Text version
Sample Task Order 1 (FFP) Task Description Unit Quantitiy Unit Cost Total Cost
| 331XX01 Mobilization and Preparatory Work | |||||||
| 331XX0101 Mobilization of Construction Equipment and Facilities | 1 | EA | $ 61,117 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0104 Setup / Construct Temporary Facilities | 1 | EA | $ 2,925,461 | JA | 1 | $ - 0 | $ - 0 |
| 331XX02 Monitoring, Sampling, Testing, and Analysis | |||||||
| 331XX0201 Meteorological Monitoring | 1 | EA | $ 9,991 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0202 Radiation Monitoring | 1 | EA | $ 12,150,270 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0203 Air Monitoring and Sampling | 66 | MO | $ 2,639,175 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0205 Sampling Surface Water / Groundwater / Liquid Waste | 66 | MO | $ 93,474 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0209 Laboratory Chemical Analysis | 1 | EA | $ 9,566,036 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0210 Radioactive Waste Analysis | 1 | EA | $ 8,156,977 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0211 Geotechnical Testing | 1 | EA | $ 57,224 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0213 On-Site Laboratory Facilities | 1 | EA | $ 8,818,390 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0290 Beryllium Monitoring, Sampling, Testing, and Analysis | 66 | MO | $ 3,048,911 | JA | 1 | $ - 0 | $ - 0 |
| 331XX03 Site Work | |||||||
| 331XX0302 Clearing and Grubbing | 5 | ACR | $ 36,530 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0304 Roads / Parking / Curbs / Walks | 1 | SY | $ 113,370 | JA | 1 | $ - 0 | $ - 0 |
| 331XX0305 Fencing | 1 | EA | $ 272,129 | JA | 1 | $ - 0 | $ - 0 |
| 331XX05 Surface Water Collection and Control | |||||||
| 331XX0507 Sediment Barriers | 66 | MO | $ 273,536 | JA | 1 | $ - 0 | $ - 0 |
| 331XX07 Air Pollution / Gas Collection and Control | |||||||
| Material Sorting/Sizing Pad Air Filter Routine Maintenance | 25 | MO | $ 16,227 | $ - 0 | $ - 0 | ||
| 331XX09 Liquids / Sediments / Sludges Collection and Containment | |||||||
| 331XX0907 Lagoons / Basins / Tanks / Dikes / Pump System | 1 | EA | $ 2,116,959 | JA | 1 | $ - 0 | $ - 0 |
| 331XX21 Demobilization | |||||||
| 331XX2104 Demobilization of Construction Equipment and Facilities | 1 | EA | $ 61,258 | JA | 1 | $ - 0 | $ - 0 |
| 331XX22 General Requirements | |||||||
| 331XX2201 Supervision and Management | 66 | MO | $ 5,270,658 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2204 Engineering, Surveying, and Quality Control | 66 | MO | $ 7,268,491 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2206 First Aid, Fire Protection, and Traffic Control | 66 | MO | $ 3,419,372 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2207 Health & Safety | 66 | MO | $ 27,589,539 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2208 Temporary Construction Facilities - Ownership | 66 | MO | $ 994,064 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2209 Temporary Construction Facilities - Operation | 66 | MO | $ 141,491 | JA | 1 | $ - 0 | $ - 0 |
| 331XX2210 Project Utilities | 66 | MO | $ 811,028 | JA | 1 | $ - 0 | $ - 0 |
Sample Task Order #1 Total (Firm Fixed Price) $ 95,911,678 $ - 0