TECHNICAL EXHIBIT 1

DELIVERABLES SCHEDULE

Deliverable Frequency # of Copies Medium/Format Submit To The contractor will submit at least 3 proposals of execution-coordinator

Within 15 days after contract award

1 Copy Paper COR

Contractor must provide technical data of each materials, appliances and equipment

15 days prior to ordering materials by contractor

3 Copy Paper/Email COR

The contractor shall submit the calculation of the cables’ sections

15 days prior to ordering materials by contractor

3 Copy Paper/Email COR

The contractor shall submit the detailed calculation of the photometric performances of each light fixtures types

15 days prior to ordering materials by contractor

3 Copy Paper/Email COR

The contractor shall submit the configuration of the lighting scenario

15 days prior to ordering materials by contractor

3 Copy Paper/Email COR DPW Energy Manager

Prior to starting any work, the contractor shall provide the contracting officer, for approval, a detailed schedule showing the successive phases of the work

3 weeks prior to start work

3 Copy Paper COR

The contractor shall submit a written Digging Permit Request

15 days before to start any earthwork

1 Copy Email COR

The contractor shall submit an as-built folder

Before submitting the final invoice

3 copy Paper/CD COR

The contractor shall provide training to operators

After starting of the installation

5 copy Paper/CD System operators