Task_Order_001_PWS_(Phase_I)_rev01.pdf

PDF 129 KB Posted

Attached to
Luckey FUSRAP Remediation
Solicitation number
W912P4-14-R-0002
Issued by

About this file

Revised Task Order PWS

View the file

Other files

File Type Posted
Amendment_4.doc DOC document
Questions_and_Answers_Round_6_Responses.docx DOCX document
Section_5.1.2.3_from_Final_Scope_of_Work_-_RFP_rev02.pdf PDF
CELRB_CBDPP_BHA_BWP_outlines.pdf PDF
UFGS_02_61_13_rev03.pdf PDF
UFGS_02_81_00_rev03.pdf PDF
Questions_and_Answers_Set_5_Responses.docx DOCX document
Service_Contract_Wage_Determination.pdf PDF
Final_Scope_of_Work_-_RFP_rev02.pdf PDF
CELRB_Beryllium_Variance_Updated_2014-09-12.pdf PDF
Davis_Bacon_Wage_Determination.pdf PDF
Final_Amendment_3.docx DOCX document
UFGS_01_32_01.00_10_rev01.pdf PDF
UFGS_02_81_00_rev02.pdf PDF
site_vist_attendance_list.pdf PDF
Final_Amendment_2.doc DOC document
SOW_Att_3_-_Volume_Estimate_Summary_rev01.pdf PDF
UFGS_02_61_13_rev02.pdf PDF
Questions_Set_4_Responses_23_dec.docx DOCX document
RFP_Questions_Set_3_Responses_ernest_23_dec.docx DOCX document
RFP_Questions_Set_2_Responses.docx DOCX document
Sample_PWS__2_(Phase_III)_rev01.docx DOCX document
Final_Scope_of_Work_-_RFP_rev01.docx DOCX document
UFGS_02_61_13_rev01.pdf PDF
Amendment_1.doc DOC document
Final_Questions_and_Answers_Round_1_Responses.docx DOCX document
UFGS_01_57_23_rev01.pdf PDF
UFGS_02_81_00_rev01.pdf PDF
Scope_of_Work_-_Revised_20_Aug_2014.pdf PDF
Sample_Project__2_PWS_(Phase_III).pdf PDF
Task_Order_001_(Phase_I)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Task_Order_001_PWS_(Phase_I).pdf PDF
W912P4-14-R-0002_Final_Luckey_Solicitation.pdf PDF
Sample_Project__2_(Phase_III)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Wage_Determination.pdf PDF
PPQ_0_Form.doc DOC document
Sample_Project__1_PWS_(Phase_II).pdf PDF
Sample_Project__1_(Phase_II)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Section_M_-_Evaluation_Factors_for_Award_09May14.pdf PDF
Section_L_-_Instruction _Conditions_and_notices_9MAY14.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION J

Luckey Soils Remedial Action Task Order 001

Phase I – Develop Remediation Work Plans Performance Work Statement

1.0 INTRODUCTION

1.1 General

This project will be included within the base award for ten-year indefinite delivery/indefinite quantity (IDIQ) single award task order contract (SATOC). Additionally, this will enable the Government to evaluate the CONTRACTOR’s proposed costs.

1.2 Contract Type

This project is a firm fixed price task order to perform the activities described in this Performance Work Statement (PWS) and in accordance with (IAW) the contract scope of work (SOW) included as Section C.

2.0 SCOPE OF SERVICES

2.1 General

In general, the effort under this PWS consists of development of remediation work plans required to implement the CONTRACTOR’s proposed Technical Approach (Proposal Volume I – Factor I). This project does not include infrastructure (Phase II) or remediation (Phase III). Further details regarding the Technical Approach proposal format and requirements are found in Section L. Work under this PWS includes, but is not limited to, the following activities:

• Project management.

• Preparation of project work plans for USACE review and acceptance.

• Establish a Safety and Health Program and prepare/implement Accident Prevention Plans (APPs) as required by Engineer Manual (EM) 385-1-1, 29 CFR 1910.120/29 CFR 1926.65 or other Occupational Safety and Health Administration (OSHA) related compliance plans pertinent to the work. Note that site work shall not proceed until the APP has been submitted to and accepted by USACE.

• Establish chemistry data quality procedures based on USACE, United States Environmental Protection Agency (USEPA) and Ohio EPA guidance.

• Development of site closure protocols (i.e., the Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM).

2.2 Work Plans

Per the requirements referenced in Section 5.1.2 of the SOW (Section C), the following pre-construction work plans shall be prepared for USACE review and acceptance:

• Project Schedule

• Site Operations Plan (SOP)

• Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)/Chronic Beryllium Disease

Prevention Program (CBDPP)/Radiation Protection Plan (RPP)

• Contractor Quality Control Plan (CQCP)

• Sampling and Analysis Plan (SAP)

• Regulatory Compliance Plan (RCP)

• Perimeter Air Monitoring Plan (PAMP)

• Water Management Plan (WMP)

• Waste Management, Transportation, and Disposal Plan (WMTDP)

• Final Status Survey Plan (FSSP)

• Contamination Control Plan (CCP)

• Backfill and Restoration Plan (BRP)

The submittal requirements are summarized in Enclosure 1 of this PWS. Note that the CONTRACTOR shall assume a 60-day review cycle for each work plan version (Preliminary Draft, Draft, and Final), which will include 30 calendar days for Government review, and 30 calendar days for the Contractor to prepare a response to the comments, revise each document, and Government back check. Final plans will be submitted for stakeholder review, including Ohio EPA with a 90-day review cycle. If stakeholder comments are significant, USACE will request additional revisions to the plans with errata sheets, as necessary.

3.0 COST ESTIMATE PREPARATION

The CONTRACTOR shall prepare a cost estimate for all tasks described in this PWS. No work plan or write-up is required, however, the bid schedule (Enclosure 2) shall be completed and detailed backup supporting the cost estimate shall be provided.

4.0 WORK BREAKDOWN STRUCTURE

Below is a summary of tasks required under this PWS, broken down by the respective work breakdown structure as specified in Section C. The Contractor shall furnish all services, materials, supplies, labor, and travel as required to perform the required work herein. All equipment and miscellaneous items deemed necessary for the performance of this PWS including, but not limited to, computers, projectors, telephones, software, field equipment, etc. shall be provided by the CONTRACTOR.

331XX01 Mobilization and Preparatory Work

331XX0103 Submittals / Implementation Plans

5.0 PERIOD OF PERFORMANCE

The period of performance for this task order shall be one (1) year from the notice to proceed.

Enclosure 1 - Submittal Requirements

Enclosure 2 – Bid Schedule

1.0 INTRODUCTION
1.2 Contract Type
2.0 SCOPE OF SERVICES
2.1 General
2.2 Work Plans
3.0 COST ESTIMATE PREPARATION
4.0 WORK BREAKDOWN STRUCTURE
5.0 PERIOD OF PERFORMANCE