This document provides a solicitation notice for the Fox River Upper & Lower Sluiceway, Spillway and Walkway Repairs project in Appleton, WI. The U.S. Army Corps of Engineers, Chicago District is seeking construction services to repair two dams on the Fox River, including removal and replacement of tainter gates, walkways, piers, and repair of bedrock scours. The estimated cost is between $5-10 million. The North American Industry Classification code is 237990 and the size standard is $39.5 million. The solicitation package is available for download only through the provided Internet site. Bids are due by the date specified in the solicitation document. The contracting office is the USACE Chicago District. Registration in the System for Award Management is required at the time of bid submission to comply with annual representations and certifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6600989835

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REFERENCE SOLICITATION NUMBER W912P6-20-B-0007

The referenced Solicitation is EXTENDED by this Amendment. Therefore, responses to this Solicitation shall be furnished no later than 1:00 p.m. (CDT) on 14 September 2020. Details regarding bid submission are contained at Section 00 21 13 of the solicitation document. The amendment partiiculars follow on the next pages, w herein including revisions to Sections 00 10 00, 01 22 00.00 10, 02 13 90, and 35 20 16.46; revisions to plans and draw ings; and responses to contractors' questions.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 17

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Aug-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P620B0007

X 9B. DATED (SEE ITEM 11)

04-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Aug-2020

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P620B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT PARTICULARS

A. CHANGES TO SOLICITATION

1. Page 1, block 13D, is revised to the following:

“Offers providing less than 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.”

2. Section 00 10 00 Bid Items; the following is a summary of the bid items that have updated:

–Item No 0007: Change quantity to 1 and unit to Job –Item No 0008: Renamed bid item –Item No 0010: Renamed bid item –Item No 0013: Renamed bid item –Item No 0014: Change quantity to 1 and unit to Job –Item No 0015: Renamed bid item

The corrected Section 00 10 00 follows:

Section 00 10 00 - Solicitation

DEFINITIONS

In the Schedule below, “ALD” means Appleton Lower Dam, and “AUD” means Appleton Upper Dam.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Mobilization

FFP

Under this line item, the contractor is required to perform mobilization activities. The contractor will be compensated for the totality of its activities needed to mobilize its equipment and labor force to the project site.

Payment Provisions: The Government will pay all costs for the mobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.

NET AMT

0002 1 Job Demobilization

FFP

Under this line item, the contractor is required to perform demobilization activities. The contractor will be compensated for the totality of its activities needed to demobilize its equipment and labor force to the project site.

Payment Provisions: The Government will pay all costs for the demobilization of all of the Contractor's plant and equipment at the lump sum price for this item. The Contracting Officer may require the contractor to furnish cost data to justify its bid price for this item if the Contracting Officer deems there is no reasonable relationship to the cost of the work in this contract. Failure to justify the line item price to the satisfaction of the Contracting Officer will result in payment determined by the Contracting Officer of the actual costs, which is not subject to appeal.

0003 1 Job ALD: Blast and Paint Gates

FFP

Blast and Paint Gates 1-5 at Appleton Lower Dam

PURCHASE REQUEST NUMBER: W81G6600989835

0004 1 Job ALD: Replace Tainter Gates

FFP

Replace Tainter Gates 6-9 Removal for Appleton Lower Dam

0005 1 Job ALD: Side Seals, Clamp Plates & Bolts

FFP

Supply and Install Rubber Side Seals, Clamp Plates and Bolts for Tainter Gates 1-9 at Appleton Lower Dam

0006 4 Each ALD: Embedded Side Seal Plates

Embedded Side Seal Plates at Appleton Lower Gates 6-9

0007 1 Job ALD: Replace Spillway Walkways

Replace Spillway Walkways at Appleton Lower Dam

0008 5 Each ALD: Pier Repair

Pier repair at Appleton Lower Dam

0009 1 Job Site Work

0010 1 Job Stoplogs and Stoplog Guides

Fabricate and Install Stoplogs and Stoplog Guides

0011 1 Job AUD: Replace Tainter Gates

Replace Tainter Gates 1-8 Removal for Appleton Upper Dam

0012 1 Job AUD: Side Seals, Clamp Plates & Bolts

FFP

Install Government-Furnished Rubber Side Seals, Clamp Plates, and Bolts for Tainter Gates 1-8 at Appleton Upper Dam

0013 8 Each AUD: Embedded Side Seal Plates

Embedded Side Seal Plates at Appleton Upper Gates 1-8

0014 1 Job AUD: Spillway Walkways

Replace Spillway Walkways at Appleton Upper Dam

0015 8 Each AUD: Pier Repair

Pier Repair at Appleton Upper Dam

0016 1 Lot Performance & Payment Bonds

FFP

FOR LINE ITEMS 0001 THROUGH 0015, the government will reimburse the Contractor for the actual cost of acceptable performance and payment bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes re: FAR 52.232-5(g).

0017 10 Each OPTION Option 1: ALD Handrails

FFP

Remove and Replace Handrails at Right Abutment and Piers 1-9 at Appleton Lower Dam

0018 1 Lot OPTION Option 1: Performance & Payment Bonds

FFP

FOR LINE ITEM 0017, the government will reimburse the Contractor for the actual cost of acceptable performance and payment bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes re: FAR 52.232- 5(g).

0019 9 Each OPTION Option 2: AUD Handrails

Remove and Replace Handrails at Piers 1-9 at Appleton Upper Dam.

0020 1 Lot OPTION Option 2: Performance & Payment Bonds

FFP

FOR LINE ITEMS 0019, the government will reimburse the Contractor for the actual cost of acceptable performance and payment bonds, upon receiving evidence of payment (paid invoice) from the bonding company or agency, not to exceed the total amount of the contract line item. The Government will not pay more than the total line item amount for the performance and payment bonds. If the actual cost of the bonds is less than the line item amount, the contract will modified to adjust the line item accordingly. Adjustment(s) to the line item will also be made for any revisions to the actual bond costs associated with contract changes re: FAR 52.232- 5(g).

SUMMATION OF PRICES

BASE WORK (Items 0001 through 0016): $____________________

OPTION 1 (Items 0017 and 0018): $____________________

OPTION 2 (Items 0019 and 0020): $____________________

TOTAL OVERALL BID PRICE

(Items 0001 through 0020): $____________________

[End of changes to Section 00 10 00]

B. CHANGES TO SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS

1. Paragraph 3.b. is changed to the following:

“b. Bids are required no later than 1:00 p.m. Central time on 14 September 2020 and shall be provided using the DoD Secure Access File Exchange (https://safe.apps.mil) as described in the instructions below.”

2. Paragraph 4.b. is changed to the following:

“b. DROP-OFF REQUEST: Bidders shall e-mail the Contract Specialist, Patricia Woodhouse, at Patricia.L.Woodhouse@usace.army.mil, WITH A COPY to the Contracting Officer Regina G. Blair at regina.g.blair@usace.army.mil, requesting a DoD SAFE drop-off link. The drop-off link should be requested NO LATER THAN THREE (3) working days prior to the BID DUE DATE to avoid the Bidder not being able to drop-off its submission, and NO SOONER THAN 14 calendar days prior to the bid opening (the link expires after 14 calendar days). You will receive an e-mail from SAFE requesting a drop off.

3. The first paragraph at Paragraph 4.g. is changed to the following:

“VIRTUAL BID OPENING AND PARTICIPATION: THE VIRTUAL BID OPENING WILL BEGIN AT 2:00

P.M. CDT ON 14 SEPTEMBER 2020.

[End of changes to Section 00 21 13]

C. CHANGES TO SPECIFICATIONS

The revised specification sections are provided with this amendment at beta.SAM.gov in the file named “Amendment 0001 revised specifications.” The following is a summary of changes made by this amendment:

1. Delete 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES Add revised 01 22 00.00 10 PRICE AND PAYMENT PROCEDURES Change: changes throughout See attached file titled: 01 22 00.00 10 Amd0001.pdf

2. Delete 02 13 90 SITE PREPARATION Add revised 02 13 90 SITE PREPARATION Change: See revised paragraph 3.2 COFFERDAMS See attached file titled: 02 13 90 Amd0001.pdf

3. Delete TAINTER GATES AND ANCHORAGES

Add revised 35 20 16.46 TAINTER GATES AND ANCHORAGES Change: revised section reference of 05 50 15 CIVIL WORKS FABRICATIONS to 05 59 20

FABRICATION OF HYDRAULIC STEEL STRUCTURES

See attached file titled: 35 20 16.46 Amd0001.pdf

[End of changes to Specifications]

D. CHANGES TO PLANS

The revised plans are provided with this amendment at beta.SAM.gov in the file named “Amendment 0001 revised plans and drawings.” The following is a summary of changes made by this amendment:

1. Delete sheet GI001, Add revised sheet GI001

2. Delete sheet V-100, Add revised sheet V-100

3. Delete sheet SS502, Add revised sheet SS502

4. Delete sheet SB302, Add revised sheet SB302

5. Delete sheet SS512, Add revised sheet SS512

6. Add sheet SD311

7. Add sheet SD312

8. Add sheet SD313

9. Add sheet SD314

10. Add sheet SB311

11. Add sheet SB312

12. Add sheet SB313

13. Add sheet SB314

14. Delete sheet SC511, Add revised sheet SC511

15. Delete sheet M-500, Add revised sheet M-500

16. Add various “For Reference Only” Drawings

[End of changes to Plans]

E. CONTRACTOR INQUIRIES

By this Amendment No. 0001, the Chicago District, USACE provides its responses to contractor inquiries:

Q1. Drawing V-100 note 4 refers to a drawing SE301 for Limestone Abutments Repairs, please provide the drawing.

USACE answer Q1: This is a typo. The drawing reference has been corrected and an amended drawing V-100 is issued with this amendment.

Q2. Drawing V-100 shows removal and disposal of the Steam House – what bid item is this associated with?

USACE answer Q2: Steam house removal shall be included with bid item 0009. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q3. Bid Item 9 is mixed in with the Appleton Lower Dam bid items, is this bid item for both the lower and upper sites.

USACE answer Q3: Yes.

Q4. On the lower dam, an eagles’ nest is shown on plans. The note claims the contractor will need permission to work during the Jan-Aug dates. How strict is this shut down going to be? What activities would be approved in this window?

USACE answer Q4: As stated on drawing V-101, no construction will be permitted within 660’ of the eagle’s nest if the eagles are nesting. Work outside the 660’ radius is permitted.

Q5. Can dam as-builts be supplied to help with the existing trunnion details?

USACE answer Q5: Reference drawings should have been included and are issued as part of this amendment.

Q6. In lieu of replacing the trunnion pins, can the pins be resurfaced onsite?

USACE answer Q6: No. The new pins are longer.

Q7. Can the contractor trim trees along the lock 1 access roadway? Some of the existing trees overhang the path and could scratch up and damage vehicles and equipment coming back to the lay down area.

Will temp site access be required for the walkway construction? (Does a temp power need to be set up or do Corps employees need to be able to access the contractors barge setup) USACE answer Q7: Trees may be trimmed. As long as vehicle access down the Lock access roadway and foot traffic access through the Lock and past the hydro to the dam is not impacted, there will be no need to provide "temp" access from the left abutment. Power to the dam comes from the Hydro plant side and needs to be maintained. Communications for the ICS system comes from the left abutment and does not need to be maintained during replacement of the walkway.

Q8. What extent of the existing gates needs to be painted? Is it required to deconstruct the gate and paint pieces individually, or can the gate be removed and blasted/painted while assembled. If gates need to be disassembled fully, new bolts will be required for the members, so we need to know what size bolts are required.

USACE answer Q8: It is not expected the gate would be deconstructed to blast and paint. The gates can be blasted/painted while assembled.

Q9. Is the train bridge at lock 3 operational? Assuming yes, please provide contact information for operator.

USACE answer Q9: The railroad bridge is owned and operated by the railroad. There is a number on the bridge to call for access. The USACE does not have contact information.

Q10. Is it required or preferred to start on a certain dam?

USACE answer Q10: There is no preference.

Q11. Page V-110 states “Existing Piers 1,2,3,4,5,6,7,8 &9 to be repaired (base)”. What is the repair detailing?

USACE answer Q11: Sheets SD311–SD314 and SB311–SB314 detail out the repair and are issued as part of this amendment.

Q12. How many sluiceway stoplogs are required for both Upper and Lower?

USACE answer Q12: Sheet SS502 has been amended to indicate that stoplogs for two sluiceway bays total are required to a height of 14 feet above sill.

Q13. F1/SS502 calls for galvanized steel stop logs and F1/SS512 calls for aluminum stop logs. It will be difficult to make weight requirements with galvanized steel, can aluminum be used in both cases?

USACE answer Q13: Sluiceway stoplogs must be galvanized steel. Sheet SS502 is amended to clarify that galvanized steel stoplogs are required for two sluiceway bays total (not 2 sets per dam) and only 1 lifting beam total (not 1 per dam) is required. The stoplogs and lifting beam are to be used at both dams.

Sheet SS512 is also amended to remove F1, C1, and A1.

Q14. SD301 says “limestone abutment to be repointed” can a you give a estimated quantity or show on the plans the area required.

USACE answer Q14: Limits of limestone repointing are shown on SD301. Government estimates 2,966 linear feet of re-pointing at an estimated average depth of 2.5 inches.

Q15. On the Appleton Lower Dam, will the trunnion pin housing on piers 1-5 be required?

USACE answer Q15: These gates do not have a gate arm bearing housing. If the question is referring to the trunnion yoke, the yokes do not require blasting and painting. Reference drawings of existing gates are provided with this amendment.

Q16. For AUD, CG310 can a play sheet be prepared to show the overall extent of depression repair? (Is it just behind the gates or also behind the spillways?)

USACE answer Q16: The depression area is only known to be downstream of the sluiceway.

Q17. For AUD, where should depression repair be included on the bid form?

USACE answer Q17: Depression repair, i.e., bedrock repair, shall be included with bid item 0009. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q18. For AUD, is any doweling required for the depression repair or just scale and pour?

USACE answer Q18: No doweling or reinforcement should be used.

Q19. For AUD, there is no stoplogs and stoglog guides item, where should price be included?

USACE answer Q19: Stoplogs and stoplog guides shall be under bid item 0010 Stoplogs and Stoplog Guides.

Amended SECTION 01 22 00.00 10 is included with this amendment and clarifies the bid item.

Q20. For ALD, there is not a bid item for the stoplogs, where should this price be included?

USACE answer Q20: Stoplogs and stoplog guides shall be under bid item 0010 Stoplogs and Stoplog Guides.

Amended SECTION 01 22 00.00 10 is included with this amendment and clarifies the bid item.

Q21. For ALD, there is no bid item for spall repair or injection grouting, where should the price be included?

USACE answer Q21: Spall repair or injection grouting shall be under bid item 0009 Site Work. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q22. For ALD, what are the extents of topsoil grading/removal? The whole island? From the South end to the gate fence?

USACE answer Q22: Note on V-100 has been revised and reference drawings are provided with this amendment.

Q23. For ALD, please supply reference drawings apldike15cvf101.pdf as noted on page V-100.

USACE answer Q23: Reference drawing is provided with this amendment.

Q24. Under what bid item is the cost for removal and disposal of steam house to be carried? Should bidder assume any lead paint and/or asbestos in the building?

USACE answer Q24: Steam house removal shall be included with bid item 0009. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment. The Government is unaware of any lead paint and/or asbestos present within the steam house building.

Q25. Can you provide more detail in the measurement and payment for 1.3.9.1 Site Work? Fencing to be Removed, Casson Trees, USACE answer Q25: Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q26. Can you provide deadline for questions? Could not locate in the solicitation.

USACE answer Q26: There is no deadline for questions; however, please have all questions submitted as soon as possible so that the acquisition schedule is not delayed.

Q27. Shall concrete demolition costs be carried in the bid item they are associated with? Pier replacement, Walkway installation? How about Step removal shown on sheet SD302? Under what bid item should those costs be covered? Same question for replacement of stairs shown on drawing SB302.

USACE answer Q27: Concrete demolition of piers shall be under bid items 0008 ALD Pier Repair and 0015 AUD Pier Repair. Amended SECTION 01 22 00.00 10 is included with this amendment and clarifies the bid item.

Q28. Under what bid item should Crack/Joint Injection shown on SB303 be performed? Is there an estimated quantity in LF and/or gallons for this work to be performed? Under what bid item should concrete surface repairs be performed as shown on drawing SB501? The detail provided (A8) is not to scale. Can you supply estimated volume or area for these types of repairs?

USACE answer Q28: Crack/Joint Injection and concrete surface repairs shall be included under bid items 0008 ALD Pier Repair and 0015 AUD Pier Repair. Amended SECTION 01 22 00.00 10 is included with this amendment and clarifies the bid item. Cracks and spall repairs shown on plans are a close approximation of required repairs. For the crack/joint repair the Government estimates approximately 20 cubic feet for Appleton lower dam and 20 cubic feet for Appleton upper dam. For the concrete surface repairs the Government estimates approximately 67 cubic feet for Appleton lower dam and 90 cubic feet for Appleton upper dam.

Q29. Under what bid item should concrete depression repairs be performed as shown on drawing CG310? A detail (A4) is provided on CG310 and we can find plan view of location on sheet V-110 but that drawing is not to scale so we do not have a length of repair in order to estimate quantity of concrete needed. Can you supply estimated volume or area for these types of repairs?

USACE answer Q29: Depression repair, i.e., bedrock repair, shall be included with bid item 0009 Site Work.

Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment. The estimated volume is 100 CYD. A revised CG310 to include this estimate will be provided via a future solicitation amendment.

Q30. Is bid item 0006 and 0013 for the “Embedded Side Seal Plates” to be inclusive of the gate Sill Plates? Are there existing sill plate currently installed?

USACE answer Q30: No, the gate sill plates shall be included under bid item 0009 Site Work. Please see paragraph

1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment. There is currently a steel channel toed down serving as a sill plate. Reference drawings are provided with this amendment.

Q31. Will stop logs be supplied by USACE for installation into bulkhead slots?

USACE answer Q31: No. Stoplogs shall be as shown on drawing SS502.

Q 32. Can you supply estimated weights of existing gates to be removed?

USACE answer Q32: Each Tainter gate weighs between 18,000 and 19,000 pounds according to the attached reference drawings. i.e., see pages 20 and 35 of the revised drawings file.

Q33. Spec section 35 20 16.46 Pg.3 (2.1.1 Metals) references section 05 50 15 Civil Works Fabrications for material requirements. Please supply this spec section if applicable to this solicitation.

USACE answer Q33: There are several references to 05 50 15 Civil Works Fabrications in this spec section. They should all be 05 59 20 FABRICATION OF HYDRAULIC STEEL STRUCTURES. Please see revised Section 35 20 16.46 provided with this amendment.

Q34. Drawing SS502 Section C1 calls for “Galvanized Steel Stoplog”. The notes on this drawing reference Spec Section 35 20 15, this spec section applies to FRP Stoplogs and calls for stoplogs to be FRP material. Please clarify.

USACE answer Q34: Sluiceway stoplogs shall be galvanized steel. Spillway stoplogs shall be FRP. Section 35 20 15 will be revised and provided via future amendment to the solicitation.

Q35. Drawing SS512 Section C1 calls for “Aluminum Stoplog”. The notes on this drawing reference Spec Section 35 20 15, this spec section applies to FRP Stoplogs and calls for stoplogs to be FRP material. This drawing also contradicts drawing SS502. Please clarify stoplog requirements.

USACE answer Q35: Sheet SS512 is amended to remove F1, C1, and A1. Section 35 20 15 will be revised and provided via future amendment to the solicitation. Drawing SS502 is amended to clarify that galvanized steel stoplogs are required for two sluiceway bays. In short, sluiceway stoplogs shall be galvanized steel, and spillway stoplogs shall be FRP.

Q36. Item No. 0010 of the Solicitation specifies “Fabricate and Install Stoplogs and Guides at ALD Spillway”, and referencing Sheet SS502, A7 these appear to be composite stoplogs—is this the entirety of the Stoplog/Guides required? There are other references to Stoplogs being replaced and of varying composition—see page 2 of 53 General Notes, 1.: “Removal of approximately 50 feet of 3-foot high flashboards at each dam and replacement with composite stoplogs”. Also, Sheet SS502 shows Galvanized Steel Stoplogs in view F1 and C1; And, Sheet SS512 shows Aluminum Stoplogs in view F1 and C1. Please verify total number of, composition of, and location of Stoplogs and Guides required.

USACE answer Q36: SLUICEWAY: Two sets of galvanized stoplogs and one lifting beam. Each set of stoplogs shall be 14’ high above sill. This is the total number of sluiceway stoplogs and lifting beam for the project.

SPILLWAY: 1 set of FRP stoplogs in the leftmost spillway bay at EACH site. SS502 and SS512 are amended and provided with this amendment.

Q37. Drawing SD300 Detail E1 shows existing utility conduits running under the spillway walkway sections. Can you tell us if these conduits are power and/or control? Can they be taken out of service during the removal and installation of the new walkways? Are they carrying something other than powering something other than power for walkway lights?

USACE answer Q37: Three-phase power and communication lines for the remote system run from the right abutment to the hoist house. The three-phase power will need to be maintained for the duration of the project. It would be acceptable for the communication lines to be down but not the power. The specifications will be revised to include this information and will be provided via amendment to the solicitation.

Q38. What is the “Hub” material to be? The “Hub” is shown on drawing SC511 View C1 “Strut Plate Section”.

USACE answer Q38: The hub material is to be forged steel in accordance with ASTM A668 Cl. J

Q39. Can Access & Work and Storage Area shown on Drawing RR100 be used for material storage and work area access from 1 January to 1 August (Eagle Nest Restriction) USACE answer Q39: As indicated on Sheet V-101, no construction will be permitted within 660 feet of the eagles’ nest if the eagles are nesting. This would include the use of construction machinery within the work and storage area.

Q40. Drawing SS512 Detail C1 shows aluminum stop logs. However, Note 5 on that drawing states stoplogs should be furnished in accordance with 35 20 15. Spec Section 35 20 15 seems to indicate stop logs should be a Fiber Reinforced Polymer material. Please confirm which material should be used.

USACE answer Q40: Please see the answers to questions 34 and 35.

Q41. Can USACE provide the approximate weights of the existing Tainter gates and associated components?

USACE answer Q41: Please see the answer provided at question 32.

Q42. Will USACE provide a bid deadline extension of 1 week? Potential coating subcontractors are having difficulties and delays pricing this work due the large volume of work being solicited at this time.

USACE answer Q42: The bid opening is extended to 14 September 2020, with bids required by 1:00 p.m. CDT;

please refer to page 1 of this amendment.

Q43. Lower Dam

a. There is a note on sheet V-100 existing piers 1-9 to be repaired. I see details for crack repair, spalling etc. at piers 2, 3, 5, 6 and 9. Are there any other repairs? Also what bid item does this work go under?

USACE answer Q43a: Sheets SD311–SD314 and SB311–SB314 detail out the repair and are included with this amendment. Concrete demolition of piers shall be under bid items 0008 ALD Pier Repair and 0015 AUD Pier Repair. Amended SECTION 01 22 00.00 10 is included with this amendment and clarifies the bid items.

b. Where should the costs for steam house demolition go? There is no bid item for this, should we include with the site work item?

USACE answer Q43b: Steam house removal shall be included with bid item 0009. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

c. Where should the costs for west fence removal and replacement go? Include with site work item?

USACE answer Q43c: Fence removal and replacement shall be included with bid item 0009. Please see paragraph

1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

d. There is no bid item for limestone abutments / wall to be repaired, repointed.

USACE answer Q43d: Limestone abutment/wall repair/repointing shall be included with bid item 0009. Please see paragraph 1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q44. Upper Dam

a. Bid item 13 is described as ALD: embedded side seal plates. Should this be AUD?

USACE answer Q44a: Section 00 10 00 is revised by this amendment. Bid Item 0013 is for AUD rather than ALD.

b. There is a note on V-110 to remove flashboards and replace with stoplogs at the western most bay only. No bid item for this at the upper dam. There is one for stoplogs at the lower dam (item 10).

USACE answer Q44b: Stoplogs and stoplog guides shall be under bid item 0010 Stoplogs and Stoplog Guides.

Amended Sections 00 10 00 and 01 22 00.00 10 are included with this amendment and clarify the bid items.

c. There is a note and detail on CG310 to repair existing bedrock depressions. There is no bid item for this. Also is there an anticipated quantity?

USACE answer Q44c: Please see the answer to question 29.

Q45. In the solicitation file on page 6 bid item 0007 (ALD: Replace Spillway Walkways) is listed as a quantity of 5, but SS100 shows dimensions for 6 spans. Should the bid item 0007 quantity be 6?

USACE answer Q45: Bid Items 0007 and 0014 are revised by this amendment to Job. ALD will have 5 spans demolished and 6 spans constructed.

Q46. Should sill plates per A1/SC510 be included under bid items #0004 and #0011, or #0006 and #0013 USACE answer Q46: No, the gate sill plates shall be included under bid item 0009 Site Work. Please see paragraph

1.3.9 of revised SECTION 01 22 00.00 10 included with this amendment.

Q47. According to A1/M-500 the bearing ID needs to be 6.094 to match the trunnion pin. The OD of the bearing will end up about 7.5”. That isn’t a problem if the hub is 1’-6” dia. like shown on A1/M-500. However on page SC511, details E1 and C1 show the hub to be only 8” dia. Which drawing is correct? If 8” dia is correct you’d only have ¼” of steel housing your bearing.

USACE answer Q47: By this amendment the hub diameter is changed to 1’. See revised drawings M-500 and SC511 provided with this amendment.

Q48. On detail A1/M-500, it is drawn as if there are two bearings, Is this detail correct or is there only one bearing?

USACE answer Q48: There are two bearings. This was done in order to alleviate edge loading of the bearing in accordance with an industry-leading greaseless bearing manufacturer's recommendations.

Q49. Is the use of Sub-Harmonic Vibratory Stress Relief acceptable on the fabrication work?

USACE answer Q49: No, there is no ASTM or Standard currently available for this process to prove its effectiveness.

Q50. Sluiceway Stoplogs: Detail F1/SS502 calls for galvanized steel stoplogs, while detail F1/SS512 calls for aluminum stoplogs. Section 35 20 14 implies galvanized steel stoplogs. Please clarify.

USACE answer Q50: Please see the answers to questions 34 and 35.

Q51. Sluiceway Stoplogs: Detail C1/SS502 calls for a new stainless-steel sill plate, but no anchorage details. Please provide detail for this condition. Would this plate be installed at each bay?

USACE answer Q51: The sill anchorage is shown in detail A1/SC510 and sill plates are required in every sluiceway bay.

Q52. Sluiceway Stoplogs: Please provide the number of bays that the sluiceway stoplogs will be required.

USACE answer Q52: Stoplogs will be required for two sluiceway bays. Please see the answer for question 13.

Q53. High-Security Chain Link Fences and Gates: Section 32 31 13.53 indicates that the new fence will be an ornamental style. Please verify if the attached picture is what expected.

[Please see photo attached to this amendment.] USACE answer Q53: Yes.

Q54. Sluiceway Stoplogs: Are sluiceway stoplogs required for this project? Or could other methods be used to dewater bays during construction?

USACE answer Q54: Stoplogs will be required for two sluiceway bays.

Q55. Steel Structures: Is lead paint to be expected on existing Tainter gates and walkways?

USACE answer Q55: The Government is unaware of the gates and walkways having any lead based paint. The Contractor can sample the coating system to better understand its composition.

Q56. Is there a specific Bid Bond form that the USACE prefers?

USACE answer Q56. The bidder shall use Standard Form 24 (per the Federal Acquisition Regulation 28-106-1(a) Bonds and bond-related forms). You may obtain a copy by visiting https://www.gsa.gov/forms-library/bid-bond (the current version is 08/2016).

Q57. Spec section 02 13 90 part 3.2 (page 144 of pdf) states cofferdams shall be designed and constructed to elevation of 591.0. Plans show elevation at lower dam bottom of the sluiceway at 698.48, upper dam bottom of sluiceway at 724.07. There appears to be an error with this 591 elevation, please clarify.

USACE answer Q57: By this amendment, the Government has revised Section 02 13 90 to remove the required elevation from paragraph 3.2.

Q58. What is the existing coating on the gates to be sandblasted and repainted? Are we to assume they are lead paint? Or will that be covered as a change during the construction process?

USACE answer Q58: The Government is unaware of the gates having any lead based paint and the existing coating system is unknown. The Contractor can sample the coating system to better understand its composition.

Q59. Spillway Stoplogs: Sheet E1/S-110 indicates new FRP stoplogs between the left abutment and pier #17. What is the bid line item for this work?

USACE answer Q59: Stoplogs and stoplog guides shall be under bid item 0010 Stoplogs and Stoplog Guides. An amendment is forthcoming to clarify the bid item description in SECTION 01 22 00.00 10.

Q60. Bedrock Depression: Sheet CG310 depicts the bedrock depression repair for the Appleton Upper Dam. Please provide a quantity for the bedrock repair. Additionally, which bid item will the bedrock depression be under?

USACE answer Q60: Please see the answer to question 29.

[End of inquiries section] https://www.gsa.gov/forms-library/bid-bond

Question 53 Photo

W912P6-20-B-0007-0001
fence picture question 53

File details come from the government source that posted it. Updated .