W912P821R0011 Amendment 0004.pdf
PDF 10 MB Posted
- Solicitation number
- W912P821R0011
About this file
This is a solicitation for surface preparation and painting services on the dredge Wheeler. The U.S. Army Corps of Engineers Engineering District New Orleans is seeking offers for cleaning and recoating exterior steel surfaces and structures on the dredge. Bids are due by July 21, 2022. The work includes abrasive blast cleaning, spot cleaning and repair, and application of new coatings to the hull and superstructure. The period of performance is 180 calendar days from award. Small businesses are encouraged to compete for the firm-fixed price contract. The solicitation includes specifications for surface preparation, coating materials, and quality control requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P821R0011 Amendment 0003.pdf | ||
| Attachment A.pdf | ||
| Attachment B.pdf | ||
| Attachment C.pdf | ||
| W912P821R0011 Amendment 0002.pdf | ||
| W912P821R0011 Amendment 0001.pdf | ||
| W912P821R0011 Combined Synopsis-Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The above numbered solicitation for Surface Preparation and Painiting Aboard w ith Dredge Wheeler is amended as follow s:
1. Add Offeror questions and Government responses.
2. Provide additional draw ings.
Proposal due date remains unchanged. Be sure to ackow ledge all amendments w ith your proposal.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 27
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Sep-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P821R0011
X 9B. DATED (SEE ITEM 11)
10-May-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Sep-2022
CODE
CONTRACTING DIV- CHIEF
7400 LEAKE AVENUE, ROOM 172
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P821R0011
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS
Q: Thank you for your response below. I have had time to dig further into the solicitation and I have the following additional RFI questions.
In attachment A Performance Work statement refers to a Section B in para 2.1, 3.1.7,
3.1.9. There is no Section B in the Solicitation. I think this section would be the format for the unit pricing for personnel and equipment. I also assume that these unit rates would be rolled up to provide the basis for the CLIN firm fixed price for each year required in Para L of Amendment 0002. Without a unit structure to price it will be difficult to evaluate competitive bids received in response to this solicitation. Should the Solicitation include a Section B for unit prices?
Attachment A also refers to a Section C for a work statement in para 3.1.5. Is there a Section C and would this section provide any guidance on the expected amount of Ft2 that would be anticipated each year? Should the Solicitation include a Section C that provides additional information on the areas expected to be included in this proposal?
The CLIN structure provided in Para L of Amendment 0002 does not specify an amount that the 25% portions are to be based on (Could be based on manhours, area, Ft2, etc.).
What basis do we use to calculate the 25% that is required?
CLIN 104, 204, 304, 404, 504 does not provide a description. What services are to be included in these items?
We understand that after the award, each Task Order will be priced with a Firm Fixed bid based on the unit rates provided in our response to this solicitation. Is there an expected format that these Task Orders will be issued in?
Given the unknown quantities of the future Task Orders, should there be any provision provided for Undisclosed work items that may not be covered by the unit pricing in the CLIN’s?
Is this going to be a sole source award?
Section B was added with amendment 0003
Q: Please confirm that the paint products, thinners, and the paint representative are to be furnished by the contractor (and not the shipyard).
The government does not have an opinion on what entities provide these materials. This should be worked out between the shipyard and contractor.
Q: Will the Owners have their own independent paint representative on this project, or will the coatings manufacture representative be handling inspections and oversight?
The government representative will be present during surface preparation and coating inspections. However, the painting contractor can have their own quality assurance.
Q: What are the major interfacing items that need to be scheduled around i.e. major shaft work, steel repairs in the hopper or topside, repairs to the hopper doors, internal steel repairs, etc? This will help us put together a more precise schedule.
Inboard Pump Repairs (MD-3) and Tailshaft Replacement (MP-1.4) are the most involved projects. The Bow Thruster Inspection (MP-3.1) should also be addressed soon after delivery since there is the potential for growth work in this item.
Q: Please confirm that coatings can be applied via brush and roll (where needed and deemed appropriate) if the proper dry film thickness is achieved.
Yes, this is acceptable.
Q: We have priced this vessel at least a dozen times and HH-1 has always had complete staging of the interior of the hopper and sometimes the center well hid in the verbiage. We don’t see it now, could it have been moved to another item? Or has it been eliminated?
If it is deemed necessary to replace any plating in the Hopper area, staging will be requested to be added locally, in the area of repairs, via growth work.
Q: Would the amount of steel repairs in the hopper mean it’s fully staged for that work?
No, all optional items included in HH-1 will be issued on an as need basis and staging will be requested via growth work in the areas where work is being performed.
Q: Page 41 provides direction for the touch up coating of the interior and exterior.
Where the term “power tool clean” is used can we assume this to be power tool clean to an SP-3 standard?
Yes, that is acceptable.
Q: What is the total amount of surface area (in square feet) for this item?
Surface area can be estimated from reference drawing 11-03-01 Forepeak Framing. This document will be sent with response.
Q: We are to spray the entire area with cleaner and then pressure wash. At what pressure should we allow for (3,000 PSI or 5,000 PSI)?
3,000 psi is acceptable.
Q: What is the total amount of surface area (in square feet) for this item?
An estimate of surface area can be estimated from the Docking Plan, drawing 07-00-01. The contractor may also request a site visit to view accessible areas around the ship.
Q: Would the lower part of the center well area be considered part of the lower exterior hull?
Yes.
Q: During the washing process would there be any existing mud / muck that would require removal? If so, how much (in M3 or tons)
Only residual mud should be present at the time of arrival. An accurate estimate cannot be obtained.
Q: What is the amount of surface area in the chain lockers (in square feet) to be cleaned and coated?
Surface area can be estimated by referencing drawing 11-03-01 and 01-03-02.
Both will be included with this response. The contractor may also perform a site visit.
Q: Due to the hazards of UHP water blasting inside of tightly confined spaces;
could the contractor utilize grit blasting to an SP-7 (which is the equivalent to a WJ-
4) in this space?
Grit blasting is allowed however all material resulting from this type of blasting should be cleaned by the contractor.
Q: Due to the hazards of UHP water blasting inside of tanks; could the contractor utilize grit blasting to an SP-6 (which is the equivalent to a WJ-3) in these tanks?
Grit blasting is allowed however all material resulting from this type of blasting should be cleaned by the contractor
Q: What is the amount of surface area in the potable water tanks (in square feet) to be cleaned and coated?
Approximately 1280 square feet for EACH tank.
Q: What is the amount of surface area of the items / spaces listed (in square feet) to be cleaned?
See drawing 11-02-01, 11-02-03, 11-03-04, 11-03-05 and 01-03-02 to estimate area.
Q: Can the owner provide assistance on how to price this item? It is impossible to accurately estimate the amount of cleaning required in these spaces at the end of the availability when its condition at arrival isn’t known and how dirty it will become during the repair period cannot be ascertained. Could we provide level of effort pricing / day rate pricing / man hour rates?
All line items of the contract must be firm fixed pricing. The contractor is encouraged to perform a site visit to gain a better understanding of work to be performed.
Q: What is the amount of surface area in the fresh water tanks (in square feet) to be cleaned and coated?
Approximately 85 square feet for EACH tank.
Q: Due to the hazards of UHP water blasting inside of tanks; could the contractor utilize power tool cleaning to an SP-3 in these tanks?
Power tool cleaning is acceptable.
(End of Summary of Changes)