W912P522R0008 Amendment 0002 OLD GSU Transformer Install.pdf

PDF 669 KB Posted

Attached to
Old Hickory Power Plant GSU Transformer Installation- Incorporate Revised Specs and Drawings
Solicitation number
W912P522R0008
Issued by

About this file

This amendment to a solicitation modifies the requirements for an Old Hickory Power Plant GSU Transformer Installation project for the Department of the Army Corps of Engineers Engineering District Nashville. The amendment incorporates updated drawings and specifications as well as adds the required FAR clause prohibiting ByteDance covered applications. Key changes include adding and updating contract drawings; modifying specifications for bid schedule line items, payment terms, and transformer installation; and extending the proposal due date to July 31, 2023.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P522R0008

W38XDD20101956

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PURPOSE: The purpose of this amendment is to incorporate updated documents as a result of the submitted questions in ProjNet and add mandated FAR clause.

a.) Added FAR Clause 52.204-27 Prohibition on a ByteDance Covered Application b.) Update FAR Clause 52.252-3 Alterations in Solicitation c.) Modified FAR Clause 252.236-7001 Contract Draw ings and Specif ications d.) See Summary Changes for a detailed list of document updates e.) All others terms and conditions of the solicitation remain unchanged

1. CONTRACT ID CODE PAGE OF PAGES

1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P522R0008

X 9B. DATED (SEE ITEM 11)

30-May-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Jul-2023

CODE

CELRN-CT CONTRACTING BRANCH

110 9TH AVE S STE A405

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The following have been added by full text:

AMENDMENT 0002 ATTACHMENTS

Solicitation W912P522R0008 Amendment 0002 Attachments

- TSpecs_OLD GSU Transformer Replacement_AM 0003_11JUL2023

- E301

- G-003

- G105 GSU Laydown Area Sheet

- LS41413A2

- q15-64^26

- q15-64^27

- q15-64^28

- q15-64^30

Solicitation No. W912P522R0008 Amendment No. 0002 Summary of Changes

I. CHANGES TO CONTRACT DRAWINGS

A. The following CONTRACT DRAWING has been added and updated.

Drawing No. Description E-301 SECTION VIEW TRANSFORMER YARD AND SWITCHYARD INSTALL (Inquiry ID 10314229)

G-003 INDEX OF REFENCE DRAWINGS

G-105 LAYDOWN AREAS

B. The following REFERENCE DRAWINGS has been added.

Drawing No. Description Q15-64/26 APPLICATION DETAILS AND SECTIONS (Inquiry ID 10324866) Q15-64/27 APPLICATION DETAILS AND SECTIONS (Inquiry ID 10324866) Q15-64/28 APPLICATION DETAILS AND SECTIONS (Inquiry ID 10324866) Q15-64/30.1 SECTIONS DETAIL A-A THRU E-E AND DETAIL A (Inquiry ID 10324866)

LS41413A2 RATING PLATE

II. CHANGES TO SPECIFICATIONS

A. The following SPECIFICATIONS were updated.

Specification No. Description 00 41 00 Bid Schedule CLINs 002 & 0015 01 22 00.00 26 1.3 Payment CLINs 0002, 0015 & 2003 (Inquiry ID 10299614, 10299615) 26 05 00.00 26 3.3.2 Transformer Installation (Inquiry ID 10299612, 10299613)

--- END OF AMENDMENT NO. 0002 TECHNICAL CHANGES---

The following have been modified:

PRICE BREAKOUT

SCHEDULE

Old Hickory GSU Transformer Replacement Installation

Item Description Estimated Unit Unit Quantity Price Amount

BASE ITEMS:

0001 Mobilization and Demobilization

1 JOB xxxxx $

0002 Remove and Dispose of 1 JOB xxxxx $ Existing Transformers and Associated Components, Oil, Protective Screens and Takeoff Towers

0003 Remove and Dispose of Existing 15kV Cables and Associated Components

1 JOB xxxxx $

0004 Transformer Rail Removal and Concrete Placement

1 JOB xxxxx $

0005 Security Fence 1 JOB xxxxx $

0006 Stripping and Grading 1 JOB xxxxx $

0007 Aggregate Work 1 JOB xxxxx $

0008 Design of the Oil Containment and Transformer Pad

1 JOB xxxxx $

0009 Seeding and Mulching 1 JOB xxxxx $

0010 Extend Switchyard Ground Grid 1 JOB xxxxx $

0011 Install Oil Containment and Transformer Pad

1 JOB xxxxx $

0012 Furnish and Install Takeoff Tower

1 JOB xxxxx $

0013 Furnish and Install 15kV Cable Precast Concrete Trench

55 LF $______ $

0014 Install 15kV Precast Concrete Trench (Government Furnished Equipment)

160 LF $______ $

0015 Furnish and Install 750 kcmil, triplexed 15kV Cables and Transition Enclosures

1 JOB xxxxx $

0016 Furnish and Install 15kV Bus and associated structures

1 JOB xxxxx $

0017 Make External Connections Between New Transformers and New and Existing Equipment

1 JOB xxxxx $

0018 Furnish, and Install New Neutral Grounding reactors

1 JOB xxxxx $

0019 Furnish, and Install New Metering CTs 1 JOB xxxxx $

0020 4" Perforated Corrugated Drain Pipe 217 LF $______ $

0021 4" HDPE Drain Pipe 139 LF $______ $

0022 Pipe Supports for Existing Oil Lines 1 JOB xxxxx $

0023 Rock Excavation 9 CY $______ $

0024 General Excavation Excluding Rock 161 CY $______ $

0025 6" SS Pipe Sleeve 15 LF $______ $

0026 4" SS Pipe Sleeve 15 LF $______ $

0027 2" Galvanized Treaded 450 LF $_____ $ Water Line

0028 4" Cast Iron Raw Water Line 450 LF $______ $

0029 Crushed Stone Leveling 22 CY $______ $ Course

0030 Furnish Spare Parts 1 JOB xxxxx $ 0031 Commissioning Services 1 JOB xxxxx $ and Training

0032 Provide As-built 1 JOB xxxxx $ Drawings

Total Base Item Price $

OPTION 1 ITEMS:

1001 Remove and Dispose of Existing North Bank Distribution Transformers and Associated Equipment

1 JOB xxxxx $

1002 Furnish and Install new 500kVA North Bank Distribution Transformers

1 JOB xxxxx $

1003 Furnish and Install New 4.4kV Load Disconnect Switch and Current Limiting Fuse

1 JOB xxxxx $

1004 Furnish and Install 15kV Bus and associated structures

1 JOB xxxxx $

1005 Furnish and Install New Current Transformers and Potential Transformers

1 JOB xxxxx $

1006 Furnish and Install New 5kV Cables and Conduit to the Load

1 JOB xxxxx $

1007 Commissioning Services and Training

1 JOB xxxxx $

1008 Provide As-built Drawings 1 JOB xxxxx $

Total Option 1 Item Price $

OPTION 2 ITEMS:

2001 Remove Existing Equipment in 1 JOB xxxxx $ the Switchyard and Update the Design

2002 Perform an Inventory of 1 Switchyard Cable

JOB xxxxx $______

2003 Install Precast Concrete 1 JOB xxxxx $______

Transition Vaults (Government Furnished Equipment)

2004 General Excavation Excluding Rock

368 CY $______ $_______

2005 Rock Excavation 18 CY $_____ $_______

2006 Install 30"x40" Precast Concrete Trench (Government Furnished Equipment) 560 LF $______ $_______

2007 4" HDPE Drain Pipe 242 LF $______ $_______

2008 4" Perforated Corrugated Pipe 1166 LF $__ $_______

2009 Crushed Stone Leveling Course 75 CY $_______ $ _

2010 Provide New Cable Tray 1 JOB xxxxx $

2011 Provide New Junction Boxes 1 JOB xxxxx $

2012 Provide New Cables and Conduit 1 JOB xxxxx $

2013 Provide New Termination Enclosures 1 JOB xxxxx $

2014 Provide New Panelboards LC14, LC15 and LC16

1 JOB xxxxx $

2015 Provide As-Constructed Drawings 1 JOB xxxxx $

Total Option 2 Item Price $

OPTION 3 ITEMS

3001 Remove Existing High 1 JOB xxxxx $ Voltage Disconnect Switches

3002 Remove Existing High Voltage, 1 1/2" Aluminum Bus

1 JOB xxxxx $

3003 Provide New High Voltage, 1 JOB xxxxx $ 1200A Disconnect Switches

3004 Provide New High Voltage, 1 JOB xxxxx $ 1200A Aluminum Bus

3005 Provide As-Constructed Drawings 1 JOB xxxxx $

Total Option 3 Item Price $

TOTAL CONTRACT PRICE (BASE PLUS ALL OPTIONS) $

OPTION ITEMS:

The Government may require the delivery of the proposal item(s) identified in the Price Breakout Schedule as an "(OPTIONAL)" item. The quantities for these items may be increased or decreased or the item(s) may not be used at all, at the discretion of the Government. The unit price or amount of optional items will remain unchanged whether the quantities are increased or decreased unless there is a change in the scope of work. The

Government may use optional items by written notice to the Contractor commencing from the date of contract award to 30 days from contract award.

-- End of Document --

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001:

PURPOSE: The purpose of this amendment is to extend the proposal due date.

a.) The proposal due date is extended from Monday, July 17, 2023 at 1:00 PM Central Time to Monday, July 31, 2023 at 1:00 PM Central Time.

b.) The ProjNet Question submission date will not be extended. Question submission closes 7 July 2023.

c.) All others terms and conditions of the solicitation remain unchanged

Amendment 0002:

PURPOSE: The purpose of this amendment is to incorporate updated documents as a result of the submitted questions in ProjNet and add mandated FAR clause.

a.) Added FAR Clause 52.204-27 Prohibition on a ByteDance Covered Application b.) Update FAR Clause 52.252-3 Alterations in Solicitation c.) Modified FAR Clause 252.236-7001 Contract Drawings and Specifications d.) See Summary Changes for a detailed list of document updates e.) All others terms and conditions of the solicitation remain unchanged

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been added by reference:

52.204-27 Prohibition on a ByteDance Covered Application JUN 2023

The following have been modified:

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

(CUI) Attch 1- W912P522R0008 TPlans OLD GSU Transformer Installation (RTA 30MAR2023).pdf, Index to Drawings Sheet ID-G002.

TSpecs_OLD GSU Transformer Replacement_AM 0003_11JUL2023 (End of clause)

(End of Summary of Changes)