W912P823B0025 Bid Abstract SIGNED.pdf
PDF 589 KB Posted
- Solicitation number
- W912P823B0025
About this file
This document is an abstract of bids received in response to a solicitation for construction services. The solicitation, number W912P823B0025, is for work on the West Shore Lake Pontchartrain, Louisiana Hurricane and Storm Damage Risk Reduction Project, WSLP 107 Levee Reach in St. John the Baptist Parish. The work consists of clearing and grubbing, placing sand fill, separator fabric, compacted clay embankment, drainage canals, culverts, access roads, fertilizing, turf establishment and other incidental work. Eight bids were received in response, ranging from $24,555,899.67 to $36,531,075.00. The government estimate was between $25,000,000 and $50,000,000. All bidders provided the required 20% bid bond except one. The award is a single firm fixed price contract. The contracting officer will review the bids for accuracy and compliance with the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Updated 23B0025 Bid Abstract SIGNED.pdf | ||
| W912P823B0025 Amendment 0004.pdf | ||
| W912P823B0025 Amendment 0003.pdf | ||
| W912P823B0025 Amendment 0002.pdf | ||
| W912P823B0025 Amendment 0001.pdf | ||
| W912P823B0025 Solicitation.pdf | ||
| Plans.pdf | ||
| Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
West Shore Lake Pontchartrain, Hurricane and Storm Damage Risk Reduction Project, WSLP-107 Levee, St. John the Baptist Parish, Louisiana
Solicitation Number: W912P823B0025
2. DATE ISSUED 3. DATE OPENED PAGE
4-Jan-23 1 0F __ PAGES
DATE SIGNED
7A. ITEM 7C. EST. D. UNIT E. UNIT F. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED
NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 Mobilization & Demobilization 1 JOB $1,405,584.75 $1,405,584.75 $2,000,000.00 $2,000,000.00 $1,004,635.10 $1,004,635.10 $4,220,000.00 $4,220,000.00 $2,855,598.00 $2,855,598.00 $2,674,000.00 $2,674,000.00 $2,120,000.00 $2,120,000.00 $1,228,078.02 $1,228,078.02
0002 Traffic Control and Coordination 1 JOB $220,000.00 $220,000.00 $80,000.00 $80,000.00 $314,456.65 $314,456.65 $55,000.00 $55,000.00 $65,000.00 $65,000.00 $462,000.00 $462,000.00 $15,000.00 $15,000.00 $636,995.71 $636,995.71
0003 Truck Wash-Down Rack 1 JOB $215,000.00 $215,000.00 $100,000.00 $100,000.00 $77,973.14 $77,973.14 $450,000.00 $450,000.00 $32,930.68 $32,930.68 $140,000.00 $140,000.00 $252,500.00 $252,500.00 $107,574.09 $107,574.09
0004 Separator Fabic 20,300 SY $4.26 $86,478.00 $3.00 $60,900.00 $6.92 $140,476.00 $5.00 $101,500.00 $5.47 $111,041.00 $11.00 $223,300.00 $4.00 $81,200.00 $4.62 $93,786.00
0005 Separator Geotextile 53,200 SY $15.00 $798,000.00 $9.50 $505,400.00 $12.50 $665,000.00 $14.00 $744,800.00 $9.52 $506,464.00 $9.50 $505,400.00 $12.50 $665,000.00 $10.36 $551,152.00
0006 Clearing and Grubbing 1 JOB $3,049,000.00 $3,049,000.00 $2,000,000.00 $2,000,000.00 $4,271,795.06 $4,271,795.06 $5,375,000.00 $5,375,000.00 $3,054,970.00 $3,054,970.00 $3,246,542.80 $3,246,542.80 $2,264,000.00 $2,264,000.00 $2,089,523.73 $2,089,523.73
0007 Drainage Chanel Excavation 1 JOB $1,371,000.00 $1,371,000.00 $1,612,000.00 $1,612,000.00 $1,801,781.02 $1,801,781.02 $2,100,000.00 $2,100,000.00 $3,766,869.50 $3,766,869.50 $1,534,867.80 $1,534,867.80 $1,850,000.00 $1,850,000.00 $2,095,266.17 $2,095,266.17
0008 Embankment, Compacted Fill 290,000 CY $47.85 $13,876,500.00 $45.00 $13,050,000.00 $58.51 $16,967,900.00 $54.00 $15,660,000.00 $36.17 $10,489,300.00 $36.58 $10,608,200.00 $50.50 $14,645,000.00 $43.06 $12,487,400.00
0009 Sand Fill
0009AA First 81,600 TON 81,600 TON $19.42 $1,584,672.00 $22.00 $1,795,200.00 $47.27 $3,857,232.00 $31.25 $2,550,000.00 $19.25 $1,570,800.00 $28.33 $2,311,728.00 $21.50 $1,754,400.00 $31.98 $2,609,568.00
0009AB All Over 81,600 TON 20,400 TON $19.42 $396,168.00 $17.00 $346,800.00 $36.42 $742,968.00 $31.25 $637,500.00 $19.25 $392,700.00 $25.00 $510,000.00 $21.50 $438,600.00 $30.28 $617,712.00
0010 Surfacing
0010AA First 16,100 TON 16,100 TON $93.85 $1,510,985.00 $75.00 $1,207,500.00 $72.00 $1,159,200.00 $80.00 $1,288,000.00 $56.69 $912,709.00 $95.68 $1,540,448.00 $89.50 $1,440,950.00 $82.30 $1,325,030.00
0010AB All Over 16,100 TON 2,930 TON $93.85 $274,980.50 $65.00 $190,450.00 $70.31 $206,008.30 $80.00 $234,400.00 $56.69 $166,101.70 $80.96 $237,212.80 $89.50 $262,235.00 $82.30 $241,139.00
0011 Seeding and Mulching 76 AC $7,520.00 $571,520.00 $7,000.00 $532,000.00 $6,521.83 $495,659.08 $8,000.00 $608,000.00 $2,600.00 $197,600.00 $8,008.00 $608,608.00 $9,200.00 $699,200.00 $3,717.95 $282,564.20
0012 Fertilizer
0012AA First 7,600 LB 7,600 LBS $6.27 $47,652.00 $2.00 $15,200.00 $8.70 $66,120.00 $2.50 $19,000.00 $1.43 $10,868.00 $2.52 $19,152.00 $2.70 $20,520.00 $1.70 $12,920.00
0012AB All Over 7,600 LB 3,420 LBS $6.27 $21,443.40 $1.00 $3,420.00 $2.27 $7,763.40 $2.50 $8,550.00 $1.43 $4,890.60 $2.69 $9,199.80 $2.70 $9,234.00 $1.70 $5,814.00
0013 Lime Soil Amendment 75 TON $630.00 $47,250.00 $100.00 $7,500.00 $444.84 $33,363.00 $300.00 $22,500.00 $1,298.45 $97,383.75 $173.60 $13,020.00 $1,100.00 $82,500.00 $1,045.97 $78,447.75
0014 Sulfur Soil Amendment 38 TON $1,900.00 $72,200.00 $100.00 $3,800.00 $1,828.95 $69,500.10 $375.00 $14,250.00 $2,043.75 $77,662.50 $1,904.00 $72,352.00 $2,600.00 $98,800.00 $2,445.50 $92,929.00
$25,548,433.65 $23,510,170.00 $31,881,830.85 $34,088,500.00 $24,312,888.73 $24,716,031.20 $26,699,139.00 $24,555,899.67
0015 Separator Geotextile - OW 4,910 SY $4.26 $20,916.60 $3.00 $14,730.00 $5.20 $25,532.00 $5.00 $24,550.00 $5.47 $26,857.70 $2.24 $10,998.40 $4.00 $19,640.00 $4.63 $22,733.30
0016 Bypass Canal Excavation - OW 1 JOB $86,200.00 $86,200.00 $200,000.00 $200,000.00 $321,275.36 $321,275.36 $280,000.00 $280,000.00 $336,812.00 $336,812.00 $168,083.80 $168,083.80 $140,000.00 $140,000.00 $265,999.03 $265,999.03
Embankment Compacted Fill - OW 1,300 CY $51.09 $66,417.00 $45.00 $58,500.00 $33.27 $43,251.00 $64.00 $83,200.00 $36.17 $47,021.00 $70.14 $91,182.00 $33.00 $42,900.00 $41.68 $54,184.00
0018 Sand Fill - OW 6,400 TON $19.41 $124,224.00 $22.00 $140,800.00 $36.69 $234,816.00 $31.25 $200,000.00 $19.25 $123,200.00 $32.41 $207,424.00 $19.00 $121,600.00 $27.44 $175,616.00
0019 Surfacing - OW 2,635 TON $93.85 $247,294.75 $65.00 $171,275.00 $65.93 $173,725.55 $80.00 $210,800.00 $56.69 $149,378.15 $97.82 $257,755.70 $72.00 $189,720.00 $82.30 $216,860.50
Corrugated Metal Pipe Culvert 60" Diameter - OW 1,365 LF $448.00 $611,520.00 $600.00 $819,000.00 $474.86 $648,183.90 $685.00 $935,025.00 $664.00 $906,360.00 $585.04 $798,579.60 $485.00 $662,025.00 $503.96 $687,905.40
Corrugated Metal Pipe Culvert 72" Diameter - OW 650 LF $629.00 $408,850.00 $700.00 $455,000.00 $555.86 $361,309.00 $940.00 $611,000.00 $754.00 $490,100.00 $717.31 $466,251.50 $615.00 $399,750.00 $607.28 $394,732.00
0022 Stone_R-90 - OW 700 TON $105.92 $74,144.00 $140.00 $98,000.00 $126.69 $88,683.00 $140.00 $98,000.00 $89.16 $62,412.00 $161.30 $112,910.00 $93.00 $65,100.00 $110.83 $77,581.00
$1,639,566.35 $1,957,305.00 $1,896,775.81 $2,442,575.00 $2,142,140.85 $2,113,185.00 $1,640,735.00 $1,895,611.23
$27,188,000.00 $25,467,475.00 $33,778,606.66 $36,531,075.00 $26,455,029.58 $26,829,216.20 $28,339,874.00 $26,451,510.90
NO. 7
A. OFFEROR
Phylway Construction, LLC
B. BID SECURITY (Type and amount) 20%, $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 6
A. OFFEROR
Onshore Materials, LLC
B. BID SECURITY (Type and amount) 20%, $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
Option Work 1 Total
7B. DESCRIPTION OF OFFERED ITEM
BASE WORK
C. REASONABLE CONTRACT C. AMENDMENTS ACKNOWLEDGED - Yes C. AMENDMENTS ACKNOWLEDGED - Yes
(Including Profit)
West Shore Lake Pontchartrain, Hurricane and Storm Damage Risk Reduction Project, WSLP-107 Levee, St.
John the Baptist Parish, Louisiana
(Check A, B or C and complete D, E, and F) NO. 1
Total
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Prescribed by GSA - FAR (48 CFR) 53.236-1
NO. 5
A. OFFEROR
Genesis 360, LLC
B. BID SECURITY (Type and amount) 20%, $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED No
NO. 3
A. OFFEROR
Cycle Costruction Company, LLC
B. BID SECURITY (Type and amount) 20%, $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED Yes
NO. 4
A. OFFEROR
Dynamic Group, LLC
B. BID SECURITY (Type and amount) 20%, $3,000,000.00
C. AMENDMENTS ACKNOWLEDGED - Yes
6. NUMBER OF AMENDMENTS ISSUED: 4
NO. 2
A. OFFEROR
Civil Works Contracting LLC
A. HIRED LABOR A. OFFEROR
b&k Construction Company, LLC
B. REASONABLE CONTRACT B. BID SECURITY (Type and amount) 20%, $3,000,000.00 B. BID SECURITY (Type and amount) 20%, $3,000,000.00
(Without Profit)
SIGNATURE
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE 9. OFFERS
ABSTRACT OF OFFERS - CONSTRUCTION Solicitation Number: W912P823B0025 2-Mar-23
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
US ARMY ENGINEER DISTRICT, MVN (NOD)
7400 Leake Avenue Cori Caimi New Orleans, LA 70118-3651 Contract Specialist
Margaret C. Maine Contracting Officer
NOTE: Civil Works Contracting LLC include math errors in bid.
3/3/2023
| 2023-03-03T08:52:44-0600 | |
| MAINE.MARGARET.COOKSEY.1151563550 |
File details come from the government source that posted it. Updated .