W912P6-20-B-0005-0001.pdf

PDF 227 KB Posted

Attached to
SHEBOYGAN, WI, BREAKWATER REPAIR (PHASE 2), USACE CHICAGO DISTRICT ACQUISITION
Solicitation number
W912P6-20-B-0005
Issued by

About this file

This solicitation package seeks bids for the Sheboygan, Wisconsin Breakwater Repair Phase 2 construction project. The project consists of demolishing and replacing 400 feet of breakwater with a rubble mound and pier supported walkway, and encasing another 700 feet of breakwater with sheet pile tied into the existing revetment. The estimated cost is between $1-5 million. The North American Industry Classification System code is 237990 and the small business size standard is $39.5 million. The solicitation is reserved exclusively for HUBZone small businesses. Bids are due by 2:00 pm CDT on September 21, 2020 and must be submitted through the System for Award Management. The point of contact is Patricia Woodhouse at the U.S. Army Corps of Engineers Chicago District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6600999939

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

REFERENCE SOLICITATION NUMBER W912P6-20-B-0005

The referenced Solicitation is NOT EXTENDED by this Amendment. Therefore, responses to this Solicitation shall be furnished no later than 2:00 p.m. (CDT) on 21 September 2020. Details regarding bid submission are contained at Section 00 21 13 of the solicitation document. The amendment particulars follow on the next pages, w herein including updated w age determination; a correction to block 11 of the soclitation document; a revised draw ing; and responses to contractors' questions.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Sep-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P620B0005

X 9B. DATED (SEE ITEM 11)

19-Aug-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Sep-2020

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P620B0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

AMENDMENT PARTICULARS

A. CHANGES TO SOLICITATION

1. Page 1, block 11, is revised to the following:

“The Contractor shall begin performance within 10 calendar days and complete it within 1,156 calendar days after receiving notice to proceed. This performance period is mandatory.”

2. Updated Wage Determination WI20200015 dated 11 September 2020 is provided by this Amendment 0001.

B. CHANGES TO PLANS

The revised plans are provided with this amendment at beta.SAM.gov in the file named “Amendment 0001 revised plans and drawings.” The following is a summary of changes made by this amendment:

1. Delete sheet S-101, add revised sheet S-101.

B. CONTRACTOR INQUIRIES

By this Amendment 0001, the Chicago District, USACE provides its responses to contractor inquiries:

Q1. What Bid Item does the cost to construct the closure at STA 13+53 go?

USACE answer Q1: The closure at Sta. 13+53 is part of the line item listed in Option 2 of the rubblemound construction.

Q2. How long are the sheets to be for the closure at STA 13+53?

USACE answer Q2: The sheeting length shall be the same as the original Phase 1 design and extend to EL. - 28 ft. Please see revised sheet S-101 provided by this amendment.

Q3. What Bid Item does the cost associated with the demolition of the existing structure to facilitate the closure at STA 13+53 & STA 17+32 go?

USACE answer Q3: For the closure at STA 13+53, this shall be assigned to the line item for the Option 2 rubblemound construction. For the closure at STA 17+32, this shall be assigned to the line item for the Option 1 rubblemound construction.

Q4. Sheet CD-301, details F1 & E5 indicate the existing structure is to be demolished to EL. 3.5, however the tie rods are far above that at EL. 5.00. Can partial demolition of the existing structure be done to facilitate tie rod installation and allow for +-3” clear around the tie rods as done previously in PH1? Removal of the existing structure to EL. 3.5 after sheeting has been install has proven to be very time consuming/costly as the existing structure removal cannot take place until the sheeting has been installed, thus leaving only +-3’ from the unbraced sheeting to the existing structure.

USACE answer Q4: No alternatives are permitted. The bidder shall bid the project as specified to be considered “responsive’ to the IFB requirements; any bid that provides otherwise will be rendered nonresponsive. Any successful contractor is welcome to submit a Value Engineering proposal via invoking FAR 52.248-3 (VE Construction) located in Section 00 70 00 of the solicitation and planned resulting contract.

Q5. The Existing Site Section A1, F1 & E5 on Sheet V-301 indicate the existing armor stone on the lakeside to be 200-2000 LB, however in PH1 the armor stones were over 12 ton in size and extended to EL. -12.00 LWD not EL. 0.00 as indicated on the above-mentioned details. Please advise if the existing conditions have changed from what was encountered in PH1 or if the above-mentioned conditions remain. Note – Detail E5 & B1 on Sheet S-301 is a more correct depiction of the existing conditions nut still does not show the armor stone at the correct size or depth.

USACE answer Q5: Refer to the Notes on Sheets V-101, V-102 and V-301 as well as Specification 05 41 10 – Metal Sheet Piling. It has been made clear that the plan views and cross sections shown on the Plan Sheets

W912P620B0005 provide a general representation of the existing site conditions and that variations between what is shown on the Plan Sheets and what is to be encountered in the field should be expected. Furthermore, the notes also indicate that elevations and dimensions shown should be considered approximate and are subject to Contractor verification. Lastly, an additional note including verbiage within Specification 05 41 10 has made it clear that the Contractor is responsible for the clearing of all SSP drivelines during performance of the Work and that the depth of the stone varies along the length of the project. Based on this information, it is the Contractor’s responsibility to perform a sufficient amount of due diligence to investigate the amount of stone present on each side of the breakwater (including verification of the site conditions) in the field prior to bid submission.

Q6. What Bid Item should the costs associated with the existing structure demolition: loading to barge, unloading onto trucks and disposal to facilitate rubble mound construction from STA 17+32 to STA 13+53 go?

USACE answer Q6: These costs should be assigned to the rubblemound line item in Options 1 and 2 and is based on stationing.

Q7. What Bid Item should the costs associated with the slab support & concrete slab over the rubble mound structure go?

USACE answer Q7: These costs should be assigned to the rubblemound line item in Options 1 and 2 and is based on stationing.

Q8. During demolition of the existing structure as required to facilitate rubble mound construction, a large amount of lakebed will need to be excavated to reach the elevations as indicated on detail E6, Sheet S-301 (digging down to EL-7.0 LWD). Where should this large amount (+-4,500 CY) of spoil be placed?

USACE answer Q8: The spoils will be mixed with breakwater debris and as such, are considered part of the demolition activities. See the demolition spec for further information regarding disposal of the breakwater material generated during the construction activities.

Q9. Detail B5 on sheet CD-301 shows the existing scour stone on the channel side to be used as part of the new scour stone construction. This will require removal and placement onto a material scow, unloading and placement into an area that requires new scour stone. How will this work be paid for? By draft readings from the material scow or is this work ancillary to rubble mound construction and not be paid for under a Scour Stone Bid item?

USACE answer Q9: Note that the means and methods described above in Question 9 are not necessarily requirements of the Contract. Existing scour stone reused during performance of the Work would be accounted for under the rubblemound construction line item in Option 1.

Q10. Detail B5 on sheet CD-301 shows the existing armor stone on the lake side to be used as part of the rubble mound construction. This will require removal and placement onto a material scow, unloading onto land, reloading onto a material scow and placement into an area that requires new armor stone. How will this work be paid for? By draft readings from the material scow or is this work ancillary to rubble mound construction and not be paid for under a Armor Stone Bid item?

USACE answer Q10: Note that the means and methods described above in Question 10 are not necessarily requirements of the Contract. Existing scour stone reused during performance of the Work would be accounted for under the rubblemound construction line item in Option 1.

Q11. Detail B6 on Sheet S-301 indicates the 12” DIA., 0.5 IN thick concrete filled pipe piles need to be driven to a required tip elevation of EL. -43.00. Based on the existing conditions, this will require the use of a large impact hammer to ensure the tip elevation is met. Is there an allowable capacity requirement that if met and indicated through PDA testing, the tip elevation requirement of EL. -43.00 will be waived?

USACE answer Q11: It is recommended that the Contractor perform a sufficient amount of due diligence (i.e., such as a WEAP analysis) to size the hammer to be used for the project based on the soil conditions provided in the Specifications in order to land the piling to the required tip elevation as shown on the Project Drawings without damage or overstressing of the piling. The ultimate capacity required per pile is 100 kips.

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

"General Decision Number: WI20200015 09/11/2020

Superseded General Decision Number: WI20190015

State: Wisconsin

Construction Type: Heavy

Counties: Wisconsin Statewide.

HEAVY CONSTRUCTION PROJECTS (Excluding Tunnel, Sewer, and Water Lines).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020 1 01/24/2020 2 02/28/2020 3 03/06/2020 4 06/05/2020 5 06/12/2020 6 06/19/2020 7 07/03/2020 8 07/17/2020 9 07/24/2020 10 08/28/2020 11 09/11/2020 file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

BOIL0107-001 01/01/2017

Rates Fringes

BOILERMAKER

Boilermaker.................$ 35.65 29.89 Small Boiler Repair (under 25,000 lbs/hr)..............$ 26.91 16.00

BRWI0001-002 06/03/2019

CRAWFORD, JACKSON, JUNEAU, LA CROSSE, MONROE, TREMPEALEAU, AND

VERNON COUNTIES

Rates Fringes

BRICKLAYER.......................$ 33.80 24.28

BRWI0002-002 06/01/2019

ASHLAND, BAYFIELD, DOUGLAS, AND IRON COUNTIES

Rates Fringes

BRICKLAYER.......................$ 39.94 23.30

BRWI0002-005 06/01/2019

ADAMS, ASHLAND, BARRON, BROWN, BURNETT, CALUMET, CHIPPEWA,

CLARK, COLUMBIA, DODGE, DOOR, DUNN, FLORENCE, FOND DU LAC,

FOREST, GREEN LAKE, IRON, JEFFERSON, KEWAUNEE, LANGLADE,

LINCOLN, MANITOWOC, MARATHON, MARINETTE, MARQUETTE, MENOMINEE,

OCONTO, ONEIDA, OUTAGAMIE, POLK, PORTAGE, RUSK, ST CROIX, SAUK,

SHAWANO, SHEBOYGAN, TAYLOR, VILAS, WALWORTH, WAUPACA, WAUSHARA,

WINNEBAGO, AND WOOD COUNTIES

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 35.51 23.37

BRWI0003-002 06/03/2019

BROWN, DOOR, FLORENCE, KEWAUNEE, MARINETTE, AND OCONTO COUNTIES

Rates Fringes

BRICKLAYER.......................$ 34.18 23.90

BRWI0004-002 06/01/2019

KENOSHA, RACINE, AND WALWORTH COUNTIES

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Rates Fringes

BRICKLAYER.......................$ 38.43 25.10

BRWI0006-002 06/01/2019

ADAMS, CLARK, FOREST, LANGLADE, LINCOLN, MARATHON, MENOMINEE,

ONEIDA, PORTAGE, PRICE, TAYLOR, VILAS AND WOOD COUNTIES

Rates Fringes

BRICKLAYER.......................$ 35.06 23.02

BRWI0007-002 06/03/2019

GREEN, LAFAYETTE, AND ROCK COUNTIES

Rates Fringes

BRICKLAYER.......................$ 35.57 24.22

BRWI0008-002 06/01/2019

MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

BRICKLAYER.......................$ 38.93 24.22

BRWI0009-001 06/03/2019

GREEN LAKE, MARQUETTE, OUTAGAMIE, SHAWANO, WAUPACA, WASHARA,

AND WINNEBAGO COUNTIES

Rates Fringes

BRICKLAYER.......................$ 34.18 23.90

BRWI0011-002 06/03/2019

CALUMET, FOND DU LAC, MANITOWOC, AND SHEBOYGAN COUNTIES

Rates Fringes

BRICKLAYER.......................$ 34.18 23.90

BRWI0013-002 06/03/2019

DANE, GRANT, IOWA, AND RICHLAND COUNTIES

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

BRICKLAYER.......................$ 35.56 24.23

BRWI0019-002 06/03/2019

BARRON, BUFFALO, BURNETT, CHIPPEWA, DUNN, EAU CLAIRE, PEPIN,

PIERCE, POLK, RUSK, ST. CROIX, SAWYER AND WASHBURN COUNTIES

Rates Fringes

BRICKLAYER.......................$ 33.40 24.68

BRWI0021-002 06/03/2019

DODGE AND JEFFERSON COUNTIES

Rates Fringes

BRICKLAYER.......................$ 35.75 24.02

BRWI0034-002 06/03/2019

COLUMBIA AND SAUK COUNTIES

Rates Fringes

BRICKLAYER.......................$ 35.56 24.23

CARP0087-001 05/01/2016

BURNETT (W. of Hwy 48), PIERCE (W. of Hwy 29), POLK (W. of Hwys 35, 48 & 65), AND ST. CROIX (W. of Hwy 65) COUNTIES

Rates Fringes

Carpenter & Piledrivermen........$ 36.85 18.39

CARP0252-002 06/01/2016

ADAMS, BARRON, BAYFIELD (Eastern 2/3), BROWN, BUFFALO, BURNETT (E. of Hwy 48), CALUMET, CHIPPEWA, CLARK, COLUMBIA, CRAWFORD, DANE, DODGE, DOOR, DUNN, EAU CLAIRE, FLORENCE (except area bordering Michigan State Line), FOND DU LAC, FOREST, GRANT, GREEN, GREEN LAKE, IOWA, IRON, JACKSON, JEFFERSON, JUNEAU, KEWAUNEE, LA CROSSE, LAFAYETTE, LANGLADE, LINCOLN, MANITOWOC, MARATHON, MARINETTE (except N.E. corner), MARQUETTE, MENOMINEE, MONROE, OCONTO, ONEIDA, OUTAGAMIE, PEPIN, PIERCE (E.

of Hwys 29 & 65), POLK (E. of Hwys 35, 48 & 65), PORTAGE, PRICE, RICHLAND, ROCK, RUSK, SAUK, SAWYER, SHAWANO, SHEBOYGAN, ST CROIX (E. of Hwy 65), TAYLOR, TREMPEALEAU, VERNON, VILAS, WALWORTH, WASHBURN, WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD

COUNTIES

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

CARPENTER

CARPENTER...................$ 33.56 18.00

MILLWRIGHT..................$ 35.08 18.35

PILEDRIVER..................$ 34.12 18.00

CARP0252-010 06/01/2016

ASHLAND COUNTY

Rates Fringes

Carpenters Carpenter...................$ 33.56 18.00 Millwright..................$ 35.08 18.35 Pile Driver.................$ 34.12 18.00

CARP0264-003 06/01/2016

KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WAUKESHA, AND WASHINGTON

COUNTIES

Rates Fringes

CARPENTER........................$ 35.78 22.11

CARP0361-004 05/01/2018

BAYFIELD (West of Hwy 63) AND DOUGLAS COUNTIES

Rates Fringes

CARPENTER........................$ 36.15 20.43

CARP2337-001 06/01/2016

ZONE A: MILWAUKEE, OZAUKEE, WAUKESHA AND WASHINGTON

ZONE B: KENOSHA & RACINE

Rates Fringes

PILEDRIVERMAN

Zone A......................$ 31.03 22.69 Zone B......................$ 31.03 22.69

CARP2337-003 06/01/2019

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

MILLWRIGHT

Zone A......................$ 33.58 21.53 Zone B......................$ 33.58 21.53

ZONE DEFINITIONS

ZONE A: MILWAUKEE, OZAUKEE, WAUKESHA AND WASHINGTON COUNTIES

ZONE B: KENOSHA & RACINE COUNTIES

ELEC0014-002 06/14/2020

ASHLAND, BARRON, BAYFIELD, BUFFALO, BURNETT, CHIPPEWA, CLARK

(except Maryville, Colby, Unity, Sherman, Fremont, Lynn & Sherwood), CRAWFORD, DUNN, EAU CLAIRE, GRANT, IRON, JACKSON, LA

CROSSE, MONROE, PEPIN, PIERCE, POLK, PRICE, RICHLAND, RUSK, ST

CROIX, SAWYER, TAYLOR, TREMPEALEAU, VERNON, AND WASHBURN

COUNTIES

Rates Fringes

Electricians:....................$ 35.98 20.98

ELEC0014-007 07/05/2020

REMAINING COUNTIES

Rates Fringes

Teledata System Installer Installer/Technician........$ 27.75 15.14

Low voltage construction, installation, maintenance and removal of teledata facilities (voice, data, and video) including outside plant, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX, fiber optic cable and equipment, micro waves, V-SAT, bypass, CATV, WAN (wide area networks), LAN (local area networks), and ISDN (integrated systems digital network).

ELEC0127-002 06/01/2020

KENOSHA COUNTY

Rates Fringes

Electricians:....................$ 41.62 30%+12.70

ELEC0158-002 06/03/2019

BROWN, DOOR, KEWAUNEE, MANITOWOC (except Schleswig), file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

MARINETTE(Wausuakee and area South thereof), OCONTO, MENOMINEE (East of a ine 6 miles West of the West boundary of Oconto County), SHAWANO (Except Area North of Townships of Aniwa and Hutchins) COUNTIES

Rates Fringes

Electricians:....................$ 33.52 29.75%+10.26

ELEC0159-003 06/01/2019

COLUMBIA, DANE, DODGE (Area West of Hwy 26, except Chester and Emmet Townships), GREEN, LAKE (except Townships of Berlin, Seneca, and St. Marie), IOWA, MARQUETTE (except Townships of Neshkoka, Crystal Lake, Newton, and Springfield), and SAUK

COUNTIES

Rates Fringes

Electricians:....................$ 40.30 22.24

* ELEC0219-004 06/01/2019

FLORENCE COUNTY (Townships of Aurora, Commonwealth, Fern, Florence and Homestead) AND MARINETTE COUNTY (Township of Niagara)

Rates Fringes

Electricians:

Electrical contracts over $180,000....................$ 33.94 21.80 Electrical contracts under $180,000....................$ 31.75 21.73

ELEC0242-005 05/31/2020

DOUGLAS COUNTY

Rates Fringes

Electricians:....................$ 39.77 70.69%

ELEC0388-002 06/01/2020

ADAMS, CLARK (Colby, Freemont, Lynn, Mayville, Sherman, Sherwood, Unity), FOREST, JUNEAU, LANGLADE, LINCOLN, MARATHON, MARINETTE (Beecher, Dunbar, Goodman & Pembine), MENOMINEE (Area West of a line 6 miles West of the West boundary of Oconto County), ONEIDA, PORTAGE, SHAWANO (Aniwa and Hutchins), VILAS

AND WOOD COUNTIES

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Electricians:....................$ 34.85 26%+11.20

ELEC0430-002 06/01/2020

RACINE COUNTY (Except Burlington Township)

Rates Fringes

Electricians:....................$ 41.86 22.66

ELEC0494-005 06/01/2020

MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

Electricians:....................$ 42.84 25.54

ELEC0494-006 06/01/2020

CALUMET (Township of New Holstein), DODGE (East of Hwy 26 including Chester Township), FOND DU LAC, MANITOWOC (Schleswig), and SHEBOYGAN COUNTIES

Rates Fringes

Electricians:....................$ 36.32 22.51

ELEC0494-013 06/07/2020

DODGE (East of Hwy 26 including Chester Twp, excluding Emmet Twp), FOND DU LAC (Except Waupuin), MILWAUKEE, OZAUKEE, MANITOWOC (Schleswig), WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

Sound & Communications Installer...................$ 21.46 18.52 Technician..................$ 31.34 20.00

Installation, testing, maintenance, operation and servicing of all sound, intercom, telephone interconnect, closed circuit TV systems, radio systems, background music systems, language laboratories, electronic carillion, antenna distribution systems, clock and program systems and low-voltage systems such as visual nurse call, audio/visual nurse call systems, doctors entrance register systems.

Includes all wire and cable carrying audio, visual, data, file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12] light and radio frequency signals. Includes the installation of conduit, wiremold, or raceways in existing structures that have been occupied for six months or more where required for the protection of the wire or cable, but does not mean a complete conduit or raceway system. work covered does not include the installation of conduit, wiremold or any raceways in any new construction, or the installation of power supply outlets by means of which external electric power is supplied to any of the foregoing equipment or products

ELEC0577-003 06/01/2019

CALUMET (except Township of New Holstein), GREEN LAKE (N. part including Townships of Berlin, St Marie, and Seneca), MARQUETTE (N. part including Townships of Crystal Lake, Neshkoro, Newton, and Springfield), OUTAGAMIE, WAUPACA, WAUSHARA, AND WINNEBAGO

COUNTIES

Rates Fringes

Electricians:....................$ 33.15 28.50%+10.00

ELEC0890-003 06/01/2020

DODGE (Emmet Township only), GREEN, JEFFERSON, LAFAYETTE, RACINE (Burlington Township), ROCK AND WALWORTH COUNTIES

Rates Fringes

Electricians:....................$ 37.41 25.95%+11.11

ELEC0953-001 06/02/2019

Rates Fringes

Line Construction:

(1) Lineman.................$ 47.53 21.43

(2) Heavy Equipment Operator....................$ 42.78 19.80

(3) Equipment Operator......$ 38.02 18.40

(4) Heavy Groundman Driver..$ 33.27 16.88

(5) Light Groundman Driver..$ 30.89 16.11

(6) Groundsman..............$ 26.14 14.60

ENGI0139-001 06/01/2020

KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WASHINGTON, AND WAUKESHA

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Power Equipment Operator Group 1.....................$ 47.66 23.15 Group 2.....................$ 47.16 23.15 Group 3.....................$ 46.66 23.15 Group 4.....................$ 45.97 23.15 Group 5.....................$ 42.39 23.15 Group 6.....................$ 37.24 23.15

HAZARDOUS WASTE PREMIUMS:

EPA Level ""A"" Protection: $3.00 per hour EPA Level ""B"" Protection: $2.00 per hour EPA Level ""C"" Protection: $1.00 per hour

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with or w/o attachments with a lifting capacity of over 100 tons; or Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with boom, leads, and/or jib lengths measuring 176 feet or longer; Self-Erecting Tower Cranes over 4000 lbs lifting capacity; All Cranes with Boom Dollies; Boring Machines (directional); Master Mechanic.

$0.50 additional per hour per 100 tons or 100 ft of boom over 200 ft or lifting capacity of crane over 200 tons to a maximum of 300 tons or 300 ft. Thereafter an increase of $0.01 per ft or ton, whichever is greater.

GROUP 2: Cranes, Tower Cranes, Pedestal Tower Cranes and Derricks with or without attachments with a lifting capacity of 100 tons or less; or Cranes, Tower Cranes Portable Tower Cranes, Pedestal Tower Cranes and Derricks with boom, leadsand/or jib lengths measuring 175 feet or less; Backhoes (excavators) 130,000 lbs and over; Caisson Rigs; Pile Drivers; Boring Machines (vertical or horizontal), Versi-Lift, Tri-Lift, Gantry 20,000 lbs & over.

GROUP 3: Backhoe (excavator) under 130,000 lbs;Self-erecting Tower Crane 4000 lbs & under lifting capacity;Traveling Crane (bridge type); Skid Rigs; Dredge Operator; Mechanic;

Concrete Paver (over 27E); Concrete Spreader and Distributor; Forklift/ Telehandler (machinery- moving / steel erection); Hydro Blaster, 10,000 psi and over

GROUP 4: Material Hoists; Stack Hoists; Hydraulic Backhoe (tractor or truck mounted); Hydraulic Crane, 5 tons or under (tractor or truck mounted); Hoist (tuggers 5 tons & over); Hydro-Excavators/Daylighters; Concrete Pumps Rotec type Conveyors; Tractor/Bulldozer/End Loader (over 40 hp);

Motor Patrol; Scraper Operator; Sideboom; Straddle Carrier;

Welder; Bituminous Plant and Paver Operator; Roller over 5 tons; Rail Leveling Machine (Railroad); Tie Placer; Tie Extractor; Tie Tamper; Stone Leveler; Rotary Drill Operator file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12] and Blaster; Percussion Drill Operator; Air Track Drill and/or Hammers; Gantrys (under 20,000 lbs); Tencher (wheel type or chain type having 8 inch or larger bucket); Milling Machine; Off-Road Material Haulers.

GROUP 5: Backfiller; Concrete Auto Breaker (large); Concrete Finishing Machines (road type); Rubber Tired Roller;

Concrete Batch Hopper; Concrete Conveyor Systems; Grout Pumps; Concrete Mixers (14S or over); Screw Type Pumps and Gypsum Pumps; Tractor, Bulldozer, End Loader (under 40 hp);

Trencher (chain type, bucket under 8 inch); Industrial Locomotives; Rollers under 5 tons; Stump Grinder/Chipper (Large); Timber Equipment; Firemen (pile drivers and derricks); Personnel Hoist, Telehandler over 8000 lbs;

Robotic Tool Carrier with or without attachments

GROUP 6: Tampers - Compactors (riding type); Assistant Engineer; A-Frames and Winch Trucks; Concrete Auto Breaker;

Hydrohammers (small); Brooms and Sweepers; Hoist (tuggers under 5 tons); Boats (Tug, Safety, Work Barges, Launch);

Shouldering Machine Operator; Prestress Machines; Screed Operator; Stone Crushers and Screening Plants; Screed Operators (milling machine), Farm or Industrial Tractor Mounted Equipment; Post Hole Digger; Fireman (asphalt plants); Air Compressors over 400 CFM; Generators, over 150 KW; Augers (vertical and horizontal); Air, Electric, Hydraulic Jacks (slipform); Skid Steer Loaders (with or without attachments); Boiler Operators (temporary heat);

Refrigeration Plant/Freeze Machines; Power Pack Vibratory/Ultra Sound Drivers and Extractors; Welding Machines; Heaters (mechanical); Pumps; Winches (small electric); Oiler and Greaser; Rotary Drill Tender;

Conveyor; Forklifts/Telehandler 8000 lbs & under;

Elevators: Automatic Hoists; Pumps (well points);

Combination Small Equipment Operators

ENGI0139-003 06/01/2020

REMAINING COUNTIES

Rates Fringes

Power Equipment Operator Group 1.....................$ 42.92 23.15 Group 2.....................$ 41.67 23.15 Group 3.....................$ 39.97 23.15 Group 4.....................$ 39.44 23.15 Group 5.....................$ 37.37 23.15 Group 6.....................$ 35.84 23.15

HAZARDOUS WASTE PREMIUMS:

EPA Level ""A"" Protection: $3.00 per hour EPA Level ""B"" Protection: $2.00 per hour file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

EPA Level ""C"" Protection: $1.00 per hour

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: Cranes, Tower Cranes and Derricks with or without attachments with a lifting capacity of over 100 tons;

Cranes, Tower Cranes, and Derricks with boom, leads and/or jib lengths 176 ft or longer.

GROUP 2: Backhoes (Excavators) weighing 130,00 lbs and over;

Cranes, Tower Cranes and Derricks with or without attachments with a lifting capacity of 100 tons or less;

Cranes, Tower Cranes, and Derricks with boom, leads, and/or jib lengths 175 ft or less; Caisson Rigs; Pile Driver

GROUP 3: Backhoes (Excavators) weighing under 130,000 lbs;

Travelling Crane (bridge type); Milling Machine; Concrete Paver over 27 E; Concrete Spreader and Distributor;

Concrete Laser Screed; Concrete Grinder and Planing Machine; Slipform Curb and Gutter Machine; Boring Machine (Directional); Dredge Operator; Skid Rigs; over 46 meter Concrete Pump.

GROUP 4: Hydraulic Backhoe (tractor or truck mounted);

Hydraulic Crane, 10 tons or less; Tractor, Bulldozer, or End Loader (over 40 hp); Motor Patrol; Scraper Operator;

Bituminous Plant and Paver Operator; Screed-Milling Machine; Roller over 5 tons; Concrete pumps 46 meter and under; Grout Pumps; Rotec type machine; Hydro Blaster, 10,000 psi and over; Rotary Drill Operator; Percussion Drilling Machine; Air Track Drill with or without integral hammer; Blaster; Boring Machine (vertical or horizontal);

Side Boom; Trencher, wheel type or chain type having 8 inch or larger bucket; Rail Leveling Machine (Railroad); Tie Placer; Tie Extractor; Tie Tamper; Stone Leveler; Straddle Carrier; Material Hoists; Stack Hoist; Man Hoists; Mechanic and Welder; Off Road Material Haulers.

GROUP 5: Tractor, Bulldozer, or Endloader (under 40 hp);

Tampers -Compactors, riding type; Stump Chipper, large;

Roller, Rubber Tire; Backfiller; Trencher, chain type (bucket under 8 inch); Concrete Auto Breaker, large;

Concrete Finishing Machine (road type); Concrete Batch Hopper; Concrete Conveyor Systems; Concrete Mixers, 14S or over; Pumps, Screw Type and Gypsum); Hydrohammers, small;

Brooms and Sweeeprs; Lift Slab Machine; Roller under 5 tons; Industrial Locomotives; Fireman (Pile Drivers and Derricks); Pumps (well points); Hoists, automatic; A-Frames and Winch Trucks; Hoists (tuggers); Boats (Tug, Safety, Work Barges and Launches); Assistant Engineer

GROUP 6: Shouldering Machine Operator; Farm or Industrial Tractor mounted equipment; Post Hole Digger; Auger (vertical and horizontal); Skid Steer Loader with or file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12] without attachments; Robotic Tool Carrier with or without attachments; Power Pack Vibratory/Ultra Sound Driver and Extractor; Fireman (Asphalt Plants); Screed Operator; Stone Crushers and Screening Plants; Air, Electric, Hydraulic Jacks (Slip Form); Prestress Machines; Air Compressor, 400 CFM or over; Refrigeration Plant/Freese Machine; Boiler Operators (temporary heat); Forklifts; Welding Machines;

Generators; Pumps over 3""; Heaters, Mechanical; Combination small equipment operator; Winches, small electric; Oiler;

Greaser; Rotary Drill Tender; Conveyor; Elevator Operator

IRON0008-002 06/01/2020

BROWN, CALUMET, DOOR, FOND DU LAC, KEWAUNEE, MANITOWOC,

MARINETTE, OCONTO, OUTAGAMI, SHAWANO, SHEBOYGAN, AND WINNEBAGO

COUNTIES:

Rates Fringes

IRONWORKER.......................$ 37.31 27.62

Paid Holidays: New Year's Day, Memorial Day, July 4th, Labor Day, Thanksgiving Day & Christmas Day.

IRON0008-003 06/01/2020

KENOSHA, MILWAUKEE, OZAUKEE, RACINE, WALWORTH (N.E. 2/3),

WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

IRONWORKER.......................$ 39.11 27.87

Paid Holidays: New Year's Day, Memorial Day, July 4th, Labor Day, Thanksgiving Day & Christmas Day.

IRON0383-001 06/01/2020

ADAMS, COLUMBIA, CRAWFORD, DANE, DODGE, FLORENCE, FOREST,

GRANT, GREENE, (Excluding S.E. tip), GREEN LAKE, IOWA, JEFFERSON, JUNEAU, LA CROSSE, LAFAYETTE, LANGLADE, MARATHON, MARQUETTE, MENOMINEE, MONROE, PORTAGE, RICHLAND, ROCK (Northern area, vicinity of Edgerton and Milton), SAUK, VERNON, WAUPACA, WAUSHARA, AND WOOD COUNTIES

IRONWORKER.......................$ 37.10 27.06

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

IRON0512-008 06/03/2019

BARRON, BUFFALO, CHIPPEWA, CLARK, DUNN, EAU CLAIRE, JACKSON,

PEPIN, PIERCE, POLK, RUSK, ST CROIX, TAYLOR, AND TREMPEALEAU

COUNTIES

Rates Fringes

IRONWORKER.......................$ 37.60 29.40

IRON0512-021 06/03/2019

ASHLAND, BAYFIELD, BURNETT, DOUGLAS, IRON, LINCOLN, ONEIDA,

PRICE, SAWYER, VILAS AND WASHBURN COUNTIES

Rates Fringes

IRONWORKER.......................$ 33.19 29.40

LABO0113-002 06/01/2020

MILWAUKEE AND WAUKESHA COUNTIES

Rates Fringes

LABORER

Group 1.....................$ 30.05 22.26 Group 2.....................$ 30.20 22.26 Group 3.....................$ 30.40 22.26 Group 4.....................$ 30.55 22.26 Group 5.....................$ 30.70 22.26 Group 6.....................$ 26.54 22.26

LABORERS CLASSIFICATIONS

GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;

Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;

Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;

Bituminous Worker (Dumper, Ironer, Smoother, and Tamper);

Concrete Handler

GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning Torch Laborer

GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

GROUP 4: Line and Grade Specialist

GROUP 5: Blaster and Powderman

GROUP 6: Flagperson; traffic control person

LABO0113-003 06/01/2020

OZAUKEE AND WASHINGTON COUNTIES

Rates Fringes

LABORER

Group 1.....................$ 29.30 22.26 Group 2.....................$ 29.40 22.26 Group 3.....................$ 29.45 22.26 Group 4.....................$ 29.65 22.26 Group 5.....................$ 29.50 22.26 Group 6.....................$ 26.39 22.26

LABORERS CLASSIFICATIONS

GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;

Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;

Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;

Bituminous Worker (Dumper, Ironer, Smoother, and Tamper);

Concrete Handler

GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated);

GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man

GROUP 4: Line and Grade Specialist

GROUP 5: Blaster; powderman

GROUP 6: Flagperson and Traffic Control Person

LABO0113-011 06/01/2020

KENOSHA AND RACINE COUNTIES

Rates Fringes

LABORER

Group 1.....................$ 29.11 22.26 Group 2.....................$ 29.26 22.26 file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Group 3.....................$ 29.46 22.26 Group 4.....................$ 29.43 22.26 Group 5.....................$ 29.76 22.26 Group 6.....................$ 26.25 22.26

LABORERS CLASSIFICATIONS:

GROUP 1: General laborer; Tree Trimmer; Conduit Layer;

Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;

Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;

Bituminous worker (Dumper, Ironer, Smoother, and Tamper);

Concrete Handler

GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning Torch Laborer

GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man

GROUP 4: Line and Grade Specialist

GROUP 5: Blaster and Powderman

GROUP 6: Flagman; traffic control person

LABO0140-002 06/01/2020

ADAMS, ASHLAND, BARRON, BAYFIELD, BROWN, BUFFALO, BURNETT,

CALUMET, CHIPPEWA, CLARK, COLUMBIA, CRAWFORD, DODGE, DOOR,

DOUGLAS, DUNN, EAU CLAIRE, FLORENCE, FOND DU LAC, FOREST,

GRANT, GREEN, GREEN LAKE, IRON, JACKSON, JUNEAU, IOWA,

JEFFERSON, KEWAUNEE, LA CROSSE, LAFAYETTE, LANGLADE, LINCOLN,

MANITOWOC, MARATHON, MARINETTE, MARQUETTE, MENOMINEE, MONROE,

OCONTO, ONEIDA, OUTAGAMIE, PEPIN, PIERCE, POLK, PORTAGE, PRICE,

RICHLAND, ROCK, RUSK, SAUK, SAWYER, SHAWANO, SHEBOYGAN, ST.

CROIX, TAYLOR, TREMPEALEAU, VERNON, VILLAS, WALWORTH, WASHBURN,

WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD COUNTIES

Rates Fringes

LABORER

Group 1.....................$ 33.72 17.95 Group 2.....................$ 33.82 17.95 Group 3.....................$ 33.87 17.95 Group 4.....................$ 34.07 17.95 Group 5.....................$ 33.92 17.95 Group 6.....................$ 30.35 17.95 file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

LABORER CLASSIFICATIONS

GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;

Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;

Stone Handler; Bitminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;

Bituminous Worker (Dumper, Ironer, Smoother and Tamper);

Concrete Handler

GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator, Demolition Burning Torch Laborer

GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk and Pavement); Strike Off Man

GROUP 4: Line and Grade Secialist

GROUP 5: Blaster; powderman

GROUP 6: Flagperson; Traffic Control

LABO0464-003 06/01/2020

DANE COUNTY

Rates Fringes

LABORER

Group 1.....................$ 34.00 17.95 Group 2.....................$ 34.10 17.95 Group 3.....................$ 34.15 17.95 Group 4.....................$ 34.35 17.95 Group 5.....................$ 34.20 17.95 Group 6.....................$ 30.35 17.95

LABORERS CLASSIFICATIONS:

GROUP 1: General Laborer; Tree Trimmer; Conduit Layer;

Demolition and Wrecking Laborer; Guard Rail, Fence, and Bridge Builder; Landscaper; Multiplate Culvert Assembler;

Stone Handler; Bituminous Worker (Shoveler, Loader, and Utility Man); Batch Truck Dumper or Cement Handler;

Bituminious Worker (Dumper, Ironer, Smoother, and Tamper);

Concrete Handler

GROUP 2: Air Tool Operator; Joint Sawer and Filler (Pavement); Vibrator or Tamper Operator (Mechanical Hand Operated); Chain Saw Operator; Demolition Burning Torch Laborer file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

GROUP 3: Bituminous Worker (Raker and Luteman); Formsetter (Curb, Sidewalk, and Pavement); Strike Off Man

GROUP 4: Line and Grade Specialist

GROUP 5: Blaster; Powderman

GROUP 6: Flagperson and Traffic Control Person

PAIN0106-008 05/01/2017

ASHLAND, BAYFIELD, BURNETT, AND DOUGLAS COUNTIES

Rates Fringes

Painters:

New:

Brush, Roller..............$ 30.33 17.27 Spray, Sandblast, Steel....$ 30.93 17.27 Repaint:

Brush, Roller..............$ 28.83 17.27 Spray, Sandblast, Steel....$ 29.43 17.27

PAIN0108-002 06/01/2019

RACINE COUNTY

Rates Fringes

Painters:

Brush, Roller...............$ 36.08 20.36 Spray & Sandblast...........$ 37.08 20.36

PAIN0259-002 05/01/2008

BARRON, CHIPPEWA, DUNN, EAU CLAIRE, PEPIN, PIERCE, POLK, RUSK,

SAWYER, ST. CROIX, AND WASHBURN COUNTIES

Rates Fringes

PAINTER..........................$ 24.11 12.15

PAIN0259-004 05/01/2015

BUFFALO, CRAWFORD, JACKSON, LA CROSSE, MONROE, TREMPEALEAU, AND

VERNON COUNTIES

Rates Fringes

PAINTER..........................$ 22.03 12.45

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

PAIN0781-002 06/01/2019

JEFFERSON, MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

Painters:

Bridge......................$ 33.30 23.86 Brush.......................$ 32.95 23.86 Spray & Sandblast...........$ 33.70 23.86

PAIN0802-002 06/01/2019

COLUMBIA, DANE, DODGE, GRANT, GREEN, IOWA, LAFAYETTE, RICHLAND,

ROCK, AND SAUK COUNTIES

Rates Fringes

PAINTER

Brush.......................$ 30.93 18.44

PREMIUM PAY:

Structural Steel, Spray, Bridges = $1.00 additional per hour.

PAIN0802-003 06/01/2019

ADAMS, BROWN, CALUMET, CLARK, DOOR, FOND DU LAC, FOREST, GREEN

LAKE, IRON, JUNEAU, KEWAUNEE, LANGLADE, LINCOLN, MANITOWOC,

MARATHON, MARINETTE, MARQUETTE, MENOMINEE, OCONTO, ONEIDA,

OUTAGAMIE, PORTAGE, PRICE, SHAWANO, SHEBOYGAN, TAYLOR, VILAS,

WAUSHARA, WAUPACA, WINNEBAGO, AND WOOD COUNTIES

Rates Fringes

PAINTER..........................$ 30.93 18.58

PAIN0934-001 06/01/2017

KENOSHA AND WALWORTH COUNTIES

Rates Fringes

Painters:

Brush.......................$ 33.74 18.95 Spray.......................$ 34.74 18.95 Structural Steel............$ 33.89 18.95

PAIN1011-002 06/02/2019

FLORENCE COUNTY

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Painters:........................$ 25.76 13.33

PLAS0599-010 06/01/2017

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

Area 1......................$ 39.46 17.17 Area 2 (BAC)................$ 35.07 19.75 Area 3......................$ 35.61 19.40 Area 4......................$ 34.70 20.51 Area 5......................$ 36.27 18.73 Area 6......................$ 32.02 22.99

AREA DESCRIPTIONS

AREA 1: BAYFIELD, DOUGLAS, PRICE, SAWYER, AND WASHBURN

COUNTIES

AREA 2: ADAMS, ASHLAND, BARRON, BROWN, BURNETT, CALUMET,

CHIPPEWA, CLARK, COLUMBIA, DODGE, DOOR, DUNN, FLORENCE,

FOND DU LAC, FOREST, GREEN LAKE, IRON, JEFFERSON, KEWAUNEE,

LANGLADE, LINCOLN, MANITOWOC, MARATHON, MARINETTE,

MARQUETTE, MENOMINEE, OCONTO, ONEIDA, OUTAGAMIE, POLK,

PORTAGE, RUSK, ST CROIX, SAUK, SHAWANO, SHEBOYGAN, TAYLOR,

VILAS, WALWORTH, WAUPACA, WAUSHARA, WINNEBAGO, AND WOOD

COUNTIES

AREA 3: BUFFALO, CRAWFORD, EAU CLAIRE, JACKSON, JUNEAU, LA

CROSSE MONROE, PEPIN, PIERCE, RICHLAND, TREMPEALEAU, AND

VERNON COUNTIES

AREA 4: MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES

AREA 5: DANE, GRANT, GREEN, IOWA, LAFAYETTE, AND ROCK

AREA 6: KENOSHA AND RACINE COUNTIES

PLUM0011-003 05/07/2018

ASHLAND, BAYFIELD, BURNETT, DOUGLAS, IRON, SAWYER, AND WASHBURN

COUNTIES

Rates Fringes

PLUMBER..........................$ 40.63 20.72

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

PLUM0075-002 06/01/2016

MILWAUKEE, OZAUKEE, WASHINGTON, AND WAUKESHA COUNTIES

Rates Fringes

PLUMBER..........................$ 40.27 21.47

PLUM0075-004 06/01/2016

DODGE (Watertown), GREEN, JEFFERSON, LAFAYETTE, AND ROCK

COUNTIES

Rates Fringes

PLUMBER..........................$ 40.52 21.47

PLUM0075-009 06/01/2016

COLUMBIA, DANE, IOWA, MARQUETTE, RICHLAND AND SAUK COUNTIES

Rates Fringes

PLUMBER..........................$ 38.82 20.12

PLUM0111-007 05/28/2018

MARINETTE COUNTY (Niagara only)

Rates Fringes

PLUMBER/PIPEFITTER...............$ 33.33 24.48

PLUM0118-002 06/01/2020

KENOSHA, RACINE, AND WALWORTH COUNTIES

Rates Fringes

Plumber and Steamfitter..........$ 43.95 24.35

PLUM0400-003 06/04/2018

ADAMS,BROWN, CALUMET, DODGE (except Watertown), DOOR, FOND DU LAC, GREEN LAKE,KEWAUNEE, MANITOWOC, MARINETTE (except Niagara), MENOMINEE, OCONTO, OUTAGAMIE, SHAWANO, SHEBOYGAN, WAUPACA, WAUSHARA, AND WINNEBAGO COUNTIES

Rates Fringes

PLUMBER/PIPEFITTER...............$ 36.74 19.06

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

PLUM0434-002 05/31/2020

BARON, BUFFALO, CHIPPEWA, CLARK, CRAWFORD, DUNN, EAU CLAIRE,

FLORENCE, FOREST, GRANT, JACKSON, JUNEAU, LA CROSSE, LANGLADE,

LINCOLN, MARATHON, MONROE, ONEIDA, PEPIN, PIERCE, POLK,

PORTAGE, PRICE, RUSK, ST. CROIX, TAYLOR, TREMPEALEAU, VERNON,

VILAS, AND WOOD COUNTIES

Rates Fringes

PIPEFITTER.......................$ 42.70 20.47

PLUM0601-003 06/03/2019

DODGE (Watertown), GREEN, JEFFERSON, LAFAYETTE, MILWAUKEE, OZAUKEE, ROCK, WASHINGTON AND WAUKESHA COUNTIES

Rates Fringes

PIPEFITTER.......................$ 46.89 25.29

PLUM0601-009 06/04/2017

COLUMBIA, DANE, IOWA, MARQUETTE, RICHLAND AND SAUK COUNTIES

Rates Fringes

PIPEFITTER.......................$ 47.08 20.89

TEAM0039-002 06/01/2020

Rates Fringes

TRUCK DRIVER

1 & 2 Axle Trucks...........$ 31.07 22.94 3 or more axles; Euclids or Dumptor, Articulated Truck, Mechanic.............$ 31.22 22.94

SUWI2011-001 11/16/2011

Rates Fringes

WELL DRILLER.....................$ 16.52

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12] for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

file:///C/Users/H6PMDPLW/Documents/Sheboygan%20BW%20Phase%20II/Solicitation/0001/WI20200015.txt[9/11/2020 09:35:12]

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to…

This is the start of the file's text. The full file is on GovTribe.