W912P823B0025 Amendment 0004.pdf
PDF 1 MB Posted
- Solicitation number
- W912P823B0025
About this file
This document provides details regarding Amendment 0004 to Solicitation Number W912P823B0025 for the West Shore Lake Pontchartrain, Louisiana, Hurricane and Storm Damage Risk Reduction Project, WSLP 107 Levee Reach, in St. John the Baptist Parish, Louisiana. The amendment responds to contractor questions, providing clarification that sand and bedding stone quantities will be paid separately under applicable bid items. It also clarifies that no interim maintenance is required during a 90-week hold period between project stages, but contractors will need to clear considerable vegetation prior to beginning the next stage. Maintenance of access roads is required if used by the contractor during the hold period and repairs are necessary.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Updated 23B0025 Bid Abstract SIGNED.pdf | ||
| W912P823B0025 Bid Abstract SIGNED.pdf | ||
| W912P823B0025 Amendment 0003.pdf | ||
| W912P823B0025 Amendment 0002.pdf | ||
| W912P823B0025 Amendment 0001.pdf | ||
| W912P823B0025 Solicitation.pdf | ||
| Plans.pdf | ||
| Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered Solicitation for West Shore Lake Pontchartrain, Louisiana, Hurricane and Storm Damage Risk Reduction Project, WSLP-107, St. John the Baptist Parish, Louisiana has been amended to:
1. Responses to Previous Questions
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Feb-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P823B0025
X 9B. DATED (SEE ITEM 11)
03-Jan-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Feb-2023
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X
West Shore Lake Pontchartrain, LA Hurricane and Storm Damage Risk Reduction Project
WSLP – 107 Levee Solicitation Number W912P823B0025
Contractor Questions
1. Is the bedding and sand required for the culvert pipes measured and paid separately or is it included for payment in the culvert pipe item?
Response: The sand and bedding stone quantities are paid for separately under the applicable bid items.
2. Regarding the Government responses to questions 1 and 3 of addendum no.3, during the 90 week hold period between stage 2 and stage 3 where no seeding and fertilizing is required and no staff is required.
Is the contractor responsible for any type of maintenance along the limits of construction?
Response: No, however, if no interim maintenance is performed, the contractor will have considerable amounts of vegetation to clear, grub, remove and dispose of prior to beginning
Stage 3 embankment work.
3. Is the contractor responsible for any maintenance along the access roads?
Response: Maintenance would be required if the road is used by the WSLP-107 contractor during the hold period and results in necessary repairs.
File details come from the government source that posted it. Updated .