Sreambank Stabilization Clarksville, Tennessee Riverside Drive W912P5-15-B-0007

SECTION 01 45 01

QUALITY CONTROL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3740 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction

ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction

INTERNATIONAL CODE COUNCIL (ICC)

ICC IBC (2012) International Building Code

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-Installation Submittals

Contractor Quality Control (CQC) Plan; G

SD-11 Closeout Submittals

Progress and Work Photographs

1.3 PAYMENT

Separate payment will not be made for providing and maintaining an effective Quality Control program, and all associated costs will be included in the applicable Bid Schedule payment items.

PART 2 PRODUCTS

Not Used

SECTION 01 45 01 Page 3

H3EXCJWP

Typewritten Text

H3EXCJWP

Typewritten Text

(QASP)

H3EXCJWP

Typewritten Text

H3EXCJWP

Typewritten Text

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Establish and maintain an effective quality control (QC) system. QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover alloperations, both onsite and offsite, and be keyed to the proposed work sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall work activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all work and related activities at the site, except as otherwise acceptable to the Contracting Officer.

3.2 QUALITY CONTROL PLAN

Submit no later than seven calendar days prior to the date of the Pre-Installation Conference, the Contractor Quality Control (CQC) Plan.

The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. The Government will consider an interim plan for the first 30 calendar days of operation. Site work will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.

3.2.1 Content of the CQC Plan

Include, as a minimum, the following to cover all operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.

SECTION 01 45 01 Page 4

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking work deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

h. Reporting procedures, including proposed reporting formats.

i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.

j. Any special inspection requirements as required in accordance with

ICC IBC

3.2.2 Acceptance of Plan

Acceptance of the Contractor's plan is required prior to the start of work.

Acceptance is conditional and will be predicated on satisfactory performance during the work. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

3.2.3 Notification of Changes

After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3.3 COORDINATION MEETING

After the Pre-Intallation Conference, before start of work, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. Also, the final or interim CQC Plan must be approved by the Government prior to scheduling the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures

SECTION 01 45 01 Page 5 which may require corrective action by the Contractor.

3.4 QUALITY CONTROL ORGANIZATION

3.4.1 Personnel Requirements

The requirements for the CQC organization are a CQC System Manager and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Safety and Health Manager must report directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization shall be responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.

3.4.2 CQC System Manager

Identify as CQC System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be a graduate engineer with a minimum of 10 years installation experience on work similar to the contract. Exceptions to the graduate engineer requirement will be considered by the Government based on review of supplied personnel experience. This CQC System Manager shall be on the site at all times during installation and shall be employed by the prime Contractor. The CQC System Manager may serve as the Safety and Health Manager but shall be assigned no separate duties as project superintendent. An alternate for the CQC System Manager shall be identified in the plan to serve in the event of the System Manager's absence. The requirements for the alternate shall be the same as for the designated CQC System Manager.

3.4.3 Specialized CQC Personnel

As needed to meet Quality Control objectives, the Contractor shall provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: Electrical, Mechanical, Civil, Structural, Environmental, Architectural, and/or Materials Technician.

These individuals shall be in addition to CQC personnel specified elsewhere in the contract. These individuals may be employees of the prime or subcontractor; shall be responsible to the CQC System Manager; shall be physically present at the work site during work on their areas of responsibility; and shall have the necessary education and experience in accordance with the experience matrix listed herein. These individuals may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan.

A single person may cover more than one area provided that they are qualified to perform QC activities in each designated area and that

SECTION 01 45 01 Page 6 workload allows.

Experience Matrix

Area Qualifications

Civil Graduate Civil Engineer or Site Manager with 2 years experience in the type of work being performed on this project or technician with 5 yrs related experience

Environmental Graduate Environmental Engineer with 3 yrs experience

Submittals Submittal Clerk with 1 yr experience

Concrete, Pavements and Soils

Materials Technician with 2 yrs experience for the appropriate area

3.4.4 Additional Requirement

In addition to the above experience and education requirements the CQC System Manager must have completed the course entitled "Construction Quality Management For Contractors". This course is periodically offered by the Corps of Engineers. Contact the Contracting Officer for additional course information including schedule and location.

3.4.5 Organizational Changes

Maintain the onsite CQC staff at the strength level needed by ongoing activities. The Contractor may adjust the onsite CQC staff as appropriate for work activities which may not require full time staff support as listed in paragraph 3.4.3 Specialized CQC Personnel. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Government for acceptance in writing.

3.5 SUBMITTALS AND DELIVERABLES

Submittals, if needed, must comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements.

3.6 CONTROL

Contractor Quality Control is the means by which the Contractor ensures that the work, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the CQC System Manager for each definable feature of the work as follows:

3.6.1 Preparatory Phase

This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

SECTION 01 45 01 Page 7

a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the contract drawings.

c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document tolerances and workmanship standards for that feature of work.

i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

j. Discussion of the initial control phase.

k. The Government must be notified at least 48 hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.

3.6.2 Initial Phase

This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.

b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing.

c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

SECTION 01 45 01 Page 8

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The Government must be notified at least 48 hours in advance of beginning the initial phase. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for future reference and comparison with follow-up phases.

g. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.6.3 Follow-up Phase

Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.6.4 Additional Preparatory and Initial Phases

Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

3.7 TESTS

3.7.1 Testing Procedure

Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.

Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish a validated testing laboratory at the project site. Perform the following activities and record and provide the following data:

a. Verify that testing procedures comply with contract requirements.

b. Verify that facilities and testing equipment are available and comply with testing standards.

c. Check test instrument calibration data against certified standards.

d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.

e. Record results of all tests taken, both passing and failing on the CQC

SECTION 01 45 01 Page 9 report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.

3.7.2 Testing Laboratories

The listing of validated testing laboratories is available at http://www.erdc.usace.army.mil/Media/FactSheets/FactSheetArticleView/tabid/9254/Article/4

3.7.2.1 Capability Check

The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel must meet criteria detailed in ASTM D3740 and

ASTM E329.

3.7.2.2 Capability Recheck

If the selected laboratory fails the capability check, the Contractor will be assessed a charge of $1,000.00 to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor.

3.7.3 Onsite Laboratory

The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.

3.8 COMPLETION INSPECTION

3.8.1 Punch-Out Inspection

Conduct an inspection of the work by the CQC Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS Clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.

3.8.2 Pre-Final Inspection

The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final

SECTION 01 45 01 Page 10

Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph must be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.

3.8.3 Final Acceptance Inspection

The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative must be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost.

3.9 DOCUMENTATION

Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:

a. Contractor/subcontractor and their area of responsibility.

b. Operating plant/equipment with hours worked, idle, or down for repair.

c. Work performed each day, giving location, description, and by whom.

When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.

d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.

e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.

f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.

g. Offsite surveillance activities, including actions taken.

h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.

SECTION 01 45 01 Page 11

i. Instructions given/received and conflicts in plans and/or specifications.

j. Contractor's verification statement.

Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Furnish the original and one copy of these records in report form to the Government daily within 24 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.

3.10 REQUIRED FORMS

Required forms are included in the QCS software specified in Section

01 45 02 QUALITY CONTROL SYSTEM (QCS).

3.11 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.

3.12 PROGRESS AND WORK PHOTOGRAPHS

3.12.1 General

The Contractor shall, during the progress of the project, furnish the Government progress photographs to depict progress and work conditions of the site work. The work photographs shall be taken at project initiation, at monthly intervals thereafter, and after completion of work. No separate payment shall be made for these services and all costs in connection thereto shall be considered incidental to costs of the representative work area.

3.12.2 Photographs

Photographs depicting progress shall be delivered to the Government along with each request for payment. Photographs depicting specific work, as specified above, shall be submitted with the monthly request for payment in the month which the work took place. The progress photographs shall be taken from not less than two positions for each work area, a minimum of 10 photographs shall be taken at different locations per month. They shall show, in as much as practical, work accomplished since the previous

SECTION 01 45 01 Page 12 photographs. Project initiation photographs shall be taken from the same location and angle as the project completion photographs. The photographs shall be high resolution digital images saved as JPEG (Joint Photographic Experts Group) files, or other acceptable compressed format. The resolution shall be no less than 1024 x 768 pixels. Each photograph shall be identified by the date and number of exposure, plus a brief description of the work photographed. The photographs shall be furnished to the Government on CD, by the time stipulated above. No separate payment shall be made for these services and all costs in connection thereto shall be considered incidental to costs of the representative work area.

3.12.3 Delinquent Photographs

For each month the Contractor fails to submit progress and work photographs, the Contracting Officer will retain $200.00 or 1 percent of the progress payment, whichever is greater. Also, the Contracting Officer may, by contract or otherwise, have the progress and work photographs taken and modify the contract amount to reflect the charges for these photographs.

3.13 DEFICIENCY TRACKING SYSTEM

The Contractor shall maintain a cumulative list of deficiencies identified for the duration of the project. Deficiencies to be listed include those identified by the Contractor's Quality Control observations, test failures, Government oral observations and Notifications of Noncompliance. As a minimum, the list shall include the information contained in the Deficiency List included in Section 01 95 00 FORMS AND ATTACHMENTS. A current copy of the list shall be maintained at the project site at all times and shall be made available for review by Government personnel. Copies of updated listings shall be submitted to the Contracting Officer at least every 30 days. Listings shall be submitted via the QCS-RMS interface as specified in Section 01 45 02, QUALITY CONTROL SYSTEM (QCS). Payment will be withheld for deficient work until it has been corrected.

-- End of Section --

SECTION 01 45 01 Page 13

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 45 02

QUALITY CONTROL SYSTEM (QCS)

PART 1 GENERAL

1.1 Contract Administration

1.1.1 Correspondence and Electronic Communications

1.1.2 Other Factors

1.2 QCS SOFTWARE

1.3 SYSTEM REQUIREMENTS

1.4 RELATED INFORMATION

1.4.1 QCS User Guide

1.4.2 Contractor Quality Control (CQC) Training

1.5 CONTRACT DATABASE

1.6 DATABASE MAINTENANCE

1.6.1 Administration

1.6.1.1 Contractor Information

1.6.1.2 Subcontractor Information

1.6.1.3 Correspondence

1.6.1.4 Equipment

1.6.1.5 Management Reporting

1.6.1.6 Request For Information (RFI)

1.6.2 Finances

1.6.2.1 Pay Activity Data

1.6.2.2 Payment Requests

1.6.3 Quality Control (QC)

1.6.3.1 Daily Contractor Quality Control (CQC) Reports.

1.6.3.2 Deficiency Tracking.

1.6.3.3 QC Requirements

1.6.3.4 Three-Phase Control Meetings

1.6.3.5 Labor and Equipment Hours

1.6.3.6 Accident/Safety Reporting

1.6.3.7 Features of Work

1.6.3.8 Hazard Analysis

1.6.4 Submittal Management

1.6.5 Schedule

1.6.6 Import/Export of Data

1.7 IMPLEMENTATION

1.8 DATA SUBMISSION VIA OPTICAL DISK

1.8.1 File Medium

1.8.2 Optical Disk Labels

1.8.3 File Names

1.9 MONTHLY COORDINATION MEETING

1.10 NOTIFICATION OF NONCOMPLIANCE

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 45 02 Page 1

H3EXCJWP

Typewritten Text

-- End of Section Table of Contents --

SECTION 01 45 02 Page 2

SECTION 01 45 02

QUALITY CONTROL SYSTEM (QCS)

PART 1 GENERAL

1.1 Contract Administration

The Government will use the Resident Management System for Windows (RMS) to assist in its monitoring and administration of this contract. The Contractor must use the Government-furnished Construction Contractor Module of RMS, referred to as QCS, to record, maintain, and submit various information throughout the contract period. The Contractor module, user manuals, updates, and training information can be downloaded from the RMS web site (http://rms.usace.army.mil). This joint Government-Contractor use of RMS and QCS will facilitate electronic exchange of information and overall management of the contract. QCS provides the means for the Contractor to input, track, and electronically share information with the Government in the following areas:

Administration Finances Quality Control Submittal Monitoring Scheduling Import/Export of Data

1.1.1 Correspondence and Electronic Communications

For ease and speed of communications, both Government and Contractor will, to the maximum extent feasible, exchange correspondence and other documents in electronic format. Correspondence, pay requests and other documents comprising the official contract record will also be provided in paper format, with signatures and dates where necessary. Paper documents will govern, in the event of discrepancy with the electronic version.

1.1.2 Other Factors

Particular attention is directed to Section 01 33 00 SUBMITTAL PROCEDURES, and Section 01 45 01 QUALITY CONTROL, which have a direct relationship to the reporting to be accomplished through QCS. Also, there is no separate payment for establishing and maintaining the QCS database; all costs associated therewith will be included in the contract pricing for the work.

1.2 QCS SOFTWARE

QCS is a Windows-based program that can be run on a stand-alone personal computer or on a network. The Government will make available the QCS software to the Contractor after award of the contract. Prior to the Pre-Installation Conference, the Contractor will be responsible to download, install and use the latest version of the QCS software from the Government's RMS Internet Website. Upon specific justification and request by the Contractor, the Government can provide QCS on optical disk. Any program updates of QCS will be made available to the Contractor via the Government RMS Website as they become available.

SECTION 01 45 02 Page 3

1.3 SYSTEM REQUIREMENTS

The following is the minimum system configuration required to run QCS:

QCS and Quality Assurance System (QAS) System

Hardware

Windows-based PC 1000 MHz Pentium or higher processor

RAM 256+ MB for workstation / 512+ MB for server

Hard drive disk 1 GB space for sole use by the QCS system

Optical Disk (CD or DVD) Reader 8x speed or higher

Monitor SVGA or higher resolution (1024x768, 256 colors)

Mouse or other pointing device

Windows compatible printer Laser printer must have 4 MB+ of RAM

Connection to the Internet minimum 56k BPS

Software

MS Windows 2000, XP, Vista or Windows 7

QAS-Word Processing software MS Word 2000 or newer

Internet browser Netscape Navigator, Microsoft Internet Explorer, or other browser that supports HTML 4.0 or higher

Email MAPI compatible

Virus protection software regularly upgraded with all issued manufacturer's updates

1.4 RELATED INFORMATION

1.4.1 QCS User Guide

After contract award, download instructions for the installation and use of QCS from the Government RMS Internet Website. In case of justifiable difficulties, the Government will provide an optical disk (CD/DVD) containing these instructions.

1.4.2 Contractor Quality Control (CQC) Training

The use of QCS will be discussed with the QC System Manager during the mandatory CQC Training class.

1.5 CONTRACT DATABASE

Prior to the pre-installation conference, the Government will provide the Contractor with basic contract award data to use for QCS. The Government

SECTION 01 45 02 Page 4 will provide data updates to the Contractor as needed, generally by using the Government's SFTP repository built into QCS import/export function.

These updates will generally consist of submittal reviews, correspondence status, QA comments, and other administrative and QA data.

1.6 DATABASE MAINTENANCE

Establish, maintain, and update data in the QCS database throughout the duration of the contract at the Contractor's site office. Submit data updates to the Government (e.g., daily reports, submittals, RFI's, schedule updates, payment requests, etc.) using the Government's SFTP repository built into QCS export function. If permitted by the Contracting Officer, email or optical disk may be used instead of QCS (see Paragraph DATA SUBMISSION VIA OPTICAL DISK). The QCS database typically includes current data on the following items:

1.6.1 Administration

1.6.1.1 Contractor Information

Contain within the database the Contractor's name, address, telephone numbers, management staff, and other required items. Within 14 calendar days of receipt of QCS software from the Government, deliver Contractor administrative data in electronic format.

1.6.1.2 Subcontractor Information

Contain within the database the name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor must be listed separately for each trade to be performed. Assign each subcontractor/trade a unique Responsibility Code, provided in QCS. Within 14 calendar days of receipt of QCS software from the Government, deliver subcontractor administrative data in electronic format.

1.6.1.3 Correspondence

Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with "S". Prefix letters initiated by the Contractor's home (main) office with "H". Letters must be numbered starting from 0001. (e.g., H-0001 or S-0001). The Government's letters to the Contractor will be prefixed with "C".

1.6.1.4 Equipment

Contain within the Contractor's QCS database a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates.

1.6.1.5 Management Reporting

QCS includes a number of reports that Contractor management can use to track the status of the project. The value of these reports is reflective of the quality of the data input, and is maintained in the various sections of QCS. Among these reports are: Progress Payment Request worksheet, QA/QC comments, Submittal Register Status, Three-Phase Control checklists.

SECTION 01 45 02 Page 5

1.6.1.6 Request For Information (RFI)

Exchange all Requests For Information (RFI) using the Built-in RFI generator and tracker in QCS.

1.6.2 Finances

1.6.2.1 Pay Activity Data

Include within the QCS database a list of pay activities that the Contractor must develop in conjunction with the work schedule. The sum of all pay activities must be equal to the total contract amount, including modifications. Group pay activities Contract Line Item Number (CLIN); the sum of the activities must equal the amount of each CLIN. The total of all CLINs equals the Contract Amount.

1.6.2.2 Payment Requests

Prepare all progress payment requests using QCS. Complete the payment request worksheet, prompt payment certification, and payment invoice in QCS. Update the work completed under the contract, measured as percent or as specific quantities, at least monthly. After the update, generate a payment request report using QCS. Submit the payment request, prompt payment certification, and payment invoice with supporting data using the Government's SFTP repository built into QCS export function. If permitted by the Contracting Officer, email or a optical disk may be used. A signed paper copy of the approved payment request is also required, which will govern in the event of discrepancy with the electronic version.

1.6.3 Quality Control (QC)

QCS provides a means to track implementation of the 3-phase QC Control System, prepare daily reports, identify and track deficiencies, document progress of work, and support other Contractor QC requirements. Maintain this data on a daily basis. Entered data will automatically output to the QCS generated daily report. Provide the Government a Contractor Quality Control (CQC) Plan within the time required in Section 01 45 01 QUALITY CONTROL. Within seven calendar days of Government acceptance, submit a QCS update reflecting the information contained in the accepted CQC Plan:

schedule, pay activities, features of work, submittal register, QC requirements, and equipment list.

1.6.3.1 Daily Contractor Quality Control (CQC) Reports.

QCS includes the means to produce the Daily CQC Report. The Contractor may use other formats to record basic QC data. However, the Daily CQC Report generated by QCS must be the Contractor's official report. Summarize data from any supplemental reports by the Contractor and consolidate onto the QCS-generated Daily CQC Report. Submit daily CQC Reports as required by Section 01 45 01 QUALITY CONTROL. Electronically submit reports to the Government within 24 hours after the date covered by the report. Also provide the Government a signed, printed copy of the daily CQC report.

1.6.3.2 Deficiency Tracking.

Use QCS to track deficiencies. Deficiencies identified by the Contractor will be numerically tracked using QC punch list items. Maintain a current log of its QC punch list items in the QCS database. The Government will log the deficiencies it has identified using its QA punch list items. The

SECTION 01 45 02 Page 6

Government's QA punch list items will be included in its export file to the Contractor. Regularly update the correction status of both QC and QA punch list items.

1.6.3.3 QC Requirements

Develop and maintain a complete list of QC testing and required structural and life safety special inspections required by the International Code Council (ICC), transferred and installed property, and user training requirements in QCS. Update all data on these QC requirements as work progresses, and promptly provide this information to the Government via QCS.

1.6.3.4 Three-Phase Control Meetings

Maintain scheduled and actual dates and times of preparatory and initial control meetings in QCS.

1.6.3.5 Labor and Equipment Hours

Log labor and equipment exposure hours on a daily basis. This data will be rolled up into a monthly exposure report.

1.6.3.6 Accident/Safety Reporting

The Government will issue safety comments, directions, or guidance whenever safety deficiencies are observed. The Government's safety comments will be included in its export file to the Contractor. Regularly update the correction status of the safety comments. In addition, utilize QCS to advise the Government of any accidents occurring on the jobsite. This brief supplemental entry is not to be considered as a substitute for completion of mandatory reports, e.g., ENG Form 3394 and OSHA Form 300.

1.6.3.7 Features of Work

Include a complete list of the features of work in the QCS database. A feature of work may be associated with multiple pay activities. However, each pay activity (see subparagraph "Pay Activity Data" of paragraph "Finances") will only be linked to a single feature of work.

1.6.3.8 Hazard Analysis

Use QCS to develop a hazard analysis for each feature of work included in the CQC Plan. Address any hazards, or potential hazards, that may be associated with the work.

1.6.4 Submittal Management

The Government will provide the initial submittal register in electronic format. Thereafter, maintain a complete list of all submittals, including completion of all data columns. Dates on which submittals are received and returned by the Government will be included in its export file to the Contractor. Use QCS to track and transmit all submittals. ENG Form 4025, submittal transmittal form, and the submittal register update must be produced using QCS. QCS and RMS will be used to update, store and exchange submittal registers and transmittals, but will not be used for storage of actual submittals.

SECTION 01 45 02 Page 7

1.6.5 Schedule

Develop a work schedule consisting of pay activities. Input and maintain in the QCS database this schedule either manually or by using the Standard Data Exchange Format (SDEF). Include with each pay request the updated schedule.

1.6.6 Import/Export of Data

QCS includes the ability to export Contractor data to the Government and to import submittal register and other Government-provided data from RMS, and schedule data using SDEF.

1.7 IMPLEMENTATION

Contractor use of QCS as described in the preceding paragraphs is mandatory. Ensure that sufficient resources are available to maintain its QCS database, and to provide the Government with regular database updates.

QCS shall be an integral part of the Contractor's management of quality control.

1.8 DATA SUBMISSION VIA OPTICAL DISK

The Government-preferred method for Contractor's submission of QCS data is by using the Government's SFTP repository built into QCS export function.

Other data should be submitted using email with file attachment(s). For locations where this is not feasible, the Contracting Officer may permit use of optical disk for data transfer. Export data onto optical disks using the QCS built-in export function. If used, submit optical disks in accordance with the following:

1.8.1 File Medium

Submit in English required data on optical disk conforming to industry standards used in the United States.

1.8.2 Optical Disk Labels

Affix a permanent exterior label to each optical disk submitted. Indicate on the label in English, the QCS file name, full contract number, contract name, project location, data date, name and telephone number of person responsible for the data.

1.8.3 File Names

The files will be automatically named by the QCS software. The naming convention established by the QCS software must not be altered.

1.9 MONTHLY COORDINATION MEETING

Update the QCS database each workday. At least monthly, generate and submit an export file to the Government with schedule update and progress payment request. As required in Contract Clause "Payments", at least one week prior to submittal, meet with the Government representative to review the planned progress payment data submission for errors and omissions.

Make all required corrections prior to Government acceptance of the export file and progress payment request. Payment requests accompanied by incomplete or incorrect data submittals will be returned. The Government

SECTION 01 45 02 Page 8 will not process progress payments until an acceptable QCS export file is received.

1.10 NOTIFICATION OF NONCOMPLIANCE

The Contracting Officer will notify the Contractor of any detected noncompliance with the requirements of this specification. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 45 02 Page 9

COVER
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 - GENERAL REQUIREMENTS
01 00 00 - GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL SCOPE OF WORK
1.2 REFERENCES
1.3 PARTNERING
1.4 COORDINATION CONFERENCES
1.5 EVALUATION OF CONTRACTOR PERFORMANCE
1.6 CONCURRENT WORK
1.7 ACCIDENT PREVENTION
1.8 SUBMITTALS
1.9 RIVER ELEVATION INFORMATION
1.10 MEASUREMENT AND PAYMENT
1.11 PROJECT SIGNS
1.11.1 General
1.11.2 Materials
1.11.3 Painting
1.11.4 Erection and Maintenance

1.12 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

PART 2 PRODUCTS NOT USED
PART 3 EXECUTION
3.1 SURVEY REQUIREMENTS
3.1.1 Initial Surveys
3.1.2 In-Progress Surveys
3.1.3 Final As-built Survey
3.1.4 Field Survey Submittals
3.1.5 Benchmarks
3.1.6 Coordination With the Government
01 22 00 - MEASUREMENT AND PAYMENT
01 22 00 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PAYMENT ITEMS
1.2.1 Survey Work
1.2.2 Floating Plant
1.2.3 Clearing and Grubbing
1.2.4 Excavation
1.2.5 Disposal
1.2.6 Geotextiles
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
1.2.7 Riprap
1.2.7.1 Payment
1.2.7.2 Measurement
1.2.7.3 Unit of Measure
1.3 BARGE LOAD
1.4 DETERMINATION OF EXCESS STONE
PART 2 PRODUCTS
PART 3 EXECUTION
01 33 00 - SUBMITTAL PROCEDURES
01 33 00 - SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
1.2.1 Submittal Descriptions SD
1.2.2 Approving Authority
1.2.3 Work
1.3 SUBMITTALS
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved
1.4.2 Information Only
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.7 INFORMATION ONLY SUBMITTALS
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting That Variations Are Compatible
1.8.4 Environmental Assessment of Variations
1.8.5 Review Schedule Is Modified
1.9 SUBMITTAL REGISTER
1.9.1 Use of Submittal Register
1.9.2 Contractor Use of Submittal Register
1.9.3 Approving Authority Use of Submittal Register
1.9.4 Copies Delivered to the Government
1.10 SCHEDULING
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
1.15 WITHHOLDING OF PAYMENT
1.16 STAMPS
PART 2 PRODUCTS
PART 3 EXECUTION
01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS
01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SUBMITTALS
1.4 REGULATORY REQUIREMENTS
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer SSHO
1.5.1.2 CQC System Manager
1.5.1.3 Crane Operators
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer SSHO
1.5.3 Meetings
1.5.3.1 Pre-installation Conference
1.5.3.2 Safety Meetings
1.6 ACCIDENT PREVENTION PLAN APP
1.6.1 EM 385-1-1 Contents
1.7 ACTIVITY HAZARD ANALYSIS AHA
1.8 DISPLAY OF SAFETY INFORMATION
1.9 SITE SAFETY REFERENCE MATERIALS
1.10 EMERGENCY MEDICAL TREATMENT
1.11 NOTIFICATIONS and REPORTS
1.11.1 Accident Notification
1.11.2 Accident Reports
1.11.3 Crane Reports
1.11.4 Certificate of Compliance
1.12 FACILITY OCCUPANCY CLOSURE
1.13 SEVERE STORM PLAN
1.14 HAZARD COMMUNICATIONS
1.14.1 General
1.14.2 Work Area Hazard Evaluation
1.14.3 Electrical Hazards
1.15 DRUG PREVENTION PROGRAM
1.16 INTERIM CHANGES TO EM-385-1-1
1.17 CONTRACTOR GUIDELINES
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 REQUIRED WORK AND OTHER WORK
3.1.1 Hazardous Material Exclusions
3.1.2 Unforeseen Hazardous Material
3.2 PRE-OUTAGE COORDINATION MEETING
3.3 CONTROL OF HAZARDOUS ENERGY LOCKOUTTAGOUT
3.4 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
3.4.1 Training
3.4.2 Fall Protection Equipment and Systems
3.4.2.1 Personal Fall Arrest Equipment
3.4.3 Existing Anchorage
3.4.4 Horizontal Lifelines
3.4.5 Guardrails and Safety Nets
3.4.6 Rescue and Evacuation Procedures
3.5 WORK LIMIT REQUIREMENTS
3.6 EQUIPMENT
3.6.1 Material Handling Equipment
3.6.2 Weight Handling Equipment
3.6.3 USE OF EXPLOSIVES
3.7 EXCAVATIONS
3.7.1 Utility Locations
3.7.2 Utility Location Verification
3.7.3 Shoring Systems
3.7.4 Trenching Machinery
3.7.5 Utilities Within and Under Concrete, Bituminous Asphalt, and Other
3.8 ELECTRICAL
3.8.1 Conduct of Electrical Work
3.8.2 Portable Extension Cords

3.9 LOCKOUT/TAGOUT

01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS
01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
PART 2 PRODUCTS
PART 3 EXECUTION
01 45 01 - QUALITY CONTROL
01 45 01 - QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 PAYMENT
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 QUALITY CONTROL PLAN
3.2.1 Content of the CQC Plan
3.2.2 Acceptance of Plan
3.2.3 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 CQC System Manager
3.4.3 Specialized CQC Personnel
3.4.4 Additional Requirement
3.4.5 Organizational Changes
3.5 SUBMITTALS AND DELIVERABLES
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.7.2.2 Capability Recheck

3.7.3 Onsite Laboratory