About this file

This file is Amendment 0001 for a federal solicitation (W912P825B0036) issued by the U.S. Army Corps of Engineers for a flood control project in East Baton Rouge Parish, Louisiana. The amendment provides detailed responses to 57 bidder questions covering technical specifications, bid item clarifications, quantities, payment terms, and construction requirements for the Comite River Diversion Project and Bayou Baton Rouge Rock Chute.

Key details include maintaining the original bid submission deadline of April 14, 2025 at 10:00 AM, reopening the opportunity for follow-up questions until April 4, 2025 at 2:00 PM, and revising several bid schedule line items and quantities. The project involves major civil infrastructure work including channel excavation, bridge construction, embankment, riprap installation, pump station construction, and related site preparation, with a total base work and optional work scope valued in the millions of dollars. The amendment addresses technical clarifications on items such as pile load testing, dewatering requirements, concrete work, electrical installations, and environmental testing responsibilities.

View the file

Other files

File Type Posted
Bid Abstract_W912P825B0036_SIGNED.pdf PDF
Amendment 0005..pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The subject solicitation for Flood Control, Amite River Tributaries, Louisiana, Comite River Basin, Comite River Diversion Project, Bayou Baton Rouge Rock Chute, East Baton Rouge Parish, Louisiana (ED 20-001) is hereby amended as follows:

1.) Provides Government responses to bidders questions received during the established Q&A period on the attached continuation pages.

2) Re-open the opportunity for potential bidders to submit questions related to the contents within this amendment only. The deadline for the submission of follow -up questions is 2:00pm local time, Friday, April 4, 2025.

3) The bid submission deadline of 14 April 2025, 10:00AM, local time, as w ell as the virtual bid opening date and time of 14 April 2025, 11:00AM, local time, remains unchanged.

4) Please be advised, the correct drop down tab in SAM.gov for the subject requirement should currently reflect as Solicitation, instead of Pre- Solicitation.

***PLEASE ACKNOWLEDGE THIS AMENDMENT AND SUBMIT WITH YOUR BID***

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 48

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P825B0036

X 9B. DATED (SEE ITEM 11)

14-Mar-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Apr-2025

CODE

CONTRACTING DIV- CHIEF

7400 LEAKE AVENUE, ROOM 172

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - SF 30 CONTINUATION

The following have been added by full text:

Amendment 0001 - Q&A

Solicitation No. W912P8-25-B-0036 Flood Control, Amite River Tributaries, Louisiana, Comite River Basin, Comite River Diversion Project, Bayou Baton Rouge Rock Chute East Baton Rouge Parish, Louisiana March 6, 2025

Contractor Questions and Government Responses

1. I was reviewing the file BAYOU BATON ROUGE BINDER 30-06-2025_Updated w 25-B- 0036_Part1, and I noticed that in the Index of Drawings on Sheet G-003, under the Right of Way section, Sheet R-004A OVERALL RIGHT OF WAY MAP is listed.

However, I was unable to locate this sheet in any of the other binder files.

Additionally, I observed that Sheet R-004A OVERALL RIGHT OF WAY MAP is not listed in Sheet G-003 within the Solicitation PDF. Could you please confirm which reference is correct?

USACE Response: New Plan Sheet R-004a will be included within the forthcoming amendment.

2. Will LADOTD surface resistivity requirements and testing be required for the Class A1 mix?

USACE Response: Yes. This requirement is stated within Specification Section 03 31

00.00 12, Paragraph 2.1.1, LSSRB 805, LSSRB 901, and Plan Sheet S-102.

3. Can USACE provide a list what is included in each of the “JOB” items?

USACE Response: Lump sum bid item quantities will be provided within the forthcoming amendment.

4. Is onsite burning allowed for trees and shrubs called to be cleared?

USACE Response: Yes. Burning is allowed per Specification Section 01100, Paragraph 10(b) and Specification Section 31 11 00.00 12, Paragraph 3.4.2, “BURNING”.

5. Has an asbestos inspection been done on the abandoned homes/building called to be demolished?

USACE Response: Pre-Demolition testing will be the Contractor’s responsibility as part of this contract. Pre-demolition testing requirements are included within Specification Section 02 41 00, Paragraphs 3.1.1 and 3.1.2.

6. I hope this message finds you well. I am reviewing the solicitation for the Comite

River Diversion Project, Bayou Baton Rouge Rock Chute Flood Control, Amite River and Tributaries, Louisiana Comite River Basin, and I noticed that the insurance requirements were not included in the documents. Could you please confirm the specific insurance requirements for this project? This information will help us ensure compliance and prepare our bid accordingly.

Upon award, the Contractor will be requested to provide any required Certificates of Insurance as part of the submittal process.

7. Please provide bidders with estimated quantities on items of work for which bids are being solicited on a job basis.

USACE Response: Lump sum bid item quantities will be provided within the forthcoming amendment.

8. In Specification Section 31 23 00.00 12, measurement of excavation will be based on the volume of material between pre-excavation surveys (prior to clearing and grubbing) and the theoretical excavation lines and grades shown on the drawings. Is the excavation line/grade referencing to the grade below riprap and bedding?

USACE Response: Yes.

9. In Specification Section 31 24 00.00 12, Paragraph 1.4.2 “Disposal Embankment”, the first sentence in part states “No separate payment will be made for depositing materials in the disposal, preload area”. What preload area is this referring to?

USACE Response: The reference to the term “preload areas” will be deleted from this paragraph.

Price and payment for embankment at the two preloads shall be included in CLIN 0040. The revised paragraph will be included within the forthcoming amendment.

10. In Specification Section 31 24 00.00 12, Paragraph 1.4.2 “Disposal Embankment”, the first sentence in states “No separate payment will be made for depositing materials in the disposal, preload area, filling the abandoned Bayou Baton Rouge, or filling low-lying areas. While in this same Section, Paragraph 3.3 “Disposal Area Embankment” clearly defines the embankment placement criteria, what is the embankment placement criteria for filling the abandoned Bayou Baton Rouge or other low-lying areas?

USACE Response: The embankment placement criteria in paragraph 3.3 shall apply to the filling of the abandoned Bayou Baton Rouge and other low-laying areas.

11. The construction drawings do not clearly define areas of fill that will be measured for payment as embankment and those areas that will not. Please define these areas on the drawings by cross-hatching, shading or otherwise so the Contractors can accurately price the work required.

USACE Response: Additional notes and hatching/shading was added to Plan Sheet C-025 for the bidder’s awareness in preparing bids. This plan sheet was included within the original solicitation/initial posting of W912P8-25-B-0036.

12. Please confirm the TRS outlined in the drawings and specifications for the pump station installation is a “means and methods” of construction and not a “requirement”. If the Contractor provides an alternate installation method, such as caisson, designed and sealed by a registered professional engineer, that it would be acceptable?

USACE Response: Yes. The Temporary Retaining Structure (TRS) is “CONCEPTUAL ONLY”.

The final design & means and methods will be the responsibility of the Contractor. The design shall be submitted to the Government for review and approval, prior to commencement of work in the field.

13. When the Contractor backfills the Temporary Bayou Baton Rouge by-pass, will the Contractor be required to remove the R-25 Riprap prior to backfilling?

USACE Response: The Riprap, R-25, shall be left in place and backfill placed ontop during fill operations. The portion of Riprap, R-25, within the limits of the Comite River Diversion Channel excavation, shall be removed and stockpiled onsite and reused as directed by the Contracting Officer.

14. How much settlement in terms of feet does the Corps anticipate at these locations Carney Road

Preload areas?

USACE Response: The anticipated preload settlement is 1-ft.

15. The scale shown on Sheet C-301 is in error. Please correct.

USACE Response: Plan Sheet C-301 will be revised and included within the forthcoming

16. What purpose will the new pump station serve at the completion of the project?

USACE Response: The environmental pump station will divert water into Bayou Baton Rouge south of the Comite Diversion.

17. On Plan Sheet C-005, there is a requirement of a R-90 riprap blanket to be placed at pile scour holes at the existing Carney Road bridge crossing. Is this riprap blanket only required at the north side row of pilings or all the pilings. Also, is this R-90 riprap paid for under CLIN 0063?

USACE Response: Riprap, R-90 is to be placed at a thickness of 1.5 feet in a 2-foot perimeter at each bent under the existing Carney Road bridge as depicted in Detail 6 on Plan Sheet C-006.

The R-90 Riprap is to be paid under CLIN 0066.

18. Do the guide levees continue through Disposal Areas 1, 2, and 3 as shown on Plan Sheet C- 023A, “Detail – Guide Levee at Disposal Area 1”?

USACE Response: The guide levees continue through the disposal areas as shown on C-023A.

Note, the guide levees in the disposal areas have a flatter canal side slope due to the disposal stockpile.

19. What are the anticipated completion dates for the upstream and downstream Comite projects which would allow this contract to remove the “plugs” on each end to tie the channel in?

USACE Response: Plug removal is included as part of the last phase of work required for this project. Both upstream and downstream projects are ongoing. USACE does not have a timeline for completion of those projects.

See Phase 5 on Plan Sheet C-026E.

20. Section 01 50 00, Paragraph 3.2, references temporary aggregate surfacing. Is this temporary surfacing paid for under CLIN 0050?

21. Can the USACE provide the most recent bridge inspection report for existing Carney Road bridge?

USACE Response: USACE does not have this information readily available to provide to the bidders. The existing bridge is posted by LADOTD.

22. Is the initial design of the Unwatering System required to be performed by a Registered

Professional Engineer?

USACE Response: Yes. The design of the Unwatering system shall be performed by a Registered Professional Engineer. This will be the responsibility of the Contractor.

23. Will the Owner (City of Baton Rouge/Parish of East Baton Rouge) furnish a generator per

Section 01640?

USACE Response: There is no generator included in site design, as shown in the site plan on sheet E-003 and the single line diagram on sheet E-004. With no generator and only one incoming power source, there is no automatic transfer switch included in the site design.

24. Section 31 62 14.00 12 “Pile Load Tests” does not provide enough detailed information on the pile load testing, including testing parameters or sample test schedule. Please provide the needed information to the bidders.

USACE Response: Service loads are provided on the plans. The procedures are provided in Paragraph 3.2.6. of specification section 31 62 14.00 12.

25. What are the handling requirements for the prestress girders?

USACE Response: The prestressed concrete girders shall be handled in accordance with Spec Section 03 45 33.00 10, Paragraph 1.7 Delivery, Storage, and Handling and “PRECAST PRESTRESSED GIRDER SPAN ERECTION NOTES” on Plan Sheet S-101.”

26. Are there any environmental restrictions on pile driving equipment?

USACE Response: There are no environmental restrictions on pile driving equipment.

27. Are there any ground bearing restrictions for equipment, i.e. cranes?

USACE Response: No. The contractor shall evaluate ground bearing pressures as part of their means and methods for construction.

28. Will stay in place pre-cast deck panels be acceptable to utilize as form work for the bridge deck?

USACE Response: The design, engineering, and construction of the formwork shall be in accordance with Specification Section 03 11 14.00 12, “FORMWORK FOR CONCRETE”. The formwork shall be submitted for review and approval by USACE prior to the start of bridge construction.

29. Will stay in place metal forms be acceptable to utilize as form work for the bridge deck?

USACE Response: (SEE ABOVE RESPONSE TO QUESTIONS 28)

30. For the abandoned oil well to be removed, please provide the bidders with the name of the owner and operator of the well and the serial number of the well.

USACE Response: This data is not available and will not be included within the forthcoming

31. Per specification section 31 62 14.00 12, “all support piles, and test piles shall be pulled”. Is it acceptable for contractor to cut concrete test piles below finished grade?

USACE Response: Yes, cutting off test and support piles below grade will be allowed as part of construction.

32. Is a CAD file available our estimating purposes?

USACE Response: CADD files will not be available until after award of this project.

33. Has lead inspection been done the existing homes and buildings?

USACE Response: Pre-Demolition testing will be the Contractor’s responsibility as part of this contract. Pre-demolition testing requirements are included within Specification Section 02 41 00, Paragraphs 3.1.1 and 3.1.2.

34. Can you use Barnett Rd for access to Carney Rd?

USACE Response: Access from Barnett Road (North of the Diversion Channel) can be used to access Carney Road. Access from Barnett Road (South of the Diversion Channel) will not be allowed due to the adjacent Comite Reach 1 construction operations.

35. Who is responsible for removing the remaining utilities that are within the job?

USACE Response: Please refer to the disposition table shown on Plan Sheet R-017, R-018, and the 01100 for responsible party for removal.

36. What is to be done with the rocks placed in the temporary bypass when the bypass is to be removed.

excavation, shall be removed and stockpiled onsite and reused as directed by the Contracting

37. Where is the TRS intended to be used?

USACE Response: The TRS intended use is for construction of the Pump Station Wet Well.

38. Do you have a specific procedure for how the Abandoned Oil well is to be removed?

USACE Response: The Contractor will be required to cut and reseal in accordance with the guidelines and regulations as required by the Louisiana Department of Natural Resources (LA- DNR). The point of contact for LA-DNR are included within Specification Section 01100.

39. Please provide the Lump Sum quantities.

USACE Response: Lump sum bid item quantities will be provided within the forthcoming

40. The pile load test items are referenced per DOTD spec, but the scope states the contractor is to include loading of test piles, reloading of test piles, redriving of test piles if required, dynamic monitoring and dynamic analysis all in accordance with LSSRB 804. All of the above are separate bid items for DOTD and a couple of them are rarely used. (reloading of test piles and redriving of test piles). Please confirm that you want the contractor to include the cost of all these items in only one bid item. If not, will you please add pay items for these items of work?

USACE Response: Include costs required per loading procedures described in 3.2.6 of the Pile Load Test specification.

41. What is the difference between items 0012 Bridge Concrete and 0016 Carney Road Bridge?

Spec 10 00 12.00 12 states all bridge concrete – bents, diaphragms, decks rails as well as all structural metalwork and pavement markings shall be paid for in CLIN 0016 Carney Road bridge. What are we supposed to include in CLIN 0012 Bridge Concrete

USACE Response: All concrete items for the bridge shall be included in the Lump Sum cost for CLIN 0012, “Bridge Concrete”. All other non-concrete items, not otherwise included in a separate pay item shall be included in CLIN 0016, “Carney Road Bridge”.

42. Throughout the bid specifications there is reference to a specification “SSOMS”. We are not familiar with this spec and could not find anything online on it. Please provide this specification.

USACE Response: The term “SSOMS” denotes BATON ROUGE SANITARY SEWER

OVERFLOW (SSO) CONTROL AND WASTEWATER FACILITIES PROGRAM MASTER

SPECIFICATIONS (SSOMS). It is referenced in Spec Section 35 45 02.00 10, Paragraph 1.3.

The document is attached to the end of the advertised specifications.

43. Does the R25 rip rap get removed before backfilling the Bayou Baton Rouge temporary by pass channel? If so, does it become property of the contractor to dispose of or will a disposal site be designated by the government?

excavation, shall be removed and stockpiled onsite and reused as directed by the Contracting

44. What is the thickness of the asphalt pavement on the existing Carney Road that gets removed?

USACE Response: The existing asphalt pavement thickness shall be assumed to be 4” deep for removal.

45. Will the R-3500 Class Rip Rap section in BBR RC that gets grouted be measured and paid for as

Riprap R-3500? Or is it incidental to the Grouted Rip rap item?

USACE Response: All grouted riprap will be paid for under CLIN 0040 regardless of gradation.

Non-grouted riprap will be paid for under CLIN 0065 thru 0069 for the appropriate gradation as specified on the plans.

46. Plan sheet C-060A is a DOTD Standard Drawing which states “for informational purposes only”. It shows rumble strips, but there is nothing in the specifications mentioning rumble strips. Will Rumble Strips be required on this project? If so, where will they be place, centerline or on the shoulders?

USACE Response: Rumple strips are not required as part of this project.

47. Please provide stationing and cross section data for each guide levee so we can verify quantity required.

USACE Response: Stationing for the guide levees has been added to Plan Sheet C-023A. This drawing will be included within the forthcoming amendment.

48. It is assumed the excavated material will be used as embankment for Guide Levees, Proposed

Banks and Abandoned Channels, Carney Road Preload, Relocation of Carney Road and Pump Station Access and Berm Road (if it meets DOTD spec for roadway embankment). The remainder of the excavation shall be placed in the Disposal Areas 1 through 5. Any excess material beyond the limits of the 5 disposal site will need to be hauled off in accordance with OW-1. Is this correct?

49. There seems to be a conflict between the payment for the filling of the Abandoned Bayou Baton Rouge, the preload embankment and filling low lying areas as stated in paragraph 31 24 00.00 12 1.4.1 and 1.4.2. Please explain what is included in CLIN 0038 Embankment – Proposed Banks and Abandoned Channels and CLIN 0039 Embankment – Carney Road Preload. 1.4.1 states this material shall be paid by the CY and 1.4.2 states no separate payment shall be made for these items.

USACE Response: CLIN 0040 “Embankment – Carney Road Preload” is for the two preloads at the Carney Road Bridge as shown on Plan Sheet C-301. CLIN 0039 “Embankment – Proposed Banks and Abandoned Channels” is for filling in low areas and abandoned channels.

50. Below is a question from a prospective well demo/capper. Realistically, there’s NOT going to be any surface visual that will indicate so basically we only have the 1978 Survey from Audrey Burke (found inside the attached well info). What happens “IF” we survey the site, dig down and CAN’T find the old stub?

USACE Response: The Contracting Officer shall be notified, and the Contractor shall follow the requirements for submitting a Request for Information for review and approval by USACE.

51. Item 0041 includes an estimated quantity of 160 LF. Sheet S-102 shows a quantity of 120 LF for this item. Which is correct?

USACE Response: The quantity will be revised to 120 LF. A revised bid schedule will be included within the forthcoming amendment.

W912P825B0036

52. Item 0042 includes an estimated quantity of 1,046 LF. Sheet S-102 shows a quantity of 1,680 LF for this item. Which is correct?

USACE Response: The quantity will be revised to 1,680 LF. A revised bid schedule will be included within the forthcoming amendment.

53. Item 0043 includes an estimated quantity of 1,147 LF. Sheet S-102 shows a quantity of 1,040 LF for this item. Which is correct?

USACE Response: The quantity will be revised to 1,040 LF. A revised bid schedule will be included within the forthcoming amendment.

54. Is item 0032 only excavation and backfill and Items 0017 only cast in place concrete?

55. Sheet E-006 shows a fabricated equipment rack and cable rack. Please provide more details for this material.

USACE Response: The material required for the equipment and cable rack is stated on Plan Sheet E-006 Keyed Notes 25.

The final design, layout, and member sizing shall be the responsibility of the Contractor.

All details shall be submitted as part of the submittal procedures for review and approval by USACE prior to ordering materials and installation in the field.

56. There are large differences between actual quantities and bid quantities in all of the pile bid items nos. 41, 42, and 43.

USACE Response: The quantity for CLIN 0041, 0042, and 0043 will be revised to match the totals shown on Plans Sheet S-102. A revised bid schedule will be included within the forthcoming amendment.

57. I believe there is an overlap in another 2 bid items. They are #0012 (Bridge Concrete) and #0016 (Carney Road Bridge).

USACE Response: All concrete items for the bridge shall be included in the Lump Sum cost for CLIN 0012, “Bridge Concrete”. All other non-concrete items, not otherwise included in a separate pay item shall be included in CLIN 0016, “Carney Road Bridge”.

(End of Summary of Changes)

SECTION 00010

Pages 00010-3, 4, 5, 6, and 7. Delete these pages in their entirety and replace with the attached revised pages 00010-3, 4, 5, 6, and 7, therefore.

SECTION 01100

Page 97/1037. Delete this page in its entirety and replace with the attached revised Drawings Index G-003, therefore.

SECTION 31 23 00.00 12

1. Page 3, paragraph 1.2.7. Delete this paragraph in its entirety and substitute “1.2.7 Reserved”, therefore.

2. Page 4, paragraph 1.3.3. Delete this paragraph in its entirety and replace with following revised paragraph, therefore:

“1.3.3 Excavation for Comite River Diversion Channel

Payment for excavation for Comite River Diversion Channel will be made at the contract unit price per cubic yard for "Excavation for Comite River Diversion Channel". Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment for excavation required for Comite River Diversion Channel; including removal and disposal of excess spoil material as specified herein and as shown on the drawings. Payment will be limited to the lines and grades shown on the drawings ”

3. Page 4, paragraph 1.3.7. Delete this paragraph in its entirety and substitute “1.3.7 Reserved”, therefore.

SECTION 31 23 19.00 12

1. Page 2, paragraph 1.2. Delete this paragraph in its entirety and replace with the following revised paragraph, therefore:

“1.2 MEASUREMENT AND PAYMENT

No measurement will be made for construction dewatering. Payment for dewatering will be made at the contract job price for "Construction Dewatering – OW", if Optional Work is exercised. Price and payment shall constitute full compensation for furnishing all plant, labor, material, and equipment; designing, furnishing, installing, maintaining, operating, flooding, rewatering, and removing the dewatering facilities; maintaining the dewatered area; and all work incidental thereto including construction of dikes, sumps, installation of wellpoints, jet eductors, wells, pumps, piezometers, removal of wellpoints, jet eductors, wells, and piezometers, plugging holes, maintaining protection dikes and closure dams, protection of slopes and all other work which may be necessary to accomplish the specified dewatering results and which is not specified to be paid for separately. Fifty percent of the job price will be paid when installation of the dewatering system has been completed, tested, evaluated, and the piezometric level of the ground water has been lowered to the limits and elevations as specified. Forty percent of the lump-sum price will be prorated on the basis of the estimated number of months that dewatering system will be required and will be paid monthly. The remaining 10 percent of the lump-sum price will be paid when the dewatering system has been removed as required herein and cleanup in connection therewith has been completed.”

2. Page 5, paragraph 1.6. After subparagraph item (12), add the follow new subparagraph item, therefore:

(13) For cost estimating purposes, the Contractor shall assume the minimum requirements regarding the dewatering system:

Minimum Dewatering Requirements:

Vacuum wellpoint system 1.5-inch PVC Wellpoint and Riser Pipes 1.5-inch Header Pipes – 50 total 25-ft Pipe Depth 7-ft Spacing between wellpoints Primary (Operating Pump) – Minimum 50 HP, 460 V, 3 Ø OR 4 gallons of diesel/hour per operating pump. (Electric or Diesel) Standby Pump- Minimum 50 HP, 460 V, 3 Ø OR 4 gallons of diesel/hour per operating pump.

Operation (Electric or Diesel) Operation Time: 1 Month, 4 hrs per day, M-F”

SECTION 31 24 00.00 12

1. Page 4, paragraph 1.2. Add the below new specification reference in its entirety, therefore:

“LOUISIANA STANDARD SPECIFICATIONS FOR ROADS AND BRIDGES (2016

Edition), LOUISIANA DEPARTMENT OF TRANSPORTATION AND

DEVELOPMENT

(LADOTD)

LSSRB 203 Excavation and Embankment”

2. Page 5, paragraph 1.4.2. Delete this paragraph in its entirety and substitute the following revised paragraph, therefore:

“1.4.2 Disposal Embankment

No separate payment will be made for depositing materials in the disposal area, filling the abandoned Bayou Baton Rouge, or filling low lying areas. Payment shall be included in the contract prices for which the work is incidental thereto.”

3. Page 12, paragraph 2.1.2. Delete this paragraph in its entirety and substitute the following revised paragraph, therefore:

“2.1.2 Embankment Material at Carney Road Bridge Header/Abutments

Headers are that portion of the embankment within 500 feet of a bridge end. In accordance with LSSRB Section 203, compact headers to 98 percent of maximum dry density as determined in accordance with DOTD TR 415 or TR 418 and percent in-place density in accordance with DOTD TR 403. The moisture content at the time of compaction, tested in accordance with DOTD TR 403, shall be within a range of plus 2 to minus 2 percentage points of optimum moisture content established in accordance with DOTD TR 415 or TR 418. Construct headers for their full height with usable soils. In accordance with LSSRB Section 203, usable soils shall have:

Minimum Plasticity Index (PI) of 11 Maximum Organic Content of 5% percent Maximum Plasticity Index (PI) of 25 Maximum Silt Content of 65% percent

No Lime treatment shall be added to the soil in order to meet the PI requirements as listed above.”

SECTION 35 31 19.04 12

1. Page 2, paragraph 1.2.2. Replace this paragraph in its entirety and substitute the following

“1.2.2 Removal and Stockpile of Riprap, R-25

No measurement will be made for the excavation, removal, and stockpile of the Riprap, R-25 placed as part of the temporary bypass channel.”

2. Page 3, paragraph 1.3.3. Replace this paragraph in its entirety and substitute the following

“1.3.3 Payment for Removal and Stockpile of Riprap, R-25

No measurement will be made for the excavation, removal, and stockpile of the Riprap, R-25 placed as part of the temporary bypass channel. Payment will be made at the contract job price for "Removal and Stockpile, Riprap, R-25". Price and payment shall constitute full compensation for furnishing all plant, labor and materials for removal, and stockpile of Riprap R-25 onsite; including excavation; and other incidental work; as specified herein and as shown on the drawings.”

DRAWINGS

1. SHEET IDENTIFICATION Nos. G-003, C-001, C-002, C-003, C-023, C-023A, C-024A, C- 024D, C-026A, C-026B, C-026C, C-026D, C-026E, C-056, C-301, C-501, B-102, R-002, R- 003, R-004, R-005, R-010, R-011 and R-019. Delete these drawings in their entirety and substitute the attached revised SHEET IDENTIFICATION Nos. G-003, C-001, C-002, C- 003, C-023, C-023A, C-024A, C-024D, C-026A, C-026B, C-026C, C-026D, C-026E, C-056, C-301, C-501, B-102, R-002, R-003, R-004, R-005, R-010, R-011 and R-019 therefore.

2. Add the attached new drawing SHEET IDENTIFICATION No. R-004A.

00010-3 Ed 20-001

SECTION 00010 – BIDDING SCHEDULE

Flood Control, Amite River Tributaries, Louisiana, Comite River Basin Comite River Diversion Project

Bayou Baton Rouge Rock Chute East Baton Rouge Parish, Louisiana

Item DESCRIPTION Estimated Quantity Unit Unit Price Estimated Amount

0001 Mobilization and Demobilization 1 JOB

0002 Safety Fence 1 JOB

Video and Photographic Documentation

1 JOB

0004 Traffic Control 1 JOB

0005 Temporary Retaining Structures 1 JOB

0006 Silt Fences 33,000 LF

0007 Straw Bales 5,000 LF

0008 Truck Wash-Down Racks 1 JOB

0009 Demolition 1 JOB

Removal of Abandoned Oil Well

GW-1

1 JOB

0011 Approach Slabs 1 JOB

0012 Bridge Concrete 1 JOB

0013 Pump Station Concrete 1 JOB

0014 Pump Station Items 1 JOB

Precast Prestressed Concrete Girders

1,380 LF

0016 Carney Road Bridge 1 JOB

Carney Road Bridge End Bents and Wingwalls

1 JOB

0018 24" RCP 32 LF

0019 18" RCP 83 LF

0020 54" RCP Extension 8 LF

0021 24" CMP 150 LF

0022 42" CMP 78 LF

0023 Electrical Work 1 JOB

00010-4 Ed 20-001

0024 Separator Geotextile - Roadway 25,600 SY

0025 Separator Geotextile - Diversion 48,500 SY

Separator Geotextile - Bayou Baton Rouge

42,500 SY

0027 Clearing and Grubbing 1 JOB

Excavation for Bayou Baton Rouge Temporary Alignment

18,000 CY

Excavation for Bayou Baton Rouge Rock Chute

167,000 CY

Excavation for Comite River Diversion Channel

712,000 CY

Excavation for Relocation of Carney Road and Pump Station Access

18,500 CY

Carney Road Bridge Abutments/Wingwalls Structural Excavation and Backfill

1 JOB

*0033 Pump Station Excavation and Backfill

1 JOB

0034 Channel Unwatering 1 JOB

0035 Pump Station Unwatering 1 JOB

Embankment - Relocation of Carney Road

27,000 CY

Embankment - Pump Station Access and Berm Road

1,000 CY

0038 Embankment - Guide Levees 6,000 CY

Embankment - Proposed Banks and Abandoned Channels

250,000 CY

Embankment - Carney Road Preload

26,000 CY

0041 Grouted Riprap 620 CY

*0042 Precast, Prestressed Concrete Pile, 14-inch x 14-inch

120 LF

*0043 Precast, Prestressed Concrete Pile, 18-inch x 18-inch

1,680 LF

*0044 Precast, Prestressed Concrete Pile, 30-inch x 30-inch

1,040 LF

0045 Pile Load Test (18-inch x 18-inch) 1 EA

0046 Pile Load Test (30-inch x 30-inch) 1 EA

0047 Asphalt Leveling Course 460 TON

0048 Asphalt Binder Course 3,300 TON

0049 Asphalt Wearing Course 2,500 TON

00010-5 Ed 20-001

0050 Cold Planing 2,750 SY

0051 Class II Base Course 21,600 SY

0052 Surfacing 580 CY

0053 Access Road and Laydown Area 1 JOB

0054 High Security Fence 488 LF

0055 Swing Gates 2 EA

0056 Barbed Wired Fencing 4,250 LF

0057 Farm Gates 2 EA

High Performance Turf Reinforcement Mats

3,200 SY

Turf Establishment and Maintenance

91 AC

0060 Utility Horizontal Directional Drilling 197 LF

0061 Guard Rails 1 JOB

0062 Vertical Lift Sluice Gate 1 EA

0063 Bedding Stone No. 1 45,750 TON

0064 Bedding Stone No. 2 3,000 TON

0065 Riprap, R-25 7,200 TON

0066 Riprap, R-90 61,500 TON

0067 Riprap, R-3500 4,100 TON

0068 Riprap, R-1500 23,000 TON

0069 Riprap, R-650 12,500 TON

*0070 Removal and Stockpile, Riprap, R-

1 JOB

0071 Non-Clog Submersible Pumps 2 EA

0072 Pipelines, Liquid Process Piping 1 JOB

TOTAL BASE WORK: $

OPTIONAL WORK (OW)

*0073 Construction Dewatering - OW 1 JOB

Hauling and Disposal, Excess Material - OW

20,000 CY

TOTAL OPTIONAL WORK: $

00010-6 Ed 20-001

TOTAL BASE + OPTIONAL WORK: $

*Denotes change to previous bid schedule.

**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.

Award will be made as a whole to one bidder.

NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED

TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE

DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR

AWARD.

NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).

NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.

NOTE 4: OPTION WORK ITEMS: The Government may require the delivery of, in whole or part, the Optional Work Item. The Government may exercise the Optional Item by written notice to the Contractor. If the Government activates the Optional Item, the activation will occur while the Contractor’s plant is within the limits of work. No additional mobilization/ demobilization will be paid to the Contractor for the Optional Work.

NOTE 5: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement.

Evaluation of options will not obligate the Government to exercise the option(s).

*NOTE 6: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF

OPTIONAL WORK. In the event that the OPTIONAL WORK is exercised under the terms of the contract, the work will be performed concurrent with the original contract duration of *1087 calendar days established for the BASE WORK items specified in Section 00700 CONTRACT CLAUSES paragraph entitled

00010-7 Ed 20-001

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.

NOTE 8: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;

http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx

Solicitation No. W912P8-25-B-0001

Bayou Baton Rouge Rock Chute

East Baton Rouge Parish, Louisiana

CLIN 0001, Mobilization and Demobilization: Contractor estimate

CLIN 0002, Safety Fence: Contractor estimate

CLIN 0003, Video and Photographic Documentation: Contractor estimate

CLIN 0004, Traffic Control: Contractor developed TCDP (Traffic Control Device Plan)

CLIN 0005, Temporary Retaining Structures: Contractor’s design

CLIN 0008, Truck Wash-Down Racks: One at each point of access for duration of project.

CLIN 0009, Demolition: Reference Shts. XD-001 and XD-002 for items to be demolished.

CLIN 0010, Approach Slabs: See table on S-102, “Summary of Bridge Quantities”, approximately 3,040 SF.

CLIN 0011, Bridge Concrete: See table on S-102, “Summary of Bridge Quantities” for concrete bridge items and estimated quantities.

CLIN 0012, Pump Station Concrete:

CONCRETE PAD 16 CY

W4xW4 Mesh 891 SF

CONCRETE HEADWALL FOR 12 INCH PVC PIPE 1 EA

CONCRETE HEADWALL FOR 18 INCH RCP 1 EA

10' DIA. WET WELL 1 EA

CLIN 0013, Pump Station Items:

FLYGT NP 3153 PUMP 2 EA

DOUBLE ALUMINIUM HATCH, 72" X 48" 1 EA

WALL-MOUNTED SLUICE GATE 1 EA

STAINLESS STEEL LIFTING CHAIN 80 LF

2" STAINLESS STEEL GUIDE RAIL 160 LF

8" CHECK VALVE WITH LIMIT SWITCH 2 EA

8" GATE VALVE 3 EA

Ladder 40 LF

HEADWALL TRASH RACK 1 EA

GUARD POST 51 EA

EMBANKMENT, COMPACTED FILL 3,495 CY

SEPARATOR GEOTEXTILE 2,584 SY

LIMESTONE 163 CY

DRIVEWAY AGGREGATE 467 CY

6 FOOT CHAIN LINK SECURITY FENCE 488 LF

15 FOOT DOUBLE-LEAF SWING GATE 2 EA

RIPRAP, R-25 1.8 TONs

BEDDING STONE NO. 1 0.5 CY

CLIN 0015, Carney Road Bridge: See table on S-102, “Summary of Bridge Quantities”. Include all bridge items not included in any other pay item.

CLIN 0016, Carney Road Bridge End Bents and Wingwalls: See table on S-102, “Summary of Bridge Quantities” for concrete bridge items and reinforcement. Include all end bent and wingwall items not included in any other pay item.

CLIN 0022, Electrical Work:

UTILITY SERVICE CHARGE 1 EA

NON-FUSED SERVICE ENTRANCE DISCONNECT

SWITCH 1 EA

METER SOCKET 1 EA

PUMP CONTROL PANEL 1 EA

TRANSFORMER 1 EA

DISTRIBUTION PANEL 1 EA

TERMINAL JUNCTION BOX 1 EA

ELECTRICAL HOUSEKEEPING PAD 1 EA

EQUIPMENT RACK 1 EA

FLOAT SWITCH AND CABLE 1 EA

GROUND INSPECTION HOLE (WELL) 1 EA

GROUND ROD 5 EA

SITE SECURITY LIGHT POLE 2 EA

LIGHT POLE BASE 2 EA

LIGHT POLE SHAFT 2 EA

LIGHT POLE MAST ARM 2 EA

LUMINAIRE 2 EA

3” RIGID METAL CONDUIT 44 LF

3” SCHEDULE 80 PVC CONDUIT 82 LF

1 ¼” PVC COATED STEEL CONDUIT 122 LF

3/4” PVC COATED STEEL CONDUIT 12 LF

1" Schedule 80 PVC Conduit 20 LF

4#1 RHW CONDUCTORS 328 LF

1#8G RHW CONDUCTORS 82 LF

2#10 RHR CONDUCTORS 64 LF

1#10G RHR CONDUCTORS 32 LF

#2/0 BARE TINNED COOPER CABLE DIRECT BURIED 142 LF

1” SCHEDULE 80 PVC CONDUIT 32 LF

#6 INSULATED XHHW-1 GROUND 48 EA

CLIN 0026, Clearing and Grubbing: There are almost 140 acres inside of the project limits and required

ROW.

CLIN 0031, Carney Road Bridge Abutments/Wingwalls Structural Excavation and Backfill: Excavation quantity dependent on contractor excavation beyond the foundation for working conditions.

CLIN 0032, Channel Unwatering: Unwatering quantity not calculated.

CLIN 0033, Pump Station Unwatering: Unwatering quantity not calculated.

CLIN 0051, Access Road and Laydown Area: Lay down area to be sized by contractor.

CLIN 0059, Guard Rails: 225 LF of guardrail at each bridge corner. Length includes a) the guardrail transition, b) the blocked out guardrail and c) the end treatment.

CLIN 0068, Pipelines, Liquid Process Piping:

DUCTILE IRON PIPE - 8 INCH 10 LF

HPDE PIPE - 12 INCH 197 LF

RCP - 18 INCH 83 LF

6" DUCTILE IRON PIPE 99 LF

COMBINATION AIR RELEASE VALVE/VACUUM

VALVE ASSEMBLY 1 EA

TAP WITH VALVE AND PRESSURE GAUGE 2 EA

PRESSURE TRANSMITTER 1 EA

CLEAN EXISTING RCP - 18 INCH 33 LF

4 FOOT DIAMETER MANHOLE 1 EA

HEAVY DUTY MAHOLE COVER 1 EA