Sample_Project__2_(Phase_III)_Bid_Schedule_Worksheet.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Luckey FUSRAP Remediation
Solicitation number
W912P4-14-R-0002
Issued by

About this file

Sample Project 2 Bid Schedule

View the file

Other files

File Type Posted
Amendment_4.doc DOC document
Questions_and_Answers_Round_6_Responses.docx DOCX document
Section_5.1.2.3_from_Final_Scope_of_Work_-_RFP_rev02.pdf PDF
CELRB_CBDPP_BHA_BWP_outlines.pdf PDF
UFGS_02_61_13_rev03.pdf PDF
UFGS_02_81_00_rev03.pdf PDF
Questions_and_Answers_Set_5_Responses.docx DOCX document
Service_Contract_Wage_Determination.pdf PDF
Final_Scope_of_Work_-_RFP_rev02.pdf PDF
CELRB_Beryllium_Variance_Updated_2014-09-12.pdf PDF
Davis_Bacon_Wage_Determination.pdf PDF
Final_Amendment_3.docx DOCX document
Task_Order_001_PWS_(Phase_I)_rev01.pdf PDF
UFGS_01_32_01.00_10_rev01.pdf PDF
UFGS_02_81_00_rev02.pdf PDF
site_vist_attendance_list.pdf PDF
Final_Amendment_2.doc DOC document
SOW_Att_3_-_Volume_Estimate_Summary_rev01.pdf PDF
UFGS_02_61_13_rev02.pdf PDF
Questions_Set_4_Responses_23_dec.docx DOCX document
RFP_Questions_Set_3_Responses_ernest_23_dec.docx DOCX document
RFP_Questions_Set_2_Responses.docx DOCX document
Sample_PWS__2_(Phase_III)_rev01.docx DOCX document
Final_Scope_of_Work_-_RFP_rev01.docx DOCX document
UFGS_02_61_13_rev01.pdf PDF
Amendment_1.doc DOC document
Final_Questions_and_Answers_Round_1_Responses.docx DOCX document
UFGS_01_57_23_rev01.pdf PDF
UFGS_02_81_00_rev01.pdf PDF
Scope_of_Work_-_Revised_20_Aug_2014.pdf PDF
Sample_Project__2_PWS_(Phase_III).pdf PDF
Task_Order_001_(Phase_I)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Task_Order_001_PWS_(Phase_I).pdf PDF
W912P4-14-R-0002_Final_Luckey_Solicitation.pdf PDF
Wage_Determination.pdf PDF
PPQ_0_Form.doc DOC document
Sample_Project__1_PWS_(Phase_II).pdf PDF
Sample_Project__1_(Phase_II)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Section_M_-_Evaluation_Factors_for_Award_09May14.pdf PDF
Section_L_-_Instruction _Conditions_and_notices_9MAY14.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sample Task Order 2 (CPFF) Task Description Unit Quantitiy Unit Cost Bid Amount

331XX01 Mobilization and Preparatory Work
331XX0101 Mobilization of Construction Equipment and Facilities (Seasonal)1EA$ 61,117JA1$ - 0$ - 0
331XX02 Monitoring, Sampling, Testing, and Analysis
331XX0201 Meteorological Monitoring1EA$ 9,991JA1$ - 0$ - 0
331XX0202 Radiation Monitoring1EA$ 12,150,270JA1$ - 0$ - 0
331XX0203 Air Monitoring and Sampling66MO$ 2,639,175JA1$ - 0$ - 0
331XX0205 Sampling Surface Water / Groundwater / Liquid Waste66MO$ 93,474JA1$ - 0$ - 0
331XX0206 Sampling Soil and Sediment1EA$ 3,332JA1$ - 0$ - 0
331XX0208 Sampling Radioactive Contaminated Media3,686.00EA$ 198,738JA1$ - 0$ - 0
331XX0209 Laboratory Chemical Analysis1EA$ 9,566,036JA1$ - 0$ - 0
331XX0210 Radioactive Waste Analysis1EA$ 8,156,977JA1$ - 0$ - 0
331XX0211 Geotechnical Testing1EA$ 57,224JA1$ - 0$ - 0
331XX0213 On-Site Laboratory Facilities1EA$ 8,818,390JA1$ - 0$ - 0
331XX0290 Beryllium Monitoring, Sampling, Testing, and Analysis66MO$ 3,048,911JA1$ - 0$ - 0
331XX03 Site Work
331XX0302 Clearing and Grubbing5ACR$ 36,530acres1$ - 0$ - 0
331XX05 Surface Water Collection and Control
331XX0507 Sediment Barriers66MO$ 273,536JA1$ - 0$ - 0
331XX07 Air Pollution / Gas Collection and Control
Material Sorting/Sizing Pad Air Filter Routine Maintenance25MO$ 16,227LS1$ - 0$ - 0
331XX08 Solids Collection and Containment
331XX0801 Contaminated Soil Collection107,205.00BCY$ 9,806,930cubic yards-$ - 0$ - 0
331XX09 Liquids / Sediments / Sludges Collection and Containment
331XX0907 Lagoons / Basins / Tanks / Dikes / Pump System1EA$ 2,116,959gallons-$ - 0$ - 0
331XX19 Disposal (Commercial)
331XX1920 Container Handling227,380.00TON$ 2,656,960each-$ - 0$ - 0
331XX1921 Transportation to Storage / Disposal Facility227,380.00TON$ 31,859,611tons-$ - 0$ - 0
331XX1922 Disposal Fees and Taxes185,324.70LCY$ 14,073,136tons-$ - 0$ - 0
331XX20 Site Restoration
331XX2001 Earthwork1EA$ 5,401,379cubic yards-$ - 0$ - 0
331XX2004 Revegetation and Planting22.3ACR$ 141,962acres-$ - 0$ - 0
331XX21 Demobilization (Seasonal and Final)
331XX2101 Removal of Temporary Facilities1EA$ 129,829JA1$ - 0$ - 0
331XX2103 Final Decontamination1EA$ 355,143JA1$ - 0$ - 0
331XX2104 Demobilization of Construction Equipment and Facilities1EA$ 61,258JA1$ - 0$ - 0
331XX2106 Submittals1EA$ 69,214JA1$ - 0$ - 0
331XX22 General Requirements
331XX2201 Supervision and Management66MO$ 5,270,658month-$ - 0$ - 0
331XX2204 Engineering, Surveying, and Quality Control66MO$ 7,268,491month-$ - 0$ - 0
331XX2206 First Aid, Fire Protection, and Traffic Control66MO$ 3,419,372month-$ - 0$ - 0
331XX2207 Health & Safety66MO$ 27,589,539month-$ - 0$ - 0
331XX2208 Temporary Construction Facilities - Ownership66MO$ 994,064month-$ - 0$ - 0
331XX2209 Temporary Construction Facilities - Operation66MO$ 141,491month-$ - 0$ - 0
331XX2210 Project Utilities66MO$ 811,028month-$ - 0$ - 0

Sample Task Order # 2 Total (Cost Plus Fixed Fee) $ 157,296,952 $ - 0

&"-,Bold"&14Luckey FUSRAP Soils Remedial Action Sample Task Order # 2 Bid Schedule

&P of &N