W912P5-15-B-0007_TSpecs_2015-08-03.pdf
PDF 12 MB Posted
- Solicitation number
- W912P5-15-B-0007
About this file
Technical Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912P5-15-B-0007_0001.pdf | ||
| W912P5-15-B-0007_Plans.pdf | ||
| WD_05-2187(Rev-16).pdf | ||
| QASP.pdf | ||
| W912P5-15-B-0007.pdf | ||
| TN150001_01-02-2015.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912P5-15-B-0007
US Army Corps Of Engineers Nashville District
STREAMBANK STABILIZATION
RIVERSIDE DRIVE
Cumberland River Watershed Cumberland River Clarksville, Montgomery County, Tennessee
Technical Specifications
July 2015
THIS PAGE INTENTIONALLY LEFT BLANK
FOR DUPLEX PRINTING
Sreambank Stabilization Clarksville, Tennessee Riverside Drive W912P5-15-B-0007
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 GENERAL REQUIREMENTS
01 22 00 MEASUREMENT AND PAYMENT
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01 QUALITY CONTROL
01 45 02 QUALITY CONTROL SYSTEM (QCS)
01 57 20 ENVIRONMENTAL PROTECTION
01 78 02 AS-BUILT DRAWINGS
01 95 00 FORMS AND ATTACHMENTS
DIVISION 31 - EARTHWORK
31 05 22 GEOTEXTILES USED AS FILTERS
31 11 00 CLEARING, GRUBBING, AND EXCAVATION
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 31 19 STONE PROTECTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL SCOPE OF WORK
1.2 REFERENCES
1.3 PARTNERING
1.4 COORDINATION CONFERENCES
1.5 EVALUATION OF CONTRACTOR PERFORMANCE
1.6 CONCURRENT WORK
1.7 ACCIDENT PREVENTION
1.8 SUBMITTALS
1.9 RIVER ELEVATION INFORMATION
1.10 MEASUREMENT AND PAYMENT
1.11 PROJECT SIGNS
1.11.1 General
1.11.2 Materials
1.11.3 Painting
1.11.4 Erection and Maintenance
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 SURVEY REQUIREMENTS
3.1.1 Initial Surveys
3.1.2 In-Progress Surveys
3.1.3 Final As-built Survey
3.1.4 Field Survey Submittals
3.1.5 Benchmarks
3.1.6 Coordination With the Government
-- End of Section Table of Contents --
SECTION 01 00 00 Page 1
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL SCOPE OF WORK
This contract covers bank stabilization at Riverside Drive in Clarksville, Tennessee. The work shall be performed in accordance with the specifications and contract drawings.
The Contractor is required to provide bank stabilization by furnishing all necessary technical expertise; planning; management; supervision;
inspection; personnel; parts; tools; fuel; equipment; vehicles and transportation; materials and supplies; except as otherwise provided for herein, required to perform the required tasks. Site access shall be exclusively from the river; however the Contractor may safely move equipment and material within the work limits to the extent required to successfully complete the project as specified herein. The Contractor is required to commence work within ten (10) days of the issuance of the Notice to Proceed, and provide the services in the performance period specified in the contract. All work shall be completed as specified, detailed and/or in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, contained herein or incorporated by reference. Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.
1.2 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices
1.3 PARTNERING
In order to most effectively accomplish this contract, the Government urges the contractor to join with the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship, both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.
SECTION 01 00 00 Page 2
1.4 COORDINATION CONFERENCES
Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to the required work. The Corps of Engineers and the Contractor will be represented at each of these meetings. Similar information concerning replacement personnel shall be forwarded to the Contracting Officer, should any replacement be required at any time during the life of this contract. Coordination conferences will be scheduled to occur when notified by the Contracting Officer.
1.5 EVALUATION OF CONTRACTOR PERFORMANCE
The Contractor's performance will be evaluated in accordance with FAR Part
42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section
01 95 00 FORMS AND ATTACHMENTS.
The Contractor's review of the evaluation shall be completed electronically at the CPARS / CCASS website, http://www.cpars.gov. This website also includes guidance and the user's manual.
Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.
1.6 CONCURRENT WORK
The work required in this contract is in addition to the routine operation and maintenance performed by Government personnel and by other contracts.
The Government may, from time to time, perform work beyond the scope of this contract, within the geographic limits of this contract using its own personnel, volunteers or other contract personnel, and the Contractor shall be required to coordinate his efforts with such work. The Contractor's work and responsibility shall include, but shall not be limited to: all planning, programming, administration and management necessary to assure that all work is conducted in accordance with the contract and all applicable laws, regulations, codes, or directives. The Contractor shall insure that all work meets or exceeds critical reliability rates or tolerances specified, or included in referenced documents. The Contractor shall perform all related Contract administrative services necessary to perform the work such as quality control; financial control; maintenance of accurate and complete Contractor records and files; and for preparing and providing reports to the Government.
1.7 ACCIDENT PREVENTION
Contract Clause entitled ACCIDENT PREVENTION addresses the contract requirement to comply with the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. Accident prevention requirements for this project are also stated in Section 01 35 26 GOVERNMENTAL SAFETY
REQUIREMENTS.
SECTION 01 00 00 Page 3
1.8 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only or as otherwise designated. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Pre-Installation Submittals
Project Schedule; G The Contractor shall submit a project schedule for this task order.
Work Plan; G After award of the contract, the Contractor shall, in writing, submit a Work Plan to the Contracting Officer detailing the activities to take place during the performance of this contract.
The plan shall include activities for the protection of historical, archaeological, and cultural resources; clearing methods, operations which will be performed from the floating plant and barges; and placement processes for materials. The Contractor shall not begin work until approval of the Work Plan.
1.9 RIVER ELEVATION INFORMATION
The work area for this job is approximately 22 river miles below Cheatham Dam as well as approximately 96 river miles above Barkley Dam. As such, river conditions can change due to variations in releases from the dam. Release information is available from USACE at http://www.lrn-wc.usace.army.mil/hh/WM_Info.htm. The National Weather Service maintains a stream gage in Clarksville on the Cumberland River. This gage data is available online at http://water.weather.gov/ahps2/hydrograph.php?wfo=ohx&gage=ckvt1. Attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS is a river stage graph, in the vicinity of the project, for years 2010 through 2015.
1.10 MEASUREMENT AND PAYMENT
Measurement and payment will be made as specified in Section 01 22 00
MEASUREMENT AND PAYMENT.
1.11 PROJECT SIGNS
1.11.1 General
The Contractor shall furnish and erect within 30 days after issuance of the Notice to Proceed, at an agreed location on his floating plant, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN. The signs shall be lettered on one side only and shall conform to EP 310-1-6a, EP 310-1-6b, and to the details and colors indicated in the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:
RIVERBANK STABILIZATION
1.11.2 Materials
The sign shall be constructed with a face sheet of 3/4 inch exterior grade
SECTION 01 00 00 Page 4 plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.
1.11.3 Painting
The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.
1.11.4 Erection and Maintenance
The signs shall be erected at the designated locations. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs out the life of the contract. The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor.
1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at:
http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance:
http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act:
http://benefits.va.gov/vow/
Army Wounded Warrior Program:
http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material:
http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_guide_t
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 SURVEY REQUIREMENTS
All surveys shall be certified by a land surveyor with current State registration. Surveyor can be certified in any state. It is not required that the Surveyor be registered in the State where the work is being performed. Prior to performing any work under this Section, coordinate all
SECTION 01 00 00 Page 5 operations with the Government's on-site representative so that surveys will be made at the appropriate time. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. All surveys shall be conducted in the presence of the Contracting Officer or his designated representative unless this requirement is waived by the Contracting Officer. In the event of unavailability of the Contracting Officer, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with the specifications. If one has not already been established, a fixed baseline along the top of the streambank to be protected shall be established. This baseline shall be parallel to the top of bank and shall be located slightly landward of the anticipated maximum landward extent of disturbance. It shall also be located such that cross-sections surveyed perpendicular to this baseline will also be perpendicular to the streambank. A sketch of this baseline shall be provided to the Contracting Officer along with horizontal coordinates at the endpoints and at all changes in alignment. These horizontal coordinates shall be in the UTM 16, NAD 83 coordinate system and shall be to the nearest foot with accuracy of +/- 0.5 foot. Cross-sections for all surveys shall be surveyed perpendicular to the streambank and shall be no more than 50 feet apart as measured along the baseline, with the readings at 5-foot intervals and at breaks in the grade along the line, unless otherwise specified. They shall extend from the baseline past the toe of riprap. Additional sections at closer spacing at significant changes in riverbank conditions may be required, as determined appropriate by the Contracting Officer. Cross-sections surveyed at locations of significant changes in riverbank conditions are for the purpose of arriving at accurate quantities for payment. The station at which the cross-section intersects the baseline shall be used to identify it. Surveyed elevations shall reference the same datum used on the drawings and shall be to the nearest tenth of a foot with an accuracy of +/- 0.1 foot. Additional elevations and/or soundings shall be taken if the Contracting Officer deems such to be necessary or advisable. The following procedures and equipment shall be utilized to perform all surveys unless alternative methods are approved by the Contracting Officer.
a. Above Water: The elevation of stone above the water surface shall be determined by the use of a leveling instrument and a rod having a base 12 inches in diameter. The bottom tip of the level shall not be placed at the highest nor lowest point of riprap. Rather the rod shall be placed at an elevation representing the average top surface of the riprap blanket.
b. Below Water: Underwater elevations shall be obtained by sounding wherever practicable. For portions of the work that are under water, sounding surveys shall be performed either by means of a sounding pole or a sounding basket weighing about 8 1/2 pounds, each of which has a base measuring 12 inches in diameter. Should sounding not be practicable, survey by fathometer will be allowed as long as it is GPS controlled.
c. Gage Board: The Contractor shall install a gage board at the project site. The gage shall be checked prior to any survey.
d. Electronic Depth Recorder (Fathometer) Method: The survey depth recorder used must be a standard model acceptable to the Contracting Officer using a GPS locator and a sounding chart that can be read directly to the nearest foot and estimated to the nearest tenth (0.1) of a foot. Accuracy shall be better than 1/2 of 1 percent. When using an electronic depth recorder the following procedures shall be used.
SECTION 01 00 00 Page 6
(1) The depth recorder shall be calibrated and adjusted for the gage, with check bar, at least six (6) times within a normal eight (8) hour work day. The gage shall be checked prior to each calibration and recorded on the sounding chart or in the field notes.
(2) Normal calibration times shall be at the beginning of the work day, mid-morning, close of morning's work, start of afternoon's work, mid-afternoon, and the end of the day.
(3) Further calibrations shall be performed whenever there is any malfunction within the depth recorder or transducer which might affect the soundings, a major gage change, or change in water temperature due to industrial discharge or other causes.
(4) The check bar shall be set at approximately the deepest sounding in the area to be sounded.
(5) The depth recorder shall be calibrated to read at low water datum.
(6) When checking the calibration at mid-morning, end of morning, mid-afternoon and end of work, the same setting used for the previous calibration shall be used.
(7) If the calibration check does not agree with the previous calibration, the depth recorder shall be calibrated to the proper setting.
(8) Under no circumstances shall the setting of the depth recorder be changed between calibrations.
(9) When sounding, the speed of the sounding boat shall be as constant as possible, preferably between 180 and 220 feet per minute.
3.1.1 Initial Surveys
In order to define the original ground conditions, the Contractor shall survey the area to receive stone protection after clearing and grubbing has been completed. This initial survey shall provide the basis by which the Contracting Officer determines and directs the extent of excavation and grading required. The riverbank protection templates shown in the Contract Documents generally define the criteria that shall be used by the Contracting Officer to determine the extent of excavation needed at each section. No excavation shall be performed prior to the Contracting Officer making this determination. Another full survey of the site shall be performed after excavation and grading is complete. The volume of excavated material shall be determined by the average end area method based on these two surveys.
These surveys shall also be used by the Contracting Officer to provide direction to the Contractor on the desired location for the riverbank protection, the desired finished slope, the location for the top of the protection, and any areas that may require stone protection or soil fill thicker than the specified thickness shown on the drawings. The riverbank protection templates shown in the Contract Documents generally define the criteria that shall be used by the Contracting Officer to determine the extent of protection needed at each section. No material placement shall be performed prior to the Contracting Officer making the determinations
SECTION 01 00 00 Page 7 described above.
3.1.2 In-Progress Surveys
The Contractor shall perform partial surveys as the work progresses to verify lines, grades and thickness established for completed work. Surveys made by the Contractor are required on each material placed to determine that the materials have been acceptably placed in the work. At least one in-progress survey shall be made by the Contractor as soon as practicable after completion of each 300-foot segment of stone placement, or as determined appropriate by the Contracting Officer. Approval of cross-sections based upon in-progress surveys shall not constitute final acceptance of the work.
3.1.3 Final As-built Survey
A final as-built survey shall be performed after all materials have been placed at the site and have been accepted by the Contracting Officer. The results of this survey will be used to check for any volume of material placed in excess of that required by the Contract Documents and the Contracting Officer, and in the preparation of the as-built drawings required in Section 01 78 02 AS-BUILT DRAWINGS.
3.1.4 Field Survey Submittals
The submittal of field survey results shall include a legible copy of all field notes, and electronic, scaled drawings of all data, including plotted cross sections. This information shall be certified by the registered land surveyor in charge of the work.
3.1.5 Benchmarks
The following benchmarks were developed by the City of Clarksville. The benchmarks are reported in TN State Plane Coordinates as follows; title, Y, X, elevation, description of location.
a) BM1,797797.538,1567465.019,390.060,XBM CCAP
b) BM2,797598.067,1567444.501,389.667,XBM MAG IN ASPH
c) BM3,797385.114,1567346.777,388.406,XBM RR SPIKE IN POWER POLE
d) BM4,797061.613,1567134.942,388.446,XBM RR SPIKE IN POWER POLE
3.1.6 Coordination With the Government
For the purpose of coordinating with the Government, the Contractor shall schedule surveys and interactions with the Government during the normal business hours of Monday through Friday 7:30 a.m. to 4:00 p.m. Central Time with the exception of Federal Holidays. The Government will make every effort to make design determinations and approve segments of completed work during the performasnce of this contract in a timely manner.
-- End of Section --
SECTION 01 00 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PAYMENT ITEMS
1.2.1 Survey Work
1.2.2 Floating Plant
1.2.3 Clearing and Grubbing
1.2.4 Excavation
1.2.5 Disposal
1.2.6 Geotextiles
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
1.2.7 Riprap
1.2.7.1 Payment
1.2.7.2 Measurement
1.2.7.3 Unit of Measure
1.3 BARGE LOAD
1.4 DETERMINATION OF EXCESS STONE
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Gaging Table Data
Stone hauling vessel gaging tables and a copy of the data and calculations used for the preparation of the tables.
1.2 PAYMENT ITEMS
Payment items for the work of this contract for which payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed payment item most closely associated with the work involved. The payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2.1 Survey Work
No separate payment will be made for field surveys including baseline surveys, initial surveys, in-progress surveys, and final as-built surveys.
All costs associated with field surveys shall be considered incidental to the costs of excavation and stone placement.
1.2.2 Floating Plant
Measurement shall be by the job for delivery, set-up and removal of the floating plant operation for the duration of the contract. Payment shall be made at the contract price for "Floating Plant Assembly/ Disassembly".
Payment shall be inclusive of all labor, materials and equipment. The Contractor may request partial payment for "Floating Plant Assembly/Disassembly" upon delivery and set up of floating plant. The balance will be paid after substantial completion of work as determined by the Contracting Officer.
1.2.3 Clearing and Grubbing
Payment will be made for Clearing and Grubbing acceptably performed as
SECTION 01 22 00 Page 2 specified in Section 31 11 00 CLEARING, GRUBBING, AND EXCAVATION.
Measurement shall be by the job. Payment shall be made at the contract unit price per job for "Clearing and Grubbing".
1.2.4 Excavation
Payment will be made for Excavation acceptably performed as specified in Section 31 11 00 CLEARING, GRUBBING, AND EXCAVATION. Measurement shall be by the number of cubic yards of material acceptably excavated and redistributed or removed from the site, including stripping and reuse of topsoil as specified herein, measured in original position, and computed by the average end-area method. This measurement does not include any yardage excavated without authorization beyond the indicated slope lines or the yardage of any material which is to be used for purposes other than those directed. The final cross-sectional area measured for each station or fraction thereof, shall not include water, mud, or muck which cannot be drained. No distinction shall be made between materials which are excavated in the dry or wet. Placement of suitable excavated material on the streambank shall be considered incidental to excavation and no separate payment shall be made. Seeding of disturbed areas outside the limits of the stone protection shall be considered incidental to excavation and no separate payment shall be made. Payment will be made at the contract unit price per cubic yard for "Excavation", which price shall constitute full compensation for all plant, equipment, tools, labor, materials, and supplies necessary to complete the work.
1.2.5 Disposal
No separate payment will be made for disposal of cleared, grubbed, and excavated materials or any other site debris. All costs associated with disposal shall be considered incidental to the costs of clearing and grubbing and/or excavation.
1.2.6 Geotextiles
1.2.6.1 Payment
Payment will be made for Geotextiles acceptably placed as specified in Section 31 05 22 GEOTEXTILES USED AS FILTERS. Payment will be made at the contract unit price and will constitute full compensation to the Contractor for providing all plant, labor, material, and equipment and performing all operations necessary for the complete and satisfactory installation of the geotextile. The following items are included in the contract unit price for Geotextiles and will not be counted a second time in the process of determining the extent of geotextile placed: Material and associated equipment and operation used in laps, seams, or extra length; securing pins and associated material, equipment, and operations. No payment will be made for geotextiles replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.
1.2.6.2 Measurement
Installed geotextiles will be measured for payment in place to the nearest square yard of protected area as delineated in the drawings.
1.2.6.3 Unit of Measure
Unit of measure: Square Yard.
SECTION 01 22 00 Page 3
1.2.7 Riprap
1.2.7.1 Payment
Payment for Riprap acceptably placed, as specified in Section 35 31 19 STONE PROTECTION, will be made at the applicable contract unit price for "Riprap". Price and payment shall constitute full compensation for furnishing, hauling, handling, placing, and maintaining the riprap until final acceptance by the Government. No payment will be made for excess riprap left in place. Existing stone placed in lieu of new stone from off-site sources will be excluded from measurement and payment.
1.2.7.2 Measurement
Riprap will be measured for payment by the ton as determined by barge displacement.
1.2.7.3 Unit of Measure
Unit of measure: ton.
1.3 BARGE LOAD
Stone delivered by barge will be measured for payment, in the presence of the Contracting Officer, by weight determined by barge displacement.
Furnish the Contracting Officer a barge displacement table not less than 10 work days prior to unloading the stone from any barge. Each table submitted shall show the name and/or number of the barge owner, the name of the fabricator, and the certification and date of certification of the person or firm preparing the table. Furnish with the barge displacement tables a drawing or sketch of each barge, dimensioned in sufficient detail to permit checking of the tables. The drawings shall show, as a minimum, the length, width, depth of the barge, and dimensions of the rake or rakes. Each such table shall have its accuracy certified by a person or firm, other than the Contractor, customarily performing this service. Each table submitted shall contain, in parallel columns, the freeboard of the barge in feet and tenths from zero to the full depth of the barge and the corresponding gross displacement to the nearest ton. Each barge shall be suitably marked with three displacement gaging locations on each side near each end of the barge and two amidship on opposite sides. Each gaging location shall be marked by a line perpendicular to the edge of the barge, 4 inches wide and 1 foot long, on both the deck and side of the barge and two amid ship on opposite sides. Barges with rakes shall have the displacement gaging lines placed at each corner of the box section between the rakes. If a barge has a box end or ends, the gaging locations shall be placed approximately 4 feet from the box end(s). The freeboard will be measured at the six gaging locations and the displacement determined by the use of "STANDARD BARGE TABLES" from the average of these measurements. The displacement will be determined before and after being unloaded and the difference between these values shall be the quantity delivered. Submit the Gaging Table Data as specified in the Submittals paragraph. Barges shall be loaded so that the readings taken at the gaging locations do not vary more than 1.5 feet port to starboard fore and aft and do not vary more than 0.5 feet port to starboard. If such is not the case, trim the carrier by shifting the stone until this limit is reached, before the measurement will be accepted. The draft shall be determined from the average of all six readings weighting the readings of the middle gage at double those of the end gages. (G1 + G2 + 2xG3 + 2xG4 + G5 + G6) divided by 8 = average draft. All carriers used in transporting stone shall be free of leaks such
SECTION 01 22 00 Page 4 as would render accurate gauging difficult. Facilities for inspecting the hold of each carrier to determine whether leakage is occurring shall be provided. Each carrier shall also be provided with adequate pumping facilities, and if water is found to be accumulating in the hold, the carrier shall be pumped dry before each gaging, both before and after unloading. Lightening by pumping or by transfer of crew or supplies will not be permitted while stone is being transferred. Rejected stone and unacceptable material shall be left aboard the barge until after the final readings have been taken.
1.4 DETERMINATION OF EXCESS STONE
All stone outside the limits and tolerances of the cross sections of the structure, except variations so minor as not to be measurable, will be deducted from the quantity of new stone for which payment is to be made.
The surveys made under paragraph IN-PROGRESS SURVEYS or paragraph FINAL SURVEYS of Section 01 00 00 GENERAL REQUIREMENTS will be used when deemed appropriate by the Government's on-site representative to calculate excess material. Weight of excess stone will be determined from the cross sections obtained on the basis that one cubic yard of volume (including voids) is equal to 3,000 pounds. If the Contractor can show that the bulk specific gravity of the stone furnished or the percentage of voids is other than as listed, shall be recomputed. Should any excess stone be disclosed above the tolerance line as defined in paragraph PLACEMENT, its volume will be computed by the average end area method, based upon the cross section in the following manner. The average end area of excess stone above the tolerance line for two (2) successive cross sections, multiplied by the distance between the cross sections will be accepted as the volume. If the Contractor chooses to not remove such excess stone, deductions for the weights thereof will be made from contract payments for new stone. In addition to the above, stone, which has been delivered to the site and has been lost or wasted or otherwise not properly incorporated into the final required work, shall be deducted from the quantity for which payment is to be made.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 22 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Environmental Assessment of Variations
1.8.5 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Pre-Intallation Submittals
Submittals which are required prior to start of work, or the start of the next major phase of work on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates of insurance
Surety bonds
List of proposed Subcontractors
SECTION 01 33 00 Page 2
List of proposed products
Construction progress schedule
Network Analysis Schedule (NAS)
Submittal register
Schedule of prices
Health and safety plan
Work plan
Quality Control(QC) plan
Environmental protection plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
SECTION 01 33 00 Page 3
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with this section.
SD-01 Pre-Installation Submittals
Submittal Register; G
SECTION 01 33 00 Page 4
1.4 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.4.1 Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.2 Information Only
Submittals not requiring Government approval will be for information only.
They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 PREPARATION
1.5.1 Transmittal Form
Use the sample transmittal form (ENG Form 4025), included in Section 01 95 00 FORMS AND ATTACHMENTS, for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the QCS software that the Contractor is required to use for this contract. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Electronic File Format
Provide submittals other than material samples in electronic format. The electronic submittal file must be compiled as a single, complete document, to include the Transmittal Form described in paragraph 1.5.1 Transmittal Form. The electronic submittal file must be named specifically according to its contents (e.g. 01 45 01-1.2_Quality Control Plan.pdf).
Electronic files must be of sufficient quality that all information is legible. Electronic format shall be in Adobe.PDF format, unless otherwise specified or directed by the Contracting Officer's Representative (COR).
Whenever possible, PDF files shall be generated from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Files exceeding 30 pages shall be indexed and bookmarked to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic submittal documents fewer than 10MB to an email address as directed by the COR. Electronic documents over 10MB shall be provided on a CD/DVD, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:
https://safe.amrdec.army.mil/safe/
SECTION 01 33 00 Page 5
1.6 QUANTITY OF SUBMITTALS
The Contractor shall submit to the Contracting Officer electronic copies of all submittals required under this contract and identified under the various specifications sections. The electronic copies shall be provided in Acrobat PDF as described in paragraph 1.5.2 Electronic File Format.
1.7 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.8.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.
The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.
1.8.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its
SECTION 01 33 00 Page 6
Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Environmental Assessment of Variations
Any variations requested by the Contractor, which may have an environmental impact, shall meet the requirements of Section 01 57 20 ENVIRONMENTAL PROTECTION. The Contracting Officer reserves the right to disapprove alternate methods, even if they are more cost effective, if the Contracting Officer determines that the proposed alternate method will have an adverse environmental impact.
1.8.5 Review Schedule Is Modified
In addition to normal submittal review period of 30 calendar days, a period of 10 additional calendar days will be allowed for consideration by the Government of submittals with variations.
1.9 SUBMITTAL REGISTER
Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and
(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 02 QUALITY CONTROL SYSTEM (QCS). The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.
1.9.1 Use of Submittal Register
Submit submittal register. Submit with QC plan and project schedule.
Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for approving
SECTION 01 33 00 Page 7 authority to receive submittals.
Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.9.2 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.9.3 Approving Authority Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.9.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Government with each invoice request.
1.10 SCHEDULING
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.
b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying
SECTION 01 33 00 Page 8 submittals required by the contract documents but which have been omitted from the register or marked "N/A."
c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.
d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
e. Except as specified otherwise, allow review period, beginning with receipt…