SECTION J
Luckey Soils Remedial Action Task Order 001
Phase I – Develop Remediation Work Plans Performance Work Statement
1.0 INTRODUCTION
1.1 General
This project will be included within the base award for ten-year indefinite delivery/indefinite quantity (IDIQ) single award task order contract (SATOC). Additionally, this will enable the Government to evaluate the CONTRACTOR’s proposed costs.
1.2 Contract Type
This project is a firm fixed price task order to perform the activities described in this Performance Work Statement (PWS) and in accordance with (IAW) the contract scope of work (SOW) included as Section C.
2.0 SCOPE OF SERVICES
2.1 General
In general, the effort under this PWS consists of development of remediation work plans required to implement the CONTRACTOR’s proposed Technical Approach (Proposal Volume I – Factor I). This project does not include infrastructure (Phase II) or remediation (Phase III). Further details regarding the Technical Approach proposal format and requirements are found in Section L. Work under this PWS includes, but is not limited to, the following activities:
• Project management.
• Preparation of project work plans for USACE review and acceptance.
• Establish a Safety and Health Program and prepare/implement Accident Prevention Plans (APPs) as required by Engineer Manual (EM) 385-1-1, 29 CFR 1910.120/29 CFR 1926.65 or other Occupational Safety and Health Administration (OSHA) related compliance plans pertinent to the work. Note that site work shall not proceed until the APP has been submitted to and accepted by USACE.
• Establish chemistry data quality procedures based on USACE, United States Environmental Protection Agency (USEPA) and Ohio EPA guidance.
• Development of site closure protocols (i.e., the Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM).
2.2 Work Plans
Per the requirements referenced in Section 5.1.2 of the SOW (Section C), the following pre-construction work plans shall be prepared for USACE review and acceptance:
• Project Schedule
• Site Operations Plan (SOP)
• Accident Prevention Plan (APP)/Site Safety and Health Plan (SSHP)/Chronic Beryllium Disease
Prevention Program (CBDPP)/Radiation Protection Plan (RPP)
• Contractor Quality Control Plan (CQCP)
• Sampling and Analysis Plan (SAP)
• Regulatory Compliance Plan (RCP)
• Perimeter Air Monitoring Plan (PAMP)
• Water Management Plan (WMP)
• Waste Management, Transportation, and Disposal Plan (WMTDP)
• Final Status Survey Plan (FSSP)
• Contamination Control Plan (CCP)
• Backfill and Restoration Plan (BRP)
The submittal requirements are summarized in Enclosure 1 of this PWS. Note that the CONTRACTOR shall assume a 60-day review cycle for each work plan version (Preliminary Draft, Draft, and Final), which will include 30 calendar days for Government review, and 30 calendar days for the Contractor to prepare a response to the comments, revise each document, and Government back check. Final plans will be submitted for stakeholder review, including Ohio EPA with a 90-day review cycle. If stakeholder comments are significant, USACE will request additional revisions to the plans with errata sheets, as necessary.
3.0 COST ESTIMATE PREPARATION
The CONTRACTOR shall prepare a cost estimate for all tasks described in this PWS. No work plan or write-up is required, however, the bid schedule (Enclosure 2) shall be completed and detailed backup supporting the cost estimate shall be provided.
4.0 WORK BREAKDOWN STRUCTURE
Below is a summary of tasks required under this PWS, broken down by the respective work breakdown structure as specified in Section C. The Contractor shall furnish all services, materials, supplies, labor, and travel as required to perform the required work herein. All equipment and miscellaneous items deemed necessary for the performance of this PWS including, but not limited to, computers, projectors, telephones, software, field equipment, etc. shall be provided by the CONTRACTOR.
331XX01 Mobilization and Preparatory Work
331XX0103 Submittals / Implementation Plans
5.0 PERIOD OF PERFORMANCE
The period of performance for this task order shall be one (1) year from the notice to proceed.
Enclosure 1 - Submittal Requirements
Enclosure 2 – Bid Schedule
| 1.0 INTRODUCTION |
| 1.2 Contract Type |
| 2.0 SCOPE OF SERVICES |
| 2.1 General |
| 2.2 Work Plans |
| 3.0 COST ESTIMATE PREPARATION |
| 4.0 WORK BREAKDOWN STRUCTURE |
| 5.0 PERIOD OF PERFORMANCE |