W912P519B00030004 Amendment 4.pdf
PDF 617 KB Posted
- Attached to
- Barkley Turbine Generator Rehabilitation Project
- Solicitation number
- W912P519B0003
About this file
This document provides details for the Barkley Turbine Generator Rehabilitation Project solicitation. The Nashville District U.S. Army Corps of Engineers will solicit a firm fixed-price construction contract to rehabilitate four turbine generators at the Barkley Power Plant in Kuttawa, Kentucky. The estimated value of the project is between $25-100 million. The scope of work includes rewinding generator units, replacing turbine components like runners and bearings, and upgrading mechanical support systems over a six to eight month period. A virtual pre-bid site visit was held in May 2020 and physical site visits are scheduled for June 2020. Questions regarding the solicitation must be submitted to the Contract Specialist by specified dates. The response will include key details about products, services, pricing terms and timelines in a direct, succinct manner suitable for business without unnecessary introductions or framing.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W38XDD01291495
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PROJECT: Barkley Pow er Plant Turbine Generator Rehabilitation, Kuttaw a, KY PURPOSE: The purpose of this amendment is to:
1. Publish the second set of Q&A to the solicitation. The final set of Q&A w ill be published in a forthcoming amendment.
2. Provide the physical Pre-Bid meeting and site visit minutes held June 19, 2020.
3. Provide the revised bid schedule in Excel, physical site visit sign-in sheet, Project Detail Sheet and Past Performance Questionnaire as separate attachments.
4. Extend the bid opening due date from Wednesday, August 5, 2020 at 1:00 p.m. Central Time to Wednesday, September 2, 2020 at 1:00 p.m. Central Time.
5. Revise the terms (paragraph b) of FAR 52.246-21, Warranty of Construction, and update Instructions to Bidders. There are no revisions to the Wage Determinations and listed for informational purposes only.
FAR 52.252-3, Alterations in Solicitation, is updated
1. CONTRACT ID CODE PAGE OF PAGES
1 25
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 31-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P519B0003
X 9B. DATED (SEE ITEM 11)
18-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
31-Jul-2020
CODE
US ARMY CORPS OF ENGINEERS-CELRN-RC-N
DIRECTORATE OF CONTRACTING
110 9TH AVENUE SOUTH, RM A405
NASHVILLE TN 37203
W912P5 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P519B0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
Q AND A 2
W912P519B0003 Barkley Turbine Generator Rehab Questions and Answers Amendment 0004
19. Can you please confirm if the Government will require individual Performance and Payment Bonds for each unit? Given the duration of the project and the requested (5) year warranty for the stator rewind and (2) year for the cavitation warranty it is not possible to provide a single Performance & Payment for the entire project.
ANSWER: In accordance with FAR 52.228-15, Performance and Payment Bonds—Construction, the penal amount of the performance and payment bonds shall be 100% of the original contract award amount. Warranties in the specifications include (1) turbine oil purification system (Section 22 00 00.00 26 paragraph 3.5.4b), (2) generator air cooler (Section 23 00 01.00 26 paragraph 1.6), (3) generator thrust bearings (Section 48 13 13.06 26 paragraph 1.5),
(4) stator windings (Section 48 13 16.00 26 paragraph 1.5), and (5) cavitation (Section 48 13 13.01 26 paragraph 1.5.3.1).
20. Please provide drawings of the stator frame, showing inner diameter of each shelf, number of reinforced angle steel behind key bars.
ANSWER: Any drawings not in the reference drawing set (W912P519B0003+RTA+TPlans.pdf) that are available to the Government will be provided upon award.
21. SECTION 48 13 16.00 26 clause “2.11.2 Stator Lamination Die” allows the use of the existing stator lamination die currently stored at Barkley powerhouse. In order to evaluate this option please provide the following information: Is the die currently in perfect operation conditions? Quantity of laminations already punched? Number of times tool was sharpened? Some pictures would be helpful. Drawings of lamination die if available for the assessment of the lamination size and the fixation method to the punching equipment.
ANSWER: The lamination die was available for inspection during the pre-bid onsite walkthrough on June 19, 2020.
Any drawings existing in Government records will be made available for inspection after award. The Government cannot assess the utility or condition of the stamping die for use with Contractor tooling as part of the Solicitation.
22. SECTION 48 13 16.00 26 clause “2.11.3 Stator Key bars” requests the supply of new key bars with stator frame modifications if applicable. Please provide the design details, pictures and drawings of existing key bars showing how these are fixed to the existing stator frame and how they will be removed in the rehabilitation. Is a different key bar design acceptable? How many key bars are required/installed per the unit? Are the current key bars providing the compression of the core? Or there are also round studs? And how many per unit?
ANSWER: Please reference the Government’s response to Question #20 for information about additional reference drawings. The specifications give the Contractor design control over keybars with the OPTION of modifying the stator clamping system if required for the design.
23. SECTION 48 13 16.00 26 clause “2.11.4 Stator Clamping System (OPTIONAL)” defines that supplies of flanges and fingers, tightening nuts and through bolts are optional, i.e., the existing ones are to be reused. Please provide the design details, pictures and drawings of these flanges and fingers, tightening nuts and through bolts, including how these are fixed and supported on the existing stator frame. Is there any record of looseness, cracks or any other problems with the existing clamping configuration?
ANSWER: There is no record of issues in maintenance logs. Please reference the Government’s response to Question #20 for information about additional reference drawings.
24. SECTION 48 13 16.00 26 clause “1.4 EXISTING GENERATOR INFORMATION” informs that the unit 1 was rewound by the National Electric Coil Company in 2013. Please provide:
• The design details, pictures and drawings of these stator coils showing the slot dimensions and core total length. These information are not available in the received drawings.
• Test Report Data of the refurbished generator Unit 1 with the same Heat Run data provided in the clause “1.4.3 Test Report Data”:
• Operating Temperature Degrees Celsius (°C) at rated kVA, voltage and power factor; Maximum Temperature Rise of Armature Winding by RTD; Average Temperature of Inlet Air and Stator Resistance (line-to-neutral) at 75°C.
ANSWER: Please reference the Government’s response to Question #20 for information about additional reference drawings.
25. SECTION 48 13 16.00 26 clause “1.4 EXISTING GENERATOR INFORMATION” informs that in 2013 the unit 1 had 23 of the 110 field coils refurbished. Please provide the design details, pictures and drawings of these refurbished field coils showing the copper dimensions, number of turns, turn insulation, ground insulation and collars thickness.
ANSWER: Please reference the Government’s response to Question #20 for information about additional reference drawings.
26. SECTION 48 13 16.00 26 clause “1.4.4 Inspection by Contractor” informs that spare coil and spare lamination are available at the powerhouse for measurement. Due to the short period for the proposal calculation, waiting until the June 18th site visit will set a disadvantage against the OEM who already own this information. Please provide the dimensions measurements and pictures of these spare coil and lamination or related drawings with original dimensions.
ANSWER: Please reference the Government’s response to Question #20 for information about additional reference drawings.
27. Technical Specifications/48 13 16.00 26/Para. 3.4/Page 26
It is difficult to obtain good quality slices of only 0.25 inch. The heat generated by the cutting process can damage small samples. It is recommended to increase the length of the slices to 1.0 inch.
ANSWER: The Government’s requirement of a 0.25 inch sample is standard and remains as stated in the Solicitation.
28. Technical Specifications/48 13 16.00 26/Para. 3.15.3/Page 32
Center the frame to the new unit centerline is easy to perform, however round the stator frame (i.e. change the shape of the stator frame) is useless if new keybars are installed.
ANSWER: This Specifications Section 48 13 16.00 26 does not require rounding of the stator frame. The frame is to be set to the new centerline, keybars installed vertically, and then the core itself is to be stacked in a concentric, vertical circle.
29. Technical Specifications/48 13 16.00 26/Para. 3.16.2/Page 32 It is asked to bring the flux density to its rated value. Since the core material saturation curves tend to flatten at or near 100% rated flux level, it can lead to high values of excitation current to magnetize the core due to rapid decrease in permeability. This might require a very large power source which could be unjustified and sometimes impractical. A lot of our experiences involve a fixed flux density of 1.0 Tesla, regardless of the rated flux level. Also at 1 Tesla most likely the 480 VAC station Service can be used for the testing.
ANSWER: The Government requires rated flux testing as standard and as stated in in the Technical Specifications.
30. Technical Specifications/48 13 16.00 26/Para. 3.29 (d)/Page 43 Due to health and safety reasons, GE's preferred method to perform the blackout test is using a UV camera that allow for an adequate level of ambient light during the test. A Blackout test in the complete darkness requires additional safety measures to protect the technicians and/or engineers (ex. barriers, flat platforms, additional safety distance if no barriers). The test using a UV camera has been successfully performed for numerous years and requested by many customers.
ANSWER: The Government recognizes the differences in test methods, but requires blackout testing as the standard and as stated in the Technical Specifications.
31. Technical Specifications /48 13 16.00 26 /Para. 1.1 /Page 5 Barkley Power Plant Units 1 through 4 have 110 field coils each. Please clarify why only 87 field coils shall be refurbished for Unit 1.
ANSWER: Unit 1 field coils damaged due to a previous failure were refurbished concurrent with the Unit 1 rewind under a separate contract in 2013.
32. Is a PPQ required for a project that is in PPIRS?
ANSWER: The apparent low bidder will be required to submit either one PPQ or Contractor Performance Assessment Report (CPAR) for each project used to satisfy a DRC. Please reference Instructions to Bidders, paragraph 13, Definitive Responsibility Criteria (DRC).
33. Will there be a Roof Replacement during the Barkley Turbine Generator Rehab Project?
ANSWER: The current roof replacement project is now in the closeout phase. However, the Government will likely award other operations and maintenance contracts for the Barkley Power House in the future.
34. In a review of Contract Clauses in the Solicitation, it is noted that clause 52.214-18 – Preparation of Bids- Construction is incorporated by reference. This clause states:
52.214-18 Preparation of Bids-Construction.
As prescribed in 14.201-6 <Blockedhttps://www.acquisition.gov/content/part-14-sealed-bidding#i1110459> (l), insert the following provision:
Preparation of Bids-Construction (Apr 1984) (a)Bids must be- (1)Submitted on the forms furnished by the Government or on copies of those forms, and
(2) Manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b)The bid form may require bidders to submit bid prices for one or more items on various bases, including- (1)Lump sum bidding;
(2)Alternate prices;
(3)Units of construction; or (4)Any combination of paragraphs (b)(1) through (b)(3) of this provision.
(c)If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words “no bid” in the space provided for any item on which no price is submitted.
(d)Alternate bids will not be considered unless this solicitation authorizes their submission.
(End of provision)
Please note that 52.214-18(a)(2) requires bids to be manually signed, presumably on Forms SF1442 and any Amendments SF30, and Form SF24/Bid Bond.
However, in Section 00 21 00, Paragraph 16, it is stated that:
The Bidder’s bid shall be submitted electronically, as described below. The IFB will provide bid submission instructions and receipt date for bid submittal. The Bidder’s bid shall not contain classified data. The use of hyperlinks in bids is prohibited.
NOTE: The only authorized transmission method for bids in response to this solicitation is electronically via SAFE online submission. NO OTHER TRANSMISSION METHODS (EMAIL, FACSIMILE, REGULAR MAIL, HAND
CARRIED, ETC.) WILL BE ACCEPTED.
Please clarify which of these requirements prevail in this apparent conflict, or if a scanned signature of the forms included with the electronic submittal will suffice.
ANSWER: A scanned signature on the forms included with the electronic submittal is acceptable
35. GE would be interested to have additional information about the powerhouse bridge crane, such as: remote operation availability, visual weight indicator installed, maintenance and inspection log book, certifications history, emergency plan. This information would be useful in assessing cost of operation and EHS.
Please confirm also that the powerhouse bridge crane will be load tested (125% of nominal maximum capacity) and certified by the Government before use by the Contractor.
ANSWER: The powerhouse bridge crane was tested to 125% on July 2016.
36. Please consider including the erection bay bearing capacity. This information will allow GE to properly plan the site work.
ANSWER: Structural and architectural drawings are included for reference with layout and rebar schedule for load determination.
37. Please clarify the scope (systems) for cooling and packing water piping replacement including limit of supply.
We have limited access to drawings. Please clarify also the associated bid item in price schedule for this scope of work.
ANSWER: Please reference Specifications Section 22 00 00.00 26 paragraph 3.15, which requires the contractor to include all cooling water piping within the turbine pit for replacement or inspection and replacement on direction from the government.
CLINS 101, 0219, 0329, and 0439 cover reassembly of each unit. The piping is part of the reassembly process as these pipes will be disassembled during the work.
38. According to section 48 13 16.24 26, the replacement of new brakes shall include cylinders, pads and piping.
But according to related bid item in price schedule (No. 0156), the scope of work shall also include electronic controls, hydraulic pumps, motors, valves, etc.
Please clarify the scope for brake system replacement including limit of supply for low pressure air actuation piping.
Please clarify if a new brake panel shall be provided in the base scope of work.
ANSWER: In accordance with Specifications Section 48 13 16.24 26, the existing braking and jacking cylinders are to be replaced with new. New mounting plates and brake pads to be supplied. New low pressure air piping is to be replaced. Replace this piping back to the governor where the air brake actuator is located. The other items (electronic controls, hydraulic pumps, motor valves, etc.) were erroneously included in the bid schedule. A new brake panel is not part of the scope of work. An updated electronic bid schedule in Excel is being provided as a separate attachment to this Amendment. This electronic file shall be completed and provided with your bid.
Transcribe the total bid price (base and all options) to Line Item (CLIN) 0001 of this Amendment.
39. Section 05 59 13 mentions only the requirements to the fabrication of the draft tube gates.
Please clarify the design requirements (allowable gate deflection, corrosion, leakage rate, seismic load, etc.) for the draft tube gates.
The scope of work assumed by GE includes: panels, structure, seals, guide shoes, elliptical springs and lifting hooks.
Please clarify if the following components shall be included in bid item No. 0112 in price schedule: bypass valve (not shown on original drawings), embedded parts, dogging device, lifting beam, lifting beam storage rack, slot covers, etc.
Is there a PE stamp requirement on this system. Please clarify.
ANSWER: There are no design requirements for the draft tube gates. Drawings Q9-79/680a, “/681a, “/681a, “/682a, and “/683a are detailed drawings and provide enough detail for fabrication. This Amendment updates the description for Item No. 01112 to highlight installation of the draft tube gates. Bidders should review Specifications Section 05 59 13 para 3.1.2, as it is required that the gates be installed in the slot after delivery. This may be challenging due to the plant’s tail deck geometry and might require a floating crane. This however will be determined by the contractor’s best means and methods.
The draft tube gates portion is a "fabricate to print." There is no design required for the fabrication of these gates and no PE stamp is required for design.
40. Condition Monitoring System Supplier advised that equipment have been updated several years ago with new air-gap and vibration sensors, and electrical auxiliaries (such as wires and relays) not fully meeting specification 48 13 16.01 and 26 05 19.00 26. Would a similar updated system as approved for Old Hickory Project be acceptable?
ANSWER: Potential systems shall be submitted via the Government submittal process and variance marked accordingly, if applicable.
41. Since we were not able to share our business cards due to the COVID-19 outbreak, are you able to provide us the phone contact information for the attendees to the site visit? We would like to contact them to see if they would like us to participate in providing the rewind kits for the Project. Also, please email us the new Solicitation Proposal due date.
ANSWER: The sign-in sheet for the June 19, 2020 physical site visit is being provided as a separate attachment to this Amendment. Extension of the bid opening due date is provided with this amendment to the solicitation.
42. Can the cut-off day for questions be extended?
ANSWER: Amendment 0003 extended the due date for questions from Friday, June 26, 2020 at 11:00 a.m. Central Time to Wednesday, July 8, 2020 at 10:00 a.m. Central Time.
43. There were no PDS or PPQ forms included in Amendment No.2. Will these be issued soon?
ANSWER: The Project Detail Sheet (PDS) and Past Performance Questionnaire (PPQ) are provided as separate attachments to this Amendment.
44. Since, up until today, there has been no response to any of the 26 questions we have submitted. Today marks the official deadline for submittal of questions.
We respectfully request that the Q&A period be extended to – at a minimum – correspond with the extended bidding period, pushing the Q&A deadline back three weeks, so that the new date for Q&A submittals would be July 15, 2020.
ANSWER: Please reference the Government’s response to question 42.
45. Water Quality- We consider the following water quality parameters as harmless conditions for non- and low-alloyed structural steels as well as for stainless steel type 1.4313/ASTM 743 CA6NM Water quality parameter Unit Harmless water quality threshold Total suspended solids (TSS, average value) mg/l Pelton:
< 1000 m: < 10 < 2000 m: < 5 ≥ 2000 m: 0 Francis, Kaplan:
< 100 m: < 60 < 300 m: < 30 ≥ 300 m: < 5 pH-Value - 5 - 9 Electric conductivity µS/cm < 300 Chloride (Cl-) mg/l < 50 Sulfate (SO42-) mg/l < 300
Please confirm the Barkley lake water quality meets the above threshold. Also, the contractor will have no warranty obligation to the extent when any damages are primarily the result of microbiologically influenced corrosion (MIC) or biological infestation (e.g., mussels, water hyacinths). Please confirm.
ANSWER: Due to the length of the period of performance of this project, the Government cannot predict the water quality in Lake Barkley. The contractor is not responsible for damage that is a result of microbiologically influenced corrosion (MIC) or biological infestation.
46. Reference Section 01 50 00 Temporary Construction Facilities and Controls. Paragraph 3.5 Government Facilities. Sub-Paragraph Government Field Office Space. Please clarify the following:
a. Specify sizes of Government Field Office Space to be provided by the Contractor.
b. Determine time frame the Contractor shall install and furnish the Government Field Office Space.
c. Indicate under which Bid Schedule Item should the price of the Government Field Office Space, and Field Office Equipment and Furnishings be allocated to.
ANSWER: Please reference the layout example in Specifications Section 01 50 50 3.5.1.1 for the Government Field Office Space size requirement. The Government Field Office Space is required 30 days after the Notice to Proceed identified in Specifications Section 01 50 50 3.5.1.1. There is no specific Bid Schedule line item for the Government Field Office Space.
47. Ref. Solicitation No. W912P519B0003 – Wage Determination – General Decision Number: KY20200051 Construction Type: Heavy. The wage determination included in the specification does not include classifications for the following Crafts/Trades expected to be utilized for the project execution at Barkley Dam:
a) Millwrights
b) Painters
c) Pipefitters
d) Generator Coils winders
Please advise what rate should the bidder use for the above classifications?
ANSWER: After contract award, the Contractor should submit to the Contracting Officer an individual Standard Form (SF) 1444, Request for Authorization of Additional Classification and Rate, for each classification not included in the Department of Labor Wage Determination.
48. In Section 01 45 00.3.4.3: Electrical and Mechanical, it states that “The electrical and mechanical individuals must be employees of the prime; be responsible to the CQC System Manager; be physically present at the construction site during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein.”
a. The Contactor notes that Mechanical and Electrical work will be taking place the entire outage. Can the Government please confirm if the intent is really to have a mechanical and electrical engineer on site for the duration of the contract in addition to the degreed CQC system manager?
ANSWER: Reference Specifications Section 01 45 00, paragraph 3.4.3, CQC Personnel for the CQC staff requirements. The mechanical CQC staff member must be on site while mechanical work is ongoing. The electrical CQC staff member must be on site while electrical work is ongoing. The CQC System Manager, Superintendent, and SSHO shall be on site while any work is ongoing for the project.
49. In Section 01 50 00 3.7 - Temporary Project Safety Fencing, it states that “As soon as practicable, but not later than 15 calendar days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site.”
a. Can the Government please confirm if the date established for commencement of the work is understood to be commencement of site work, or work on the contract, i.e. NTP?
ANSWER: Temporary project safety fencing shall be furnished and erected no later than 15 calendar days after mobilization.
50. In consideration that the project schedule is (7) years long and this is Sealed Bid, the Contractor kindly requests that the Government include a Contract Clause for Economic Price Adjustment, such as 52.216-3 Economic Price Adjustment-Semistandard Supplies.
ANSWER: Per FAR 16.203-4(b), the Contracting Officer shall insert 52.216-3, Economic Price Adjustment – Semistandard Supplies, when contracting by negotiation. This project is being procured using sealed bidding, therefore this clause is not applicable.
SITE VISIT MEETING MINUTES
CELRN-RCN 30 July 2020
MEMORANDUM FOR RECORD
SUBJECT: Barkley Turbine Generator Rehabilitation (W912P519B0003), Pre-Bid Meeting and Site Visit
1. Purpose: To summarize the Pre-Bid Meeting and Site Visit held on 19 June 2020.
2. Attendees:
Government:
Mr. Bradley Cressman, Mechanical Engineer, CELRN-EC-CD-EM Mr. Jamie Holt, Power Project Superintendent, CELRN-OPW-BAP Mr. John Reed, Senior Project Engineer, CELRN-ECC-W Ms. Dana Sexton, Hydropower Project Manager, CELRN-PM-P Ms. Stacy Wiggins, Branch Contracting Chief/Contracting Officer, CELRN-RCN
Vendors:
A. Andritz Hydro Mr. Yungfeng Gao Mr. Brian Murtha
B. GE Renewable Energy
Ms. Megan Nesbitt
C. Gulf Coast Electric Motor Services Mr. Michael Mizell Mr. Victor Rodriguez
D. Lesman Mr. Eric Reimer
E. National Electric Coil Mr. Benjamin Carr Mr. John Stender
F. Voith Hydro, Inc.
Mr. Renato Alimonda Mr. Christopher Lang
3. Summary of Discussions: Ms. Dana Sexton started the meeting at 9:00 a.m. Central Time. Ms. Stacy Wiggins provided a brief overview of the project and contracting requirements.
a. INTRODUCTIONS: Government employees introduced themselves and attendees signed-in.
b. Solicitation W912P519B0003, Barkley Power Plant Turbine Generator Rehabilitation, will be a firm fixed price construction contract competed as full and open. The estimated magnitude for this project is between $25,000,000 and $100,000,000.
c. PROJECT DESCRIPTION: This project is being solicited as an Invitation for Bid (IFB) with Definitive Responsibility Criteria (DRC). This procurement includes a base contract with multiple contract options to rehabilitate four (4) turbine generators.
d. QUESTIONS: Questions were addressed to the best of the Government’s ability, but anything said at the Pre- Bid Meeting and Site Visit is considered not official unless it is in writing in the issued amendment to this solicitation. Questions shall be in writing and sent to Contract Specialist Kristal Jones at email address Kristal.R.Jones@usace.army.mil no later than Friday, June 26, 2020 at 11:00 a.m. Central Time. Questions received after this deadline will not be addressed. (NOTE: Pursuant to Amendment 0003, issued on July 1, 2020, extended the due date for questions to Wednesday, July 8, 2020 at 10:00 a.m. Central Time.)
e. An amendment will be posted with the information and questions from Pre-Bid Meeting and Site Visit on www.beta.sam.gov website.
f. SOLICITATION OVERVIEW:
(1) Reference Section 00 21 00 of the solicitation, Instructions to Bidders, for all of the details in regards to submitting your bids.
(2) Bids are due by Wednesday, August 5, 2020 at 1:00 p.m. Central Time. (NOTE: Pursuant to this amendment, bids are now due by Wednesday, September 2, 2020 at 1:00 p.m. Central Time.)
(3) Bids will be submitted electronically using DoD Safe website (https://safe.apps.mil/). Reference Instruction to Bidders, paragraph 16, for specific details on how to request access to this site.
(4) Basis for Selection of Award: Award shall be made to the lowest priced bidder who is found to be responsive and responsible.
In accordance with FAR 52.217-5, the Government intends to evaluate bids for award purposes by adding the total price for all options to the total price for the basic requirement. Any, some or all of the options may be exercised at any time but no later than 5 calendar days of submittal approval that triggers the need for an option.
In order for the Contractor to be determined responsible, they must meet the Definitive Responsibility Criteria (DRC) listed in the Instruction to Bidders, paragraph 13, page 25 of the solicitation.
(5) Bidders are required to be registered in System for Award Management (SAM) prior to submission of bids (reference Section 00 21 00, Instruction to Bidders, paragraph 20).
(6) Attendees were reminded if there was a discrepancy between what is said during the visit and what is written in the solicitation, the document governs along with the date that questions were due to Ms. Kristal Jones.
4. Mr. John Reed provided an overview of the submittal process; measurement and payment procedures; and safety requirements.
5. Mr. Jamie Holt conducted a safety briefing before the plant walk thru.
6. Attendees toured the construction site which ended approximately at 1:00 p.m. Central Time.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 05-Aug-2020 01:00 PM to 02-Sep-2020 01:00 PM.
CLIN 0001
The CLIN extended description has changed from:
Rehabilitate four (4) turbine-generators at the Barkley Power Plant, Kuttawa, KY in accordance with the technical specifications and plans. NOTE: This CLIN should include the total for all bid schedule line items (base and all options).
To:
Rehabilitate four (4) turbine-generators at the Barkley Power Plant, Kuttawa, KY in accordance with the technical specifications and plans. NOTE: This CLIN should include the total for all bid schedule line items (base and all options) priced on the Excel Bid Schedule provided with Amendment 0004.
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
INSTRUCTIONS TO BIDDERS
INSTRUCTIONS, CONDITIONS & NOTICES TO BIDDERS
GENERAL REQUIREMENTS
1. Intent: The intent of this solicitation is to award one (1) contract for the Barkley Power Plant Turbine Generator Rehabilitation construction project, Kuttawa, KY.
2. Disclosure of Magnitude of Construction Project: The estimated magnitude of this requirement is between $25,000,000 and $100,000,000.
3. Basis of Selection of Award: Award shall be made to the lowest priced bidder who is determined to be responsive and responsible. See Federal Acquisition Regulation (FAR) 52.214-19, Contract Award—Sealed Bidding—Construction, for more information. In accordance with FAR 52.217-5, Evaluations of Options, the Government intends to evaluate bids for award purposes by adding the total price for all of the options to the total price for the basic requirement. Any, some or all of the options may be exercised at any time but no later than 5 calendar days of submittal approval that triggers the need for an option.
4. Type of Contract: The Government intends to award one (1) firm fixed-price construction contract.
5. Who May Submit: This procurement is full and open.
6. North American Industry Classification System (NAICS) Code and Small Business Size Standard: The NAICS code for this project is 237990, Other Heavy and Civil Engineering Construction, with a size standard of $39,500,000.
7. Specifications and Drawings: Specifications and Drawings will be provided as separate files and will be available on beta SAM. See the complete drawings and specification package located at www.beta.sam.gov
The Specifications and Drawings are part of the solicitation/contract and shall be considered in that respect (see Defense Federal Acquisition Regulation Supplement (DFARS) 252.236-7001, Contract Drawings and Specifications).
8. Pre-Bid Site Visit: An organized site visit has been scheduled to occur during the solicitation period. Bidders should inspect the job site prior to submitting a bid. Bidders should take such other steps as may be reasonably necessary to ascertain the nature and location of the work and the general and local conditions that can affect the work or the cost thereof. Failure to do so will not relieve bidders from the responsibility for properly estimating the difficulty or cost of successfully performing the work. The Government assumes no responsibility for any understanding or representations concerning conditions made by any of its officers, agents or employees, unless included in the solicitation, the specifications or related documents. Please refer to FAR 52.236-27 Alt I, Site Visit (Construction) incorporated by full text in this solicitation, for information pertaining to the scheduled site visit.
REGISTRATION: Only registered persons will be permitted to attend the site visit. In addition to the information below, please also provide your firm’s name, firm’s CAGE and/or Unique Entity Identifier (formerly known as DUNS) number, and name and position title of primary point-of-contact and their telephone number and email address. Please provide this information via email to kristal.r.jones@usace.army.mil.
Contractors and/or potential contractors wishing to attend a pre-bid meeting held at or in LRN restricted/controlled areas (such as a Power Plant or Navigation Lock) shall submit a Nashville District (LRN) Security Access Form to the Contract Specialist two (2) business days prior to the site visit or meeting. If submitting the document in less than five business days, the bidder may not receive approval for participation. The Contract Specialist will notify the Contractor if the request is approved or denied. Any pre-bid meeting which will cover anything other than public domain information shall be limited to U.S. Citizens, except under unique circumstances.
U.S. CITIZENS: The bidder shall submit a Nashville District Corps of Engineers U.S. Citizen Pre-Bid and/or Site Visit Request Form to the LRN Point of Contact, Contract Specialist Kristal Jones, no later than two (2) business days prior to the site visit. If submitting the document in less than five business (5) days, the bidder may not receive approval for participation. The LRN POC will notify the individual(s) if the request is approved or denied.
The Security Access Form and guidance is available as a pdf attachment on www.beta.sam.gov with this solicitation and is titled Pre-Bid Meeting and/or Site Visit Request Form.
FOREIGN NATIONALS (FNs): All non-U.S. Citizens, including permanent residents wishing to attend the site visit must be approved in advance. FNs wishing to attend a site visit shall submit a completed Nashville District Corps of Engineers Foreign National Pre-Bid Meeting Request Form and legible color copies of two (2) of the following documents: Passport (unexpired or expired), Certificate of U.S. Citizenship (INS Form N-560 04 N- 561), Certificate of Naturalization (INS Form N-550 or N-570), unexpired foreign Passport with I- 551 stamp or attached INS Form I-94 indicating unexpired employment authorization, an Alien Registration Receipt Card with photo (INS Form I-151 or I-551), unexpired Temporary Resident Card (INS Form I-688), unexpired Employment Authorization Card (INS Form I- 688A), unexpired Reentry Permit (INS Form I-327), unexpired Refugee Travel Document (INS Form I-571), or unexpired Employment Authorization Documentation issued by the INS which contains a photograph (INS Form I-688B) to the LRN Point of Contact, Contract Specialist Kristal Jones . These documents must be submitted two (2) weeks prior to the site visit unless otherwise stated herein. FN requests require approval at the Headquarters U.S. Army Corps of Engineers (HQUSACE) level. Exceptions will be considered on a case by case basis but will be limited. The form is available as a pdf attachment on www.beta.sam.gov with this solicitation and is titled Foreign National Pre-Bid Meeting Request Form.
Due to the social distancing guidelines provided by the Centers for Disease Control and Prevention (CDC) because of COVID-19, this site visit will be a video conference presentation that will be held on Thursday, May 28, 2020 at 10:00 a.m. Central Time.
In order to participate in the virtual site visit, contractors must submit a site visit request form for each company representative. Site visit request forms can be found at www.beta.sam.gov under the Attachments section of this solicitation. Companies with foreign national representatives must submit a Foreign National Site Vist Request Form, which can found at www.beta.sam.gov under the Attachments section of this solicitation. All site visit request forms, including site visit request forms for foreign nationals, must be submitted by Thursday, May 21, 2020 at 3:00 p.m. Central Time to Contract Specialist Kristal Jones at the aforementioned e-mail address.
Upon approval of submited site visit request forms, contractors will receive via e-mail the site visit agenda, which will include teleconference and Defense Visual Information Distribution Service (DVIDS) access information, and photographs prior to the virtual site visit pre-bid meeting.
Physical site visits are tentatively scheduled to be held on Thursday, June 18, 2020 and Friday, June 19, 2020 in order for bidders to see and access a de-watered unit. Please note due to the social distancing guidelines provided by the CDC, bidders will only be allowed to have no more than two (2) company representatives to participate in the physical site visit.
9. POINT-OF-CONTACT: For questions and /or concerns regarding the virtual pre-bid meeting site visit, please contact Contract Specialist Kristal Jones via email at the address referenced above.
These will be the only site visits for this project. If you miss the scheduled site visits, no other arrangements will be made due to personnel and time restrictions.
10. POC for Communication/Questions: Any communications regarding this procurement must be made in writing to the Nashville Contracting Branch, Attn: Kristal Jones at email kristal.r.jones@usace.army.mil.
Inquiries must identify the solicitation number, the requestor’s company name, address, email address, and telephone number to include area code.
Phone calls or requests to arrange meetings at the Nashville District during the solicitation period to discuss project requirements or company’s capabilities are highly discouraged and will not be scheduled.
QUESTIONS: Questions regarding the solicitation must be submitted to Kristal Jones via email at kristal.r.jones@usace.army.mil no later than Wednesday, July 8, 2020 at 10:00 a.m. Central Time.
11. Amendments Prior to Date Set for Closing of Invitation for Bid (IFB). The right is reserved as the interest of the Government may require, to revise or amend the specifications or drawings or both prior to the date set for submission of bid. Such revisions and amendments, if any will be announced by an amendment or amendments to this IFB. If the revisions and amendments are of a nature which requires material changes in quantities or prices proposed or both, the date set for receipt of bids may be postponed by such number of days as in the opinion of the issuing officer will enable bidders to revise their bid. In such cases, the amendment will include an announcement of the new date for receipt of bid.
12. NOTICE TO BIDDER: Use of Class I Ozone-Depleting Substances
a. In accordance with Section 326 of P.L. 102-484, the Government is prohibited from awarding any contract which includes a specification or standard that requires the use of a Class I ozone-depleting substance (ODS) identified in Section 601(a) of the Clean Air Act, (42 U.S.C 767a(a)), or that can be met only through the use of such a substance unless such use has been approved, on an individual basis, by a senior acquisitions official who determines that there is no suitable substitute available.
b. To comply with this statute, the Government has conducted a best effort screening of the specifications and standards associated with this acquisition to determine whether they contain any ODS requirements. This requirement has no relationship to ODSs.
c. If the bidder possesses any special knowledge about any other ODSs required directly or indirectly at any level of contract performance, the U.S. Army would appreciate if such information were surfaced to the Contracting Officer for appropriate action. To preclude delay to the procurement, the bidder should provide any information as soon as possible after release of this IFB and prior to the submission of bids to the extent practicable. It should be understood that there is no obligation on the bidder to comply with the request and that no compensation can be provided for doing so.
13. DEFINITIVE RESPONSIBILITY CRITERIA (DRC)
a. To ensure award is made to a responsible bidder, a determination of responsibility will be conducted.
As part of this responsibility determination, the Contracting Officer will utilize the guidance contained in FAR Subpart 9.1, Responsible Prospective Contractors. In accordance with FAR 9.104-1, to be determined responsible, a prospective contractor must:
(1) Have adequate financial resources to perform the contract, or the ability to obtain them;
(2) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;
(3) Have a satisfactory performance record, similar in scope and magnitude of that stated in the contract requirement;
(4) Have a satisfactory record of integrity and business ethics;
(5) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors);
(6) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(7) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
b. Definitive Responsibility Criteria: In addition to examining the criteria in FAR 9.104-1, the Contracting
Officer will also examine whether the low bidder can meet the requirements of the four (4) definitive responsibility criteria. The apparent low bidder will be required to provide evidence showing their company meets the following experience requirements.
1. The following requirements must be self-performed as a prime or a sub-contractor:
a. A minimum of (3) projects completed within the last twenty (20) years, or two (2) projects completed in the last twenty (20) years and one (1) project that is currently substantially complete, that demonstrate design and scale model testing of new Kaplan runners. The projects must have a minimum blade diameter of 200 inches for two (2) out of the three (3) projects and 150 inches for one (1) out of the three (3) project, or 200 inches for all three (3) projects.
b. A minimum of two (2) projects completed within the last twenty (20) years, or one (1) project completed in the last twenty (2) years and one (1) project that is currently substantially complete, that demonstrate design of a static oil head system for Kaplan runners.
c. A minimum of two (2) projects completed within the last twenty (20) years, or one (1) project complete, that demonstrate experience designing and installing a new or replacement 13.8KV salient pole generator with a size no less than 30 MW.
2. The following requirements must be performed as a prime, a sub-contractor, or sub-contracted while operating as the prime contractor:
a. A minimum of two (2) projects completed within the last twenty (20) years, or one (1) project completed in the last twenty (20) years and (1) project that is currently substantially complete, that demonstrate disassembly of a Kaplan turbine generator unit. The projects must have a minimum blade diameter of 200 inches for one (1) out of the two (2) projects and 150 inches for one (1) out of the two (2) project, or 200 inches for all two (2) projects.
b. A minimum of two (2) projects completed within the last twenty (20) years, or one (1) project complete, that demonstrate experience rehabilitating field coils for a salient pole generator with field current rating and synchronous speed no less than 800 amps and 65 (-10/+85) rpm, respectively.
c. A minimum of two (2) projects completed within the last twenty (20) years, or one (1) project complete, that demonstrate experience installing via continuous stacking method a core for a
13.8 KV salient pole generator of a size no less than 30 MW.
3. At least one of the self performed submitted projects must have been completed within the last six
(6) years with a contract value of at least $50 million.
4. The bidder’s workplace safety record shall be checked using either of the following methods:
a. The Bidder shall provide a letter from their insurance company stating the Bidder's most current experience modification rate (EMR). Bidders providing an EMR greater than 1.0 will be determined not responsible.
b. The Bidder shall provide a total recordable incident rate (TRIR) calculation for calendar year
2018. The TRIR calculation shall be provided on the OSHA Form 300A. Bidder's submitting a TRIR greater than 3.0 will be determined not responsible.
*Define “substantially complete” as at least 50% complete.
**Define “20 years” as 20 years from the date this solicitation is posted.
***Define "6 years" as 6 years from the date this solicitation is posted.
****A Project Detail Sheet (PDS) along with either a Contractor Performance Assessment Report (CPAR) or PPQ is required for each project submitted. Each CPAR submitted shall have a recommendation of, “I would recommend them for similar requirements in the future.” Each PPQ submitted shall state “Yes” to the question “Would you hire or work with this firm again?”. In addition to providing all of the required information on the PDS template, the PDS shall explicitly define why the submitted project meets the DRC for which it had been submitted. One PPQ or CPAR shall be provided for each project used to satisfy a DRC. PPQs must be sent from their customer directly to Kristal Jones at kristal.r.jones@usace.army.mil.
The Contracting Officer will verify the submitted projects meet the definitive responsibility criteria as part of the responsibility determination. Bidders are not required to submit additional documentation related to these criteria at the time of bid. Instead, within three (3) business days after the date of bid opening, the Government will request supporting documentation from the apparent low bidder. If the apparent low bidder is determined not responsible, then the Government will request supporting documentation from the next lowest bidder. This process will continue until a bidder is determined responsible, or until all bidders have been determined not responsible. Bidders will be required to provide documentation within three (3) business days after receipt of request from the Government.
Failure to meet the three (3) business day deadline may result in a not responsible determination.
WHAT, HOW, AND WHERE TO SUBMIT BID
14. The following documents must be submitted with your IFB in original and one (1) copy:
(1) SF 1442, Solicitation, Offer and Award
a. Should include:
i. Unique Entity Identifier (known as DUNS)
ii. CAGE number
iii. Tax Payer ID number
(2) Solicitation amendments acknowledged, if applicable
(3) Bid Schedule
(4) Original Bid Guarantee with Power of Attorney
15. PUBLIC OPENING OF BIDS: Bids will be publicly opened at the date and time indicated in Block 13 of the Standard Form 1442 or otherwise stated in the latest amendment (if applicable). The Bid Opening will be a broadcast via live audio telephone conference. Interested parties may access the conference by calling the following number and entering the access code when prompted.
USA Toll-Free: (888) 273-3658 Access Code: 9843550 Security Code: 1234
16. Bidders shall submit their bids no later than the time and date specified in Block 13 of SF 1442 of this solicitation or the latest amendment (if applicable) as follows:
The Bidder’s bid shall be submitted electronically, as described below. The IFB will provide bid submission instructions and receipt date for bid submittal. The Bidder’s bid shall not contain classified data. The use of hyperlinks in bids is prohibited.
NOTE: The only authorized transmission method for bids in response to this solicitation is electronically via SAFE online submission. NO OTHER TRANSMISSION METHODS (EMAIL, FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.) WILL BE ACCEPTED.
The Bidder’s bid must be received by the Government…