0011038590
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1) Revise "Instructions to Offerors" under section L of this requirement.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 05-Sep-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912PA-17-R-0006
X 9B. DATED (SEE ITEM 11)
24-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
05-Sep-2017
CODE
US MILITARY FORCE - RCO BENELUX
LINDSAY K. CARRINGTON
32-02-7179617 (FAX 9610)
LEUVENSESTEENWEG 13
1932 SINT-STEVENS-WOLUWE
BELGIUM
W912PA 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912PA-17-R-0006
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION I - CONTRACT CLAUSES
The following have been modified:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 120 days. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
INSTRUCTIONS TO OFFERORS
PROPOSAL PREPARATION
A. General Instructions: This section provides general guidance for preparing proposals, as well as specific instructions on the format and content of the proposal. Throughout this section, the term “Offeror” means the prime contractor submitting the proposal. The Offeror’s proposal must include all data and information requested and must be submitted in accordance with these instructions. Any Offeror who submits an incomplete package may be considered unacceptable. The offer shall be compliant with the requirements as stated in the Request for Proposal (RFP). A proposal that is sufficiently documented to support cost/price and technical requirements in a complete, orderly, and specific detailed manner will enable the Government to perform a thorough and fair evaluation. Non-compliance with the instructions and RFP may result in an unfavorable proposal evaluation and may be grounds to eliminate the proposal from consideration for contract award.
B. Type of Acquisition: Selection of the best value Offeror will be made using Lowest Priced Technically Acceptable (LPTA) procedures with the technical factors evaluated on an Acceptable/unacceptable basis.
C. Discrepancies and Ambiguities: If an Offeror believes the requirements in these instructions contain an error, omission, ambiguities, or are otherwise unsound, the Offeror shall immediately notify the KO in writing with supporting rationale.
D. Mistakes: Mistakes in Offeror’s proposal shall be handled in accordance with FAR 14.407- 4 as referenced in FAR 15.508.
E. Postponement of Proposal Closing Date: If a determination is made to postpone a proposal closing date, an announcement of the determination shall be posted to the Electronic Posting System (EPS) and, if practicable, before issuance of a formal RFP amendment otherwise communicated to prospective Offerors.
F. Post-Award/Pre-Performance Conference: A post-award/pre-performance conference will be scheduled by the Contracting Officer (CO) and held prior to the commencement of any work at that installation under the awarded contract. The Offeror or their duly authorized representative is required to attend the post-award/pre-performance conference.
G. Discussions: When discussions or requests for revised offers are not conducted or requested by the Government, the prices identified in Section B shall be valid through the proposal acceptance period (SF 1442 Block 13 D).
H. Contract Document: Sections K, L and M apply to the solicitation phase only; therefore, they will not be a physical part of the resulting contract.
I. Points of Contact (POC): The POC for this acquisition is Michael Brown, Contracting
Officer (KO), and Lindsay Carrington, Contracting Specialist (KS). Written requests for clarification may be sent to the KO/KS e-mail. Address any questions or concerns to them using the following contact information:
Michael Brown Lindsay Carrington (michael.c.brown105.civ@mail. mil) (lindsay.k.carrington.civ@mail.mil)
409th Contracting Support Brigade 409th Contracting Support Brigade Unit 28100 - Box 15 APO, AE 09714 Unit 28100 - Box 15 APO, AE 09714 +32-(0)2-717-9653 +32-(0)2-717-9617
Questions and comments pertaining to this RFP shall be submitted in writing by e-mail to the individuals listed above not later than close of business on the tenth (10th) day prior to the closing date of this RFP, as amended. The government reserves the right to disregard questions submitted after the proposed deadline.
L-1 PROPOSAL PREPARATION INSTRUCTIONS
The proposal package must be completed and returned to the Contracting Office identified in Block 7 of the SF 1442. Electronic submissions are preferred and shall be sent to both of the following two email addresses:
michael.c.brown105.civ@mail.mil usarmy.rheinland-pfalz.409-contr-sptbde.mbx.409csb-bru-request@mail.mil.
It is the responsibility of the contractor to confirm that proposals have been received by the Government within the stated deadlines identified within the proposal.
A. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Proposals must be complete, self-sufficient, and respond directly to the requirements of this solicitation. Alternate proposals will not be accepted. The response shall consist of three (3) separate volumes; Volume I – Executed Contract Documentation and Price Proposal, Volume II - Technical Proposal, Volume III – Past Performance.
B. The Contracting Officer has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the Contracting Officer will review this determination and if, in the Contracting Officer's opinion, adequate price competition exists no additional cost information will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the Contracting Officer determines that adequate price competition no longer exists; Offerors may be required to submit information to the extent necessary for the Contracting Officer to determine the reasonableness of the price.
C. Format for proposal Volumes I and II shall be as follows:
1. Company Name and solicitation number shall be included in the header of each page.
Each volume will be labeled with the following format: W912PA-17-R-0006, COMPANY NAME, Volume I Executed Contract Documentation and Price Proposal;
Volume II Technical Proposal; or Volume III Past Performance. See following Table for specific number of copies and pages, etc.
TITLE # OF COPIES MAXIMUM # OF PAGES
Volume I Executed Contract Documentation and Price Proposal
Original No page limitation
Volume II Technical Proposal
Original 10 pages
Volume III Past Performance
Original No more than 2 pages per contract listed
2. Electronic copies shall be searchable documents compatible with Adobe Reader 9 and/or
Microsoft 2007.
3. Documents submitted in response to this solicitation must be consistent with the following:
a. Requirements of the solicitation, and government standards and regulations pertaining to the specification.
b. Evaluation Factors for Award in Section M of this solicitation.
4. The estimated magnitude of construction for this project is between $250,000 and $500,000.
D. Specific Instructions, SUBMIT THE FOLLOWING:
VOLUME I – EXECUTED CONTRACT DOCUMENTATION AND PRICE PROPOSAL.
1. Chapter 1 – SF 1442. Complete applicable blanks. In doing so, the Offeror accedes to the contract terms and conditions as written in the RFP Sections A through J. These sections constitute the model contract.
2. Chapter 2 – Section B. Insert the proposed price to provide a complete and usable end product in accordance with the terms and conditions stated in this solicitation. Offerors who do not comply with this requirement shall be considered unacceptable and not eligible for award.
3. Chapter 3 – Section C through J. Complete applicable blanks, the Offeror shall submit only those pages that require a fill-in.
4. Chapter 4 – Section K. Complete the representations, certifications, and acknowledgments. Section K shall be returned in its entirety.
5. Acknowledge all amendments issued to the solicitation.
VOLUME II -TECHNICAL PROPOSAL
Offerors must meet a standard in the Technical Factor in order for their technical proposal to be determined “technically acceptable.” The standards are defined in Section M for the factor.
1. Technical: The offeror shall provide a proposed project work schedule which addresses, at a minimum, tasks and subtasks that are essential for the accomplishment of this project.
VOLUME III –PAST PERFORMANCE
Offerors must meet a standard in the Past Performance Factor in order for their proposal to be determined “acceptable.” The standards are defined in Section M for the factor.
2. Past Performance: The Offeror shall provide past performance information that is acceptable to the subject solicitation.
(End of Summary of Changes)