This is a synopsis for a federal solicitation seeking proposals for a flood control project in Louisiana. The project involves construction of a railroad bypass, highway bridges over 150 feet long with drilled shafts approximately 50 feet below a diversion channel, excavation of the channel, utility relocations, placement of riprap and concrete blocks, roadwork, traffic control, and other tasks. Proposals are due in April 2019 and the contract value is estimated between $25-100 million. Evaluation will be based on past performance, technical approach, key personnel and project management, and price. The solicitation will provide detailed evaluation factors and instructions for submission. The agency is the US Army Corps of Engineers New Orleans District. Offerors must register in SAM and proposals must adhere to FAR Part 15 procedures for negotiated procurements.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
The above numbered solicitation for Flood Control, Amite River and Tributaries, LA, Comite River Basin, Comite River Diversion Project, US Highway 61 and Kansas City Southern Railway Bridges, East Baton Rouge Parish, LA; ED-18-035 (W912P819R0033) is hereby amended as follows: See items below and continuation pages.
1. The SF1442 has been updated and is attached.
2. Contractor Questions and Responses are attached.
3. The proposal due date remains 02 January 2020, 11:00 a.m. CST.
U.S. Army Corps of Engineers, New Orleans District Contracting Division 7400 Leake Avenue, Room 326 New Orleans, LA 70118
W912P819R0033
ED-18-03512/13/2019
04/05/2019
1 56
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
W912P819R0033
US ARMY CORPS OF ENGINEERS, NEW ORLEANS
DISTRICT
CONTRACTING DIVISION
7400 LEAKE AVENUE
NEW ORLEANS, LA 70118
Comite Hwy. 61 & Kasas City Southern RR
Flood Control, Amite River and Tributaries, LA, Comite River Basin, Comite River Diversion Project, US Highway 61 and Kansas City Southern Railway Bridges, East Baton Rouge Parish, LA ED; 18-035
This is an Unrestricted Best Value Procurement. The estimated value of this work is between $25,000,000 to $100,000,000.
The work consists of construction of new diversion channel, railroad shoofly, Highway 61 bypass roadway, demolition and installation of the new roadway, construction of the railroad and highway bridges, construction of drilled shafts, utility relocations, construction of access roads and culverts, maintaining storm water management during construction, pile installation, traffic control and coordination, and preventive measures taken to ensure existing facilities and utilities remain undamaged.
The deadline for submitting questions for the subject request for proposal is 03 December 2019, 11:00 AM CST. Any questions received after this deadline will not be considered.
*See Section 00130 - Proposal Evaluation Criteria paragraph "RFP SUBMITTAL REQUIREMENTS".
US ARMY CORPS OF ENGINEERS, NEW ORLEANS
DISTRICT
ATTN: CEMVN-CT-W RACHEL WOODS
7400 LEAKE AVENUE, ROOM 326
NEW ORLEANS, LA 70118
Rachel A. Woods 504-862-1335
ED 18-035
03/27/2019
01/02/2020
11:00 a.m
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
US Army Corps of Engineers New Orleans Area Office 7400 Leake Avenue, New Orleans, LA 70118
USACE Finance Center Attn: CEFC-AO-P 5720 Integrity Drive, Millington, TN 38054-5005
Amendment 0007 Contractor Questions for:
MVN Flood Control, Amite River and Tributaries, LA, Comite River Basin, Comite River Diversion Project, US Highway 61 and Kansas City Southern Railway Bridges, East Baton Rouge, LA ED-18-035 , Solicitation Number W912P819R0033
1) The contract completion time has been significantly decreased. We respectfully request the original contract duration of 634 calendar days be reinstated. The project necessitates multiple by-passes, multiple phases of work, and sequential construction. To reduce the 634CD to 516CD increases inherent risk and raises safety issues associated with multiple shifts and night time work. Please take our concerns in consideration and reinstate the 634CD for completion.
USACE Response: The previous scope took into account restricted access due to multiple relocations that had to occur concurrent with construction. Now, the majority of the existing utilities have been relocated which will allow unencumbered access to the project site by the Contractor to start construction on the railway shoofly. No change to the project duration will be made by USACE.
2) Amendment 4, Section 34 11 25.16 that is mentioned at the end of the text before the drawings, is not attached to the Amendment.
USACE Response: Spec Section 34 11 25.16, “BALLAST”, will be included within Amendment 0007.
3) Is there a cost associated with the ROE agreement for the KCS Railroad attached to
Amendment 5?
USACE Response: The Fee for the ROE agreement is included within Attachment C, “KCS Right of Entry Agreement Form”, Paragraph 4, included within Amendment 0005.
“4. FEE: Contractor agrees to pay to Railway Company for the use of Railway Company’s right-of-way and the privilege hereby granted, such use and privilege being expressly limited to the facilities described above, the one-time sum of ONE AND NO/100 DOLLARS ($1.00), payable upon execution of this Agreement.”
4) The contract asks that the HPTRM area be seeded and fertilized. We have performed the installation of the HPTRM in the past and experience indicates that sod is the best way to establish grass growth. Please consider adding a sod item to the bid for installation over the
HPTRM.
USACE Response: The Contractor shall bid the project based upon the requirements stated within the advertised contract plans and specifications.
Amendment 0007 Contractor Questions for: MVN Flood Control, Amite River and Tributaries, LA, Comite River Basin, Comite River Diversion Project, US Highway 61 and Kansas City Southern Railway Bridges, East Baton Rouge, LA ED-18-035, Solicitation Number
5) The quantity for the 66" drilled shafts is overestimated. Please revise the quantity and issue a new bid item sheet.
USACE Response: The estimated quantity for bid item 0042, “DRILLED SHAFT (66”)”, will be revised from 6,804 LF to 2,268 LF, and included within Amendment 0007.
6) The Bidding schedule in Amendment 3 (the latest bid schedule revision to my knowledge) has
Item #0052 16” Steel Pipe Pile 5,691 LF, however the quantity show on sheet S-202 has this quantity corrected to 5,823 LF from an Amendment. Can you tell me which one is correct and how should proceed with pricing that item?
USACE Response: The estimated quantity for bid item 0052, “16” STEEL PIPE PILE”, will be revised from 5,691 LF to 5,823 LF, and included within Amendment 0007.
7) Due to the large scope of the project, short time frame for preparation of the bid, and upcoming holidays we would like to request the project bid date be delayed to help facilitate a more accurate bid.
USACE Response: Amendment 006 extends the proposal due date.
8) Please verify the qty is correct for CLIN 73- HPTRM Hydroseeding. It is currently 73 acres.
USACE Response: The estimated quantity for bid item 0073, “HPTRM HYDROSEEDING”, will be revised from 73 AC to 7 AC, and included within Amendment 0007.
9) CLIN 0016- requires lime treatment (12" thick).
-Where is the lime treatment required? The details don’t appear to call it out.
-The specification refer bidders to LDOTD requirements. However, it doesn’t specify which type of LDOTD treatment is required (Ty B, C, D, E, etc.)
-What application rate/ percentage of lime treatment is required (i.e. 6%)?
USACE Response: Refer to Plan Sheet C-111, for details of the 12” thick lime treatment. The typical sections for the roadway shows number 9 as “12” LIME TREATMENT (TYPE E) (9% BY VOLUME) within the legend.
Southern Railway Bridges, East Baton Rouge, LA ED-18-035, Solicitation Number
10) On the referenced solicitation, we would ask the Government to consider extending the solicitation due date approximately 2 weeks. The project was re-established (after a 7-month delay) on 11/19/19 leaving very minimal time for preparation of bids. As this is a best value procurement, it is difficult to assemble this bid in a relatively short time frame (especially with the holidays mixed in).
11) Contractor respectfully submits the following question, in regard to the subject project.
This project has been on hold for an extended period of time, causing contractors to move on to other endeavors with their work forces. To now resurrect it on such short notice with such a short turn around for site tour (11/22), last day for RFI’s (11/25) and bid turn in date (12/06), added to the fact that the Thanksgiving Holiday is upon us, will certainly make responding to your solicitation extremely difficult if not entirely impossible, given the scope of work. It is requested that USACE, New Orleans District reconsider and grant an extension to at least mid- January, 2020.
12) Regarding the subject solicitation, we request that you please extend the proposal due date to 31
January 2020 to provide appropriate time to restart the bid, perform an appropriate small business outreach, and complete proposal efforts considering vacation and holiday schedules.
13) We would like to request that the RFP Offers Due Date be extended to accommodate the upcoming Thanksgiving holiday.
14) Please consider postponing the due date for this project’s solicitation response to mid-January.
The postponement will allow for greater participation by qualified firms, and a competitive offer from our firm. Without a postponement we will not be able to respond.
15) In regards to the US 61 Bridge Quantities, most of my takeoffs are not matching the Engineer’s supplied Estimated Quantities found on Plan Sheet S-102. Specifically, the quantity for the Class A1 Concrete (Bent Cap), Class A1 Concrete (Column), Class A1 Concrete (Retaining Wall), and Concrete Approach Slabs. I realize that the majority of these items are not measured and paid for by the unit, however I am concerned if I am missing something or if USACE left information out of the plan set. Please advise
Southern Railway Bridges, East Baton Rouge, LA ED-18-035, Solicitation Number
USACE Response: Plan Sheet S-102 will be revised with the correct quantities, and included within Amendment 0007.
16) After speaking with precast vendors, I am concerned with the availability of the Precast
Prestressed Single Cell Box Girders. Along with lack of availability, I feel the price for these will be much higher than USACE is expecting. Would USACE be open to an alternate precast girder being used in lieu of the Precast Prestressed Single Cell Box Girders?
USACE Response: The Contractor shall bid the project based upon the requirements stated within the advertised contract plans and specifications.
SECTION 00010
Pages 00010-3 thru 7. Delete these pages in their entirety and substitute the attached revised pages 00010-3 thru 7 therefore.
SECTION 01100
Pages 11 thru 26. Delete these pages in their entirety and substitute the attached revised pages 11 thru 26, 26a, and 26b therefore.
SECTION 01 33 00
Delete the Submittal Register at the end of this section in its entirety, and substitute the revised attached Submittal Register therefore.
SECTION 34 11 25.16
Add the attached new Section 34 11 25.16.
DRAWINGS
SHEET IDENTIFICATION No. S-102. Delete this drawings in its entirety and substitute the attached revised SHEET IDENTIFICATION No. S-102 therefore.
00010-3 ED 18-035
SECTION 00010 – BIDDING SCHEDULE
Flood Control Amite River and Tributaries, Louisiana, Comite River Basin, Comite River Diversion Project
US Highway 61 and Kansas City Southern Railways Bridges East Baton Rouge Parish, Louisiana
Item DESCRIPTION Estimated
Quantity Unit Unit Price Estimated Amount
BASE WORK
0001 MOBILIZATION AND
DEMOBILIZATION 1 JOB
0002 VIDEO AND PHOTOGRAPHIC
DOCUMENTATION 1 JOB
0003 RAILROAD FLAGGING
SERVICES 1,200 HR
0004 RAILROAD INSURANCE 1 JOB
0005 TRAFFIC CONTROL AND
COORDINATION 1 JOB
0006 STRAW BALES 10,000 LF
0007 SILT FENCES 51,500 LF
0008 TRUCK WASHDOWN RACKS 1 JOB
0009 DEMOLITION 1 JOB
0010 US 61 RECONSTRUCTION 1 JOB
0011 US 61 DIVERSION 1 JOB
EXCAVATION FOR US 61
RECONSTRUCTION AND US
61 DIVERSION
32,000 CY
NON-PLASTIC EMBANKMENT
FOR US 61
RECONSTRUCTION
1,500 CY
0014 NON-PLASTIC EMBANKMENT
FOR US 61 DIVERSION 20,000 CY
0015 EXCAVATION FOR US 61
DIVERSION REMOVAL 10,500 CY
0016 LIME TREATMENT (12” THICK) 49,600 SY
0017 CLASS II BASE COURSE (12”
THICK) 22,900 SY
0018 CLASS II BASE COURSE (10”
THICK) 5,000 SY
0019 CLASS II BASE COURSE (8
1/2” THICK) 8,300 SY
0020 GEOTEXTILE FABRIC
(ROADWAY) 58,000 SY
00010-4 ED 18-035
0021 ASPHALT WEARING COURSE 13,500 TN
0022 ASPHALT BINDER COURSE 14,500 TN
0023 ASPHALT BASE COURSE 8,500 TN
0024 ASPHALT MILLING 35,500 SY
0025 AGGREGATE DRIVEWAY
SURFACING 2,500 SY
0026 CB-01 2 EA
0027 CB-02 MODIFICATION 1 EA
0028 18” SIDE DRAIN PIPE 539 LF
0029 24” SIDE DRAIN PIPE 355 LF
0030 24” CROSS DRAIN PIPE RCPA 124 LF
0031 36” RCP 56 LF
0032 42” RCP 38 LF
0033 DRAIN SAFETY ENDS 6 EA
0034 CLEARING AND GRUBBING 1 JOB
0035 SITE GRADING 1 JOB
0036 FERTILIZING AND SEEDING 24 AC
0037 US 61 NB & SB BRIDGES 1 JOB
PRECAST PRESTRESSED
CONCRETE GIRDERS (TYPE
III)
4,169 LF
US 61 NB & SB BRIDGE END
BENTS/WINGWALLS,
STRUCTURAL EXCAVATION
AND BACKFILL
1 JOB
0040 TEST SHAFT (66”) 1 EA
0041 TRIAL SHAFT (66”) 1 EA
0042* DRILLED SHAFT (66”) 2,268 LF
PRECAST PRESTRESSED
CONCRETE PILE, 14-INCH X
14-INCH
264 LF
PRECAST PRESTRESSED
CONCRETE PILE, 18-INCH X
18-INCH
1,320 LF
0045 GUARD RAILS 1 JOB
00010-5 ED 18-035
0046 APPROACH SLABS 1 JOB
0047 KCS RAILROAD BRIDGE 1 JOB
0048 PRECAST PRESTRESSED
SINGLE CELL BOX GIRDERS 1,220 LF
KCS RAILROAD BRIDGE
ABUTMENTS/RETAINING
WALLS
1 JOB
0050 TRIAL SHAFT (144”) 1 EA
0051 DRILLED SHAFT (144”) 604 LF
0052* 16” STEEL PIPE PILE 5,823 LF
0053 TEST PILE (18” PCP) 1 EA
0054 TEST PILE (16” PIPE PILE) 1 EA
0055 KCS SHOOFLY 1 JOB
0056 BALLAST 3,600 TN
0057 EXCAVATION FOR KCS
SHOOFLY 6,500 CY
0058 EMBANKMENT FOR KCS
SHOOFLY 750 CY
0059 SUBBALLAST 4,400 TN
0060 RAILROAD DRAINAGE PIPE
(48” CMP) 109 LF
0061 RAILROAD DRAINAGE PIPE
(24” CMP) 209 LF
0062 RAILROAD TRACK AND
ACCESSORIES 3311 LF
0063 CHANNEL EXCAVATION 710,000 CY
0064 CHANNEL RIPRAP (1/4 TON) 22,000 TN
0065 STABILIZATION RIPRAP (100
LB) 40 TN
0066 RANDOM RIPRAP (40 LB) 60 TN
0067 CHANNEL BEDDING
MATERIAL 2,600 CY
0068 CHANNEL FILTER MATERIAL 19,200 CY
CHANNEL LINING,
ARTICULATED CONCRETE
BLOCK
35,900 SY
0070 GEOTEXTILE FABRIC
(CHANNEL) 42,400 SY
0071 HIGH PERFORMANCE TURF
REINFORCEMENT MAT 33,000 SY
00010-6 ED 18-035
0072 CONSTRUCTION
UNWATERING 1 JOB
0073* HPTRM HYDROSEEDING 7 AC
TOTAL BASE WORK: $
OPTIONAL WORK
0074 TRAFFIC CONTROL AND
COORDINATION - OW 1 JOB
0075 CLEARING AND GRUBBING -
OW 1 JOB
0076 RELOCATED BARNETT ROAD
- OW 1 JOB
EXCAVATION FOR
RELOCATED BARNETT ROAD
- OW
12,400 CY
NON-PLASTIC EMBANKMENT
FOR RELOCATED BARNETT
ROAD - OW
8,600 CY
0079 CLASS II BASE COURSE (8
1/2” THICK) - OW 4,388 SY
0080 GEOTEXTILE FABRIC
(ROADWAY) - OW 8,371 SY
0081 ASPHALT WEARING COURSE
- OW 630 TON
0082 ASPHALT BINDER COURSE -
OW 1,259 TON
0083 42” RCPA - OW 100 LF
0084 48” RCPA - OW 152 LF
0085 60” RCPA - OW 167 LF
0086 FENCING (PERMANENT) - OW 5,200 LF
TOTAL OPTIONAL WORK: $
TOTAL BASE + OPTIONAL WORK $
*Denotes a change from the previous Bidding Schedule.
**The unit "JOB" as used in this Bidding Schedule is synonymous with the term "Lump Sum" used elsewhere within these plans and specifications.
Award will be made as a whole to one bidder.
NOTE 1: Bidders shall furnish unit prices for each item listed in the Schedule requiring a unit price. If the bidder fails to insert a unit price in the appropriate blank for required item(s), but does furnish an extended total, or an estimated amount for such item(s), the Government shall deem the unit price to be the quotient obtained by dividing the extended amount for that line item by the quantity. IF A BIDDER OMITS BOTH THE UNIT PRICE AND THE EXTENDED
00010-7 ED 18-035
TOTAL OR ESTIMATED AMOUNT FOR ANY ITEM, ITS BID SHALL BE
DECLARED NON-RESPONSIVE AND THEREFORE INELIGIBLE FOR
AWARD.
NOTE 2: Any bid may be rejected if the Contracting Officer determines in writing that it is unreasonable as to price. Unreasonableness of price includes not only total price of bid, but the price for individual line items as well. Any bid may be rejected if the prices for any line items or sub line items are materially unbalanced (See FAR 14.404-2, Rejection of Individual Bids).
NOTE 3: THE NOTICE TO PROCEED (NTP): The successful bidder is advised that performance and payment bonds shall be submitted in accordance with the time frame in block 12B of SF 1442. The NTP will be issued immediately after verification of acceptable performance and payment bonds. Within seven (7) days after issuance of the NTP, the Contractor shall initiate a meeting to discuss the submittal process with the Area or Resident Engineer or his authorized representative. Physical work cannot start until the Accident Prevention Plan, Contractor Quality Control Plan, and other submittals which may be required, have been submitted and approved and all preliminary meetings called for under the contract, have been conducted.
NOTE 4: RAPID VENDOR PAYMENT: Web based instructions for the submission of invoices;
http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx
NOTE 5: OPTIONAL WORK ITEMS. The Government may require the delivery of the numbered line item(s), identified in the schedule as OPTIONAL WORK Items, in the quantities and prices stated in the schedule. The Contracting Officer may exercise the OPTION WORK Items by written notice to the Contractor. Bidders shall bid on all items including optional items (see “Evaluation of Options” FAR 52.217-5). Failure to bid on all items will result in a non-responsive bid.
NOTE 6: EVALUATION OF OPTIONS (FAR 52.217-5 JUL 1990). Except when it is determined in accordance with FAR 17.206(b) not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for this basic requirement.
Evaluation of options will not obligate the Government to exercise the option(s).
*NOTE 7: TIME ADJUSTMENT IN THE EVENT OF THE EXERCISE OF
OPTIONAL WORK. In the event that OPTIONAL WORK items are exercised under the terms of the contract, the time required for completion of the contract will not be adjusted but shall be performed concurrent with the original contract duration of 516 calendar days established for the BASE WORK items specified in the Contract Clause entitled “COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK (FAR 52-211-10 – APR 1984)”.
http://www.mvn.usace.army.mil/BusinessWithUs/Contracting/RapidVendorPayment.aspx
01100-11 Ed 18-035
7. CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall be executed in three (3) copies. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet specified requirements.
8. ENVIRONMENTAL LITIGATION
(a) The term "environmental litigation", as used herein, means a lawsuit alleging that the work has an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
(b) If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If the order is not due in any part to acts or omissions of the Contractor (or a Subcontractor at any tier) other than as required by this contract, such suspension, delay, or interruption shall be as if ordered by the Contracting Officer under the Contract Clause in Section 00700, entitled Suspension of Work (FAR 52.242-14). The period of such suspension, delay or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.
9. UTILITIES AND IMPROVEMENTS
(a) All known utilities within the limits of the work, such as pipes, communication lines, power lines, etc., that would interfere with construction work shall be removed, modified or relocated by the appropriate utility at no cost to the Contractor unless otherwise noted in the plans and/or specifications. The Contractor shall cooperate with the authorities or company representatives and shall conduct his operations in such manner as to result in a minimum of inconveniences to the owners of said utilities. The Contractor shall notify each utility owner from the subsequent lists below (Entergy, DEMCO, City of Zachary, AT&T, Level 3 Communications, Madison River, Shell Bengal, ExxonMobil, 01100-12 Ed 18-035
Marathon, ORX, and MOHSEP) by certified mail 45 days, 15 days, and by telephone 72 hours prior to the date utilities need to be moved or when work is to be performed in the vicinity of the utility. The Contractor shall provide a copy of these notifications to the Contracting Officer.
(b) Any unidentified pipes or structures which may be found within the limits of the work during the course of construction shall not be disturbed nor shall construction or excavation be performed at these locations unless and until approved by the Contracting Officer.
(c) Notices to Owners and Authorities. The Contractor shall notify owners (Entergy, DEMCO, City of Zachary, Baton Rouge Public Works, AT&T, Century Link, Cox Communications, ORX, Marathon, Exxon, Shell, Florida Gas Transmission (FGT), American Midstream, Colonial Gas, and Enlink Gas) of utilities when prosecution of the work may affect them. When it is necessary to temporarily disconnect utility services, the Contractor shall give notices sufficiently in advance to enable the affected persons to provide for their needs.
Notices shall conform to any applicable local ordinance and, whether delivered orally or in writing, shall include appropriate information concerning the interruptions and instructions on how to limit their inconvenience. Utilities and other concerned agencies shall be contacted at least 48 hours (excluding Saturdays, Sundays and legal holidays) prior to cutting or closing streets or other traffic areas or excavating near underground utilities or pole lines.
(d) Electric Transmission and Distribution Lines (Entergy and DEMCO). While constructing the project, the Contractor will be working near, and under Entergy and DEMCO overhead power lines. The Contractor shall contact Entergy and DEMCO prior to start of construction to coordinate all construction work with Entergy and DEMCO in order to insure safety.
(1) The Contractor shall maintain a minimum distance from all power lines as required by NEC, Entergy and EM 385-1-1. Contractor shall be responsible for determining the maximum height and reach attainable by any part of any piece of equipment, and after coordinating with Entergy to determine the height and location of the power line, shall determine if the required clearance will be violated. The Contractor shall not work within the required clearance of the lines unless the lines are de-energized. If the clearance will be violated, prior to beginning any operations in the area, the Contractor shall coordinate with Entergy/DEMCO to de-energize the line. If the line is to be de-energized but is to remain in place, rather than being removed, the Contractor shall establish a procedure with Entergy to ensure that the Contractor shall have sufficient notice to allow removal of all equipment which may violate the required clearance from the area prior to the line being re-energized. These procedures and requirements shall also apply to any buried power lines.
01100-13 Ed 18-035
(2) It shall be the Contractor's sole duty and responsibility to provide for the safety of his/her men, equipment, subcontractors and the general public during operations in the vicinity of overhead and underground power lines; and to assure that all of his/her operations and those of his employees and subcontractors comply with OSHA, EM 385-1-1, the National Electric Safety Code, and all applicable Parish, State and Federal codes and regulations.
(e) The utility dispositions and contacts are as shown below.
1. ITEM G1 – American Midstream - 12” Diameter Steel HP Gas
DISPOSITION: ITEM G1 HP gas pipeline has been directionally drilled and relocated. The Contractor shall notify American Midstream when working in the vicinity of this pipeline.
ITEM G4 – American Midstream - 8” Diameter Steel HP Gas
DISPOSITION: ITEM G4 HP gas pipeline has been directionally drilled and relocated. The Contractor shall notify American Midstream when working in the vicinity of this pipeline.
ITEM G5 – American Midstream 6” Diameter Steel HP Gas
DISPOSITION: ITEM G5 HP gas pipeline has been removed. The Contractor shall notify American Midstream when working in vicinity of this pipeline.
Mr. Daniel Fayard IV, Sr. Project Manager, Jacobs Engineering 3330 West Esplanade Ave., Suite 612 Metairie, LA 70002 Phone: (504) 849-2217 Cell: (985) 807-8272 Email: Dan.fayard@jacobs.com
2. ITEM G2 – Enlink Midstream - 8” Diameter Steel HP Gas
DISPOSITION: ITEM G2 HP gas pipeline has been directionally drilled and relocated. The Contractor shall notify Enlink Midstream when working in the vicinity of this pipeline.
Mr. James Reynolds, Senior Landman, Enlink Midstream mailto:Dan.fayard@jacobs.com
01100-14 Ed 18-035
2300 South College Road Lafayette, LA 70508 Phone: (337) 354-1718 Cell: (337) 654-9536 Email: James.reynolds@enlink.com
3. ITEM G3 – Colonial Pipeline - 6” Dia Steel HP Gas
DISPOSITION: ITEM G3 HP gas pipeline has been removed and abandoned. The Contractor shall notify Colonial Pipeline when working in the vicinity of this pipeline.
Mr. Heath Bryant, Relocation Project Manager Colonial Pipeline 1185 Sanctuary Parkway, Suite 100 Alpharetta, GA 30009 Phone: (678) 762-2284 Cell: (713) 502-2364 Email: HBryant@ColPipe.com
4. ITEM G6 – Florida Gas Transmission (FGT) - 24” Dia Steel HP Gas
ITEM G7 – Florida Gas Transmission (FGT) - 30” Dia Steel HP Gas
NOTE: The phrase, "FGT Facility", "FGT Pipeline", "FGT representative", and "FGT Company" in Notes 1 through 30 below, refer to Florida Gas Transmission 24" & 30" Dia. Steel HP Gas Pipelines.
DISPOSITION: These pipelines shall not be disturbed. Florida Gas Transmission has cleared the project for the construction of the US 61 Bypass road. However, should the Contractor require the use of the Irene Road Borrow Pit access road as shown, he/she shall adhere to the requirements as follows:
(1) The Contractor shall provide a minimum of forty-eight
(48) hour notice to Florida Gas, prior to any installation, construction, excavation, or demolition work on the easement area, the Contractor shall also call appropriate LOUISIANA ONE CALL or 811 center at least 48 hours prior to any excavation activities. A FGT representative must be present when any work is done on the easement area. The Contracting Officer’s representative will have the authority to shutdown work by the Contractor if his/her activities are judged to be unsafe by the FGT representative.. The FGT mailto:James.reynolds@enlink.com mailto:HBryant@ColPipe.com
01100-15 Ed 18-035 representative shall be invited to participate in the Contractor’s safety meetings. This provision applies each time the FGT pipeline facilities are crossed.
(2) Normal ground cover (a minimum of three feet (3’) of pipeline cover) shall be maintained by the Contractor over the subsurface pipeline facilities within the easement area.
(3) Structures shall not be erected within, above, or below the pipeline easement with underground supports, foundations, or anchors. No apparatus will be allowed on the easement that obstructs the line-of-sight vision from ground level.
(4) For vehicles and/or construction equipment requesting approval to cross an FGT facility, each crossing location will be reviewed on a case-by-case, site specific basis, which will include a wheel load calculation to be completed and approved on every vehicle and/or construction equipment crossing a company facility. Three feet (3’) of minimum cover will also be required over the FGT pipeline facilities at all equipment crossings for standard TX/LADOT maximum axle load vehicles (20,000 lbs. per axle). On occasion, matting or other suitable material will be required to be installed so to achieve the necessary support for such crossing. This too will be site specific and case-by-case only.
(5) Any public road proposal or modification to existing roadway must be approved by the FGT before construction, to determine the possible need for pipeline alterations to comply with Federal and State regulations.
(6) For proposed road/drive crossings FGT will determine if the existing pipe is adequate for the new conditions.
Including protection of the pipelines, from imposed conditions caused by soil overburden and superimposed loading due to traffic. Load calculations must be performed to verify these conditions. Where consent for roadway crossing has been granted, a minimum of forty-two inches (42”) of cover, including thirty-six (36”) of undisturbed or compacted soil, shall be maintained within the easement area. Roadways crossing the pipeline shall be near right angles.
01100-16 Ed 18-035
Note: If the FGT company is required to perform maintenance on the pipelines, the Contractor will be responsible for the cost of road/drive replacement).
For proposed parking areas or parking lots FGT will determine if the existing pipe is adequate for the new conditions. Including protection of the pipelines, from imposed conditions caused by soil overburden and superimposed loading due to traffic. Load calculations must be performed by the Contractor to verify these conditions before construction is allowed. Wherever new construction results in concrete or asphalt being place over the right-of-way, measures must be in place to conduct necessary surveys to maintain the integrity of the pipelines. These test sites must be on 25’ intervals for the length of the pavement area.
Note: if the FGT company is required to perform maintenance on the pipelines, the Contractor will be responsible for the cost of pavement replacement.
(7) Where the encroachment includes utilities, all such utilities crossing the basement area must have a minimum separation of twenty four inches (24”) between the utility and the company pipeline(s) at the point of crossing and must cross at 90 degree angle (open cut excavations). No utilities shall be constructed between the surface of the easement area and the top of the subsurface pipeline facilities. When the pipeline is unreasonably deep permission may be granted to cross over the pipeline with twenty four inches (24”) of clearance. Above ground utilities shall be constructed above the easement area with a minimum of twenty five feet (25’) clearance to grade.
(8) No parallel utilities are permitted within the easement area.
(9) Berms or temporary spoil piles are not allowed within the right-of-way easement unless approved by the FGT company. Depth of cover shall not exceed 7 feet from the top of pipe to final grade. Contact the FGT company Right- Of-Way representative while the earthwork is still in the planning stage.
(10) The FGT utility company will review and approve any proposed temporary storage of material, equipment, or
01100-17 Ed 18-035 vehicles within the right-of-way easement. At no time will storage be allowed over the pipeline(s).
(11) Where consent for utility lines has been granted, electric lines shall be encased in steel throughout the easement area; fiber optic, telephone and cable television lines must be encased in PVC pipe throughout the easement area. Cables energized to 600 volts or more shall cross a minimum of three feet (3’) below the subsurface pipeline facilities, be encased in concrete, color coded red, across the entire right-of-way width, and have external, spiral wound, neutrals grounded on each side of the right-of-way.
The cable crossing shall be clearly and permanently marked on each side of the right-of-way where permissible.
(12) Where consent for fencing has been granted, the Contractor shall install and maintain a vehicle access gate at least twelve feet (12’) in width at each point in the fence line(s) crossing the easement area. Posthole excavations for fencing on the easement area shall not be greater than eighteen inches (18”) below the ground surface elevation.
No fence posts shall be placed over the pipeline facilities of closer than five feet (5’) on either side of the pipeline facilities. Any such fence shall be constructed and maintained by the Contractor in such a manner that does not prevent FGT personnel from viewing the easement area from the ground level through the fence(s) (i.e. no solid fences allowed). No fencing parallel to the FGT utility company pipeline facilities will be allowed within the easement area. FGT access to its pipeline facilities shall be maintained by the Contractor. If the gate is locked with the Contractors lock, the Contractor shall provide FGT with keys or allow an FGT lock to be installed in series to enable access.
(13) No above or below ground utility appurtenance, junction boxes or retention ponds are allowed within the easement area.
(14) No roto-mixing or vibrating machinery is allowed within the easement area.
(15) All pile driving operations within 20’ of a FGT pipeline/facility or adjacent to an FGT easement will be required to pre-drill or auger all pilings to 3’ below the bottom elevation of the pipeline(s).
01100-18 Ed 18-035
(16) Crossing excavations shall be sloped or shored to allow entry into the excavation. Time will be allowed for FGT company representative to inspect and make coating repairs as the subsurface pipeline facilities are exposed.
(17) Open ditches where consent has been given must cross the easement at or near right angles with at least thirty six inches (36”) of cover remaining at the lowest point of the ditch.
(18) Twelve inches (12”) of backfill around the subsurface pipeline shall be sand or clean fill; free of rocks and debris.
Rock Shield shall be installed around pipeline facilities.
(19) No more than twenty feet (20’) of pipe shall be exposed at any given time; if more than twenty feet (20’) of pipe is to be exposed, engineering stress calculations must be performed by FGT engineering and approved by FGT company operations prior to allowing any more than the twenty feet (20’) of exposed pipe.
(20) Excavators shall be equipped with barred tooth buckets and side cutters removed when digging or excavating within easement area. All mechanical excavation performed within 3 feet of the pipeline shall be performed parallel to the pipeline (i.e. track-hoe cannot reach over the pipe to dig on the opposite side of the pipeline).
(21) All excavation within 18” from top or 36” from the side or bottom of the pipeline shall be by manual means. After top exposure, excavation up to 12” from the side or bottom of the exposed pipeline may proceed by mechanical means if the FGT representative is satisfied it may be done safely with the equipment and operator available.
(22) All metallic foreign line crossings shall have Micarta board placed between the FGT pipeline facilities and the foreign crossing to prevent any interference with the cathodic protection system and equipment from the foreign crossing.
Drilled crossing are exempt from the use of Micarta boards.
(23) Barriers adequate to prevent vehicular damage to any exposed pipeline facilities shall be installed and maintained at all times.
01100-19 Ed 18-035
(24) Cathodic protection test stations and line markers shall be protected from damage by construction activity.
(25) No installation, construction, excavation, or demolition work shall be performed within the easement area on weekends or holidays unless owner agrees to reimburse the company for its cost, including overtime cost, associated with inspection during those periods.
(26) The Contractor shall provide and install temporary construction fence along the easement boundaries for the proposed work area to preserve and protect the pipeline(s).
The fence shall be maintained for the duration of the development or construction activity. Access across the FGT‘s easement will be granted at specific locations for vehicle and equipment traffic once a Wheel Load Calculation has been completed. Additional cover or matting may be required. Any changes to this requirement must be approved in writing by FGT prior to start of work.
(27) The Contractor shall not allow any seismographic activity within 300 feet of the pipeline without the approval of FGT Operation Manager. The Contractor will be will be responsible for any damage to the pipeline. Louisiana One- Call center should be notified at least 48 hours prior to the start of the project.
(28) Where consent for landscaping has been granted, The Contractor shall not plant any trees and shrubs on the easement area which are classified as “deep rooted” or are projected to exceed an eventual growth height of four (4) feet. Trees and shrubs shall be planted so that no part, at its ultimate growth, shall be closer than ten feet (10’) to the pipeline facilities. Plants or any other obstruction shall not hide or screen any pipeline markers. Line-of-sight vision will be maintained along the easement at ground level.
(29) Directionally drilled crossing will require a minimum 5-foot separation between company pipeline and foreign line crossing the entire ROW. Potholes are dug to observe that the drilling and pulling process does not damage the pipeline. If it is not practical to expose the FGT pipelines, contact the FGT representative to determine alternatives.
Boring equipment, if required, shall incorporate a mechanism for real time positioning and controlling bore bit/auger to
01100-20 Ed 18-035 ensure the required clearance is maintained throughout the boring process.
(30) The Contractor agrees that protection of the Florida Gas Transmission Company (FGT) Pipeline Facilities will be maintained at all times. Should it be reasonably necessary for FGT to remove any portion of the Encroachment within the Easement Area in order to construct, maintain, operate, repair, replace, remove, or resize FGT’s existing or additional Pipeline Facilities, the Contractor or its successors and assigns, shall pay the cost of removing and replacing or reinstalling such removed portion of the Encroachment. In addition, all repair and maintenance work performed by FGT on its existing or additional pipeline facilities located on its premises, shall be performed in a reasonable and workmanlike manner and FGT shall restore the surface and grade of the Owned Premises where the work is performed, but shall not be liable for loss, damage, or replacement to the Encroachment or any associated equipment and facilities that exist within the Easement Area, and in this regard, the Contractor does hereby release FGT, its employees, agents, officers, and directors from any and all liability for any such loss or damage. The parties hereto understand that this Agreement in no way constitutes a waiver by FGT of its rights to enjoy the Premises or the Easement Area unencumbered by the construction and operation of the Encroachment. It is expressly agreed to by and between the parties hereto that if the Contractor is in violation of any terms or conditions set forth in this Agreement, and such violation is not cured within ten (10) days of written notice to Owner, FGT may at any time terminate this Agreement upon written notice to Owner. In the event of such termination, Owner shall immediately remove any and all of said Encroachment, which may be situated on the Easement Area, or if Owner fails to remove any and all of said Encroachment, FGT may, at its option, remove said Encroachment at the expense of Owner and without any liability whatsoever. It is further agreed that the failure by FGT to exercise such option as to any such violation shall not constitute a waiver of FGT’s future right to exercise such option as to the same or any future violation.
Upon the termination of this Agreement, the Contractor shall remove from the Easement Area all of the Encroachment and restore the surface of the Easement Area to good condition and to FGT’s satisfaction, including the leveling
01100-21 Ed 18-035 and grading of all ruts, excavations, depressions and mounds caused by, or resulting from, the Encroachment.
The provisions of the Easement, and all rights, powers, privileges, and duties, obligations, and liabilities created thereby, remain in full force and effect and are not affected hereby except to the extent and in the manner set forth above.
Mr. Cary Farber Project Director Engineering & Construction Florida Gas Transmission - Energy Transfer Phone: (337) 475-4218 Cell: (337) 304-8860 Email: cary.farber@energytransfer.com
5. ITEM G8 – City of Zachary - 2” Dia HDPE Gas
DISPOSITION: Utility shall not be disturbed. Contact the City of Zachary when working in the vicinity of this item for any requirements.
Mr. Chris Davezac City of Zachary P.O. Box 310 4700 Main Street Zachary, LA. 70791 Phone: 225-654-0201 Cell: 225445-4992 Email: chris.davezac@cityofzachary.com
Mr. Jeff Johnson City of Zachary P.O. Box 310 4700 Main Street Zachary, LA 70791 Phone: None Available Cell: 225-445-4992 Email: None Available
Bianca Hillhouse City of Zachary (Consultant) P.O. Box 310 4700 Main Street Zachary, LA 70791 Phone: (225) 769-2810 Cell: None Available Email: bhillhouse@pecla.com http://fgttransfer.energytransfer.com/ mailto:steve.miller@energytransfer.com mailto:chris.davezac@cityofzachary.com mailto:bhillhouse@pecla.com
01100-22 Ed 18-035
6. ITEM PG1 – SHELL Pipeline - 24” Dia HP Gas
DISPOSITION: ITEM PG1 High Pressure Gas Pipeline has been directionally drilled and relocated prior to construction..
Mr. David Bergeron Jr.
Land & Permitting 305 East Hwy 30 Gonzales, La. 70737-4777 Phone: 225-474-7089 Cell: 225-937-4753 Email: d.bergeron@shell.com
7. ITEM PG2 – ExxonMobil Pipeline - 16” Dia. HP Gas
DISPOSITION: It is anticipated that the ITEM PG1 HP gas pipeline will be in place, i.e. directionally drilled and relocated prior to construction of the project. The anticipated date of relocation is by the end of March 2020. The Contractor shall notify ExxonMobil when working in the vicinity of this pipeline.
Mr. Dooley Oubre, R/W Claims ExxonMobil Pipeline Phone: 225-715-3981 Email: dooley.g.oubre@exxonmobil.com
8. ITEM PG3 – Marathon Pipeline LLC - 20” Dia. HP Gas
DISPOSITION: ITEM PG3 HP gas pipeline has been directionally drilled and relocated. Contractor shall notify Marathon Pipeline LLC when working in the vicinity of this pipeline.
Mr. Greg Newman, Sr. R/W Specialist Marathon Pipeline LLC 20-C Industrial Drive Lexington, OH 44904 Phone: 419-884-0800 Cell: 419-564-8826 Email: gcnewman@marathonpetroleum.com
9. I TEM PG4 – ORX - 16” Dia. HP Gas
DISPOSITION: ITEM PG4…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .