Section 5.1.2.3 of the Scope of Work

View the file

Other files

File Type Posted
Amendment_4.doc DOC document
Questions_and_Answers_Round_6_Responses.docx DOCX document
CELRB_CBDPP_BHA_BWP_outlines.pdf PDF
UFGS_02_61_13_rev03.pdf PDF
UFGS_02_81_00_rev03.pdf PDF
Questions_and_Answers_Set_5_Responses.docx DOCX document
Service_Contract_Wage_Determination.pdf PDF
Final_Scope_of_Work_-_RFP_rev02.pdf PDF
CELRB_Beryllium_Variance_Updated_2014-09-12.pdf PDF
Davis_Bacon_Wage_Determination.pdf PDF
Final_Amendment_3.docx DOCX document
Task_Order_001_PWS_(Phase_I)_rev01.pdf PDF
UFGS_01_32_01.00_10_rev01.pdf PDF
UFGS_02_81_00_rev02.pdf PDF
site_vist_attendance_list.pdf PDF
Final_Amendment_2.doc DOC document
SOW_Att_3_-_Volume_Estimate_Summary_rev01.pdf PDF
UFGS_02_61_13_rev02.pdf PDF
Questions_Set_4_Responses_23_dec.docx DOCX document
RFP_Questions_Set_3_Responses_ernest_23_dec.docx DOCX document
RFP_Questions_Set_2_Responses.docx DOCX document
Sample_PWS__2_(Phase_III)_rev01.docx DOCX document
Final_Scope_of_Work_-_RFP_rev01.docx DOCX document
UFGS_02_61_13_rev01.pdf PDF
Amendment_1.doc DOC document
Final_Questions_and_Answers_Round_1_Responses.docx DOCX document
UFGS_01_57_23_rev01.pdf PDF
UFGS_02_81_00_rev01.pdf PDF
Scope_of_Work_-_Revised_20_Aug_2014.pdf PDF
Sample_Project__2_PWS_(Phase_III).pdf PDF
Task_Order_001_(Phase_I)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Task_Order_001_PWS_(Phase_I).pdf PDF
W912P4-14-R-0002_Final_Luckey_Solicitation.pdf PDF
Sample_Project__2_(Phase_III)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Wage_Determination.pdf PDF
PPQ_0_Form.doc DOC document
Sample_Project__1_PWS_(Phase_II).pdf PDF
Sample_Project__1_(Phase_II)_Bid_Schedule_Worksheet.xlsx XLSX spreadsheet
Section_M_-_Evaluation_Factors_for_Award_09May14.pdf PDF
Section_L_-_Instruction _Conditions_and_notices_9MAY14.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5-4

• Construction QA/QC.

• Mobilization and demobilization activities.

• Construction site layout (equipment and material laydown areas, parking, office trailers, site entrance and exit, and sediment erosion and control measures).

• Site security measures.

• Fire Safety Procedures.

• Layout and security measures for a waste transfer facility if intermodal transportation (truck and rail) is used.

• Decontamination areas and methods.

• Utilities to be used by the CONTRACTOR and connection points.

• Temporary access road details (proposed layout, widths, and cross section).

• Traffic control measures.

• Cross-section details of stockpile areas, decontamination facilities, and sediment erosion and control measures.

• Methods to be used to control radionuclide, particulate and organic compound emissions.

• Surveying requirements and frequency.

• Methods to be used for locating underground utilities, including equipment, tools, and excavation techniques to be used in the vicinity of underground utilities.

• Structures, utilities, and areas to be protected, including excavation offset distances from structures, roads, utilities and storage / loading areas.

• Excavation areas and sequencing of the work.

• Construction equipment to be used.

• Stockpile areas and material handling details.

• Methodology for determining the volume of place-back soils used.

• Monitoring, sampling and analysis associated with:

o The Final Status Survey Plan (FSSP);

o Imported fill;

o Place-back soils;

o Construction QA/QC; and o Perimeter air monitoring.

• Monitoring wells to be decommissioned.

• New monitoring wells to be installed, including installation methods and construction details.

Any supporting data, information, calculations or assumptions used in the preparation of the SOP shall be included.

5.1.2.3 Accident Prevention Plan / Site Safety and Health Plan / Chronic Beryllium Disease Prevention Program / Radiation Protection Plan

The CONTRACTOR shall utilize the services of a Certified Industrial Hygienist (CIH) with at least ten (10) years experience in the development and/or management and implementation of safety programs for HTRW cleanup, facility D&D or other projects with hazards similar to the Luckey Site, preferably involving beryllium and radionuclides, to develop a site-specific APP/SSHP in accordance with

5-5 requirements located in USACE EM 385-1-1, 15 September 2008, “Safety and Health Requirements Manual” and any specific requirements of this SOW. The APP/SSHP shall be developed and submitted in the format provided in Appendix A of USACE EM 385-1-1 and include all applicable plans using the APP/SSHP Checklist as a guide. The CONTRACTOR shall use the site specific UFGS 01 35 26 (Governmental Safety Requirements) and UFGS 01 35 29.13 (Health, Safety and Emergency Response Procedures for Contaminated Sites), both located in Appendix B of this SOW, to complete the APP/SSHP.

The CONTRACTOR shall complete the APP/SSHP Checklist and submit this as an attachment to the APP/SSHP. The CONTRACTOR shall complete an Activity Hazard Analysis (AHA) per EM 385-1-1, 01.A.13 for each work activity, and submit these as attachments to the APP/SSHP. The CONTRACTOR shall fill out a Monthly Man Hour Report and submit this to the COR by the fifth work day of the following month. The CONTRACTOR will complete an Accident Reporting Form 3394, when needed, and submit this to the KO or COR. The APP/SSHP Checklist, AHA template, Monthly Man Hour Report, Accident Reporting Form 3394, and Crane Certificate of Compliance can all be found in Attachment 5. The CONTRACTOR will submit all other relevant safety plans as attachments to the APP/SSHP (see EM 385-1- 1 Appendix A).

The CONTRACTOR shall utilize the services of a Certified Industrial Hygienist (CIH) with experience in beryllium health and safety to prepare a Luckey Site-Specific Chronic Beryllium Disease Prevention Program (CBDPP) as an attachment to the APP/SSHP. Included in the CBDPP will be a Baseline Inventory and Hazard Assessment (BIHA) of beryllium contamination on site.

The CBDPP will contain all necessary elements to allow the CONTRACTOR to minimize the number of beryllium-exposed staff, including official visitors and visiting specialists (e.g., mechanics, specialty craftsmen for short term duties, etc), minimize the amount of the beryllium exposure, and minimize the duration of the beryllium exposure. The minimum required topics to be addressed in the CONTRACTOR CBDPP are presented in Appendix B. The CONTRACTOR is not limited to these topics but the CBDPP submittal will be a deliverable subject to KO acceptance prior to the Notice to Proceed with any site work.

The BIHA will result in the establishment of anticipated work zone boundaries, including the Exclusion Zone (EZ), Contamination Reduction Zone (CRZ), and Support Zone (SZ). All access points and decontamination areas are to be clearly delineated on the site drawings, which will also indicate where the “potential exposure to beryllium” exists. The CBDPP-required signage will be in place before Notice to Proceed with any site work is granted. PPE requirements, including training for use (donning & doffing), care, and inspection, will be clearly defined for each area and will be based on the potential exposure to beryllium. The SHM will continually assess the potential exposure to beryllium on site and may modify the work zone boundaries based on additional sampling results and changing activity in each work zone. See UFGS 01 35 29.13 Section 1.16 (SITE CONTROL MEASURES) for additional information. The CONTRACTOR must adhere to the USACE Occupational Exposure Limit of 0.2 micrograms per cubic meter (µg/m3) and Action Level of 0.1 µg/m3 as indicated in the attached Beryllium Exposure Standard Variance Letter for Luckey (Appendix B), to ensure employee protection.

Exposure monitoring and air sampling shall be performed by a competent person to evaluate

5-6 effectiveness of prescribed PPE and to evaluate worker exposure to site related contaminants and hazardous substances used in the cleanup process.

Per EM 385-1-1, 15 Sep 08, Section 01.A.17, the Site Safety and Health Officer (SSHO), as a minimum, must have completed the 30-hour OSHA Construction Safety Training, and must be on-site at all times when work is being performed. See UFGS 01 35 26 and UFGS 01 35 29.13 (Appendix B), for additional requirements of the SHM and SSHO.

The CONTRACTOR shall utilize the services of a Certified Health Physicist (CHP) with at least ten (10) years’ experience in radioactive waste handling and disposal operations, to develop a RPP that is commensurate with the scope and extent of the activities, and is sufficient to ensure compliance with the provisions of the applicable standards. The RPP will be signed by the CHP and be an attachment to the APP/SSHP. The CONTRACTOR shall develop a RPP to address the radioactive materials encountered at the project site.

If a crane will be used, the CONTRACTOR is required to comply with requirements of OSHA and EM 385- 1-1, Chapter 16, and complete the Crane Certificate of Compliance. The completed certificate shall be attached to the APP/SSHP as well as posted in the cab of the crane.

ALL Contractor accidents, involving injuries (including First Aid), illnesses or property damage, occurring during the execution of this contract shall be reported to USACE within 4 hours of the contractor becoming aware of its occurrence. Reporting injuries, illness or property damage to the COR may be sufficient. Based upon the severity of the injury, illness or property damage, more detailed reporting (i.e. ENG Form 3394) may be required. More detailed notification will include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). The USACE initial contact shall be made personally (telephone or email messages only are not acceptable) to one of the following:

1. COR - To be determined

2. KO - Jeff Ernest: Office (716) 879-4173; Blackberry (716) 803-5405; Email

Jeffrey.G.Ernest@usace.army.mil

3. Project Manager - Stephen Buechi: Office (716) 879-4287; Email

Stephen.P.Buechi@usace.army.mil

Site work shall not proceed until the APP/SSHP has been submitted to and accepted by USACE.

Safety is a key operating principle for USACE, and, therefore, the CONTRACTOR shall adhere to the application of all applicable federal, state, and local requirements. The following documents shall be used as applicable in the preparation of the APP/SSHP, RPP, and CBDPP:

• USACE EM 385-1-1 (15 Sep 2008) Safety and Health Requirements Manual;

5-7

• USACE ER 385-1-92 (1 May 2007) Safety and Occupational Health Requirements for Hazardous, Toxic and Radioactive Waste (HTRW) Activities.

• UFGS-01 35 26 Governmental Safety Requirements (Appendix B)

• UFGS-01 35 29.13 Health, Safety, and Emergency Response Procedures for Contaminated Sites

(Appendix B

• USACE ER 385-1-80 (30 June 2010) Ionizing Radiation Protection

• USACE EM 385-1-80 (30 May 1997) Radiation Protection Manual

• CESO Variance Request, EM 385-1-1, Section 06.A.01 a, Exposure Standards, dated 12

September 2014 (Appendix B)

The following documents maybe used as applicable in the preparation of the APP/SSHP, RPP, and

CBDPP:

• USDOL OSHA 29 CFR 1926 Safety and Health Regulations for Construction

• USDOL OSHA 29 CFR 1910 Occupational Safety and Health Standards

• USDOL OSHA 29 CFR 1910.120 or 1926.65 HAZWOPER Standard

• USNRC 10 CFR Part 20 Standards of Protection Against Radiation

• DOE 10 CFR 850 Chronic beryllium Disease Prevention Program

USACE Safety and Health Requirements Manual, EM 385-1-1: http://140.194.76.129/publications/eng-manuals/EM_385-1-1_languages/EM_385-1-1_English_2008/toc.html

5.1.2.4 Contractor Quality Control Plan

The CONTRACTOR is responsible for quality QC and shall establish and maintain an effective QC system.

The CQCP is the means by which the CONTRACTOR ensures that the construction (including subcontractors and suppliers) complies with the requirements of the contract. At least three phases of control must be conducted for each definable feature of the construction work; a preparatory phase, an initial phase, and a follow-up phase.

The CONTRACTOR shall provide and maintain an effective QC program that will ensure that all documents and design activities required by this SOW are prepared and provided in a manner that meets professional engineering quality standards.

The CQCP shall include, as a minimum, the following to cover all design and construction operations, both on site and off site, including work by subcontractors, fabricators, suppliers, designers of record, consultants, and architect/-engineers (AE):

• A description of the QC organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three- phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.

• The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function. CQC organization requirements are provided in Appendix B (UFGS Section 01 45 00.00 10).