ABSTRACT_OF_BIDS_W912P6-14-B-0008_MCCOOK_GRDWATER_MONITORING_WELLS.pdf
PDF 20 KB Posted
- Attached to
- McCook Groundwater Monitoring Wells
- Solicitation number
- W912P6-14-B-0008
About this file
Bid Abstract for IFB W912P6-14-B-0008.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF BIDS
Solicitation No. W912P6-14-B-0008 Project Title: McCook Groundwater Monitoring Wells Bid Opening Date and Time: 28 July 2014 at 2:00PM Number of Amendments Issued: 4
ITEM DESCRIPTION Quantity U/M Unit Price Amount Unit Price Amount Unit Price Amount
00 01 MOBILIZATION TO THE PROJECT SITE 1 LS $34,957.00 34,957.00$ 60,000.00$ 60,000.00$ 30,000.00$ 30,000.00$ 00 02 DEMOBILIZATION TO THE PROJECT SITE 1 LS $6,463.28 6,463.28$ 50,000.00$ 50,000.00$ 6,000.00$ 6,000.00$ 00 03 TEMPORARY CONSTRUCTION FACILITIES 1 LS $121,631.06 121,631.06$ -$ -$ 6,000.00$ 6,000.00$ 00 04 MONITORING WELLS G-01, G-02, G-03, and G-07 1 LS $688,477.19 688,477.19$ 613,500.00$ 613,500.00$ 285,000.00$ 285,000.00$ 00 05 WATER QUALITY SAMPLING AND ANALYSIS 7 EA $5,926.24 41,483.68$ 7,857.14$ 55,000.00$ 6,500.00$ 45,500.00$ 00 06 STANDBY TIME 20 HRS $1,778.84 35,576.80$ 500.00$ 10,000.00$ 800.00$ 16,000.00$ 00 07 PERFORMANCE AND PAYMENT BOND FOR LINE ITEMS (0001 TO 0006) 1 LS $13,928.84 13,928.84$ 11,500.00$ 11,500.00$ 11,500.00$ 11,500.00$
BASE TOTAL 942,517.85$ 800,000.00$ 400,000.00$
OPTIONS:
00 08 MOBILIZATION TO THE PROJECT SITE (OPTION) 1 LS $974.17 974.17$ 60,000.00$ 60,000.00$ 27,000.00$ 27,000.00$ 00 09 DEMOBILIZATION TO THE PROJECT SITE (OPTION) 1 LS $6,463.28 6,463.28$ 50,000.00$ 50,000.00$ 6,000.00$ 6,000.00$ 00 10 TEMPORARY CONSTRUCTION FACILITIES (OPTION) 1 LS $99,905.48 99,905.48$ -$ -$ 4,000.00$ 4,000.00$ 00 11 MONITORING WELLS G-04, G-05, and G-06 (OPTION) 1 LS $516,357.89 516,357.89$ 265,500.00$ 265,500.00$ 220,000.00$ 220,000.00$ 00 12 DECOMMISSIONED WELL (OPTION) 1 LS $24,088.42 24,088.42$ 15,000.00$ 15,000.00$ 12,000.00$ 12,000.00$ 00 13 WATER QUALITY SAMPLING AND ANALYSIS FOR OPTION WELLS (OPTION) 5 EA $5,926.24 29,631.20$ 11,000.00$ 55,000.00$ 6,500.00$ 32,500.00$ 00 14 PERFORMANCE AND PAYMENT BOND FOR LINE ITEMS (0008 TO 0013) (OPTION) 1 LS $10,161.31 10,161.31$ 4,500.00$ 4,500.00$ 8,500.00$ 8,500.00$
OPTION TOTAL 687,581.75$ 450,000.00$ 310,000.00$
GRAND TOTAL (BASE & OPTIONS) 1,630,099.60$ 1,250,000.00$ 710,000.00$
CERTIFICATION:
Independent Bidder #1 Bidder #2 Government
Architectural Consulting Group of Chicago, Incorporated
Estimate Raimonde Drilling Corporation
I CERTIFY that all the bids recorded on this abstract of bids were opened and read and received in response to the above named Solicitation Number.
NAME AND TITLE OF CERTIFYING OFFICE
REGINA G. BLAIR, DISTRICT CHIEF OF CONTRACTING
SIGNATURE:
DATE: 31 July 2014
File details come from the government source that posted it. Updated .