needed to complete the works? |
| The contract award is anticipated by 30 September 2018. A notice to proceed shall be issued within 60 days after the effective date of contract. The project completion date is 30 days after notice to proceed. (Days = Calendar Days) |
| 2 |
| Is the project completion based upon calendar or working days? |
| Calendar days. |
| 3 |
| Does the existing vapor barrier stay? |
| No, new one foreseen under TP-4-01 |
| 4 |
| Should concrete gutter be repaired? |
| Yes, to be done as TP-3-03 |
| 5 |
| Should any repairs been done on brick walls? |
| No, nothing to be done on brick walls |