Barkley Power Plant Turbine Generator Rehab NOI
Solicitation number
W912P519B0003
Issued by

About this file

This document includes an industry review presentation and notice of intent for the Barkley Power Plant Turbine Generator Rehabilitation project. The U.S. Army Corps of Engineers, Nashville District, seeks to increase generator maximum output from 41.52 MW to 46.5 MW by rewinding units 2, 3, and 4. The project also involves assessing and refurbishing mechanical systems to support increased load. An industry review webinar will be held on February 20, 2019 to present draft plans and specifications and seek contractor feedback. Questions must be submitted by March 1, 2019. The presentation outlines the project scope including turbine replacement for four units, generator rewind for three units, and refurbishment of disassembled parts. It provides draft definitive responsibility criteria for bidder qualification and describes the acquisition strategy as an invitation for bid with definitive responsibility criteria.

View the file

Other files

File Type Posted
GE_Reference_Drawings.pdf PDF
Newport_News_Reference_Drawings.pdf PDF
NEC_Reference_Drawing.pdf PDF
Trabon_Reference_Drawings.pdf PDF
Government_Reference_Drawings.pdf PDF
Barkley_TG_Draft_TPlans.pdf PDF
Barkley_TG_Draft_TSpecs.pdf PDF
Barkley_Rehab_Draft_Bid_Schedule_V7.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

.59

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Industry Day #2 February 20, 2019

BARKLEY TURBINE

GENERATOR

REHABILITATION

File Name

TOPICS OF DISCUSSION

Scope of Work:

Turbine Replacement for 4 units Generator Rewind for 3 units Refurbishment and inspection of disassembled parts

Changes since last Industry Day Installation of Government Owned transformers Asbestos Abatement Acquisition Strategy

PROJECT SCOPE

Refurbish units at Barkley to restore reliability

• Full turbine and generator rehabilitation on Unit 2, 3, and 4

• Turbine only on Unit 1 Small uprate – maximum output from 41.53 MVA to 46.5

MVA

New output rating of 41.85 MW @ .90 p.f.

Converting grease filled to oil filled hubs

Adding vibration monitoring New Kaplan turbine runners

Turbine Parts:

New Parts

Replacement 302” Turbine Runner, CA6NM blades and Steel Hub Discharge ring insert and stainless steel overlay to the bottom of the discharge area New Static Oil Head design and pipes to extend oil head oil to new runner hub

Vibration Monitoring System

PROJECT SCOPE

PLANS AND SPECIFICATIONS

• Reference drawings of existing unit and powerhouse

• Contract drawings

– Addition of a Static oil head and oil filled runner concept

– Kaplan blade seal leakage detection system concept

– Fabrication of draft tube gates

• Specifications

- Design and Model test

- Runner Fabrication

- Turbine work platform design

- Generator coil design

CHANGES SINCE LAST INDUSTRY DAY

• Installation of Government owned replacement transformers is not included in the contract.

• Asbestos mitigation has been removed from the contract.

– Government will run a separate contract for asbestos mitigation in parallel with turbine-generator contractor.

– Prime contractor will not have direct control over asbestos mitigation procedures during the turbine-generator tear down.

ACQUISITION STRATEGY

Invitation for Bid (IFB) with Definitive Responsibility Criteria

(DRC)

– FAR 9.104-2 DRC Definition: “Definitive Responsibility Criteria are specific and objective standards established by an agency as a precondition to award which are designed to measure a prospective contractor's ability to perform the contract.”

– Bidders to submit DRC responses with bids.

– 8 draft DRC’s total for this contract.

For all DRC’s:

– Define “substantially complete” as at least 50% complete.

– Define “10 years” as 10 years from the date solicitation is posted.

– Define “6 years” as 6 years from the date solicitation is posted.

– Past Performance Questionnaires (PPQ) shall be submitted for each project with an overall recommendation that the customer would work with the contractor again.

DRAFT DEFINITIVE RESPONSIBILITY CRITERIA

1. Provide a minimum of (3) projects completed within the last (10) years, or (2) projects completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate design and scale model testing of new Kaplan runners with a minimum blade diameter of 200 inches.

2. Provide a minimum of (2) projects completed within the last (10) years, or (1) project completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate design of a static oil head system for Kaplan runners with a minimum blade diameter of 200 inches.

3. Provide a minimum of (2) projects completed within the last (10) years, or (1) project completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate disassembly of a Kaplan turbine generator unit with a minimum blade diameter of 200 inches.

4. Provide a minimum of (2) projects completed within the last (10) years, or (1) project completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate experience designing and installing a new or replacement 13.8KV salient pole generator with a size no less than 30 MW.

5. Provide a minimum of (2) projects completed within the last (10) years, or (1) project completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate experience rehabilitating field coils for a salient pole generator with field current rating and synchronous speed no less than 800 amps and 65 (-10/+85) rpm, respectively.

6. Provide a minimum of (2) projects completed within the last (10) years, or (1) project completed in the last (10) years and (1) project that is currently substantially complete, that were self-performed as a prime or sub-contractor, that demonstrate experience installing via continuous stacking method a core for a 13.8 KV salient pole generator of a size no less than 30 MW.

7. At least one of the submitted projects must have been completed within the last (6) years with a contract value of at least $50 million.

8. The Bidder's workplace safety record shall be checked using either of the following methods:

The Bidder shall provide a letter from their insurance company stating the Bidder's most current experience modification rate (EMR). Bidders providing an EMR greater than 1.0 will be determined not responsible.

The Bidder shall provide a total recordable incident rate (TRIR) calculation for calendar year 2018. The TRIR calculation shall be provided on the OSHA Form 300A. Bidder's submitting a TRIR greater than 3.0 will be determined not responsible.

QUESTIONS AND COMMENTS

Industry will be given nine (9) calendar days to submit questions to Lether Robinson at lether.e.robinson@usace.army.mil at the conclusion of the Industry Review Webinar.

All questions and comments must be submitted to Lether Robinson no later than 01 March 2019 at 4:00 pm Central Time.

Information gathered will be used by the Government to make appropriate acquisition decisions.

Replies to responses, comments, or suggestions will not be provided or published.

ITEMS POSSIBLY CONTAINING ASBESTOS

Generator

• Asbestos dust in air housing from brake pads

• Wiring insulation in air housing

• Water piping insulation (if present)

• Miscellaneous gaskets and seals

• Stator coil packing (rewedge may have replaced all of these materials – use spares)

• Packing / fillers, Blocking, Lasing

• Stator coils (chisel out sample areas)

• bottom coil – slot portion

• top coil – slot portion

• transition from slot to jumper / end winding / turn

• jumper / end winding / turn

• Field coil (chisel out sample area from spares)

• Rotating exciter (chisel out from spares)

• Poles and Coils

• Generator leads and connection point putty – primarily field winding connection joints

• Check GE Bill of Materials – may be called out

• Can chisel apart a sample joint and reinsulate

Turbine

• Original turbine shaft packing

• Original wicket gate packing

• Original oil head packing.

• Original turbine blade packing

• Original electrical wiring in the turbine pit.